砂石料加工系统工程施工总进度表
- 格式:xls
- 大小:51.00 KB
- 文档页数:1
中旬下旬上旬中旬下旬上旬中旬下旬上旬中旬下旬上旬中旬下旬
1准备工程项1202003-8-12003-8-202003-8-12003-8-20
1.1施工设备进场项1102003-8-12003-8-102003-8-12003-8-10
1.2场内场外道路项1102003-8-12003-8-102003-8-12003-8-10
1.3场区平整工程项1152003-8-62003-8-202003-8-62003-8-20
1.4风水电及临时住房项1152003-8-12003-8-152003-8-12003-8-15
2土建工程812003-8-62003-10-252003-8-62003-10-25
2.1土石方挖填m319313562003-8-62003-9-302003-8-62003-10-11
2.1.1回车平台及道路m311200252003-8-212003-9-142003-8-212003-9-14
2.1.2篦子筛、粗碎、中碎、预筛分、主筛分及砂处理m3370.6102003-8-62003-8-152003-8-292003-9-8
2.1.3成品粗、细骨料场m31920152003-8-162003-8-302003-8-162003-8-30
2.1.4地磅房m3195.752003-9-262003-9-302003-10-72003-10-11
2.1.5供水系统m3541.6102003-8-312003-9-92003-8-312003-9-9
2.1.6沉砂池及排水m31484162003-9-102003-9-252003-9-102003-9-25
2.1.7胶带机m3553.5152003-8-112003-8-252003-8-112003-8-25
2.2混凝土浇筑m31065(钢筋制安12.92t)612003-8-112003-10-102003-8-262003-10-16
2.2.1篦子筛、粗碎、中碎、预筛分、主筛分及砂处理m3320.2(钢筋制安12.92t)152003-8-112003-8-252003-8-112003-8-25
2.2.2成品粗、细骨料场m31232003-9-202003-9-222003-9-202003-9-22
2.2.3地磅房m354.352003-10-62003-10-102003-10-122003-10-16
2.2.4供水系统m390.5432003-9-232003-9-252003-9-232003-9-25
2.2.5沉砂池及排水m3284.5102003-9-262003-10-52003-9-262003-10-5
2.2.6胶带机m3303.46252003-8-262003-9-192003-8-262003-9-19
2.3砌筑工程m3894712003-8-162003-10-252003-8-162003-10-25
2.3.1回车平台及道路m3164302003-8-162003-9-142003-8-162003-9-14
2.3.2成品粗骨料场m3227152003-10-12003-10-152003-10-12003-10-15
2.3.3成品细骨料场m3198102003-10-162003-10-252003-10-162003-10-25
2.3.4供水系统m315.462003-9-152003-9-202003-9-152003-9-20
2.3.5沉砂池及排水m3178.4102003-9-212003-9-302003-9-212003-9-30
2.3.6生产用房m2350302003-8-162003-9-142003-8-162003-9-14
3金属结构制安工程t170822003-8-212003-11-102003-8-212003-11-10
3.1篦子筛车间t13.9112003-8-212003-8-312003-8-212003-8-31
3.2粗碎、中碎及预筛分车间t12.25152003-9-62003-9-202003-9-262003-10-10
3.3主筛分车间t24302003-9-212003-10-202003-9-232003-10-22
3.4洗砂机及砂处理单元t0.552003-9-12003-9-52003-11-42003-11-8
3.5成品粗骨料场t1.952003-9-12003-9-52003-9-12003-9-5
3.6地磅房t0.352003-9-12003-9-52003-11-62003-11-10
3.7胶带机t117.15822003-8-212003-11-102003-8-212003-11-10
4机电设备安装工程项1602003-9-222003-11-202003-9-222003-11-20
4.1生产设备订货及进场项1402003-9-222003-10-312003-9-222003-10-31
4.2粗碎车间项182003-10-12003-10-82003-10-22003-10-8
4.3中碎车间项172003-10-92003-10-152003-10-92003-10-15
4.4预筛分车间项172003-10-162003-10-222003-10-162003-10-22
4.5主筛分车间项192003-10-232003-10-312003-10-232003-10-31
4.6洗砂机及砂处理单元项172003-11-12003-11-72003-11-92003-11-15
4.7地磅房项152003-11-82003-11-122003-11-162003-11-20
4.8胶带机项1502003-10-22003-11-202003-10-22003-11-20
4.9管路敷设项1152003-11-62003-11-202003-11-62003-11-20
5系统调试及试运行项152003-11-212003-11-252003-11-212003-11-25
6系统正式生产项12003-11-262003-11-26
工期最早开工日期2003年11月最早完工日期2003年7月2003年8月2003年9月2003年10月最迟开工日期最迟完工日期xxx水电站砂石料加工系统工程施工总进度表序号项目名称单位工程量
图号:ZLF—CI(投)—004