Universal Beijing, Theme Park

北京环球主题公园项目

Method Statement of Testing & Commissioning

for HVAC Systems

暖通空调系统调试方案

Package No.标段号: Package 1

Document No./文件编号: 719-904+917-MS-HV-SMCC-TC001

REV

版本号

DATE

日期

REASON FOR

ISSUE

发布原因

ORIG

初稿

CHK

审核

APPR

批准

本文件属于北京国际度假区有限公司的财产,其版权由北京国际度假区有限公司独占所有。未经北京国际度假区有限公司事先明确书面许可,承包商/供货商/供货厂家或其他主体均不得以任何方式直接

或间接地复制、修改、传播,泄露、公开或以其他任何方式使用部分或全部文件内容及所含商业信息.

T h i s d o c u m e n t t h e r e o n i s t h e p r o p e r t y o f B e i j i n g I n t e r n a t i o n a l R e s o r t C o ., L t d , w i t h c o p y r i g h t e x c l u s i v e l y o w n e d b y B e i j i n g I n t e r n a t i o n a l R e s o r t C o ., L t d . W i t h o u t p r i o r w r i t t e n p e r m i s s i o n f r o m B e i j i n g

I n t e r n a t i o n a l R e s o r t C o ., L t d ., n o c o n t r a c t o r /v e n d o r /s u p p l i e r o r o t h e r b o d y s h a l l b e a l l o w e d t o r e p r o d u c e , m o d i f y , d i s s e m i n a t e , d i s c l o s e o r u t i l i z e p a r t o f o r t h e w h o l e c o n t e n t a n d c o m m e r c i a l i n f o r m a t i o n

i n c l u d e d i n t h e d o c u m e n t i n a d i r e c t , i n d i r e c t o r o t h e r w a y .

Universal Beijing, Theme Park Method Statement of Testing & Commissioning for

HV AC Systems 北京环球主题公园项目暖通空调系统调试方案

718-813-603-MS-HV-SMCC-TC001

REV 版本:0

目录

TABLE OF CONTENTS

1 目的PURPOSE...................................................................................................................... - 3 -

2 简介INTRODUCTION ........................................................................................................... - 3 - 2.1参考规范及标准R EFERENCE C ODES AND S TANDARDS (3)

2.2定义D EFINITIONS (6)

2.3缩略语A CRONYMS AND A BBREVIATIONS (8)

3 工作范围SCOPE OF WORK................................................................................................ - 12 -

4 测试及调试流程TESTING & COMMISSIONING PROCEDURE .......................................... - 13 - 4.1测试前检查P RE-T ESTING I NSPECTION .. (13)

4.2性能测试P ERFORMANCE T ESTING (13)

4.3文件和可交付成果D OCUMENTATION AND D ELIVERABLES (14)

5 测试及调试仪器TEST & COMMISSIONING INSTRUMENT............................................... - 14 - 5.1工具T OOLS. (14)

5.2测试证书T EST C ERTIFICATES (15)

6 测试及调试方法TEST & COMMISSIONING METHODOLOGY .......................................... - 15 - 6.1空调通风系统测试A IR C ONDITIONING V ENTILATION S YSTEM T EST. (15)

6.1.1 测试前检查Pre-testing Check ............................................................................. - 15 -

6.1.2 风管漏光检测Light Leakage Test ............................................... 错误!未定义书签。

6.1.3 风管漏风检测Air Leakage Test ........................................................................... - 17 -

6.1.4 空调机组试运转及调试HVAC Start-up and Commissioning ............................. - 18 -

6.1.5 风机试运转及调试Fan Start-up and Commissioning ......................................... - 18 -

6.1.6 风系统平衡测试Air Balancing Test .................................................................... - 21 -

Universal Beijing, Theme Park Method Statement of Testing & Commissioning for

HV AC Systems 北京环球主题公园项目暖通空调系统调试方案

718-813-603-MS-HV-SMCC-TC001

REV 版本:0

6.2空调水系统测试A IR C ONDITIONING W ATER S YSTEM T EST (22)

6.2.1 测试前检查Pre-testing Check ............................................................................. - 22 -

6.2.2 水力平衡调试Water Balancing Test .................................................................... - 22 -

6.3联合试运行及调试I NTEGRATED S TART-UP AND C OMMISSIONING (23)

6.3.1 测试前检查Pre-testing Check ............................................................................. - 23 -

6.3.2 联合试运行及调试Integrated Start-up and Commissioning .............................. - 24 -

6.4噪声测试N OISE L EVEL T EST (25)

6.4.1 测试前检查Pre-testing Check ............................................................................. - 25 -

6.4.2 空调系统噪声测试Air Conditioning System Noise Test ..................................... - 25 -

6.4.3 室内噪声测试Indoor Noise Test .......................................................................... - 26 -

7 测试及调试人员TEST & COMMISSIONING PERSONNEL ................................................. - 26 -

8 附录APPENDICES............................................................................................................... - 27 -

附录A:风管漏风检测记录表A PPENDIX B:D UCTWORK A IR L EAKAGE T EST R ECORD (28)

附录B:现场组装空调机组漏风检测记录表A PPENDIX B:S ITE-ASSEMBLED AHU A IR L EAKAGE T EST R ECORD (29)

附录C:房间室内风量温度测量记录表A PPENDIX C:R OOM A IR V OLUME AND T EMPERATURE T EST R ECORD (30)

附录D:管网风量平衡记录表A PPENDIX D:D UCT A IRFLOW B ALANCING T EST R ECORD (31)

附录E:设备单机试运转记录表A PPENDIX E:E QUIPMENT S TAND-ALONE S TARTUP R ECORD (32)

附录F:空调系统试运转调试记录表A PPENDIX F:A IR C ONDITIONING S YSTEM S TARTUP &

C OMMISSIONING R ECORD (33)

附录G:空调水系统试运转调试记录表A PPENDIX G:A IR C ONDITIONING W ATER S YSTEM S TARTUP &

C OMMISSIONING R ECORD (34)

1 目的

PURPOSE

本调试方案将涵盖北京环球主题公园项目零售品仓库暖通空调系统在技术规格书230000章节,GB标准及制造商建议下的性能测试。

This method statement will cover the performance testing and commissioning of HVAC Systems for Retail/Merch Warehouse, Universal Beijing Theme Park Project under the specification Section 230000, GB standard and manufacturer recommendations.

2 简介

INTRODUCTION

2.1参考规范及标准

Reference Codes and Standards

下列参考规范及标准将应用于暖通空调系统的性能测试:

The following references shall be used for performance testing of HVAC Systems:

-GB 50242-2002 “建筑给排水及采暖工程施工质量验收规范”

GB 50242-2002 “Code for Acceptance of Construction Quality of Water Supply Drainage and Heating Works”.

-GB 50243-2016 “通风与空调工程施工质量验收规范”

GB 50243-2016 “Code of Acceptance for Construction Quality of Ventilation and Air Conditioning Works”.

-GB/T 13274-1991 “一般用途轴流通风机技术条件”

GB/T 13274-1991 “Technical Specification for General Purposes Axial Fans”.

-JB/T 10281-2014 “消防排烟通风机”

JB/T 10281-2014 “Smoke and Heat Exhaust Fan”.

-GB/T 1236-2000 “工业通风机用标准化风道进行性能试验”

GB/T 1236-2000 “Industrial Fans –Performance Testing Using Standardized Airways”.

-JB/T 8690-2014 “通风机噪声限值”

JB/T 8690-2014 “Fans –Noise Limited Value”.

-JB/T 8689-2014 “通风机振动检测及其限值”

JB/T 8689-2014 “Fan Vibration Detection and Its Limited Value”.

-GA 211-2009 “消防排烟风机耐高温试验方法”

GA 211-2009 “High Temperature-resistant Test Methods for Smoke and Heat Exhaust Ventilators”.

-GB/T 10178-2006 “工业通风机现场性能试验”

GB/T 10178-2006 “Industrial Fans –Performance Testing in Site”.

-JB/T 6411-2014 “暖通空调用轴流通风机”

JB/T 6411-2014 “Axial Fan for Heating Ventilation and Air Conditioner”.

-GB 50275-2010 “风机、压缩机、泵安装工程施工及验收规范”

GB 50275-2010 “Code for Construction and Acceptance of Fan, Compressor and Pump Installation”.

-JB/T 9067-1999 “空气幕”

JB/T 9067-1999 “Air Curtain”.

-GB/T 14296-2008 “空气冷却器与空气加热器”

GB/T 14296-2008 “Air Cooling and Air Heating Coils”.

-GB 50738-2011 “通风与空调工程施工规范”

GB 50738-2011 “Code for Construction of Ventilation and Air Conditioning”.

-GB/T 2888-2008 “风机和罗茨鼓风机噪声测量方法”

GB/T 2888-2008 “Methods of Noise Measurement for Fans Blowers Compressors and Roots Blowers”.

-GB 3095-2012 “环境空气质量标准”

GB 3095-2012 “Ambient Air Quality Standard”.

-GB/T 18883-2002 “室内空气质量标准”

GB/T 18883-2002 “Indoor Air Quality Standard”.

-GB 50176-2016 “民用建筑热工设计规范”

GB 50176-2016 “Code for Thermal Design of Civil Building”.

-GB 50411-2019 “建筑节能工程施工质量验收标准”

GB 50411-2019 “Code for Acceptance of Energy Efficient Building Construction”.

-GB 50303-2015 “建筑电气工程施工质量验收规范”

GB 50303-2015 “Code for acceptance of Construction Quality of Building Electrical Engineering”.

-GB 50150-2016 “电气装置安装工程电气设备交接试验标准”

GB 50150-2016 “Electric Equipment Installation Engineeri ng – Standard for Hand-over Test of Electric Equipment”.

-CJ/T 476-2015 “建筑机电设备抗震支吊架通用技术条件”

CJ/T 476-2015 “Specification of Seismic Supports for Mechanical and Electrical Components”. -GB 50981-2014 “建筑机电工程抗震设计规范”

GB 50981-2014 “Code for Seismic Design of Mechanical and Electrical Equipment”.

-GB 50011-2010 (2016) “建筑抗震设计规范”

GB 50011-2010 (2016) “Code for Seismic Design of Buildings”.

-GB 50556-2010 “工业企业电气设备抗震设计规范”

GB 50556-2010 “Code for Aseismic Design of Electrical Facilities in Industrial Plants”.

-GB 50016-2014 (2018) “建筑设计防火规范”

GB 50016-2014 (2018) “Code for Fire Protection Design of Buildings”.

-GB 50189-2015 “公共建筑节能设计标准”

GB 50189-2015 “Design Standard for Energy Efficiency of Public Buildings”.

-GB/T 4208-2017 “外壳防护等级(IP代码)”

GB/T 4208-2017 “Degrees of Protection Provided by Enclosure (IP Code)”.

-技术规格书230500 “暖通空调通用施工结果”

Specification 230500 “ Common Work Results for HVAC”.

-技术规格书230510 “暖通空调基本要求及方法”

Specification 230510 “ HVAC Basic Requirements and Methods”.

-技术规格书230513 “暖通空调设备的通用电动机要求”

Specification 230513 “ Common Motor Requirements for HVAC Equipment”.

-技术规格书230549 “暖通空调系统抗震”

Specification 230549 “ Seismic Restraint for HVAC”.

-技术规格书230553 “水暖管道及设备标识”

Specification 230553 “ Identification for HVAC Piping and Equipment”. -技术规格书230593 “暖通空调系统测试、调节及平衡”

Specification 230593 “Testing and Adjusting and Balancing for HVAC”. -技术规格书230800 “暖通空调系统调试”

Specification 230800 “Commissioning of HVAC”.

-技术规格书230900 “暖通空调系统仪表及控制”

Specification 230900 “Instrumentation and Control for HVAC”.

-技术规格书230993 “控制顺序”

Specification 230993 “Control Sequence General and Airside”.

-技术规格书233400 “风机”

Specification 233400 “Fans”.

-技术规格书233433 “空气幕”

Specification 233433 “Air Curtains”.

-技术规格书233616 “空调末端设备”

Specification 233616 “Air Terminal Units”.

-技术规格书237314 “组合式空调机组”

Specification 237314 “Combined Air Conditioning Units”.

-技术规格书237314 “组合式空调机组”

Specification 237314 “Combined Air Conditioning Units”.

-技术规格书260526 “电气系统接地和保护接地”

Specification 260526 “ Grounding and Bonding for Electrical Systems”. -技术规格书260549 “电气系统抗震”

Specification 260549 “ Seismic Restraint for Electrical Systems”.

-技术规格书260583 “电气系统验收测试”

Specification 260583 “ Acceptance Testing for Electrical Systems”.

-技术规格书260916 “电气控制和继电器”

Specification 260916 “Electrical Control and Relays”.

-技术规格书262419 “电机控制中心”

Specification 262419 “Motor-Control Centers”.

-技术规格书262923 “变频电机控制柜”

Specification 262923 “Variable-frequency Motor Cabinet”.

-制造商的指导及推荐

Manufacturer’s instruction and recommendation.

-已批准的暖通空调系统深化设计图纸

Approved Installation Shop Drawings for HVAC Systems.

-已批准的暖通空调系统安装方案

Approved Method Statement of Installation for HVAC Systems.

备注:应采用上述参考文件的最新版本。

Note: The latest revision of the above-mentioned references shall be used.

2.2定义

Definitions

通风工程

Ventilation Works

送风、排风、防排烟、除尘和气力输送系统工程的总称。

General term for the supply air, exhaust air, smoke exhaust, dust removal and pneumatic conveying system engineering.

空调工程

Air Conditioning Works

舒适性空调、恒温恒湿空调和洁净室空气净化及空气调节系统工程的总称。

General term for comfort air conditioner, constant temperature and humidity air conditioner and clean room air purification and air conditioning system engineering.

空调

Air Conditioning

通过处理和输配空气,控制空间的空气温度、湿度、洁净度和气流速度等参数,达到给定要求的技术。

Through the treatment and distribution of air, control the air temperature, humidity, cleanliness and air flow speed and other parameters, to achieve the given requirements of the technology.

通风

Ventilation

为改善生产和生活条件,采用自然或机械方法,对某一空间进行换气,以使空气环境满足卫生和安全等适宜要求的技术。

In order to improve production and living conditions, natural or mechanical methods are used to ventilate a certain space so that the air environment meets appropriate requirements such as health and safety.

风管系统工作压力

Design Working Pressure

系统总风管处最大的设计工作压力。

Maximum design working pressure at the main air duct of the system.

漏风量

Air Leakage Volume

风管系统中,在某一静压下通过风管本体结构及其接口,单位时间内泄出或渗入的空气体积量。

In the air duct system, the volume of air released or penetrated in unit time through the structure and interface of the air duct under a certain static pressure.

系统风管允许漏风量

Duct System Permissible Air Leakage Volume

按风管系统类别所规定的平均单位表面积、单位时间内最大允许漏风量。

According to the average unit surface area and maximum allowable air leakage per unit time specified by the type of duct system.

漏风率

Air Leakage Rate

风管系统、空调设备、除尘器等,在工作压力下空气渗入或泄漏量与其额定风量的百分比。

Air duct system, air conditioning equipment, dust remover, etc., air infiltration or leakage under working pressure as a percentage of its rated air volume.

强度试验

Strength Test

在规定的压力和保压时间内,对管路、容器、阀门等进行耐压能力的测定与检验。Measure and inspect the pressure resistance of pipelines, vessels, valves, etc. within the specified pressure and holding time.

严密性试验

Leakage Test

在规定的压力和保压时间内,对管路、容器、阀门等进行抗渗漏性能的测定与检验。Measure and inspect the leakage resistance of pipeline, vessel and valve within the specified pressure and holding time.

空气洁净度等级

Air Cleanliness Classification

以单位体积空气中,某粒径粒子的数量来划分的洁净程度标准。

The standard of cleanliness divided by the number of particles of a certain size in unit volume of air.

空调通风系统能耗系数

Coefficient of Energy Consumption for Air Conditioning (CEC)

空调通风系统全年一次能源总消耗量与假想空调负荷全年累计值的比值。

The ratio of the total primary energy consumption of the air conditioning and ventilation system to the annual cumulative value of the hypothetical air conditioning load.

水力失调率

Rate of Hydraulic Disorder

空调水系统中各并联管路的实际流量通设计流量的偏差,与设计流量的比值。

The deviation of the actual flow through the design flow of each parallel pipeline in the air conditioning water system, and the ratio of the design flow to the actual flow.

风量失调率

Rate of Airflow Disorder

风系统中各并联支管的实际风量同设计风量的偏差,与设计风量的比值。

The deviation of the actual air volume of each parallel branch pipe from the design air volume in the wind system and the design air volume.

换气次数

Air Changes

每小时的通风量与房间容积之比。

The ratio of the amount of ventilation per hour to the volume of the room.

最小新风量

Minimum Fresh Air Requirement

建筑物内满足人体健康和环境舒适所需的新鲜空气量。

The amount of fresh air in a building that meets human health and environmental comfort.

2.3缩略语

Acronyms and Abbreviations

3 工作范围

SCOPE OF WORK

本工作方法和程序确定了暖通空调系统现场性能测试所涉及的方式,过程和顺序,包括空调系统、通风系统及其相关设备,这些工作将根据技术规范230000章节完成。现场性能测试将按照批准的安装施工图和本文件中的详细说明进行。

This work method and procedure establishes the manner or process and sequence of activities involved in the field performance testing of HVAC Systems, including air conditioning system, ventilation system and its associated devices which will be completed under the specification Section 230000. Field performance testing will be carried out as shown on the approved installation shop drawings and as detailed here in this document.

本调试计划的范围是零售品仓库(单体编号:813)的暖通空调系统。下列设备和材料应在现场进行试验:

The scope of this Commissioning Plan is the HVAC Systems of Retail/Merch Warehouse (Building No.: 813). The following equipment and materials shall be tested on-site:

-空调通风系统测试

Air Conditioning Ventilation System Test

-空调水系统测试

Air Conditioning Water System Test

-联合试运行及调试

Integrated Start-up and Commissioning

-噪声测试

Noise Level Test

-温湿度测试

Temperature and Humidity Test

4 测试及调试流程

TESTING & COMMISSIONING PROCEDURE

4.1测试前检查

Pre-Testing Inspection

测试前检查的目的是确保所有部件和系统在性能测试前处于令人满意和安全的状态。

同时进行本阶段设备材料的初步调整和检验,为即将进行的功能性能测试铺平道路。

The purpose of pre-testing inspection is to ensure that all components and systems are in a satisfactory and safe condition before performance testing. Preliminary adjustment and inspection of equipment and materials at this stage shall also be carried out at the same time to pave way for the coming functional performance testing.

在进行任何性能测试之前,承包商将确保安装符合所有相关的法定要求和法规。

Before carrying out any performance testing, the Contractor shall ensure that the installation complies with all relevant statutory requirements and regulations.

4.2性能测试

Performance Testing

性能测试的目的是证明设备/装置可以满足230000规范中指定的功能和性能要求。功能性能测试应从单个组件的测试到安装中不同系统的测试进行。

The purpose of performance testing is to demonstrate that the equipment/installation can meet the functional and performance requirements as specified in the Specification 230000. Functional performance test should proceed from the testing of individual components to the testing of different systems in the installation.

所需的特定测试和测试顺序将根据系统的类型和大小,系统数量,施工顺序,与其他设备的接口,与建筑元素的关系以及规格中指示的其他具体要求而有所不同。系统测试可能必须根据工作进度分阶段进行。

The specific tests required and the order of tests will vary depending on the type and size of systems, number of systems, sequence of construction, interface with other installations, relationship with the building elements and other specific requirements as indicated in the specifications. The testing of systems may have to be carried out in stages depending on the progress of work.

必须评估功能性能测试期间发现的任何性能缺陷,以确定原因以及它们是否属于合同义务。在完成必要的纠正措施后,承包商将重复测试。

Any performance deficiencies revealed during the functional performance tests must be evaluated to determine the cause and whether they are part of the contractual obligations.

After completion of the corrective measures, the Contractor shall repeat the tests.

如果由于承包商无法控制的情况而无法完成任何测试,则应将其妥善记录并报告给业主和监理,然后由业主与有关各方联络以解决该情况。承包商应在达到适当的测试环境后立即恢复其测试工作。

If any test cannot be completed because of circumstances that are beyond the control of the Contractor, it shall be properly documented and reported to the Owner, who shall then liaise with the relevant parties to resolve the situation. The Contractor shall resume his testing work immediately upon the attainment of a suitable testing environment.

4.3文件和可交付成果

Documentation and Deliverables

承包商将所有检验和测试结果记录在适当的测试记录表中,并在每项单独测试中注明参考。

All inspection and Testing results will be recorded by the Contractor in the appropriate test record forms, the reference of which is shown against each individual test.

所有测试完成后,将提交测试结果供审查。交接之前,承包商应与业主共同对业主代表所选择的暖通空调系统进行功能测试,以验证其是否符合规范。

Upon completion of all tests, test results shall be submitted for review. Prior to cutover, the Contractor shall perform a function test, jointly with the Owner, of HVAC Systems selected by the Owner representative, to verify conformance to the Specifications.

测试报告将以电子和纸质形式提交。

Test reports shall be submitted in electronic and hard copy.

5 测试及调试仪器

TEST & COMMISSIONING INSTRUMENT

暖通空调系统的现场测试将使用以下工具和设备

The following tools & equipment will be used for testing of HVAC Systems on-site.

5.1工具

Tools

典型的测试设备如下:

5.2测试证书

Test Certificates

开始工作之前,所有校准证书都将随测量和/或测试设备提供。

All calibration certificates will be available with the measuring and or test equipment prior to start work.

6 测试及调试方法

TEST & COMMISSIONING METHODOLOGY

6.1空调通风系统测试

Air Conditioning Ventilation System Test

6.1.1测试前检查

Pre-testing Check

调试工程师将在测试前检查以下项目:

Commissioning engineer will be responsible for checking the following items during pre-testing:

-各固定连接部位应无松动。

There should be no looseness in each fixed connection.

-轴承处有足够的润滑油,加注润滑油的种类和剂量应符合产品技术文件的要求。

There is sufficient lubricating oil at the bearing. The type and dosage of the lubricating oil should meet the requirements of the product technical documents.

-机组内及管道内应清理干净。

The inside of the unit and the pipeline should be cleaned up.

-用手盘动风机叶轮,观察有无卡阻及碰擦现场,再次盘动,检查叶轮动平衡,叶轮两次应停留在不同位置。

Turn the fan impeller by hand, observe if there is any blockage or rubbing on the scene, turn it again, check the balance of the impeller, and the impeller should stay in different positions twice.

-风管调节阀门启闭灵活,定位装置可靠。

Flexible opening and closing of air duct regulating valve, reliable positioning device.

-检测电机绕组对地绝缘电阻应大于0.5M?。

Check the insulation resistance of the motor winding to ground should be over 0.5MΩ. -风阀、风口应全部开启,三通调节阀应调到中间位置,风管内的防火阀应放在开启位置,新风口、一次回风口前的调节阀应开启到最大位置。

The air valve and air vent should be fully opened, the three-way control valve should be adjusted to the middle position, the fire valve in the air duct should be placed in the open position, and the control valve in front of the new air outlet and the primary air return opening should be opened to the maximum position.

-检查新风调节阀、回风调节阀、排风调节阀及防火阀的状态。检查并紧固所有紧固件。

Check the condition of the fresh air control valve, return air control valve, exhaust air control valve and fire damper. Inspect and tighten all fasteners.

-检查过滤器及盘管的清洁状况。

Check the cleanliness of the filters and coils.

-检查管路系统是否畅通。

Check that the piping system is free.

-检查软连接的安装及连接状态。

Check the installation and connection status of the soft connection.

-检查末端的安装及末端风阀是否完全开放。

Check the end installation and the end damper is fully open.

-检查防火阀是否处于完全开放位置。

Check whether the fire damper is in the fully open position.

-风机进、出口处柔性短管连接应严密,无扭曲。

The flexible short pipe connection at the fan inlet and outlet should be tight and free of distortion.

-检查管道系统上阀门,按设计要求确定其状态。

Check the valve on the piping system and determine its condition according to the design requirements.

-盘车无卡阻,并关闭所有人孔口。

There is no jam in the crank, and all the openings are closed.

-检查变风量末端装置的电气控制元器件是否动作灵敏、可靠及工作正常。

Check whether the electrical control components of the VAV box is sensitive, reliable and working properly.

-检查变风量末端装置附件中的通水盘管的性能满足要求。

Check that the performance of the water supply coil in the accessory of the VAV box meets the requirements.

-检查变风量末端装置附件中的过滤器的性能满足要求。

Check that the performance of the filter in the accessory of the VAV box meets the requirements.

-检查变风量末端装置控制单元单体供电测试过程中,信号及反馈应正确,不应有故障显示。

Check that during the single power supply test of the control unit of the VAV box, the signal and feedback should be correct, and there should be no fault display.

6.1.2风管漏风检测

Air Leakage Test

调试工程师将在现场测试及调试以下项目:

Commissioning engineer will be responsible for testing and commissioning the follow items on-site:

-风管组两端的风管端头应封堵严密,并应在一端留有两个测量接口,分别用于连接漏风量测试装置及管内静压测量仪。

The air pipe ends at both ends of the air pipe group should be tightly sealed, and two measurement interfaces should be left at one end, which are used to connect the air leakage test device and the static pressure measuring instrument in the pipe.

-将测试风管组置于测试支架上,使风管处于安装状态,并安装测试仪表和漏风量测试装置。

Place the test air duct set on the test support, make the air duct in the installed state, and install the test instrument and air leakage test device.

-接通电源、启动风机,调整漏风量测试装置节流器或变频调速器,向测试风管内注入风量,缓慢升压,使被测风管压力示值控制在要求测试的压力点上,并基本保持稳定,记录漏风量测试装置进口流量测试管的压力或孔板流量测试管的压差。

Turn on the power, start the fan, adjust the air leakage test device throttle or frequency converter, inject the air volume into the test air pipe, and slowly increase the pressure, so that the measured air pipe pressure indication value is controlled at the required pressure point It is basically stable, and records the pressure of the inlet flow test tube of the air leakage test device or the pressure difference of the orifice flow test tube.

-记录测试数据,计算漏风量;应根据测试风管的面积计算单位面积漏风量;计算允许漏风量;对比允许漏风量判定是否符合要求。

Record the test data to calculate the air leakage; calculate the air leakage per unit area based on the area of the test duct; calculate the allowable air leakage; compare the allowable air leakage to determine whether it meets the requirements.

6.1.3空调机组试运转及调试

HVAC Start-up and Commissioning

以下为本建筑之空调机组列表。

The table hereunder shows AHU for this building.

调试工程师将在现场测试及调试以下项目:

Commissioning engineer will be responsible for testing and commissioning the follow items on-site:

-启动时先“点动”,检查叶轮与外壳有无摩擦和异常声响,风机的旋转方向应于机壳上箭头所示方向一致。

"Jog" first to check if there is any friction or abnormal noise between the impeller and the casing. The rotation direction of the fan should be the same as the direction indicated by the arrow on the casing.

-用电流表测量电动机的启动电流,待风机正常运转后,再测量电动机的运转电流,运转电流值应小于电机额定电流值,如运转电流值超过电机额定电流值,应将总风量调节阀逐渐关小,直至降到额定电流值。

Use a current meter to measure the starting current of the motor. After the fan is running normally, measure the running current of the motor. The running current value should be less than the rated current value of the motor. If the running current value exceeds the rated current value of the motor, the total air volume regulating valve should be closed gradually. Small until it drops to the rated current value.

-额定转速下的试运转应无异常振动与声响,连续试运转时间不应小于2小时。

The test run at rated speed should be free of abnormal vibration and sound, and the continuous test run time should not be less than 2 hours.

6.1.4风机试运转及调试

Fan Start-up and Commissioning

以下为本建筑之风机列表。

The table hereunder shows FANS for this building.

调试工程师将在现场测试及调试以下项目:

Commissioning engineer will be responsible for testing and commissioning the follow items on-site:

-测量离心风机的电机和风机皮带轮、轴尺寸及两轴之间的距离。

Measure centrifugal fan motor and fan pulley, shaft size and distance between two shafts.

-启动时先“点动”,检查电动机转向正确;各部位应无异常现场,当有异常现场时,应立即停机检查,查明原因并消除。

"Jog" first to check that the motor is turning correctly; there should be no abnormal scenes in all parts. When there are abnormal scenes, stop the machine immediately to check the cause and find out the cause.

-用电流表测量电动机的启动电流,待风机正常运行后,再测量电动机的运转电流,运转电流值应小于电机额定电流值。

Measure the starting current of the motor with an ammeter. After the fan runs normally, measure the running current of the motor. The value of the running current should be less than the rated current of the motor.

-额定转速下的试运转应无异常振动与声响,连续试运转时间部应少于2小时。

The test run at rated speed should be free of abnormal vibration and sound, and the continuous test run time should be less than 2 hours.

最新暖通空调施工方案(通用版)

最新暖通空调施工方案(通用版) 目录 一、编制依据 (1) 二、工程概况 (1) 2.1 建筑概况 (1) 三、施工准备及工作计划 (1) 3.1技术准备 (1) 3.2现场准备 (1) 3.3机具准备 (2) 3.4材料准备 (2) 3.5组织机构及人员的配备 (2) 四、通风工程施工工艺 (3) 4.1 镀锌钢板风管的制作 (3) 4.2 风管制作工艺 (5) 4.3 风管加固 (8) 4.4 风管安装 (9) 五、通风空调设备安装 (13) 5.1 材料设备检查 (13) 5.2 安装前的准备工作与安装要求 (13) 5.3 风机安装 (13) 5.4 漏风量测试 (14) 六、采暖系统安装 (14)

6.1材料要求及连接方式 (14) 6.2材料质量要求 (15) 6.3管道连接 (15) 6.4 管道支架制作、安装 (15) 6.5管道安装 (15) 6.6阀门安装 (16) 6.7管道系统试压和清洗 (16) 6.8管道保温 (16) 6.9系统调试 (16) 七、工期保证措施 (17) 八、成品保护 (17) 九、安全文明施工 (18) 一、编制依据 本工程总承包合同;本工程施工图纸;国家、行业相关现行规范、规程;国家相关法律法规;企业质量、安全、环境体系程序文件;***地方相关标准、规程等。 《通风与空调工程施工质量验收规范》(GB50243-2002) 《建筑给排水及采暖工程施工质量验收规范》(GB50242-2002) 《通风与空调工程施工规范》(GB50738-2011) 《建筑安装工程施工及验收规范》(GB50300-2013) 《施工现场临时用电安全技术规范》JGJ46-2005

机电工程系统调试方案

机电工程系统调试方案 作者:吴国强阅读:2364次上传时间:2005-02-02 推荐人:jswgq-55 (已传论文 20 套) 简介:完整的机电系统调试方案,包括组织机构图及岗位职责,调试纪律,交接班制度,通风空调系统,空调水系统,给排水系统,热水系统,电气照明及动力系统调试过程。 关键字:机电调试组织机构图通风空调相关站中站:补水、膨胀及水处理专题 1 机电系统调试组织机构图及岗位职责 调试工作机构图 岗位职责 调试指挥小组职责: 检查调试前的准备工作的落实情况。 签发起动和停车命令。 听取各值班班长的试运转报告,协调各专业间的调试工作。 组织处理调试中的重大问题。 组织落实各项指令及及时反馈信息。 专业负责人的职责:

组织并实施各项起动前的准备。 进行技术交底、安全交底。 检查值班操作人员的操作规程、安全规程的执行情况。 复核运行记录,填写调试记录。 发生异常情况紧急停车。 组织实施检修工作。 调试值班人员职责: 严格执行操作规程和安全规程,认真进行操作。 监视设备运行情况,发现问题及时向专业负责人汇报。 如实、全面、准确、清晰的填写调试值班记录。 在专业负责人的指挥下实施运行中的检修。 2 调试纪律: 服从命令听从指挥。 精神集中、坚守岗位。 严禁违章指挥、严禁违章操作。 3 调试交接班制度: 值班人员提前15分钟进入现场,在专业人员的召集下开好班前会,交班人员必须在交班完毕后方可离去。 交班人员必须详细的介绍运行情况和运行记录,专业负责人除自己交接班外,还需检查专业内其他人员的交接情况。 交班过程中发现设备的故障,交班人员应协助接班人员排除故障。 4 给水系统调试 系统要求

仪表施工(流量计)检修实施方案

仪表施工(流量计)检修实施方案

————————————————————————————————作者:————————————————————————————————日期:

仪表施工检修方案 (流量计) 编制: 审核: 批准: 2016年3月

目录 1.适用范围 2.编制依据 3.施工前应具备的条件 4.施工程序 5.施工组织结构 6.质量要求和技术要 7.质量检查管理措施 8.HSE保证措施

1、适用范围 本方案适用本方案适用宁波**化学工业有限公司仪表设备变送器的安装、检修及调试。工控制系统采用目前工业过程控制主流系统DCS(集散控制系统),实现全装置的监控和连锁控制。 2、编制依据 2.1 GB50093-2002 《自动化仪表工程施工及验收规范》 2.2 HG20137-94 《化学工业工程建设交工技术文件规定》 2.3 GBJ131-90 《自动化仪表安装工程质量检验评定标准》 3、施工前应具备的施工条件 3.1设计图纸、有关技术文件及必要的仪表安装说明书已齐全; 3.2需对检修文件包的工作内容进行检查,熟悉检修工序,不明白或有异议的内容要同文件准备人员进行沟通,并核实备品备件的到货情况 3.3 编制好仪表施工设备材料供应计划; 3.4 仪表施工用场地、工作间、仓库及材料堆放场地已准备完毕; 3.5标准仪表应准备齐全,并具备有效的检定合格证书。 4.施工程序 施工准备→仪表电缆拆除→仪表设备拆除→仪表设备清理检查→仪表校验→仪表设备安装→接线→仪表系统调试→配合工艺开车→交工资料验收 5.施工组织结构

6. 质量要求和技术要求 6.1施工准备 6.1.1熟悉说明书及技术资料,了解仪表设备的安装标准规范及特殊要求。 6.1.2 技术人员应向参加施工的有关人员进行技术交底。 6.2仪表施工的基本要求 6.2.1仪表设备拆装前,应有充分的组织准备,要做到图纸齐全、运输线路清楚、统一指挥、明确分工,确保设备安全、稳妥地安装完毕。 仪 表 技 项 施工队长 材 料 员质 量 员安 全 员施 工 一组 施 工 二 组调 试 组

暖通空调工程施工方案(通用)

目录 一、编制依据 (1) 二、工程概况 (1) 2.1建筑概况 (1) 三、施工准备及工作计划 (1) 3.1技术准备 (1) 3.2现场准备 (1) 3.3机具准备 (2) 3.4材料准备 (2) 3.5组织机构及人员的配备 (2) 四、通风工程施工工艺 (3) 4.1 镀锌钢板风管的制作 (3) 4.2 风管制作工艺 (5) 4.3 风管加固 (8) 4.4 风管安装 (9) 五、通风空调设备安装 (13) 5.1 材料设备检查 (13) 5.2 安装前的准备工作与安装要求 (13) 5.3 风机安装 (13) 5.4 漏风量测试 (14) 六、采暖系统安装 (14) 6.1材料要求及连接方式 (14) 6.2材料质量要求 (15) 6.3管道连接 (15) 6.4 管道支架制作、安装 (15) 6.5管道安装 (15) 6.6阀门安装 (16) 6.7管道系统试压和清洗 (16) 6.8管道保温 (16)

6.9系统调试 (16) 七、工期保证措施 (17) 八、成品保护 (17) 九、安全文明施工 (18)

一、编制依据 本工程总承包合同;本工程施工图纸;国家、行业相关现行规范、规程;国家相关法律法规;企业质量、安全、环境体系程序文件;延安地方相关标准、规程等。 《通风与空调工程施工质量验收规范》(GB50243-2002) 《建筑给排水及采暖工程施工质量验收规范》(GB50242-2002) 《通风与空调工程施工规范》(GB50738-2011) 《建筑安装工程施工及验收规范》(GB50300-2013) 《施工现场临时用电安全技术规范》JGJ46-2005 《国家建筑标准设计图集》08K132 二、工程概况 1、工程名称:延安市新天地商业步行街(西区)工程 2、工程地点:延安新区(北区) 3、建筑面积:50865.60平方米,商业街 4、结构类别:框架结构 5、建设单位:延安市新区投资开发建设有限公司 6、设计单位:清华大学建筑设计研究院有限公司 7、承包范围:采暖系统、通风系统、防排烟系统 三、施工准备及工作计划 3.1技术准备 3.1.1认真熟悉图纸,编制施工方案确定施工方法,配合图纸会审等相关内容做好准备工作。 3.2现场准备 3.2.1根据施工总平面的布置和结合实际情况布置施工现场平面。 3.3机具准备 机具在人员进场之后,施工之前运入现场,按施工平面图布置定位,本工程所有使用的主要机具名称、数量详见下表5:

暖通空调系统调试方案最新版本

暖通空调系统调试方案 一、调试准备 ㈠、调试部署 1、调试小组 建立调试领导小组,以项目经理任组长,项目部专业工程师、各施工单位专业工程师、专业分包负责人、监理工程师、物业公司工程人员、设备供应厂家(冷冻机或锅炉厂家、冷却塔厂家、板换厂家、空调末端厂家、水泵厂家、楼控厂家、配电柜厂家、风机厂家等))技术人员为组员。编制调试小组通讯录,统一调试对讲机通话频道。 2、职责 ⑴项目经理 负责组织调试工作,组织专业工程师编制调试方案和调试计划,协调解决调试过程中各专业间相互配合和出现的问题,监督、检查调试进度。 ⑵项目部专业工程师 专业工程师负责编制空调系统调试方案和调试计划。在项目经理的领导下组织各相关单位实施具体的调试,对参加调试的施工人员进行培训和技术交底。 ⑶各施工单位和专业分包单位 负责本专业的调试,共同完成暖通空调系统的联合试运行。 ⑷设备供应商 设备供应厂家负责所供应设备的技术性能保证。对调试人员进行设备技术性能的培训,指导设备的调试,及时解决试运行过程中出现的技术问题。 ㈡、调试准备 1、技术准备 (1)调试前,调试人员应熟悉空调系统全部设计资料,包括施工图纸、设计说明等,充分领会设计意图,了解各种设计参数、系统工艺流程及空调设备的性能和使用方法等,清楚送、排风系统、冷冻水、采暖水、冷却水及自动调节系统之相互间的关系。 (2)调试前请设备厂家技术人员对调试人员进行培训。 (3)项目工程师对调试人员进行调试方案技术交底(包括安全措施)。 (4)项目工程师、监理、施工单位调试人员、设备厂家技术人员等一起深入现场,检查空调系统工程安装质量和各设备机房、管井土建完成情况,有不合格或不完善的地方,做好记录,限期整改。

最新最全机电系统调试策划方案

机电系统调试方案 一、机电系统调试组织机构图及岗位职责 1.调试工作机构图 2.岗位职责 ⑴调试指挥小组职责: 1)检查调试前的准备工作的落实情况。 2)签发起动和停车命令。 3)听取各值班班长的试运转报告,协调各专业间的调试工作。4)组织处理调试中的重大问题。 5)组织落实各项指令及及时反馈信息。 ⑵专业负责人的职责: 1)组织并实施各项起动前的准备。 2)进行技术交底、安全交底。 3)检查值班操作人员的操作规程、安全规程的执行情况。 4)复核运行记录,填写调试记录。 5)发生异常情况紧急停车。 6)组织实施检修工作。 ⑶调试值班人员职责:

1)严格执行操作规程和安全规程,认真进行操作。 2)监视设备运行情况,发现问题及时向专业负责人汇报。 3)如实、全面、准确、清晰的填写调试值班记录。 4)在专业负责人的指挥下实施运行中的检修。 二、调试纪律: 1.服从命令听从指挥。 2.精神集中、坚守岗位。 3.严禁违章指挥、严禁违章操作。 三、调试交接班制度: 1.值班人员提前15分钟进入现场,在专业人员的召集下开好班前会,交班人员必须在交班完毕后方可离去。 2.交班人员必须详细的介绍运行情况和运行记录,专业负责人除自己交接班外,还需检查专业内其他人员的交接情况。 3.交班过程中发现设备的故障,交班人员应协助接班人员排除故障。 四、给水系统调试 1.系统要求 1)室外给水管道、室内给水管道等,工作介质为液体的管道一般应进行水冲洗,如不能用水冲洗或不能满足清洁要求时,可采用空气进行吹洗,当应采取相应措施。 2)水冲洗的排放管必须接入可靠通畅的排水管网,并保证排泄物的畅通和安全。排放管的截面不应小于被冲洗管截面的60%。 3)冲洗用水采用城市给水管网接入的饮用水。 4)水冲洗应以管内可能达到的最大流量不小于1.5m/s的流速进行。 2.调试方法 1)把进入各用水点的阀门全部关闭严密。 2)把各分支系统上的控制阀门关闭,并把水箱口处阀门关闭严密。 3)由室外给水网给地下室蓄水池供水,并对浮球阀经水位调试调整,确保浮球阀的正常工作。待蓄水池注满水后,检查蓄水池的出水管处是否有渗漏等现象;完毕后由电气专业配合启动水泵,检查给水设备的供水是否正常;待正常后,检查是否有水的渗漏,合格后并做好记录备查。 4)上述步骤调试成功后,关闭所有支系统的阀门后,打开给水主管阀门对主系统进行

仪表系统调试方案

仪表系统调试方案 1 概述 仪表进入系统调试,标志全装置仪表安装基本结束,仪表风到位,仪表接地、DCS接地、DCS本机自调结束,系统调试不受环境干扰。仪表系统调试是自控安装的重要环节,是对全装置仪表在中交前的又一项质量把关和检验。因此,系统调试在组织和管理上一定要严细、慎密、认真,甲乙方配合要默契。 2 系统调试总体说明 1)系统调试是在现场仪表已经过其自身的单体调试,控制室DCS-I/O卡也已经内部系统测试且所有信号传递都已畅通的情况下进行的。 2)系统调试中,所有检测单元都在其检测的工艺参数取样处加摸拟信号,所有控制回路输出都直接至控制网上,即:系统调试覆盖了整个回路的始终。 3)系统调试应使系统测量的精度及输出信号的精度在允许的范围内,并对有报警要求的点检查设定报警的准确性。 4)对调节控制回路,除完成输入、输出的全部调试内容外,应检测PID作用及输出的正反作用” 5)联锁回路:模拟其全部的联锁工艺条件及检查其全部的联锁输出。 6)复杂的调节回路:进行多输入多输出的系统模拟调试,验证结果的正确性。 7)成套设备的随机仪表、分析仪表、PLC内部逻辑等协同制造商代表共同调试。 3 调试方法和步骤 3.1 变送器的测试 先调整好变送器的零点和量程,但零值误差不得超过基本误差的1/2,以缓慢的速度调整压力信号源,依次给出变送器测量范围的0%,50%,l00%,100%,50%,0%视操作站CRT显示对应各点的输出值,计算各点的系统误差。系统误差的最大值应在允许范围之内。

3.2 温度的测试 mV DCS I/O 卡 机 柜 DCS 系 统 柜 操 作 站 电阻箱DCS I/O 卡 机 柜DCS 系 统 柜 操 作 站 3.3 调节阀的校验 由操作站输出模拟信号,依次给出4mA、12mA、20mA、20mA、12mA、4mA检查调节阀动作情况。 操作站DCS 系 统 柜 DCS I/O 卡 机 柜 I/P 转 换 器 调 节 阀 A 3.4 开关球阀的调试

机电安装工程调试方案

阜阳市体育中心综合体育馆 机电安装工程调试方案 1、准备工作 1、1人员准备 以现场项目部为基础,成立调试指挥小组: 组长: 曹凯 组员: 张宏明、张伟、程辉、柯善煜、黄欢、黄伟成、肖书爽、蔡华旗、程平安 调试作业人员:电工6人、管工8人、钳工1人、通风工4人。 1、2现场准备 (1)土建、装饰工程已经完成,场地已清理干净,各设备间,配电房(间 均为正式门、锁。各层、间的防火分隔已经完成。 (2)调试所需的电、水能够正常供应,配电所由专人值班。相关的(非本单位专业安装工程已经完成并具备调试配合状态,相关的设备厂家技术人员已经到场并对其负责部分完成了检查与调试。 (3)调试指挥协调体系已经建立,并能有效运行。 (4)设计图纸与相关技术资料已经备齐,有关设备及系统的性能技术参数已经得到熟悉。 (5)各系统安装工作已经完成,经检查符合相关质量验评标准。(未完成的系统已采取有效的隔断措施) (6)调试所需的通讯工具、机具设备、监视测量装置已准备到位。 (7)调试方案已批准。 2、各专业调试方案 2、1电气调试方案 (1)调试准备

A、业主方需配合事项 供电局保证正式电源送到配电房低压柜并完成相关调试工作以确保低压配电柜送电调试工作能正常进行,所有低压配电柜电气元件有的耐压试验检测报告及产品说明资料。 B、总包方需配合事项 总包需协调现场相关施工单位配合做好成品保护工作,在调试过程中不允许随意进入配电间,严禁调试无关人员触动配电箱。 C、安装方需完成事项 在调试前需完成调试方案并递交监理等单位审核通过。调试前做好人员、机具等的准备工作。保证调试时通讯畅通,确保发生故障时能在最短时间切断电源,并及时处理。 送电调试前需认真检查,确保待调试的供电回路已按图纸及规范要求施工完毕;确保电缆回路编号及配电箱编号正确;确保所有空气开关、及各种开关处于关闭状态;确保所有供电回路电气绝缘经过摇测并符合规范要求。各保护接零及重复接零系统安装完毕,配电箱及设备外壳接地完好,接地电阻符合设计及规范。 在调试前对班组进行详细交底,并由张伟统一指挥协调,定人定岗,操作人应配备绝缘鞋及绝缘手套。准备好调试所需相关仪表。 (2)配电房低压进线柜送电 调试小组检查地下室配电房低压配电柜,保证低压柜内外无各种杂物,确认各开关动作灵活可靠,并各开关处于关闭状态;检查低压柜各出线端子,保证电缆连接牢固可靠;核对低压配电柜上回路编号与供电电缆回路编号,确保其一一对应。检查主楼进线柜与联络柜之间的电气联锁就是否正确,相序就是否一致,防止误操作造成事故。检查合格后方可闭合开关,供电到各低压柜。

暖通工程调试方案详解

xxxxxxxxxxxx项目 通风与空调工程系统调试方案编制人:审核人:批准人: 工程名称: 工程地址: 建设单位: 施工单位: 零年月

一、工程概况 本工程总建筑面积约1万平方米,其中地上四层,建筑总高度22.8m,建筑结构形式为框架结构。具体实施范围包括以下三个系统:空调系统;通风系统;防排烟系统。数据机房楼空调室内负荷为6170KW,新风及办公区域冷负荷为95KW,机房辅助区域(风机盘管系统)的空调冷负荷为106KW。 (1)空调冷热源及空调水系统: ?空调冷源采用离心式冷水机组,制冷站设置3台3517KW(1000RT)冷水机组,按照(2+1)配置。冬季设置板式换热器,环境温度低时采用自然冷 却提供冷量,每台冷冻机配一台换热器,规格大小与冷冻机相匹配;换 热器的配置与冷冻机相同,换热器同冷冻机串联安装,冬季可提供部分 或全部自然冷却冷量,以节省能耗。 ?为确保制冷系统能连续制冷,保证数据中心机房的温度在设计范围之内,设置一个有效容量为248m3的蓄冷罐作为不间断供冷系统,蓄水储冷水 罐内水温设计为12度,可以满足不小于10分钟的全荷载设计供冷量。 ?冷冻水系统共设置2套自动补水排气定压装置(1用1备),采用单罐双泵型自动控制补水,负责对机房及其支持区冷冻水系统进行自动补水。 ?每台冷水机组设置与之配套的冷却塔、板式换热器、冷水一次泵、冷水二次泵。冷冻水供回水温度为12/18℃。冷冻水采用一、二次泵系统,一 次泵定流量、二次泵变流量运行。 ?冷却水循环系统主要供给冷水机组冷凝器循环冷却用水;在冬季亦直接为空调冷水系统板式换热器提供冷却水。本次工程采用冷却塔与冷冻机 一对一的布置方式,每组冷却塔及相应冷却水泵随联动的冷水机组开/ 停;屋面共设置冷却塔三组,要求屋面布置的其他室外机散热设备距离 冷却塔的距离大于3米。本次冷却塔选型原则为按照夏季极端湿球温度 进行选型。冷却塔夏季进水温度38℃,出水温度32℃,设计湿球温度 28.8℃;冬季进水温度15℃,回水温度10℃,设计湿球温度1℃。 ?精密空调机组自带有电动两通调节阀,水源热泵新风机组及水源热泵多联机外机的回水管上均设置电动调节阀回水管上设置电动两通阀(开关 型),确保系统按需供水,保证空调效果,节省运行能耗。

建筑机电安装工程调试方案

建筑机电安装工程调试方案 1 空调调试方案 1).工程概况 本工程大空间空调采用低速单风道全空气系统,集中回风。小空间办公、会议室及标准客房空调采用风机盘管加新风系统。除标准客房新风空调箱设置在二个技术夹层内,通过竖向风管及每层的水平风管送至每各客房间外,其余空调设备均分层设置。地上部分的空调箱(包括新风空调箱)均设干蒸汽加湿装置;地下室、卫生间平时通风,防排烟风机在发生火警时,由消防中心控制该防烟分区的排烟口开启,同时关闭排烟系统与平时通风、空调系统兼用的不需要的排烟风口,并开启风机进行排烟。当烟气温度达280℃时,排烟风管上防火阀关闭,排烟风机停止运行。 本工程通风、空调设计参数如下: (1)室外设计参数 (2)室内设计参数

2)编制依据 (1)《通风与空调工程施工质量验收规范》GB50243-2002 (2)建设单位提供的设计文件、图纸资料。 3)调试目的、要求 在新建的空调系统安装结束,正式投入使用前,需由设计、施工和建设单位联合组成调试小组,对系统进行测试调整,这对于检验设计是否正确、施工是否可靠、设备性能是否合格,都是必不可少的环节,也是施工单位交工前的重要工序。 空调通风系统测定与调整的目的,就是要检测各空调机组送风量和排风、排烟风机、风量是否满足设计要求,并按设计要求调整平衡各个风口的风量,以保证室内换气次数、温度、湿度、噪声、空气流速等满足人体舒适性要求。 检测完毕后,应针对检测中发现的问题提出恰当改进的措施,使系统更完善,从而使空调机组在运行中达到经济和实用的目的。 4)调试内容 根据本工程空调系统特点,通风空调系统的无生产负荷联动试运转后测定和调整包括以下内容: (1)风管漏风量测试 (2)通风机风量、风压及转速的测定 (3)系统风量与风口风量测定与调整 (4)通风机、空调机及风机盘管噪声测定

电气仪表工程施工方案..教学总结

XXX项目消防泵站工程 电气(信)、仪表系统安装及调试 施 工 方 案 编制: 审核: HSE 审核: 日期: 二0一二年七月

1、工程概况: XXX工程电气(信)、仪表工程设计说明书。 2、编制依据 2.1 《电气装置安装工程施工及验收规范》GBJ232-82; 2.2 《电气装置安装工程电气设备交接试验标准》GB50150-91; 2.3 《电气装置安装工程电缆线路施工及验收规范》GB50168-92; 2.4 《电气装置安装工程接地装置施工及验收规范》GB50169-92; 2.5 《电气装置安装工程盘、柜及二次回路施工及验收规范》GB50171-92; 2.6 《自动化仪表工程施工及验收规范》GB50093-2002; 2.3 本工程电气(信)、仪表工程设计图纸及说明; 3、电气、仪表及DCS系统工程施工技术 3.1 电气保护管的预埋要和土建同步进行,避免和减少日后凿墙打洞工作,在电气保护管敷设过程容易发生异物落入,出现堵塞现象,故应用木塞等对管口进行封堵,尤其是在现浇砼板、柱、墙内进行暗敷时,要重点检查管口封堵密封情况,防止在砼浇捣过程,管口振松脱落,致使砼浆流入管道内堵塞管道造成返工。 3.2 电气线路及电气设备内电气连接应紧密。螺栓连接处要加弹簧垫圈,投入运行前要加塞进行检查,达到规定要求后方可投入运行,以防运行中松动、过热、脱落。 3.3 按爆炸和腐蚀环境组织电气施工,遵守相应规程,选用适合环境的设备、材料和施工工艺。 3.4 仪表安装前应按设计位号核对其型号、规格及材质。其外观应完好无损,附件齐全。 3.5 仪表安装前应进行单体试验和校核。 3.6 现场仪表安装时,其位置不得影响工艺操作。显示仪表应安装在便于观察和维修的位置(仪表中心距地面高度宜为1.2m-1.5m)。 3.7 仪表宜安装在远离机械振动、强电磁场、介质腐蚀、高温、潮湿的场所。 3.8 仪表安装时不应敲击及振动安装后应牢固、平正,不承受配管和其它机械外力。 3.9 安装在工艺管道的仪表或测量元件,宜在管道吹扫后试压前安装,仪表标定流向应与被测介质流向一致。仪表或测量元件的法兰轴线应与工艺管线轴线一致,固定时使其受力均匀。 3.10 仪表设备上的接线盒、引入孔的位置不应向上,以避免油、水及灰尘进入盒内,当不可避免时应采取密封措施。 3.11 仪表设备标志牌上的文字及端子编号等应书写或打印正确、清楚。 3.12 仪表设备(盘、箱、柜、台等),严禁用非机械加工方法开孔或切割。 3.13 压力仪表不宜安装在振动较大的设备或管线上。 3.16 浮筒液位计安装前,应检查设备接口的垂直度,浮筒应垂直安装,其垂直度允许偏差

机电设备安装与调试施工方案

m 国2K 利水电第五工程J3有眼公司 SeORFDRO ENGINEERING BUREA U 5 No.S YlHa?nDonc£oi

系统机电设备安装与调试施工方案 1 安装组织及准备工作 1.1 概述本系统安装的主要机电设备包括破碎机、棒磨机、筛分机、洗砂机、脱水筛、胶带机、给料机、电动弧门、水泵、废水处理设备、石粉回收设备、除铁器、金属探测器、汽车衡、电力变压器及配电屏柜、控制设备等,设备台套多达300 台套,种类繁杂,而且会出现交叉作业。 安装以片区为单位同时进行,本系统分粗碎半成品安装组、成品安装组、供水安装组、供电安装组等4 个安装组,每组以车间为单元分小组进行。每个安装组的组长为本组安装质量、进度和安全的第一责任人;每个安装小组的小组长为本小组安装质量、进度和安全的第一责任人;每小组配备兼职技术员、安全员一名,每个安装组配备专职技术员、安全员2?3名,对各小组的设备安 装质量和安全进行监督。 对本系统进口设备的安装,我单位将从我公司调集有丰富安装和使用经验的工人和技术人员,配合厂家技术专家,使进口设备的安装达到一流水平。 在认真做好现场安装工作同时,依据安装进度分步进行单台设备调试和试运转,在系统所有设备安装完毕后,进行系统调试及联动运转,同时按要求对设备做好维护工作。 1.2 机电设备的采购按监理人批准的工艺设计和设备清单进行采购,对业主指定厂家的设备严格在指定厂家采购。所有设备保证满足: (1) 所采购的主要设备仪器是国内外先进技术水平的全新设备; (2) 设备的技术性能指标符合设计图纸、相应的规范和监理人的要求; (3) 设备仪器制造质量优良、性能可靠; (4) 设备、仪表、器材是国内或国际大型企业生产的产品。 1.3 设备的交货验收 所有设备到达施工现场后,我单位和监理人共同对其采购的设备材料进行现场开箱检查,检查项目包括:货物的外观质量、数量、品牌、型号、规格、性能、重量及尺寸等,检查后出具一份验收清单。 对到达施工现场的所有设备,我单位指派专人进行看管并进行必要的防护,对主要的零部件采取专门措施防护,确保到场设备的安全。 1.4 安装前向监理提供的资料

暖通空调调试方案

1. 编制依据与系统原理 1.1编制依据 根据目前施工进展,室外管网系统及各楼栋的暖通空调系统管线测试基本上已施工完毕,吊顶内风口安装、机房内的管线设备接驳及竖向管道保温也正在进行,现已进入试运转及系统测试阶段,编制该调试方案,旨在优质优速的完成暖通空调系统的后期调试任务。 编制该方案的理论依据为: 1.1.1.《通风与空调工程施工及验收规范》(GB50243-97); 1.1. 2.《建筑采暖卫生与煤气工程质量检验评定标准》(GBJ302-88); 1.1.3.《通风与空调工程质量检验评定标准》(GBJ304-88); 1.1.4.《电气装置安装工程电气设备交接试验标准》(GB50150-91); 1.1.5.《电气装置安装工程质量检验评定标准》(GBJ303-88); 1.1. 6.《压缩机、风机、泵安装工程施工及验收规范》(JBJ29-96); 1.1.7.《制冷设备、空气分离设备安装工程施工及验收规范》(JBJ30-96)。 1.2系统原理 本工程制冷机房设于软件开发楼地库层,设有两台约克螺杆式冷水机组,供应7/12度冷冻水,冷却塔设在生活区二层屋顶上,空调热源由锅炉房供给,分别供给软件开发楼、生活楼、动力区等。空调凝

结水各层集中后,排向卫生间或新风机房内地漏。新风由新风机组经风道送至各房间。 软件开发楼的办公、会议、终端机房、测试机房等用房冬夏外区设风机盘管供冷供热;阶梯教室、多功能厅设定风量全空气系统,过度季节采用全新风系统;电话机房、消防控制中心等设有新风系统,并预留独立冷热源的分体空调器电源。在软件楼的防烟楼梯间设正压送风系统。无外窗的内走道设机械排烟系统,风机采用消防电源。 各排烟口设手动和自动开启装置,由消防控制室控制,并与排烟风机联锁。生产楼计算机房专门选用风冷冷媒直接热泵空调机。 本工程的空调水系统为分区两管制,冷热源为四管制,末端为两管制,异程式另在水平干管设置平衡阀。本工程的通风系统完善,室内及走廊间设置导气管以维持压力平衡。软件开发楼地库层的变配电室及设备机房设单独的送排风系统。 2.施工部署及准备工作 2.1人员机构组成 整个系统的调试由周晓钟负责,唐伟配合电气操作,李达对整个系统进行协调,张雪峰对整个系统提供技术支持,史云祥对该系统的质量安全负责,王红星对该系统的文明施工及成品保护负责。项目配备各专业班组中有一名任组长,每天严格按计划执行次日的施工任务。 具体详见“调试人员机构表”。 2.2根据本调试任务的工作量,划分为六个阶段: 2.2.1、准备阶段(包括调试计划、人力分工安排、施工机具仪表、

机电工程调试方案

机电工程联合调试方案 14.1 机电联合调试简述 14.1.1 机电工程联合调试的重要性 按本工程设计功能要求,机电安装工程相对于整个建筑工程而言,具有非常重要的地位,主要体现在以下三点: 1 建筑安全是第一位的; 2 确保本建筑的使用功能; 3 对控制系统的运行要求高。 基于以上三点,机电工程的综合调试显得尤为重要,它是保证各功能正常实现,并相互兼容的必要手段。 14.1.2 对本工程联合调试的理解 联合调试是检验安装工程各分部设计、安装等环节质量的一个重要工序,是检查工程产品质量是否良好的一个重要方法。针对本工程的项目功能,联合调试的重点是低压供配电系统、通风空调系统、消防火灾自动报警及联动系统、智能建筑系统。 1 联合调试的重点 本工程的空调系统的联合调试,使本工程空调系统在智能建筑系统的监测控制下安全有效地运行处相当重要的地位;消防火灾自动报警系统的联合调试也是本工程的重中之重。 2 实施总承包管理与配合 为保证各项系统联合调试安全、顺利地进行,在行使总承包单位各项管理、组织职能的职责前提下,总承包单位本身的配合与服务工作也是总承包单位的重要义务。 14.2 联合调试的总体策划 14.2.1 联合调试各阶段的策划

总承包单位是本工程的施工阶段主要管理者,联合调试工作又是本工程竣工前的关键工序,做好调试工作的策划,是本工程调试工作顺利进展、保证调试质量的前提条件和重要保证。 1 联合调试前总体策划的主要内容 1) 联合调试组织机构的策划; 2) 联合调试实施流程和技术方案的策划与制定; 3) 联合调试开始时间和总体进度计划; 4) 联合调试各阶段的各项保证措施; 5) 与相关方的协调措施; 6) 与第三方检测单位之间的协调措施; 7) 与相关职能部门的协调措施; 8) 与业主、监理、设计等单位的协调与配合措施; 9) 与专业分包、精装等单位的管理、协调与配合措施; 10) 调试过程中可能出现问题的预案的应对措施; 2 联合调试过程中策划的主要内容 1) 对于交叉作业的预见与协调; 2) 多专业、多工种同时作业之间工序协调; 3) 调试过程中出现问题的协调与应对措施; 4) 调试过程中各相关方的协调措施; 3 联合调试完成后策划的主要内容 调试完成后,与业主协调培训与交工验收的程序和计划。 14.2.2 联合调试与检测遵循的主要原则 1 电气工程是其它系统的前提条件,所以先电气系统后其它系统;电气工程先动力后照明;最后调试柴油发电机。

仪表调试方案

仪表调试方案 一、目录 1、单体仪表调校 2、DCS、PLC调试 3、仪表回路调试 4、蝶阀遥控系统调试 二、内容 1、单体仪表调校 1. 1 仪表单校一般规定 A、应按说明书及有关规程进行。 B、调校前均要按仪表规格表(设备表)认真核对仪表的位号、规格型号、特性、尺寸、材质、测量范围、刻度、分度号及计量单位等。 C、所有仪表均要进行外观检查,供电220VAC 的电动仪表均要进行绝缘电阻测试。 D、调校所用的标准仪器必须在鉴定合格期内,标准表基本误差的绝对值不应超过被校表基本误差绝对值的1/3。 E、仪表校验点一般不少于5 点,并应在刻度范围内均匀选取。 F、调校完毕后,要认真填写校验记录,记录要清晰、整洁,并保存好原始记录。 1.2 仪表单体校验项目 1)压力表、温度计、安全阀校验 2)调节阀、SDV阀

A、行程基本误差变差、检验 B、事故全行程时间测试 C、泄流量检查 D、膜头气密性试验 E、阀体强度试验及严密性试验 3)接近开关接点动作检查 4)智能式变送器 A、调试 B、基本误差检验 5)特殊仪表检验及其它 A、现场无法调校的仪表设备(如各种流量计)不进行单体调试。该部分仪表如需调校(标定)则由供货商负责,或者由有关部门负责联系检验单位并送检。 B、随机仪表的单体调校可参考上述同类型的仪表进行。 C、对于未提及到的常规仪表设备的单体调校,可参照上述仪表所作的检验项目进行,不再另行规定检验项目。 1. 3 仪表回路联校 1.3. 1 具备条件 系统回路试验是对系统硬、软件、电缆及现场仪表作全面考核的手段,进行回路试验,必须事先满足下列条件的情况下才能进行。 A、所有与系统控制有关的外部常规仪表、零部件必须经过调试、检查合格。

电气工程系统调试方案修订稿

电气工程系统调试方案内部编号:(YUUT-TBBY-MMUT-URRUY-UOOY-DBUYI-0128)

电气工程系统调试方案 1?、机电系统调试组织机构图及岗位职责 ⑴、调试工作机构图 ⑵、岗位职责 ⑶、调试指挥小组职责: ⑷、检查调试前的准备工作的落实情况。 ⑸、签发起动和停车命令。 ⑹、听取各值班班长的试运转报告,协调各专业间的调试工作。 ⑺、组织处理调试中的重大问题。 ⑻、组织落实各项指令及及时反馈信息。 ⑼、专业负责人的职责: ⑽、组织并实施各项起动前的准备。 ⑾、进行技术交底、安全交底。 ⑿、检查值班操作人员的操作规程、安全规程的执行情况。⒀、复核运行记录,填写调试记录。 ⒁、发生异常情况紧急停车。 ⒂、组织实施检修工作。 ⒃、调试值班人员职责: ⒄、严格执行操作规程和安全规程,认真进行操作。 ⒅、监视设备运行情况,发现问题及时向专业负责人汇报。⒆、如实、全面、准确、清晰的填写调试值班记录。 ⒇、在专业负责人的指挥下实施运行中的检修。

2?、调试纪律: ⑴、服从命令听从指挥。 ⑵、精神集中、坚守岗位。 ⑶、严禁违章指挥、严禁违章操作。 3?、调试交接班制度: ⑴、值班人员提前15分钟进入现场,在专业人员的召集下开好班前会,交班人员必须在交班完毕后方可离去。 ⑵、交班人员必须详细的介绍运行情况和运行记录,专业负责人除自己交接班外,还需检查专业内其他人员的交接情况。 ⑶、交班过程中发现设备的故障,交班人员应协助接班人员排除故障。 4?、电气照明系统调试 ㈠、系统要求 ⑴、电气管线敷设完毕,穿线完毕。 ⑵、各种灯具接线完,各种开关面板接线完。 ⑶、管线经过绝缘电阻测试合格。 ⑷、配电箱安装完毕,且经过绝缘测试合格。 ⑸、桥架、电缆敷设完毕,电缆绝缘测试合格。 ⑹、母线敷设完毕,绝缘测试合格。 ⑺、配电箱、柜安装完毕,绝缘测试合格。 ⑻、各种高低压配电柜安装完毕,测试合格。 ㈡、调试方法 ⑴.先检查各种照明配电柜是否已全部切断电源。

现代暖通空调设备的安装与调试

现代暖通空调设备的安装与调试 发表时间:2016-11-03T10:22:58.733Z 来源:《基层建设》2016年16期作者:郑银湖 [导读] 摘要:暖通空调的应用越来越广泛,但其安装施工过程却较为复杂,施工的不确定性大,安装中经常会出现各种质量问题。只有找到问题所在,对症下药,才能减少甚至避免问题的出现。 身份证号码:44058219840124XXXX 摘要:暖通空调的应用越来越广泛,但其安装施工过程却较为复杂,施工的不确定性大,安装中经常会出现各种质量问题。只有找到问题所在,对症下药,才能减少甚至避免问题的出现。 关键词:现代暖通;空调设备;安装与调试 一、引言 随着国民经济的快速持续发展,作为支柱产业之一的建筑业也得到迅猛发展。而作为建筑业的重要组成部份的暖通空调业,其新产品、新技术、新材料更是层出不穷。暖通空调业发展所遵循的原则,概括起来就是:节能、环保、可持续发展,保证建筑环境的卫生与安全,适应国家的能源结构调整战略,创造不同地域特点的暖通空调发展技术。暖通空调的应用越来越广泛,但其安装施工过程却较为复杂,施工的不确定性大,安装中经常会出现各种质量问题。所以应重视空调的而安装过程,并解决在这过程中出现的问题。 暖通施工是在整个建筑工程的后期进行的,因此就形成了暖通工程的另一个特点―――工期长。对于建设周期长的暖通施工来说,安装管理就显得很有必要。一个良好的安装管理策略可以提高工作效率,可以在最大的程度上节约成本,为施工方和建造方带来双重效益。 二、施工过程中存在的问题及解决方案 1、施工中存在的问题 (1)、未按规划设计施工 暖通空调设备在安装前一定要做好规划,因为暖通空调的整体管路极其复杂,而每一处管道的设计用途也不尽相同,如果事先的规划工作没有做好,就会给工程施工环节,带来极大的困难。所以坚决不能在尚未读懂设计图纸,尚未形成整体施工安装的思路之前进行管道施工作业。如此贸然进行工程施工,会出现一部分管道安装位置不合理等问题,对工程质量产生巨大的影响。 (2)、暖通空调系统设备噪声超标 在暖通空调运行的过程中,噪声一直是困扰用户的一个非常重要的问题。而噪声的来源主要为末端设备出现彼此碰撞进而引发设备噪声,噪声也是暖通空调设备安装过程中一项比较棘手的问题。风机盘技术在经过长时间的发展后,已经较为成熟,因而制品比较符合国家公布的噪声标准。但是在实际中却存在许多不一致的情况。根据厂家向客户提供的参数值来看,现场测试值就已经超过了国家规定的噪声标准。因此要必要做好相应的布局设计,同时需要做好隔音措施。 (3)、空调水循环发生的问题 水循环系统是暖通空调施工中的核心步骤,一旦此环节发生问题,整个空调系统可能都无法正常运行。冷冻水系统管道循环不畅是空调冷冻水系统最常见的问题。其管道循环不好的原因包括以下两点:①空调水系统管道的污物直接造成空调水系统发生堵塞。②管道安装过程中,由于施工协调管理不及时,安装质量无法满足规范要求,造成管内多处气囊形成。 (4)、结露滴水问题 空调系统在调试和运行中会出现结露滴水的现象,出现这一问题的原因是多方多面的,归纳起来主要有:管道安装和保温问题,管道与管件、管道与设备之间连接不严密。造成漏水主要原因有管道安装没有严格遵守操作规程施工。管道、管件材料质量低劣,进场时没有进行认真检查。系统没有严格按规范进行水压试验。 2、解决方案 (1)、严抓施工管理 第一,布局设计是对设备噪音控制的重点,必要时应采取适当的隔音措施。设计中必须标出设备噪音参数要求。空调设备安装之前需做仔细的检查甚至是通电试运行,若发现噪音超过国家标准需立即更换或完善消声措施,以避免问题扩大。第二,对于水循环系统的漏水问题,应该在施工前对管线管路的安装位置合理的布置,对于管线的坡高以及管线的标高准确设计,严格执行安装。最大程度上降低管道气囊的出现概率。并且在气囊不可避免的位置通过一些排气手段,比如设置排气阀等方法。消除气囊所带来的各种问题。第三,要避免条形漏风口的出现,以避免漏风口出现风哨的声音。为防止噪音,还可以在机房内使用对声音有吸附作用的材料,在空调组外使用隔音材料。以及对可能产生振动的设备施加减震措施。第四,穿墙部位冷冻管加设保温保护套管,确保穿墙部位保温层的连续性和严密性。三是加强吊顶封板前,对风机盘管滴水盘等处的杂物清理检查。四是加强对设备滴水盘的保护,特别是吊顶封板前的检查。 (2)、严控施工过程 严格执行项目部的各项施工管理制度,加强项目部内部及与各方面的协调工作。每天组织协调会议,解决施工中的协调问题。对比较复杂的部位,在施工前应组织专门的协调会,使各专业队伍进一步明确施工顺序和责任。 (3)、加强各专业间的配合 建筑工程是多专业之间相互配合完成的,暖通空调设备安装施工更是如此。从施工前期的预留孔洞、预埋管线、设备基础预制和后期的地面、墙面封堵,明沟、暗沟砌筑,地面找平,电源接驳、电气控制装置的设置等。这些配合均需在施工初期专业间就相互沟通、制定配合方案相互配合,为暖通空调工程的安装施工工作做好准备。 三、现代暖通空调的调试 (1)、认真编制调试方案 空调施工管理人员应认真编制空调调试专项方案,针对冷冻水、冷却水的水压试验,系统管道冲洗,冷凝水的坡度调整和满水试验,风管的严密性试验,各子系统的风量调整,噪音的调整,设备单机调试,系统的联动调试都应有详细的论述和切合实际的措施。 (2)、调试过程 通风空调系统的联合试运转调试是重中之重,关系到工程最终使用功能的实现与能源利用效率的高低。空调系统带冷源的正常试运转应大于 8 h,测定和调整的范围主要为空调水系统、空调通风系统。在联合试运转时要具体问题具体分析,如果系统风量达不到设计要求,

自动化仪表单体调试方案设计

实用标准文档
***项目 自动化仪表单体调试方案
编制 Prepared by 审核 Reviewed by 批准 Approved by 版本 Rev. 日期 Date
文案大全

实用标准文档
目录
1 适用范围 2 编制依据 3 工程简述及主要实物量 4 调试人员组织机构 5 调试用仪器和工具 6 仪表设备的单体调校总则 7 施工工序及采用的施工方法 8 质量控制措施 9 仪表调试施工记录
1.适用范围
文案大全

实用标准文档
本方案适用于*****项目的仪表单体调试工作。 2.编制依据 2.1 业主提供的相关图纸、设计说明 2.2 该工程的招标文件 2.3《自动化仪表工程施工及质量验收规范》GB50093-2013 2.4《石油化工仪表工程施工技术规程》SH/T 3521-2007 2.5《石油化工建设工程项目施工过程技术文件规定》SH/T 3543-2007 2.6《石油化工建设工程项目交工技术文件规定》SH/T 3503-2007 3.工程简述及主要实物量 3.1 工程简述
本工程设计范围所有单体内的仪表,涉及仪表种类:压力仪表有现场指示压力表、压 力变送器、差压变送器等;温度仪表包括热电偶、热电阻及一体化温度变送器,温度 开关、双金属温度计等;流量仪表有现场指示流量计及远传流量计,流量变送器等; 物位仪表包括浮筒液位计,差压液位变送器等;执行器包括调节阀、开关阀等。
3.2 主要实物量
序号
名称
单位
数量
备注
1 压力变送器

2 差压变送器

3 一体化温度变送器 套
4 浮筒液位计

5 压力开关

6 温度开关

7 压力表

8 双金属温度计

9 热电偶

10 热电阻

11 调节阀/开关阀

4.调试人员组织机构