■ 本试题为交大培训PMP 全真模拟试题1(PMBOK 第四版)特别提醒请注意:PMP 考前模拟试题,仅为并仅提供考生考前模拟测试用;■ 正式PMP 认证考试时间为四个小时;■ 正式PMP 认证考试题量和题型为200个单选题(四个选项);■ 正式PMP 认证考试语言为中英文对照,题意以英文为准;■ 正式PMP 认证考试格式以下列第一、二题格式为准1. In response to the new regulation about treatment of toxic wastes, you propose a project to make new policies as a PM expert of a toxic waste treatment company.The proposal reveals the importance of which item below?A. Taking legal requirements as a basis of initiating projectsB. Looking for mew and effective methodsC. Insisting to behave under legal requirements and ethic standardsD. Time limitation of projects1. 你是一家处理毒废物公司的项目管理专家,为了响应环保机构颁布的有关有毒废物处理的新规定,你建议启动一个项目来编写有毒物质的新处理指南。
这个建议显示了以下哪一点的重要性?A. 将法律要求作为项目启动的基础B. 不断寻求新的和有效的方法C. 坚持按法律要求和道德标准行事D. 项目必须完成的时间范围2. This tool and technique of Monitor and Control Risk is applied to examine and document the effectiveness or risk response in dealing with identified risks and their root cause, as well as the effectiveness of the risk management process.What is it?A. Risk reassessmentB. Project change requestsC. Project risk auditD. Workaround2. 这是一个监控风险的工具方法,它被用以检查并记录风险应对措施在处理已识别风险及其根源方面的有效性。
这是什么工具?A. 风险再评估B. 项目变更请求C. 项目风险审计D. 权变措施3. You’re working on an internal service project and are in the beginning of the Planningprocesses. You noticed that specific staff members were named as project team members during your review of the project charter.Which of the following does this question describe?A. Resource availabilityB. Pre-assignmentC. Staffing management planD. Virtual teams3. 你管理一个内部服务项目并处于计划过程中,你注意到在你审阅项目章程时发现某些员工已经被指定为项目团队成员。
这个问题说明了:A. 资源可用性B. 预分派C. 人员配备管理计划D. 虚拟团队4. The risk management plan accomplishes all of the following except:A. It defines the methodology to risk management on the project.B. It describes the risk categories.C. It defines the roles and responsibilities of the risk management team.D. It addresses responses to individual risks and how they will be carried outproject.theduring4. 风险管理计划进行以下各项,但不包括:A. 定义项目风险管理的方法论B. 描述风险类别C. 定义风险管理团队的角色职责D. 处理单个风险的应对以及在项目中如何实施5. You are using the interviewing technique of the Perform Quantitative Risk Analysis process.The probability distribution you intend to use is triangular distribution.All of the following statements are true regarding this question except:A. Interviewing techniques are used to quantify the probability and impact ofthe risks on project objectives.B. The information gathered depends on the type of probability distributionused.C. The triangular distribution typically uses symmetrical discrete distribution.D. Triangular distributions rely on relative likelihood to quantify risks.5. 你在实施风险定量分析过程使用访谈技术,你打算使用的概率分布是三角分布。
下面哪一个说法是错误的?A. 访谈技术应用于项目目标风险的概率和影响的量化B. 收集的信息取决于所选用的概率分布类型C. 三角分布典型的使用对称的非连续性概率分布D. 三角分布依靠相对概率来量化风险6. If EV = 114, PV = 120, and AC = 103, what are CPI and SPI, respectively?A. 1.1 and .95B. 1.2 and 1.05C. 1.05 and 1.2D. .95 and 1.16. 如果EV = 114, PV = 120, AC = 103,那么CPI和SPI分别是多少?A. 1.1 和.95B. 1.2 和1.05C. 1.05 和1.2D. 0.95 和1.17. Your company is very excited to work on a major mew project. Although the contract is notyet signed, your management wants you to go ahead and begin to staff the project.What should you do?A. Wait until the last minute to do soB. Ask the customer for a letter of intentC. Explain to management that this would not be a good idea at this pointD. Only start to collect resumes and not committee any funds7. 承担一个重要的新项目使你的公司非常兴奋。
尽管合同还没有签订,但你的管理层却让你往下进行并开始为项目配置人员。
你应该怎么做?A. 等待,直到最后时刻再这样做B. 向客户索要一份意向书C. 向管理层解释在此时这样做不合适D. 只开始收集个人简历并且不负责任何资金8. These two processes in the Controlling process group are performed in parallel to assurecorrectness and acceptance of the work. Which are they?A. Perform Quality Assurance and Verify ScopeB. Perform Quality Assurance and Control ScopeC. Perform Quality Control and Verify ScopeD. Perform Quality Control and Control Scope8. 在控制过程中有两个过程同步进行以保证工作的正确性和验收,这两个过程分别是:A. 实施质量保证和核实范围B. 实施质量保证和控制范围C. 实施质量控制和核实范围D. 实施质量控制和控制范围9. All of the following statements are true regarding the time constraints of imposed dates andkey events except:A. Imposed dates and key events constraints are inputs to integrated changeprocess.controlB. Imposed dates apply to activities that must start no later than or finish nolater than a specific date.C. The key events time constraint applies to the completion of deliverables bythe requested date of a stakeholder.D. Requested completion dates often become expected dates and thereforepose a time constraint.9. 关于时间约束中的强制日期和关键事件,那个说法是错误的?A. 强制日期和关键事件是整体变更控制过程的输入B. 强制日期应用于其开始或完成日期不得迟于某一指定日期的那些活动C. 关键事件的时间约束是指干系人所要求的完工活动的期限D. 请求的完工日期经常成为预期的完工日期,因此成为时间约束10. You are asked to perform a feasibility study to determine the best project to run. The project’sinitial investment is $29,000. Alternative A’s cash flows are $14,000 for year 1 and $19,000 for year 2. Alternative B’s cash inflows are $21,000 for year 1 and $20,000 for year 2.Alternative C’s cash inflows are $15,000 for year 1 and $20,000 for year 2. Assume a 10 percent cost of capital. Which project should you recommend based on the NPV of the three alternatives?A. Alternative AB. Alternative BC. Alternative CD. None of the above10. 你被要求执行一个可行性分析来决定最佳项目。