斜塔空间扭索斜拉桥塔吊布置及附着设计
- 格式:pdf
- 大小:388.76 KB
- 文档页数:2
一、编制原则 ........................................................................................................................................................ - 1 -二、编制依据 ........................................................................................................................................................ - 1 -三、工程概况 ........................................................................................................................................................ - 1 -四、周边环境 ........................................................................................................................................................ - 2 -五、施工内容 ........................................................................................................................................................ - 3 -六、劳力、施工机具、配合机具......................................................................................................................... - 3 -七、施工方案 ........................................................................................................................................................ - 4 -1、桩基施工方案 (4)2、承台施工方案 (5)3、塔柱施工方案 (6)⑴塔吊布置................................................................................................................................................ - 6 -⑵施工电梯................................................................................................................................................ - 6 -⑶地泵管道布置 ........................................................................................................................................ - 7 -4、索塔施工 (13)5、边墩墩身施工方案 (16)6、主梁施工方案 (16)八、危险源及防范措施 ...................................................................................................................................... - 17 -1、主要危险源 (17)2、危险性分析 (18)3、危险源防护措施 (20)九、安全管理措施 .............................................................................................................................................. - 22 -一)、施工安全管理组织制度 . (22)1、安全生产组织管理................................................................................................................................ - 22 -2、安全生产岗位职责................................................................................................................................ - 22 -3、安全教育培训措施................................................................................................................................ - 32 -二)、施工安全技术措施 (35)1、爬模施工安全技术措施........................................................................................................................ - 35 -2、塔吊安全技术措施................................................................................................................................ - 37 -3、施工电梯安全操作技术措施................................................................................................................ - 38 -4、斜拉索施工安全技术措施.................................................................................................................... - 38 -5、脚手架安全技术措施............................................................................................................................ - 41 -6、测量作业安全技术措施........................................................................................................................ - 41 -7、施工用电、机械设备的安全管理措施 ................................................................................................ - 42 -1)施工用电的安全管理措施.................................................................................................................... - 42 -2)机械设备的安全管理措施.................................................................................................................... - 44 -8、劳保用品管理........................................................................................................................................ - 44 -9、防火及夜间施工的安全管理措施 ........................................................................................................ - 44 -10、具体保障制度...................................................................................................................................... - 45 -11、例会制度.............................................................................................................................................. - 45 -12、安全技术交底制度.............................................................................................................................. - 45 -13、安全生产责任制.................................................................................................................................. - 46 -14、安全教育培训制度.............................................................................................................................. - 46 -15、安全生产检查制度.............................................................................................................................. - 49 -三)、安全生产须知及操作规程 .............................................................................................................. - 51 -1、安全文明生产须知................................................................................................................................ - 51 -2、使用防护用品须知................................................................................................................................ - 52 -3、塔吊安全操作规程................................................................................................................................ - 53 -4、钢筋工安全操作规程............................................................................................................................ - 54 -5、汽车起重机安全操作规程.................................................................................................................... - 54 -6、吊装作业安全须知................................................................................................................................ - 55 -8、高空作业安全操作规程........................................................................................................................ - 56 -9、拆除作业安全须知................................................................................................................................ - 57 -10、机械操作规程...................................................................................................................................... - 58 -11、电焊、氧割操作规程.......................................................................................................................... - 58 -12、混凝土输送泵操作规程...................................................................................................................... - 60 -13、安全用电操作规程.............................................................................................................................. - 61 -14、搅拌站安全操作规程.......................................................................................................................... - 62 -15、车辆运输安全操作规程...................................................................................................................... - 62 -16、机动车辆驾驶员安全注意事项.......................................................................................................... - 63 -17、模板工操作规程.................................................................................................................................. - 64 -18、电梯安全操作规程.............................................................................................................................. - 65 -19、警卫人员注意事项.............................................................................................................................. - 66 -xxxx主桥安全专项施工方案一、编制原则安全生产是党和国家的一贯方针和基本国策,是保护劳动者的安全和健康,促进社会生产力发展的基本保证,为保障从事公路工程施工生产人员的安全,预防事故的发生,有效指导现场安全施工,特编写本专项安全防护措施。
可编辑修改精选全文完整版一、工程概况:东海大桥V标主航道桥为双塔单面扇形双索斜拉桥,主塔为花瓶式。
主跨420米,全桥长度(73+132+420+132+73)830米。
塔高150米,桥面宽33米,主梁为钢箱梁结构,全桥标准段共24×4段,非标段10段,中跨合拢段1段,标准段长8米。
斜拉索采用塑包平行钢丝束,钢丝采用Φ7镀锌钢丝,护套采用双层,内层为黑色高密度聚乙烯,外层为白色高密度聚乙烯。
斜拉索共有192根,单索最短为NMC1索,索长59.3米,重2.168吨。
最长索为NSC24索,索长227.606米,重19.4吨。
本桥塔上锚固为单塔双孔式,锚固端支座分为两种:齿块锚固端和钢锚梁锚固端。
斜拉索锚具均采用张拉端冷铸锚,锚具按钢丝丝数编排分别为121Φ7,139Φ7,163Φ7,187Φ7,211Φ7,223Φ7,241Φ7,265Φ7,283Φ7,共九类。
二、施工流程安装钢锚梁→软牵引系统与索头连接→挂索→展索→桥面索头锚固→软牵引张拉完成斜拉索安装→张拉→成桥后索力调整1、钢锚梁安装(一)、概况东海大桥V标斜拉桥主塔塔上锚固为单塔双孔式,锚固端支座分为两种,即齿块锚固端和钢锚梁锚固端,本桥钢锚梁总数为64件,种类为16种,施工时,每一对钢锚梁安装完成后,挂上相应的斜拉索,自下而上依次进行。
(二)、施工流程分类→清理→起吊→安装→焊接1)、分类未起吊前,应按图纸要求将16种钢锚梁的规格与塔内支座索道孔号对号入座,挂上标牌,避免错装。
2)、清理找出需要安装的锚固梁后对其进行清理,清除表面油污浮锈,以保证焊接时的质量。
3)、起吊挂索前,先安装对应的锚固梁,梁自重在0.6吨,塔吊起吊后从塔顶的人孔放进塔柱内,然后转换给塔顶5吨卷扬机,由卷扬机吊到相应的牛腿上。
4)、安装钢锚梁放置在牛腿上后,利用撬杠或手拉葫芦调整钢锚梁位置,使塔上索道孔与钢锚梁上锚座孔同心,然后点焊固定位置,验收合格后,按设计要求进行焊接。
斜拉桥斜拉索施工方案1、概况该桥斜拉索采用填充型环氧涂层钢绞线斜拉索,塔上设置张拉端,梁下为锚固端;每侧主塔设12 对斜拉索,全桥共24 对斜拉索,其规格为15-27 、15-31 、15-34 、15-37 、15-43 、15-55 、15-61 共 7 种,斜拉索采用平行钢绞线斜拉索体系。
斜拉索由固定端锚具、过渡段、自由段、HDPE护套管、张拉端锚具及索夹、减振器等构成。
2、斜拉索施工工艺本工程主梁采用前支点挂篮悬臂现浇施工,斜拉索挂索方式与支架现浇和后支点挂篮施工有所不同,需在挂篮上设置索力转换装置。
其基本工艺流程详见附《表 3 施工工艺框图》。
3、斜拉索施工准备(1)、施工前准备工作施工前准备工作包括:施工平台、施工机具的准备;施工人员的工作分配;斜拉索锚具的组装和安装; HDPE外套管的焊接等。
①、施工平台准备斜拉索挂索施工前,在主塔和箱梁处设置施工平台,以方便施工人员操作。
主塔施工处在塔内、外均设置施工平台,箱梁处施工平台设置在挂篮上。
施工平台的搭设满足施工要求,并采取适当的安全措施,确保人员和设备的安全可靠。
②、施工机具准备正式施工前,所有施工机具就位。
张拉用千斤顶、油泵和传感器经过有资质的第三方进行配套标定。
因本工程斜拉索规格较大,采用机械穿索方式进行挂索施工,双塔双索面同时施工时,主要施工设备清单如下。
序号设备名称设备规格数量用途1 HDPE管材热熔焊接机SHD3502 台HDPE外套管接长焊接用2 单孔千斤顶及配套油泵SM22-200 5 套钢绞线单根张拉用3 单孔振弦式压力传感器JMZX-3103 5 台钢绞线索力监测用4 穿心式千斤顶及配套油1500T 2 台斜拉索整体调索用泵5 卷扬机5T 4 台钢绞线穿索用6 张拉反力架15-85 和 15-91 4 套钢绞线单根张拉用7 紧索器15-91 2 套斜拉索紧索用8 放线架自制 4 台钢绞线单根穿索放线用9 其它辅助设备斜拉索张拉、附件安装用③、施工人员分配为有效安排斜拉索施工的各环节,统一协调指挥,斜拉索施工前,需进行人员的工作分配。
独柱斜塔空间扭面背索斜拉桥的索塔施工摘要:介绍了在独柱斜塔空间扭面背索斜拉桥施工中,由于采取了合理的施工工艺,选取了合适的施工设备,确保了大桥主塔施工顺利进行。
关键词:独柱斜塔、斜拉桥,索塔,施工1、工程概况主桥上构为独柱斜塔空间扭面背索斜拉桥,墩、塔、梁固结,跨径组成为96m+220m。
其中边跨主梁为96m预应力混凝土边箱梁,主跨为220m钢箱梁,桥塔采用独柱斜塔,预应力混凝土箱梁伸过桥塔10.5m,通过1.5m钢混结合段与钢箱梁连接。
斜拉索间距混凝土箱梁侧为4.21m,钢箱梁侧为12m,边跨混凝土箱梁侧为双索面,主跨钢箱梁侧为准单索面。
其中钢箱梁长209.5m,混凝土箱梁长106.5m(含塔梁固结区)。
桥型布置见图1。
主塔全高133.147m。
塔身顺桥向偏离铅垂面8°,倾向岸侧。
主塔采用空心断面,因塔、梁固结,在固结区设7.5m厚的实心段。
上、中塔柱间设厚为1.5m 的混凝土隔板,提供底部钢锚箱的支撑平台,完成上、中塔柱截面的过渡。
主塔上塔柱内设有14节钢锚箱,钢锚箱与塔柱混凝土组成组合结构。
图1、主桥桥型布置图2、主要施工设备2.1塔吊因钢锚箱吊装需要,塔柱施工需配备一台6500KN·m塔吊。
塔吊高130米,主要承担索塔钢锚箱的吊装与斜拉索的挂设工作,为增强塔吊的稳定性,共设置3道附着。
附着采用桁架结构体系。
塔吊基础布置在已浇筑的混凝土箱梁上。
箱梁下设4根φ820×10mm钢管支撑于承台上。
2.2电梯由于塔柱的构造特殊性,两个挂索面无法安装电梯,其余两个面是斜面也无法安装,所以将电梯安装在塔吊上。
电梯选用SCQ100/100单笼型。
电梯与塔柱之间设通道,电梯通过附着固定于塔吊标准节上。
3、索塔施工支架及液压爬模体系索塔总高度为137.147m,根据索塔的结构特点,共分成30节段,标准段高度4.04m。
塔柱节段划分及爬模安装见图4所示。
施工顺序见图5.中塔柱和上塔柱采用液压爬模施工,共24段。
斜拉桥有哪些方案施工1. 引言斜拉桥是一种特殊的桥梁结构,通过利用斜向拉索来支撑主体桥面的一种桥梁形式。
斜拉桥在城市桥梁建设中具有独特的优势,因为它既能跨越较大的跨度,又能保持桥梁的结构简单和美观。
斜拉桥的设计和施工是一个复杂而严谨的过程,本文将介绍一些斜拉桥的方案施工。
2. 方案一:单塔单索斜拉桥单塔单索斜拉桥是最简单的斜拉桥形式之一。
它只有一座塔和一组斜向拉索。
施工开始时,首先建造桥面和塔体结构。
然后,在塔顶设置起重设备,利用起重设备将钢索吊装到预定位置。
接下来,拉索固定在桥面和塔体结构上。
最后,进行验收和调试,确保斜拉桥的安全和完整。
3. 方案二:双塔多索斜拉桥双塔多索斜拉桥是一种较为复杂的斜拉桥形式。
它由两座塔和多组斜向拉索组成。
施工过程与单塔单索斜拉桥类似,但需要注意的是需要进行更多的索力计算和结构分析。
在施工过程中,通常需要使用更大的起重设备和更先进的技术,确保桥梁的稳定性和安全性。
4. 方案三:混合结构斜拉桥混合结构斜拉桥是将斜拉桥与其他桥梁结构形式相结合的一种方案。
例如,可以将钢结构的斜拉桥与混凝土梁相结合,形成一种新的混合结构。
施工过程中,首先建造钢结构的斜拉桥部分和混凝土梁部分。
然后通过焊接或螺栓连接两者,形成稳定的整体结构。
最后,进行验收和调试,确保斜拉桥的安全和稳定。
5. 方案四:斜拉桥的索杆制作斜拉桥的索杆是连接桥面与塔体的重要组成部分。
施工过程中,通常需要特殊设备来制作索杆,如钢绞线预应力工序,通过应用预应力技术,将多根钢绞线缠绕在一起形成一根较粗的成型钢绞线,确保索杆具备足够的强度和稳定性。
索杆制作完成后,再通过吊装设备将索杆安装到预定位置,并与桥面和塔体进行连接。
6. 方案五:斜拉桥的索力计算与调整斜拉桥的索力计算与调整是确保桥梁运行安全的重要步骤。
施工过程中,需要通过专业软件进行索力的计算和分析,确保各索杆的受力均衡。
在施工完成后,还需要定期进行索力的调整和检查,以应对外部荷载和环境变化的影响,保持斜拉桥的结构安全和稳定。