隧道洞口塌方原因
- 格式:doc
- 大小:23.00 KB
- 文档页数:3
隧道洞口坍塌原因分析及处理措施摘要:重庆市石柱县至黔江区高速公路千担坡隧道左洞长439米,右洞长354米,地质情况较复杂,且洞口Ⅴ级围岩浅埋偏压,隧道在开挖过程中山体失稳,出现了进口及洞身浅埋段坍塌情况。
本文以千担坡隧道为背景,针对隧道洞口浅埋偏压及地质不稳等情况出现洞口边坡失稳、隧道坍塌等,提出原因分析和处理措施。
并通过现场施工证明措施可行、有效,从而为解决隧道类似问题提供相应参考。
关键词:隧道坍塌原因分析处理措施可行有效Cause Analysis and treatment measures of tunnel entrance collapseHe jianjun(Third Engineering Co., Ltd., China Railway 20th Bureau Group, Chongqing 400000)Abstract: Qiandanpo Tunnel on the expressway from Shizhu County to Qianjiang District in Chongqing is 439 meters long in the left hole, and 354 meters in the right hole. The geological situation is more complex, and the shallow buried bias pressure at the entrance of the tunnel. During the excavation process, the mountain stability is reduced, and the entrance and the shallow buried section of the tunnel body are unstable and collapsed. In this paper, based on qiandan Po tunnel as the background, the cause analysis and treatment measures are put forward in view of the slope instability and tunnel collapse occurring in the tunnel entrance under the conditions of shallow buried bias pressure and geological instability. Through the field construction, it is proved that the measures are feasible andeffective, so as to provide the corresponding reference for solvingthe similar problems in tunnel.Key words: tunnel collapse cause analysis treatment measures feasible and effective1引言隧道施工中浅埋偏压及地质复杂洞口开挖经常会因为地质不稳、防护措施不到位、爆破支护不及时等情况的影响,造成隧道洞口坍塌、边坡失稳,甚至隧道冒顶,从而造成隧道进洞风险高、危害施工人员安全、工期延误和财产损失。
隧道塌方情况汇报怎么写
隧道塌方情况汇报。
根据最新的调查和统计,我们对隧道塌方情况进行了全面的汇报,以下是具体情况:
一、塌方地点,塌方事件发生在XX隧道XX段,具体位置为XX处。
二、塌方时间,塌方事件发生于XX年XX月XX日,具体时间为XX时XX 分。
三、塌方原因,经过初步调查,隧道塌方的原因主要是由于长期的地质变化和地下水位变化所致,同时也可能受到了外部因素的影响。
四、塌方规模,隧道塌方造成了XX米长、XX米宽、XX米深的塌方洞口,导致隧道交通中断。
五、人员伤亡情况,目前没有收到人员伤亡的报告,但因为塌方事件导致了交通中断,可能会对周边居民和车辆造成一定的影响。
六、应急处理措施,针对隧道塌方事件,我们已经立即启动了应急预案,组织相关人员进行现场处置,同时通知了相关部门和单位,协调做好交通疏导和安全防护工作。
七、后续工作安排,我们将继续加强现场监测和处置工作,同时加强与相关部门的沟通和协调,全力做好隧道塌方事件的应对和处理工作,确保人员安全和交通畅通。
以上是对隧道塌方情况的汇报,我们将继续关注事件进展,做好隧道塌方事件的处理和善后工作。
希望各位单位和部门能够给予支持和配合,共同努力,保障隧道安全和交通畅通。
铁路隧道施工安全事故案例及因素分析一、铁路隧道施工安全事故类型及案例(一)、复杂岩溶隧道突水、突泥。
1、2023年1月21日,宜万铁路马鹿箐隧道出口段平导开挖至DK255+978时发生突水、突泥,突水总量约18万方,在抢险抽水时又多次发生突水。
马鹿箐隧道全长7879m,最大埋深约660m,隧道自进口至出口为连续15.3‰上坡。
在线路左侧30m预留二线位置设立贯通平导,平导全长7850m。
隧道穿越地层中灰岩地层为7408m,占隧道总长的94%,隧道区域漏斗、落水洞、暗河十分普遍,岩溶强烈发育,管道岩溶水系极为复杂。
这次事故除多人逃生外,导致10人死亡,1人失踪。
2、2023年8月5日凌晨1:00时左右,宜万铁路野三关隧道I线斜井向进口方向DK124+602掌子面右侧下部发生突水、突泥,总突水量约15万方,突泥量5.4万方。
斜井工区Ⅰ线距掌子面约220米填满淤泥和石块,其他地段淤泥厚1~4米不等。
野三关隧道Ⅰ线全长13846米,隧道最大埋深695米,设计为人字坡。
Ⅰ线左侧30m设立Ⅱ线。
隧道穿越石马坝背斜及二溪河向斜,发育有5条暗河及管道流。
突水后,5个掌子面人员受困,共计52人被困。
43人获救,其中1人医治无效死亡。
9人中有2人在隧道内死亡,7人失踪。
(二)、软弱围岩隧道塌(坍)方1、2023年4月30日15时30分太中银铁路吴堡隧道3#斜井掌子面左侧拱脚部位发生坍方, 坍方量约8立方米,导致当场死亡4人,1人受轻伤。
2、2023年8月6日18点30分左右,石太客专南庄隧道出口DIK151+603掌子面处上导坑开挖刚完毕,在准备架设拱架过程中,上导坑DIK151+603~610段已完毕的初期支护忽然发生整体坍塌。
导致1人死亡,1名失踪。
(三)、隧道掌子面后方塌方1、2023年6月6日10时20分,大理至丽江铁路下河村2#隧道DK11+195处发生局部坍方,致使正在进行施工作业的一台挖掘机和一名司机被困,经紧急抢救,于当天16时58分将被困司机救出。
隧道地震破坏的主要形式及影响因素分析皇 民1,2,刘马群1,王安华3,郭廷喜4(1.河南工程学院土木工程系,河南郑州451191;2.西南交通大学土木工程学院,四川成都610031;3.陕西省机械施工公司路桥公司,陕西西安710032;4.陕西煤化建设(集团)有限公司,陕西西安710021)摘 要:随着我国交通基础设施的飞速发展,大量的铁路、公路隧道以及城市地铁相继修建。
然而,国内外现有抗震规范中关于地下洞室等地下结构的条文都十分简略,难以适应高烈度地震区地下洞室的建设发展。
在对以往隧道震害调查的基础上,分析隧道震害破坏的主要形式,并总结影响隧道震害的主要因素,对当前隧道抗减震设计具有一定的指导意义。
关键词:隧道;震害;破坏形式;影响因素中图分类号:U458 文献标识码:A 文章编号:100825696(2010)0120060203The R esearch of Tunnel E arthqu ake Dam age Forms and the R easonsHUAN G Min 1,2,L IU Ma 2qun 1,WAN G An 2hua 3,GUO Ting 2xi 4(1.Henan Institute of Engineering ,Department of Civil Engineering ,Zhengzhou 451191,China ;2.School of Civil Engineer 2ing ,Southwest Jiaotong University ,Chengdu 610031,China ;3.Highway Bridge Company of Shanxi Mechanical Construction Company ,Xi ′an 710032,China ;4.Shanxi Coal Chemical Construction Group Corporation ,Xi ′an 710021,China )Abstract :Wit h t he rapid develop ment of Chinese transportation infrast ruct ure ,many railways ,highways and city subway t unnels have been built.However ,existing seismic norms abo ut underground t unnels and ot her underground st ruct ures of t he p rovisions are too briefly at home and abroad ,which cannot adapt to t he develop ment of underground caverns at t he high intensity eart hquake zone const ruction.Based on t he research of t unnel eart hquake damage ,t his paper analyzes t he main forms of t unnel damage ,and summari 2zes t he reasons of t unnel damage ,which have important inst ructing role for t unnel aseismic design.K ey w ords :t unnel ;eart hquake damage ;forms of damage ;reasons of damage收稿日期:2009206222基金项目:国家自然科学基金资助项目(50878187);国家自然科学主任基金(50848020)作者简介:皇 民(1975-),男,讲师,博士研究生,研究方向:隧道地下工程抗减震分析. 1995年以前,抗震工程学者曾指出:关于地下结构,虽然迄今为止尚无严重震害事例,但从地下结构受震破坏的经验来看,可以设想这类结构今后仍有可能出现震害,设计时对此应有必要的充分准备。
隧道塌方的原因及防治摘要:随着我国交通建设的快速发展,隧道数量不断增加,隧道施工遇到的不良地质问题越来越多。
如何避免或减少隧道坍方的发生,以及在坍方发生后如何迅速有效地进行处理也越发引起关注。
本文从不良地质、设计及施工等方面分析了隧道塌方的原因,从初期预防与后期治理两方面论述了处理隧道塌方的方案,并提出了具体的安全保证措施,可为类似工程提供参考。
关键词:隧道塌方成因分析防治1、概述隧道属于地下工程,地下工程的典型特点是地质条件存在不确定性。
在施工过程中岩石既是施工中的开挖对象,同时又是支护对象,岩石在开挖后,原有的岩体结构和受力平衡被破坏,岩体在自重的用下,应力重新分布,构成新的受力平衡体系,极易发生塌方等地质灾害[1][2]。
不仅给隧道施工带来巨大困难,且延误工期,耗费资金,并成为未来隧道出现病害的主要根源。
因此准确掌握地质情况,充分了解围岩的性质和围岩的自稳能力,以采取合理有效的开挖方法和支护措施,在隧道施工中十分必要。
2、隧道塌方的原因分析隧道塌方由多种因素共同诱发,为揭示塌方事故原因的规律性,采用数理统计的方法对已辨识出的风险因素作进一步分析[3]。
根据风险因素辨识结果,按照风险来源首先将风险因素归结为自然因素、人为因素2大类,见图1。
对其在事故中出现的频率进行统计。
据统计表明,约96%的事故伴随有各种不良地质,67%的事故伴随有水的影响,78%的事故中含有人为因素的影响。
另外有统计表明,与地质相关的风险因素中:围岩破碎软弱地层、结构面产状不利出现频率较高;与水相关的风险因素中:地下水发育、连续降雨降雪出现频率较高。
由上述统计结果可知,地质因素是塌方事故的主要内在因素,人为因素的影响是事故的重要诱发因素。
图1隧道塌方影响因素2.1地质条件原因由于地质条件的复杂多变,地下工程难免会通过褶皱构造、断层、节理裂隙发育地带产生塌方;由于围岩本身不稳定而导致结构松散,节理面有泥质物及岩屑充填;由于支护的不及时而暴露时间过长,会导致围岩风化严重;或因通过断层,突然遇到较高水压富水洞段,地下水向洞室内漏出,淘空了断层构造带中破碎岩体和充填物时,以及由于岩层产状不利或因岩爆等诸多地质原因而产生不同程度的塌方。
隧道塌方的原因及处理方法隧道塌方是指隧道内部结构或土石体发生变形或崩塌的现象。
这种事故可能导致严重的人员伤亡和财产损失。
隧道塌方的原因可以是多方面的,以下是一些常见的原因及相应的处理方法。
1. 地质问题:地质构造异常、地震、岩层松散等因素都可能导致隧道塌方。
在设计和建设隧道时,需要进行详细的地质勘察和工程地质评价,采取相应的支护措施,如加固岩体、安装钢支撑等。
2. 水问题:地下水渗漏和涌水是导致隧道塌方的重要原因之一。
在施工过程中,需要进行有效的排水措施,如设置排水管道、加固涵洞等。
此外,定期检查和维修隧道内的排水设施也是必要的。
3. 施工质量问题:不合理的施工方法、材料质量问题、施工操作不当等都可能导致隧道结构失稳。
因此,建设者需要按照相关规范和标准进行施工,并进行质量监控和验收。
4. 自然灾害:如洪水、地震、泥石流等自然灾害的发生也可能引发隧道塌方。
建设者应该在设计和施工过程中充分考虑这些灾害的影响,并采取相应的防护措施,如设置防洪闸门、加固洞口等。
处理隧道塌方的方法主要包括以下几个方面:1. 应急处置:一旦发生隧道塌方,需要立即采取应急措施,确保人员的安全撤离,并通知相关部门进行抢险救援工作。
2. 修复和加固:在处理隧道塌方后,需要对受损的结构进行修复和加固工作。
这包括清理堆积物、修复支撑结构、加固岩体等。
3. 安全检测:隧道塌方后,需要进行全面的安全检测,确保其余部分的结构安全稳定。
这包括使用仪器设备进行地质勘察、结构测试等。
4. 预防措施:为了避免隧道塌方事故的发生,建设者应在设计和施工阶段采取预防措施。
这包括进行充分的地质勘察、合理的设计、严格的施工管理等。
综上所述,隧道塌方是一种严重的事故,可能导致严重的后果。
因此,在设计、建设和运行阶段都需要采取相应的措施来预防和处理隧道塌方的可能性,以确保隧道的安全稳定运行。
高速公路隧道施工塌方原因分析及控制措施发布时间:2022-07-26T04:03:47.219Z 来源:《新型城镇化》2022年15期作者:魏维[导读] 本文简单介绍了隧道坍塌的主要类型以及产生机制,在此基础上分析了坍塌产生的因素并给出了常用预防措施和处治对策。
四川公路桥梁建设集团有限公司公路三分公司四川双流 610200摘要:由于地质条件的复杂,在高速公路隧洞施工过程中坍塌现象也时有发生,而坍塌问题一直是隧洞施工中经常出现的施工事故和工程质量通病,如果及时合理的进行防治工作不但可以保证工程施工安全,还可以保证工期并节约建筑投资。
本文简单介绍了隧道坍塌的主要类型以及产生机制,在此基础上分析了坍塌产生的因素并给出了常用预防措施和处治对策。
关键词:高速公路;隧道坍塌;机理;成因;控制措施高速公路隧道的挖掘施工过程中,坍塌已经成为了一个比较常见的事件,会给隧道施工人员带来很大的影响,包括耽误工期、产生严重的机械损毁,甚至危及到工作人员的安全。
目前,中国国内外不少在建的和已有的隧道均有过坍塌现象。
防止坍塌的产生、坍塌产生后的处理工作已成为隧道工程建设的关键所在。
隧洞工程建设中产生坍塌的因素是多种多样的,既有地质自然条件的因素又有为工程建设方式、建筑质量的因素。
所以,防坍、治塌工作已成为隧洞工程建设的主要问题。
一、高速公路隧道塌方的原因分析1.1地质因素高速公路隧道建设是一个典型的地下工程,很容易受地貌状况的限制,同时由于人们无法充分判断工程中建设区的地貌特征,从而很容易在出现恶劣地貌区的时候发生事故,所以人们一定要更加多的重视恶劣地貌区的建设与施工。
而经过对各类坍塌事件的调查人们也发现,由于土壤可以直接导致坍塌增加,因此大约有百分之四十五的坍塌来自土壤的压力。
同时由于水也可以导致围岩结构的抗拉强度与正应力状况产生变化,因为孔隙水压强变化大,使得较小结构表面的有效正应力也会因此而减少,但是假如围岩内部还存在较软结构面,则充填材料就会在水的引导下流走或者使夹层材料变为液态,上述情况就可以削弱岩块面结构的抗剪力强度。
隧道洞口塌方原因
在地质不良的地段修筑隧道,常会遇到洞顶围岩下榻、侧壁滑动,甚至冒顶等严重事故,这些现象在施工中称为塌方。
塌方威胁人身安全、使施工延误工期、围岩更不稳定。
那么隧道洞口塌方的原因有哪些?一起来看一看吧。
隧道洞口塌方原因
1不良地质及水文地质条件
(1)隧道穿过断层及其破碎带,或在薄层岩体的小曲褶、错动发育地段;通过各种堆积体;在软弱结构面发育或泥质充填物过多地段。
(2)隧道穿越地层覆盖过薄地段。
(3)水是造成塌方的重要原因之一。
2隧道设计考虑不周
(1)隧道选定位置时,地质调查不细,未能作详细的分析,或未能查明可能坍方的因素,没有绕开可以绕避的不良地质地段。
(2)缺乏详细的的地质及水文地质资料,引起施工指导或施工方案的失误。
3施工方法和措施不当
(1)施工方法与地质条件不相适应;地质条件发生变化,没有及时改变施工方法;工序间距安排不当;施工支护不及时,支撑架立不合要求,或抽换不当“先拆后支”;地层暴露过久,引起围岩松动、
风化、导致塌方。
(2)喷锚支护不及时,喷射混凝土的质量、厚度不符合要求。
(3)新奥法施工的隧道,没有按规定进行量测,或信息反馈不及时,决策失误、措施不力。
(4)围岩爆破用药量过多,因震动引起坍塌。
(5)对危石检查不重视、不及时,处理危石措施不当,引起岩层坍塌。
如果你想了解更多有关隧道塌方的原因,请关注。