冠梁、支撑梁施工方法冠梁、支撑梁施工方法提要:拆除的方法考虑到本工程的环境,不容许采用爆破方式,所以我们将采用人工和小型机械方式分段拆除。
具体做法:先将支撑梁做好分段线不超过2m长冠梁、支撑梁施工方法1深基坑支护方式本工程深基坑支护采用一道钢筋混凝土冠梁及内支撑结构,该支撑体系能够充分发挥混凝土材料的受力特点,具有足够的刚度和变形小的特点。
能够确保基础施工、周边邻近建筑物和地下管网等公共设施的安全。
2支撑的工艺流程及施工顺序第一层土全面挖至支撑垫层标高→垫层底模施工→凿护壁结构锚固筋(格构柱顶清理)→测量弹线、钢筋绑扎→模板安装及固定→防护栏杆预埋铁件→检测沉降钉、轴力监测仪埋设→混凝土浇筑施工→混凝土养护→拆模清理→下层土方开挖。
冠梁、支撑梁施工顺序:冠梁、支撑梁施工随围护结构的钻孔灌注桩施工和立柱桩施工同步进行,浇注长度控制在30m左右,以减少混凝土温度变化引起的收缩裂缝。
冠梁、支撑梁的施工面用小型挖机开槽,灌注桩桩顶用人工凿桩,保留或接长锚固钢筋。
立柱桩中的钢格构架,用人工清理保证锚固高度,经验槽复核后浇注垫层,梁侧模用机制九夹板,采用商品混凝土浇筑。
施工缝预留好钢筋,并用九夹板封堵。
开槽的土方不外运,留作支撑梁回填土和土方车辆在支撑上走行需铺路基箱的架空垫层。
3混凝土冠梁、支撑的施工方案支撑、冠梁体系钢筋、模板施工(1)支撑土底人工清理夯实,进行c15细石混凝土垫层浇筑厚100,细石混凝土随捣随抹平,表面标高用水平仪及时检测找平,使标高满足要求。
(2)测量弹线后,先绑扎钢筋,然后安设和固定模板。
(3)支撑体系钢筋绑扎先绑扎圈梁或冠梁钢筋,然后绑扎支撑钢筋。
支撑主筋按设计要求长度伸进冠梁内,多支撑节点处钢筋要合理交叉,避免影响梁的有效高度。
(4)冠梁与支撑的施工缝按设计要求设置,如设计无要求,且无整体浇捣的可能,则每根梁分3段施工,每施工段长度35~40m,不得随意留置施工缝。
(5)冠梁和支撑的模板采用九夹板制作,用Φ48钢管,扣件Φ14对拉螺栓拉结牢固,作为一个整体的制模体系。
一.工程概况工程名称:***工程工程地点:***建设单位:***房地产开发有限公司设计单位:***建筑设计咨询有限公司监理单位:***建设监理有限公司施工单位:***工程有限公司本工程包含住宅楼1栋、2栋、3栋、4栋、5栋、6栋、7栋,各栋楼±相当于绝对标高,本工程结构类型为框架剪力墙结构。
总建筑面积约万m2,其中地下建筑面积约万m2,地上建筑面积约万m2。
地下室二层。
二.设计要求1.后浇带处所有梁板等混凝土构件钢筋连续布设钢筋要求双层双向拉通布置。
2.后浇带浇筑时间宜滞后45天以上,并采用高一级微膨胀混凝土浇筑,低温入模。
3.微膨胀混凝土要求水中养护14天的限制膨胀率:后浇带≥%,地下室侧壁≥%,顶板楼盖≥%,地下室底板≥%,且后期膨胀性能稳定。
4.施工缝和后浇带宜留设在结构受剪力较小位置,一般设于跨度1/3范围内。
施工要求在地下室底板、侧壁、顶板留设施工缝时均应加止水钢板。
三.后浇带、施工缝做法1.楼(屋)面后浇带构造注:适用于地下室中间层板、地下室顶板、楼面板及屋面板。
2.地下室侧壁后浇带3.地下室底板后浇带构造4.地下室水平施工缝止水带5.地下室-2层与-1层交接处做法四.后浇带施工过程中的质量安全保证措施1.后浇带钢筋质量保证措施后浇带处的钢筋随结构梁板墙钢筋一起绑扎,其施工技术措施与质量保证措施按钢筋工程施工的要求处理。
后浇带梁筋不断开,板筋及墙体水平筋断开。
后浇带钢筋绑扎完成后在钢筋表面刷水泥砂浆保护钢筋不生锈。
2.结构主体混凝土施工过程中的后浇带处理方法在进行结构主体施工时,后浇带部分的模板工程按不设后浇带处理,也就是模板按梁、墙、板正常的构件支模方式来安装。
为保证后浇带在混凝土浇筑过程中不被污染和浇筑,在支模和绑扎钢筋时,采用钢丝网片隔离,同时在后浇带模板面上钻孔或墙底设排浆孔。
在主体混凝土浇筑完成后混凝土终凝前后清理后浇带去的混凝土污染物。
3.后浇带的留置在进主体墙梁板混凝土施工时,采用放置快易收口网留置后浇带,并在墙体后浇带界面处墙体内中竖向焊接固定止水钢板,在地下室底板后浇带界面处的板厚中部焊接固定止水钢板(止水钢板的U形盘盘口朝上)。
冠梁及钢筋混凝土支撑施工5.1施工工艺流程导墙、路面破除及开挖→测量放样→连续墙头部分凿除→场地平整及垫层施工→钢筋制作与安装→模板安装→模板复核→混凝土浇筑→拆模和养护→下一段施工。
5.2施工方法5.2.1导墙、路面破除及开挖①首先进行路面及导墙破除;②沿导墙内侧开挖一条宽2m的沟槽,深度开挖至墙顶标高以下0.5m,便于存放凿除的砼块,随基坑开挖时一起外运;③支撑开挖工艺流程:放线→挖土→修边坡→维护坡面→挖土至坑底面设计标高→基底找平。
④支撑开挖采取分步开挖、分步支护的方法,按设计要求进行开挖。
开挖完毕后,采用小型机具或铲等进行切削清坡,以保证坡面平整并达到设计坡度。
⑤由于砼支撑的跨度大,应在制作时按设计要求预起拱,垫层上应铺设薄膜或油毛毡。
5.2.2测量放样(1)根据设计图纸提供的坐标计算出每道钢筋混凝土支撑中线与冠梁交点处坐标,计算成果经技术负责人复核无误后进行测放,并报监理进行复核。
(2)待基坑内土体开挖至砼支撑底部后,立即将中心线引入坑内,以控制底模及模板施工,确保钢筋混凝土支撑中心线的正确无误。
(3)在冠梁及支撑混凝土浇注前,将其顶面标高放样于模板面上,以控制钢筋混凝土支撑顶面标高。
(4)待钢筋混凝土支撑模板拆除后,检查钢筋混凝土支撑的中心线和平整度、垂直度是否符合设计及规范要求。
5.2.3凿除内导墙和地连墙顶部混凝土1、墙头凿除施工方法施工时应凿除地下连续墙至第一道钢筋砼支撑底标高处,凿除连续墙施工方法如下:将地连墙开挖出来后,测量班对设有测斜管、声测管的墙体及冠梁底标高用红油漆进行标识。
墙头凿除采用风镐进行凿除,墙顶凿除应一次性到位,露出新鲜的混凝土部分,在凿除时应小心谨慎,避免把测斜管或声测管破坏,影响检测。
凿除过程中注意钢筋的保护,严禁将钢筋割断,凿除完成后将钢筋进行调直,然后采用清水将墙顶碴块清理干净。
墙头凿除时严禁用炮机等机械凿除。
若因操作不当造成凿除长度超过设计长度的情况出现,应立即停止凿除,将墙碴块清理干净后重新支5.2.4冠梁及钢筋混凝土支撑钢筋绑扎①冠梁及砼支撑钢筋在钢筋加工厂加工,现场安装。
地下室结构施工缝施工方案一、工程概述本工程为地下室结构施工,其中施工缝的施工是整个地下室工程中的重要环节之一。
地下室施工缝的施工主要包括墙板、顶板、底板的水平施工缝和竖向施工缝。
本方案主要针对地下室结构施工缝的施工进行详细阐述。
二、施工缝处理原则1、施工缝应避开地下室结构中的重要部位,如地下室地板与上部主体结构的交接处,以及地下室内部的重要设施处。
2、施工缝应按照设计要求进行留设,保证其位置、数量、形式、尺寸等符合设计要求。
3、施工缝的处理应遵循“先地下,后地上;先主体,后维护”的原则,确保地下室结构的整体性和稳定性。
4、在处理竖向施工缝时,应采用凸缝形式,并保证凸缝的高度和宽度符合设计要求。
5、在处理水平施工缝时,应采用凹缝形式,并保证凹槽的深度和宽度符合设计要求。
6、施工缝的处理应采用可靠的措施,保证其密封性、防水性、抗渗性等性能符合设计要求。
7、在浇筑混凝土时,应保证混凝土的密实度和平整度,避免出现蜂窝、麻面等现象。
8、在处理施工缝时,应注意安全,避免出现安全事故。
三、墙板水平施工缝处理方案1、墙板水平施工缝应设置在距底板面以上500mm处,并保证其平整度。
2、在处理墙板水平施工缝时,应先清理干净墙板表面,并涂刷一道水泥基渗透结晶型防水涂料,以提高墙板的防水性能。
3、在涂刷水泥基渗透结晶型防水涂料后,应铺设一道遇水膨胀止水条,并采用可靠的措施固定止水条。
4、在浇筑混凝土时,应保证混凝土的密实度和平整度,避免出现蜂窝、麻面等现象。
5、在浇筑混凝土后,应采用可靠的措施对墙板表面进行养护,保证其质量。
四、顶板水平施工缝处理方案1、顶板水平施工缝应设置在距底板面以上500mm处,并保证其平整度。
2、在处理顶板水平施工缝时,应先清理干净顶板表面,并涂刷一道水泥基渗透结晶型防水涂料,以提高顶板的防水性能。
3、在涂刷水泥基渗透结晶型防水涂料后,应铺设一道遇水膨胀止水条,并采用可靠的措施固定止水条。
4、在浇筑混凝土时,应保证混凝土的密实度和平整度,避免出现蜂窝、麻面等现象。
目录第一章编制说明..................................... 错误!未定义书签。
1.1编制依据.................................... 错误!未定义书签。
1.2 适用范围...................................... 错误!未定义书签。
1.3编制原则.................................... 错误!未定义书签。
第二章工程概况...................................... 错误!未定义书签。
第三章施工进度计划ﻩ错误!未定义书签。
3.1 施工进度计划................................. 错误!未定义书签。
3.2 资源配备ﻩ错误!未定义书签。
第四章总体施工方案ﻩ错误!未定义书签。
4.1施工具体安排ﻩ错误!未定义书签。
4.2 施工工艺流程.................................. 错误!未定义书签。
4.3冠梁与钢筋混凝土支撑施工方法ﻩ错误!未定义书签。
4.3.4冠梁及钢筋混凝土支撑钢筋绑扎ﻩ错误!未定义书签。
第五章冠梁及钢筋混凝土支撑施工质量保证措施ﻩ错误!未定义书签。
5.1质量控制标准.................................. 错误!未定义书签。
5.2混凝土支撑测点................................ 错误!未定义书签。
5.3质量保证证措施................................ 错误!未定义书签。
第六章安全文明施工措施. (16)第一章编制说明1.1 编制依据(1)天津地铁1号线东延至国家会展中心项目施工招标文件、施工图纸;(2)《混凝土结构工程施工质量验收规范》(GB50204-2002)(2011年版) (3)《钢筋焊接及验收规程》(JGJ18-2012)(4)《地下铁道工程施工及验收规范》(GB50299-1999 2003年版)(5)《建筑地基基础工程施工质量验收规范》(GB50202-2002)(6)类似工程的施工实践经验。
支撑梁施工缝留置原则和位置好呀,今天我们来聊聊支撑梁施工缝留置的原则和位置。
说白了,这就是在建筑施工中,怎么放置那些缝隙的问题。
听起来有点无聊,不过这可是一门大学问哦。
你想想,支撑梁就像是大楼的脊梁,肩负着整个建筑的重量,没了它可真是寸步难行。
施工缝的设计就像给大楼穿衣服,穿得合不合适可全在这一缝。
先说说施工缝的位置吧。
我们可不能随随便便就选个地方留下缝。
这就好比你吃饭时,吃到一半放下筷子,夹个菜的位置可得想清楚。
缝的位置最好是在受力较小的地方,别让它承受太多压力。
比如说,在支撑梁的中部或是两端的地方,选择在那些弯曲不大的区域,真心不错。
这样一来,不仅能避免承重问题,还能减少将来的维护麻烦。
听着就觉得贴心,对吧?我们得考虑施工缝的数量。
想象一下,做一道菜,放了太多的调料,不好吃就是不好吃。
施工缝也是一样,留得太多,反而让结构变得脆弱,像个小孩在风中摇摇欲坠。
所以,一般情况下,施工缝的数量要控制得当。
大多数情况下,施工缝不宜超过两到三处,这样一来,安全性才能有保障。
让人觉得,这样设计真是高明。
然后,还得提到缝的形状和尺寸。
你说,形状能有什么大不了的,切个方形就完了。
可是你别小看这形状,它可是影响到整个梁的受力情况的。
形状不对,梁就像被打了折,受力分布不均。
为此,我们通常会选择矩形或者L型的施工缝,这样更利于后续的混凝土浇筑和连接,避免那些多余的烦恼。
施工缝留置的原则也要符合一些规范。
不能随便就放到那儿,得遵循设计图纸和相关标准。
像是“有规可循”这句老话,真的是有道理。
这样才能确保建筑的安全性,毕竟我们可不想在住进去后,夜里听到咯吱咯吱的声音,吓得不敢睡觉。
安全第一,生活才会幸福,对吧?施工缝的处理也是一门艺术。
施工缝留下后,后续的处理可不能马虎。
可得确保缝内的清洁,避免脏东西进驻,这样才能让后面的混凝土与前面的完美结合。
就好比你吃个汉堡,里面的生菜跟酱料要搭配得当,才能好吃嘛。
施工缝一旦处理得当,结构强度才能有保障。
厦门万科。
金域华府A—4地块总承包工程施工缝处理方案编制:审核:批准:南京建工集团有限公司2011年月日地下室结构施工缝施工方案一、工程概况厦门·万科金域华府A4地块工程(1#、2#、3#、5#、7#、8#、9#、地下室)由厦门市万科滨海置业有限公司投资兴建,图纸为厦门合道工程设计集团有限公司设计,工程位于厦门市集美区杏东路以北,总建筑面积约为13。
7万平方米.工程地下一层,1#3#5#7#楼地上41层,8#9#楼地上18层,其余建筑为多层,主要建筑用途为住宅、商业及车库。
本工程采用冲孔灌注桩和预制管桩基础,钢筋混凝土平板式筏基厚500mm,。
底板和承台均采用抗渗混凝土强度等级C40,抗渗等级为S8。
整个工程基础底板顶标高统一为黄海高程0.15m。
在主楼与裙房之间设置800mm宽的沉降后浇带.沉降后浇带的封闭时间将在沉降观测结果证明主楼之沉降已趋向稳定后再浇灌.由于本工程地质条件复杂,受桩基础影响,地下室局部不具备结构施工条件,经甲方、监理、设计等单位协商,为工程按计划顺利进行、减少窝工等方面的损失,决定在地下室顶板、底板留设施工缝。
二、施工缝留设方法根据规范及施工现场实际情况,施工缝的位置应设置在结构受剪力较小和便于施工的部位, 柱应留水平缝,梁、板、墙应留垂直缝;单向板,施工缝应留置在平行于板的短边的任何位置;有主次梁的楼板,宜顺着次梁方向浇筑, 施工缝应留置在次梁跨度中间1/3 的范围内;墙上的施工缝应留置在门洞口过梁跨中1/3 范围内,也可留在纵横墙的交接处;楼梯上的施工缝应留在踏步板的1/3 处。
其留设部位详见《地下室底板结构施工缝留设示意图001》及《地下室顶板结构施工缝留设示意图002》;在混凝土浇筑时用钢板网隔离,在混凝土初凝后将钢板网拆除,形成施工缝;施工缝处的钢筋与后浇筑部分的钢筋错开,采用直螺纹接头连接。
三、施工缝处理方法砼终凝后,施工缝在浇筑混凝土前,拆除钢板网,用斩斧或钢杆将表面凿毛,清理松动石子,凿深20~30MM,待二次浇筑砼时,提前用压力水将缝面冲洗干净,边浇边刷素水泥浆一道,以增强咬合力。
地下室施工缝及后浇带施工专项方案一、施工缝的定义和作用1.1施工缝是指为了控制混凝土干缩变形而设置的隔离缝,防止干缩开裂的发生。
1.2施工缝的作用是可以缓解混凝土的干缩应力、降低混凝土的内应力、控制混凝土的变形、提高混凝土结构的整体性能。
二、施工缝的设置要求2.1施工缝的间距应不超过混凝土板高度的30倍。
2.2 施工缝的深度一般为板厚的1/3,但不应小于20mm。
2.3 施工缝的宽度不应小于10mm,可根据结构设计及施工要求适当调整。
三、施工缝的施工方法3.1常用的施工缝包括:(1)板面缝:设置在混凝土地下室板上的缝隙。
(2)柱缝:设置在混凝土柱上的垂直缝隙。
(3)壁面缝:设置在混凝土墙体上的缝隙。
3.2施工缝的施工方法通常有以下几种:(1)震动法:使用震动器在浇筑混凝土时震动,使混凝土流动性好,从而减少干缩裂缝的产生。
(2)分段浇筑法:将大块混凝土分成若干小块进行分段浇筑,有利于干缩应力的释放。
(3)预留缝板法:在浇筑混凝土之前,在需要设置缝隙的位置插入一块预留缝板,使缝隙得以保留。
(4)挠性接头法:将混凝土板和柱子之间设置挠性接头,以吸收板和柱间的变形差异。
四、后浇带的作用和施工要求4.1后浇带是为了提高地下室结构的整体性能而进行的加固措施。
4.2后浇带的设置要求:(1)后浇带的宽度一般不应小于150mm,应根据具体的结构设计确定。
(2)后浇带应设置在地下室板和墙体的连接部位以及板与板之间的交接处。
(3)后浇带的厚度应根据结构设计和施工要求确定,通常不小于板厚的1/3(4)后浇带的混凝土强度应与原混凝土一致,使用相同的材料和施工工艺进行浇注。
五、施工缝和后浇带的施工流程5.1施工缝的施工流程:(1)确定施工缝的位置,按照结构设计要求进行标记。
(2)在混凝土浇筑之前,进行震动或其他方法使混凝土流动性好。
(3)在混凝土还未完全凝固之前,将预留缝板插入到需要设置缝隙的位置。
(4)在混凝土凝固后,拆除预留缝板,修整缝隙边缘,以保证缝隙的整体性和平整度。
英语作文快乐元宵节Happy Lantern Festival!The Lantern Festival is a traditional Chinese holiday celebrated on the fifteenth day of the first lunar month. It marks the end of the Chinese New Year celebrations. On this day, people enjoy eating tangyuan, a traditional Chinese dessert made of glutinous rice balls in sweet syrup.The highlight of the Lantern Festival is the lantern displays. People hang colorful lanterns in their homes, in the streets and in parks. People also carry lanterns in parades and enjoy watching lion dances.The Lantern Festival is a time for family reunions. People get together to enjoy the festive atmosphere and to share their joy with one another.I hope everyone enjoys the Lantern Festival and has a wonderful time!英语作文盼元宵The Lantern Festival falls on the fifteenth day of the first lunar month and it is a traditional Chinese festival.People usually celebrate the Lantern Festival by eating yuanxiao, setting off fireworks and enjoying the beautiful lanterns. On that day, people will hang colorful lanterns in front of their houses andthe whole street is filled with festive atmosphere.This year, I am looking forward to the coming of the Lantern Festival. I can't wait to make yuanxiao with my family and enjoy the beautiful lanterns. I am also looking forward to setting off fireworks and sharing the joy with my family and friends.The Lantern Festival is a time for family reunion and I am sure it will be a memorable one.英语作文元宵观灯The Lantern Festival is an important traditional event in China. On the evening of Lantern Festival, people usually go out to watch the lanterns, guess riddles and eat yuanxiao, a special food for the festival.This year, due to the epidemic, I was not able to go out and celebrate the Lantern Festival with my family and friends. Instead, I stayed at home and watched the live broadcast of the Lantern Festival celebration. The beautiful lanterns lit up the night sky and the riddles were so interesting. I also enjoyed the delicious yuanxiao with my family.Although I could not celebrate the Lantern Festival in person, I still had a great time at home. I was glad that I could still share the joy of the festival with my family. I hope that next year, the epidemic will be over and I can celebrate the Lantern Festival with my family and friends.英语作文元宵节的一天Today is the Lantern Festival!I woke up early in the morning and went out with my parents. The streets were decorated with colorful lanterns. On the way, we tasted the delicious tangyuan. At night, we went to the square to watch the lantern show. There were all kinds of beautiful lanterns in different shapes and sizes. Some of them were shaped like birds, animals and flowers. The most beautiful one was a dragon-shaped lantern. It was so big and colorful that it lit up the whole square.We also played some traditional games, such as guessing lantern riddles, spinning the wheel of fortune, and dragon dance. I was so excited that I almost forgot the time.At the end of the day, I went home with a happy heart. I will never forget this special day.英语作文元宵节灯会The Lantern Festival is a traditional Chinese festival which falls on the fifteenth day of the first month of the lunar calendar. On this day, people often go to the temple fairs and watch the dragon and lion dances.This year, our school held a grand Lantern Festival celebration. In the afternoon, the students and teachers gathered in the playground and lit up the colorful lanterns. The colorful lanterns lit up the sky,making the atmosphere more festive. Then, the students and teachers began to perform the dragon and lion dances. The dragons and lions were so vivid and lifelike that the audience was amazed.After the performance, the teachers and students took part in the lantern riddle guessing game. Everyone was very excited and had a great time. At the end of the celebration, we all enjoyed delicious snacks and watched the fireworks.The Lantern Festival celebration was a great success. It was a memorable moment for everyone.作文元宵节看舞龙The traditional Chinese festival, the Lantern Festival, is coming. On that day, people will go to the square to watch the dragon dance.The dragon dance is very exciting. The dragon is made of colorful silk and paper. It is several meters long and looks like a real dragon. When the dragon is dancing, the dragon dancers will wave their arms and legs, which looks very vivid.The dragon dance is accompanied by drums and gongs. The rhythm of the drums and gongs is fast and powerful. Everyone is clapping and cheering for the dragon.The dragon dance is a traditional Chinese custom. It is said that it can bring good luck and fortune. People are very happy when they watch it.On the Lantern Festival, the dragon dance is a must-see. I hope everyone can enjoy the wonderful performance of the dragon dance.作文元宵乐Tonight is the day of reunion, the Lantern Festival.The night sky is full of stars, and the moon is round and bright. Everywhere is full of joy and laughter. The streets and alleys are decorated with colorful lanterns. People are lighting up the lanterns and enjoying the beautiful scenery.In the evening, I went out with my family and saw many people carrying lanterns and singing folk songs. We also took part in the fun. We bought a big lantern and wrote our wishes on it. Then we lit it up and sent it up to the sky, hoping that our wishes would come true.The Lantern Festival is a special day for us to get together, share joy and happiness, and express our love for each other. May the Lantern Festival bring us more joy and happiness!作文自己做元宵Lantern Festival is an important traditional Chinese festival, usually celebrated on the 15th day of the first month of the lunar year. On that day, people usually eat yuanxiao, a kind of sweet dumpling made of glutinous rice flour with different kinds of fillings inside.During the Lantern Festival, people also go out to enjoy the night view, admire the beautiful lanterns in different shapes and sizes. Besides, there are some activities like guessing lantern riddles and dragon dance. All these activities make the festival more enjoyable and meaningful.Lantern Festival is not only a traditional festival, but also a time for family reunion. On this special day, people get together to celebrate and share the joy of the festival.I love the Lantern Festival. Every year, I look forward to it. I enjoy eating delicious yuanxiao and watching the beautiful lanterns. It is a great time to bond with my family and friends.。
冠梁、支撑梁施工方法冠梁、支撑梁施工方法提要:拆除的方法考虑到本工程的环境,不容许采用爆破方式,所以我们将采用人工和小型机械方式分段拆除。
具体做法:先将支撑梁做好分段线不超过2m长冠梁、支撑梁施工方法1 深基坑支护方式本工程深基坑支护采用一道钢筋混凝土冠梁及内支撑结构,该支撑体系能够充分发挥混凝土材料的受力特点,具有足够的刚度和变形小的特点。
能够确保基础施工、周边邻近建筑物和地下管网等公共设施的安全。
2 支撑的工艺流程及施工顺序第一层土全面挖至支撑垫层标高-垫层底模施工-凿护壁结构锚固筋(格构柱顶清理)-测量弹线、钢筋绑扎一模板安装及固定-防护栏杆预埋铁件一检测沉降钉、轴力监测仪埋设一混凝土浇筑施工-混凝土养护-拆模清理一下层土方开挖。
冠梁、支撑梁施工顺序:冠梁、支撑梁施工随围护结构的钻孔灌注桩施工和立柱桩施工同步进行,浇注长度控制在30m左右,以减少混凝土温度变化引起的收缩裂缝。
冠梁、支撑梁的施工面用小型挖机开槽,灌注桩桩顶用人工凿桩,保留或接长锚固钢筋。
立柱桩中的钢格构架,用人工清理保证锚固高度,经验槽复核后浇注垫层,梁侧模用机制九夹板,采用商品混凝土浇筑。
施工缝预留好钢筋,并用九夹板封堵。
开槽的土方不外运,留作支撑梁回填土和土方车辆在支撑上走行需铺路基箱的架空垫层。
3混凝土冠梁、支撑的施工方案支撑、冠梁体系钢筋、模板施工(1) 支撑土底人工清理夯实,进行C15细石混凝土垫层浇筑厚100,细石混凝土随捣随抹平,表面标高用水平仪及时检测找平,使标高满足要求。
(2) 测量弹线后、先绑扎钢筋,然后安设和固定模板。
(3) 支撑体系钢筋绑扎先绑扎圈梁或冠梁钢筋,然后绑扎支撑钢筋。
支撑主筋按设计要求长度伸进冠梁内,多支撑节点处钢筋要合理交叉,避免影响梁的有效高度。
(4) 冠梁与支撑的施工缝按设计要求设置,如设计无要求,且无整体浇捣的可能,则每根梁分3段施工,每施工段长度35〜40m,不得随意留置施工缝。
. .
温州新城大厦工程
基坑支撑梁及冠梁
施
工
缝
处
理
方
案
编制人:
审核人:
批准人:
***********建设集团有限公司
项厦目部大城江南京宁建一五年九月二十二0 日教育资料word . .
目录
一、工程概
况 .......................................................
..1
二、编制依
据 .......................................................
..1
三、施工准
备 .......................................................
..1
四、施工工
艺 .......................................................
..1
㈠基坑支撑梁施工缝处
理 (2)
㈡冠梁施工缝处
理 (3)
五、质量保证措
施 (4)
六、安全保护措
施 (5)
七、文明施工措
施 (5)
教育资料word
. .
教育资料word
. .
一、工程概况
温州新城大厦位于温州市中心公园路西北侧,建筑总高度为54.3m,地上12层,地下2层,主体为框架-剪力墙结构,总建筑面积为25700.7m2。
○○1012个流水段进行施工,第一施工段为~本工程基坑支撑梁、冠梁主要分○○○○○○○○○○L轴~H101~10//A~轴段。
在安装G~/H~轴段,第二施工段为L1○H轴南侧延伸1/3跨(即段模板和钢筋绑扎时,模板和钢筋往3000mm),如下图所示。
支撑梁施工缝留设平面图
二、编制依据
1、温州新城大厦工程施工图纸
2、《混凝土结构工程施工质量验收规范》GB50204-2002(2011版);
3、《混凝土泵送施工技术规程》JGJ/T10-2011
三、施工准备
1、人员准备:组织4名工人进行施工缝留设,安排施工员监督施工缝的留设处理工作。
2、材料准备: 10mm网眼钢丝网,施工线,22#扎线等。
3、机械工具准备:砂轮机1名,钢丝剪2把,手提焊机1台。
手锤2个,扎勾4个。
四、施工工艺
第一施工段的支撑梁、冠梁钢筋安装完成后,立即组织人员进行施工缝钢丝网的安装及处理。
具体施工步骤如下:
教育资料word
. .
㈠基坑支撑梁施工缝处理
○○H轴为基准往南量出3轴往南3m处,用钢卷尺以1、施工缝留设在米,H然后在钢筋面上弹出墨线。
2、在基坑支撑梁下方设置长700mm,宽300mm,高300mm水泥条,防止浇筑混凝土时水泥浆流失。
3、将预先裁剪好的钢丝网用铁丝绑扎在施工缝部位,确保绑扎牢固。
4、用B12钢筋间隔300mm水平焊接在支撑梁箍筋上,将2根B12钢筋竖向放置并与水平钢筋焊接形成整体,防止浇筑混凝土时钢丝网胀模。
5、将50×100mm木方置于支撑梁上方,用铁丝固定。
6、浇筑支撑梁混凝土。
7、混凝土浇筑完成后,随即派专人对钢丝网外侧漏出或撒落的砼碴及时清理干净,变形的钢筋及时调直复位。
8、施工缝的处理和砼浇筑:在浇筑第二施工段支撑梁混凝土前,清理施工缝部位的钢丝网、砼碴,用斩斧将表面凿毛并清理松动石子,待二次浇筑砼时,提前
用压力水将缝面清洗干净,刷素水泥浆一道,增强咬合力。
教育资料word
. .
冠梁施工缝处理㈡○○米,3H轴为基准往南量出1、施工缝留设在处,用钢卷尺以H轴往南3m 然后在钢筋面上弹出墨线。
水泥条,防止浇筑混凝土
300mm300mm,高2、在冠梁下方设置长1200mm,宽时水泥浆流失。
3、将预先裁剪好的钢丝网用铁丝绑扎在施工缝部位,确保绑扎牢固。
钢筋竖向放置B12水平焊接在冠梁箍筋上,将2根钢筋间隔4、用B12250mm 并与水平钢筋焊接形成整体,防止浇筑混凝土时钢丝网胀模。
木方置于冠梁上方,将钢丝网压紧,用铁丝绑扎牢固。
×5、用50100mm 6、浇筑冠梁混凝土。
、混凝土浇筑完成后,随即派专人对钢丝网外侧漏出或撒落的砼碴及时清理7教育资料word . .
干净,变形的钢筋及时调直复位。
8、施工缝的处理和砼浇筑:在浇筑第二施工段冠梁混凝土前,清理施工缝部位的钢丝网、砼碴,用斩斧将表面凿毛并清理松动石子,待二次浇筑砼时,提前用
压力水将缝面清洗干净,刷素水泥浆一道,增强咬合力。
五、质量保证措施、指定专职责任人,由管理钢筋专业施工员负责该项工作的落实,并进行施1 工全过程的监督。
施工缝的钢丝网安装完成后,制度,项目部的质量检查小组,“三检”2、竖持及时对钢丝进行检查,发现问题及时纠正,自检合格并交由监理验收后才交由混凝土班组浇筑施工。
、加强混凝土施工过程的监控,务必振捣密实,混凝土表面待收水后进行刮3 平和打磨反砂。
、施工缝部位,必须严格按上述主要施工工艺和步骤进行操作,并全过程加4教育资料word . .
强监督实施,务必达到质量要求。
5、对有关的施工管理人员和实际操作人员进行施工方案交底以及施工技术、操
作要领和注意事项交底,务使各有关施工人员掌握施工技术,达到质量目的,避免造成不必要的返工。
6、基坑支撑梁、冠梁施工正值夏季,做好混凝土养护工作,做到7天内经常保持砼表面湿润,新浇砼要达到1.2Mpa后才能在砼面进行操作,新浇筑的支撑梁、冠梁不得堆放材料、不得上人行走。
六、安全保护措施
1、工人上班时要正确戴好安全帽,不得穿拖鞋或赤脚。
2、钢丝网要按所量度的尺寸切割好后才运送至施工现场安装,不宜在施工现场
切割。
3、进行电焊时,电缆线要架空,操作人员要按规定配备防护用具,所焊部位的
模板要淋湿,清理干净周边杂物,并办理动火作业审批手续,落实专人监管,才准动火烧焊,现场要配备灭火器材,烧焊完成后监护人要检查周围是否留有火种,确认无火险隐患后才能离开,动火作业监护人要认真检查并作动火记录。
4、小型工具和短钢筋等材料要用工具袋或胶桶装好,不得放在基坑临边等危险地方,不得上下抛掷物料。
4、交叉作业时,要相互协作,做好相互保护措施,以免发生碰撞引起误伤。
七、文明施工措施
1、专人负责维护和整改,文明施工直接负责人带领杂工班,专项负责施工现场的材料堆放、杂物的清理同时施工人员要积极配合搞好现场的文明施工。
2、所有施工作业人员必须做到服从领导,听指挥,不得盲干,发扬团结协作教育资料word
. .
精神,不得因一点小事引起争执吵架。
3、每班组下班前要清理干净施工现场,务必做到工完场清,将所剩的材料归类
到原来存放位置或仓库,机械和工具归仓。
所施工部位的杂物要清理干净,钢筋如有变形和跑位的要及时调整和复位。
教育资料word。