第9节 计划评审方法和关键路径法
- 格式:ppt
- 大小:688.00 KB
- 文档页数:44
进度管理工程的关键路径法和计划评审下载提示:该文档是本店铺精心编制而成的,希望大家下载后,能够帮助大家解决实际问题。
文档下载后可定制修改,请根据实际需要进行调整和使用,谢谢!本店铺为大家提供各种类型的实用资料,如教育随笔、日记赏析、句子摘抄、古诗大全、经典美文、话题作文、工作总结、词语解析、文案摘录、其他资料等等,想了解不同资料格式和写法,敬请关注!Download tips: This document is carefully compiled by this editor. I hope that after you download it, it can help you solve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you! In addition, this shop provides you with various types of practical materials, such as educational essays, diary appreciation, sentence excerpts, ancient poems, classic articles, topic composition, work summary, word parsing, copy excerpts, other materials and so on, want to know different data formats and writing methods, please pay attention!摘要进度管理在工程项目中至关重要,它涉及到项目的时间安排、资源分配和任务优先级等方面。
第七章计划评审方法和关键路径法计划评审方法(program evaluation and review technique,简写为PERT)和关键路线法(critical path method,简写为CPM)是网络分析的一个组成部分,广泛应用于系统分析和计划的目标管理。
计划评审方法广泛应用于建筑施工和新产品的研制计划、计算机系统的安装调试、军事指挥及各种大型复杂工程的控制管理。
§1.PERT网络图1-l PERT网络图的一些基本概念l.作业指任何消耗时间或资源的行动,如新产品设计中的初步设计、技术设计、工装制造等。
2.事件标志作业的开始或结束,本身不消耗时间或资源,或相对作业讲,消耗量可以小得忽略不计。
某个事件的实现,标志着在它前面各项作业(紧前作业)的结束,又标志着在它之后的各项作业(紧后作业)的开始。
PERT网络图中,事件通常用圆圈表示,作业用箭线表示。
起点事件终点事件(i,j)最初事件最终事件3.路线指PERT网络图中,从最初事件到最终事件的由各项作业连贯组成的一条路。
图中从最初事件到最终事件可以有不同的路,路的长度是指完成该路上的各项作业持续时间的长度和。
各项作业累计时间最长的那条路,称为关键路线,它决定完成网络图上所有作业需要的最短时间。
1-2 建立PERT网络图的准则和注意事项1.绘制PERT网络图时,一般从左到右,从上到下。
事件的编号箭头处必须大于箭尾处。
2.两个事件之间只能画一条箭线,表示一项作业。
对具有相同开始和结束事件的两项以上作业,要引进虚事件和虚作业。
图中,④是虚事件,(4,5)是虚作业,用虚箭线表示。
3.各项作业之间的关系及它们在PERT网络图上的表达方式如下:(1)作业a结束后可以开始b和c(2)作业c在a和b均结束后才能开始(3)a、b两项作业均结束后可以开始c和d(4)作业c在a结束后即可进行,但作业d必须同时在a和b 结束后才能开始4.PERT网络图中不允许出现回路5.为了方便计算和做到美观清晰,PERT网络图中应通过调整布局,尽量避免箭线之间的交叉。