王圪堵水库左坝肩下游护坡反滤设计王红;许晓【摘要】针对王圪堵左坝肩下游坡坡脚出现冒水现象,通过已有观测资料及绕坝渗流分析确定原有工程措施作用较明显,为了确保左坝肩岸坡和坡脚不发生渗透破环,从而保证王圪堵水库左坝肩下游坡安全,进行反虑设计。
%On the basis of the analysis on grain size distribution of fine sand and silty fine sand in the engineering area of the pro‐tected soil ,the filtration is designed ,ensuring the safety of downstream slope protection on left dam abutment of Wanggedu reservoir .【期刊名称】《杨凌职业技术学院学报》【年(卷),期】2014(000)002【总页数】3页(P37-39)【关键词】冒水;细沙;粉细砂;反滤【作者】王红;许晓【作者单位】陕西省水利电力勘测设计研究院,陕西西安 710001;陕西省水利电力勘测设计研究院,陕西西安 710001【正文语种】中文【中图分类】TV2231 工程概况王圪堵水库位于陕西省榆林市横山县境内黄河一级支流无定河中游,是一座以供水、拦沙为主,兼顾灌溉等综合利用的Ⅱ等大(2)型水利枢纽工程。
水库总库容3.89亿m3,坝后电站装机3.75 MW。
王圪堵水库枢纽工程由碾压均质土坝、泄洪排沙洞、溢洪道、放水洞和坝后电站五部分组成。
均质土坝坝顶高程1 054 m,最大坝高46.0 m,坝长950 m,坝顶宽度8.0 m,大坝上游坝坡坡比1∶3.0,在高程1 024 m处设一级马道,马道宽2 m。
下游坝坡坡比1∶2.5,在高程1 030 m处设一级马道,马道宽2 m。
左岸段和河床段采用混凝土防渗墙和帷幕灌浆作为垂直防渗体截断强透水层,右岸段采用截水槽和帷幕灌浆作为垂直防渗体截断强透水层,坝后设置水平排水带和排水棱体,形成上防下排的防渗体系。
王圪堵水库工作桥桥墩抗震设计计算简析张斌(陕西省水利电力勘测设计研究院陕西西安 710001)摘要:地震是地球内部构造运动的产物,是一种自然现象,地震给人类社会带来的灾难,造成不同程度的人身伤亡和经济损失。
为了减轻或避免这种损失,本文以王圪堵水库工作桥桥墩为例,分析了地震时多自由度弹性体系的地震反应分析基本理论和方法。
供同类型的设计研究参考。
关键词:多自由度、底部剪力法、抗侧移刚度、地震影响系数α1工程概况王圪堵水库位于榆林市横山县城关镇西北12km。
工程区地震动峰值加速度a=0.039g,地震特征周期T g=0.35s,场地类别为第Ⅱ类,设计地震分组为第一组,设防烈度采用6度。
工作桥桥墩设计选用C30钢筋砼圆形重力式桥墩。
桥墩身高度为21m,墩顶直径为D1.26m,墩底为D2.1m,墩身侧坡50:12分析与计算2.1基本假定(1)桥墩砼为均质、连续、各项同性的弹性材料;(2)不计入地基与结构相互作用的影响;2.2计算简图根据计算要求,桥墩身高21m,可将桥墩以3m分为一段,共七段。
由于最低部一段与基础刚接,所以底部一段的质量应集中在底部向上0.6h处较合理,其余各段的质量集中在每一段的中心截面0.5h处,等效成7个质点的多自由度体系,如下图所示:2.3重力荷载计算计算每一段的重力荷载代表值G i 。
G 1=9.6KN G 2=9.04 KN G 3=8.48 KN G 4=7.91 KN G 5=7.35 KN G 6=6.78 KN G 7=6.22 KN2.4侧移刚度计算桥墩的侧移刚度D 值按下式计算:D=212hi ci c ——桥墩的线刚度i c =E c I c /h,其中E c 砼的弹性模量,I c 为每段中心截面的惯性矩; h ——为桥墩的计算高度;桥墩侧移刚度D 值2.5水平地震作用下桥墩的内力和侧移计算(1)横向自振周期T 1计算。
T 1=0.45+0.0011×H 2/d式中:H ——桥墩的高度;d ——桥墩1/2处截面的直径; T 1=0.45+0.0011×212/1.68=0.74 (2)水平地震作用计算根据《建筑抗震设计规范》,对于结构高度不超过40m ,质量和刚度沿高度分布比较均匀,变形以剪切型为主,可用底部剪力法计算水平地震作用。
榆林市王圪堵水库输水工程主要地质问题分析童建平【摘要】:本文通过对榆林市王圪堵水库输水工程中几个重点工程地质问题的阐述,表明了陕北地区长输水线路工作重点所在,论述了黄土湿陷、地基液化及高地下水位等工程地质问题对长引水线路的影响程度及处理思路,阐明了作者对于陕北地区长引水线路工程地质勘察工作的一些思路及观点,并总结了一些该类工程地质勘察工作的方法。
【关键词】:引水线路;工程地质条件;地下水;黄土湿陷1工程概况陕西省榆林市王圪堵水库输水工程是王圪堵水库向榆横工业园区供水的主体工程,属大(2)型水利工程。
工程位于榆林市横山县与榆阳区交界的无定河及至以北的沙漠,输水工程起点为王圪堵水库坝后电站出水口,沿无定河左岸河漫滩自流至左岸支沟曹家沟下游约300m处,经泵站加压后沿东北方向跨越硬地梁沟后到达瓦渣梁高位水池,后跨越沙界沟、二石磕沟及沙河沟自流至榆横工业园区水厂,线路全长28.7km。
该输水工程采用管道输水,管径1.8m,总体管线以地埋式为主,一般埋置深度4~5m,过沟段主要以倒虹形式穿过。
输水工程由两处加压泵站,一处汇流池,四处过沟倒虹等7个建筑物及26.7km的输水管线组成。
输水管线平面布置图如图1。
输水线路一级泵站无定河无定河水天沟曹家沟硬地梁河沟界沙二石磕沟沙河进水口水厂硬地梁倒虹沙界沟倒虹二石磕倒虹沙河沟倒虹高位水池二级泵站芦河大坝供水管线平面位置示意图图12引水管线工程地质条件工程区位于毛乌素沙漠东南边缘地带,地形西北高东南低,沙漠区海拔高程1060~1400m,地形相对高差一般30~50m,沿线地貌单元按成因可划分为河流侵蚀堆积地貌和风蚀堆积地貌两种。
河流侵蚀堆积地貌主要分布在无定河河谷及沿线冲沟,主要地貌单元有河漫滩及河流阶地;风蚀堆积地貌主要分布在无定河以北的沙漠区边沿,主要地貌单元为风积新月形沙丘及零星出露的黄土梁峁。
工程区揭露的地层岩性主要为第四系松散堆积物,主要有全新统人工堆积,坡积堆积,冲积堆积,冲洪积堆积,风积堆积;上更新统风积堆积,冲、湖积堆积;中更新统风洪积堆积。
榆林王圪堵水库压力钢管制作及安装施工工艺【摘要】王圪堵水库压力钢管采用主材16MnR,φ1600mm主管壁厚18mm,管道地处毛乌素沙漠,具有技术含量高,施工强度大,质量要求高等特点。
目前已完成安装的压力钢管,施工质量达到设计要求,施工进度满足合同工期要求。
现将压力钢管制作及安装过程中采取的主要施工工艺及施工技术作一介绍,为今后水利水电工程施工积累经验。
【关键词】压力钢管制作安装施工技术1 工程概况榆林王圪堵水库输水工程压力钢管布置为地埋式双管线的钢管。
管材全部选用16MnR。
压力钢管采购包括王圪堵水库输水工程加压管道起始段、管道穿越沙界沟、沙河沟两条窄深沟道的桥式倒虹和完全倒虹段的钢管。
压力管道主管φ1600mm,壁厚18mm,设计管压均为2.5Mpa,单管线长2760.69m,最大折角不大于8°,管顶覆土厚度2.5m。
2 施工特性所有钢管均为地埋式安装,露天施工,待验收完毕,进行二期混凝土浇筑。
压力钢管安装施工与土挖施工、混凝土施工有着密切的联系,需要与施工各方进行密切的协作。
压力钢管制作、安装特点:(1)制作储备量大、堆放场地面积大。
压力钢管安装主要在土建方将管槽开挖并浇筑一期混凝土后进行,在管床凝固并达到设计要求后方可实施钢管安装。
安装施工前将有大量的成品钢管储备,加上钢管为圆形空心体,堆放场地利用率较低,因此需要大面积的堆放场地,对场地的平整度有一定的要求。
(2)施工难度大。
压力钢管管径大多为1.6m(内径),标管长度为7.5m,单节重量达到5.6吨左右,施工时需要配备大型的施工设备,吊装及运输工序操作复杂。
而安装工期比较紧,安装施工时往往需要多个工作面同时进行,施工难度较大。
(3)影响安装施工因素多。
压力钢管安装施工时,其安装程序受多种因素制约,因钢管安装依附土建施工进度而开展,因此需充分考虑整体施工进度、混凝土浇筑、关键控制工期要求等多种因素对安装施工的影响。
安装施工时需加强与施工各方的协作,营造良好施工氛围,合理安排施工程序,力求快速施工。
毕业设计(论文)题目榆林王圪堵水库枢纽布置及重力坝设计专业水利水电工程班级学生指导教师2013 年摘要本毕业设计题目为《榆林王圪堵水库枢纽布置及重力坝设计》,题目来源于王圪堵水库工程实际,属设计类课题。
设计的目的及意义主要在于巩固、扩大和提高所学水利水电理论知识,使其得到实际运用,并使之系统化,锻炼和培养运用所学专业基础理论知识解决工程实际,并进行设计、计算、制图的能力,提高撰写专业技术报告的水平。
在本次设计中,依据所给的水文气象和水利动能资料,采用半图解法进行了该工程的调洪计算,取得了泄水和引水等建筑物的型式、孔口尺寸的大小和设计洪水工况和校核洪水工况下所对应的洪水水位;依据工程地质条件,采用比较筛选法,对该工程进行了坝址选择、坝轴线选择和坝型的选择,取得了大坝枢纽平面布置图;依据工程地质资料和重力坝设计规范要求,采用抗剪断强度公式和材料力学法分别对大坝进行了抗滑稳定分析和应力计算,得到的结果表明大坝的剖面设计满足规范要求;依据调洪计算的结果,采用三圆弧法和WES曲线法对溢流坝段进行了设计,得到溢流坝段的剖面尺寸;依据计算得到的泄水建筑物的形式和水工设计手册第六卷,进行了泄水建筑物的水力计算,得到了溢流坝段的水面线和侧墙的高度。
设计获得了坝型选择和枢纽布置,调洪计算,混凝土重力坝设计,泄水建筑物设计,构造设计,地基处理等成果。
具体设计详见设计说明书,另外除了设计说明书外,还有反映本次设计成果的CAD设计图纸,以及设计过程中攥写的开题报告、外文翻译报告各一份。
所获成果满足设计规范要求、满足毕业设计任务书要求等。
关键词:枢纽布置,混凝土重力坝,非溢流坝,溢流坝,坝体稳定Yu lin wanggedu plugging reservoir project layout and design of gravity damABSTRACTThe design is about the project layout of the wanggedu hydraulic complex and concrete gravity dam. The topic of the design comes from the wanggedu Engineering. The purpose of the design mainly is making the knowledge we learned for water resources and hydraulic engineering into practice and making it systematize, and the ability for designing, computing and writing.In this design, based on the kinetic energy of hydro-meteorological and water conservancy information to, use of semi-graphic method for flood regulating calculation of the project, has made building types, such as discharge and water orifice size size and design flood conditions and check under flood water level of the flood. Based on the engineering geological conditions, using the comparison method, for the project to be the axis of the dam dam site selection, selection and choice of dam type, hub of the dam had been made a floor plan. Based on an engineering geology and gravity dam design code requirements and material mechanics method on shear strength formula respectively on dam stability against sliding analysis and stress calculation, the result indicates that the cross section of the dam design meets regulatory requirements. Flood regulating calculation based on the results of a three-arc method and WES curve method for design of spillway dam section, be overflow dam section dimensions. Based on the calculated discharge structure of hydraulic design manual, sixth form and volume, for hydraulic calculation of discharge structures, got overflow dam of height of the water surface profile and side walls.Design of dam type selection and layout, flood regulating calculation, design of concrete gravity dam, discharge structure design, structural design, Foundation treatment results. Besides of having design instruction to describe the details, there are nine drawings to reflect the design achievements.Resultsobtained meet the design specification requirements and meet the requirements of the design plan descriptions of the graduation, etc.KEY WORDS:layout of hydro project,concrete gravity dam, non-overflow dam,overflow dam,corridor system目录前言 (1)1 工程概述 (2)1.1 工程概况 (2)1.2 工程特性表 (2)2 设计任务及依据 (4)2.1 设计任务及设计阶段 (4)2.2 工程等别及防洪标准 (4)2.3 设计依据 (5)2.3.1 设计标准、规范及规程 (5)2.3.2 设计基本资料 (5)3 基本资料 (6)3.1 水文气象 (6)3.1.1 流域概况 (6)3.1.2 坝址设计与校核洪水成果 (6)3.1.3 气象条件 (7)3.1.4 泥沙资料 (7)3.2 工程地质资料 (8)3.2.1 坝址区工程地质条件 (8)3.2.2 岩土工程特性 (8)3.2.3 坝基工程地质 (9)3.2.4 建筑材料 (9)3.3 水利与水能 (10)3.3.1 坝址下游水位流量关系 (10)3.3.2 枢纽的供水、灌溉和发电等概况 (11)3.4 其他资料 (11)4 枢纽布置设计 (13)4.1 坝址选择 (13)4.2 坝轴线选择 (13)4.3 坝型选择 (14)4.4 泄水和引水等建筑物的型式与孔口尺寸选择 (14)4.5 调洪计算 (15)4.5.1 调洪计算的原理 (15)4.5.2 起调水位的分析与选择 (16)4.5.3 调洪计算的过程 (16)4.5.3.1 泄水隧洞的尺寸计算 (17)4.5.3.2 方案拟订 (18)4.5.3.3 设计洪水工况的调洪的计算 (20)4.5.3.4 校核洪水工况的调洪计算 (27)4.5.3.5 调洪计算成果汇总及分析 (35)4.6 泄水建筑物设计 (36)4.6.1 排沙底孔设计 (36)4.6.2 溢流坝消能防冲计算 (37)4.6.2.1 挑流消能水面线计算 (37)4.6.2.2 溢流坝段挑流消能水力要素的计算 (43)5 混凝土重力坝专题设计 (44)5.1 非溢流坝段设计 (44)5.1.1 坝体断面设计 (44)5.1.2 坝基面荷载作用的标准值计算(以单宽计算) (47)5.1.3 坝基面稳定计算 (48)5.1.4 抗滑稳定分析 (49)5.1.5. 应力分析计算 (50)5.2 溢流坝段设计 (57)5.3 坝基处理 (59)5.3.1 坝基开挖 (59)5.3.2. 坝基帷幕灌浆 (59)5.3.3 坝基固结灌浆 (60)5.3.4 左坝肩防渗墙设计 (60)5.4 坝体构造设计 (60)5.4.1 坝顶构造 (60)5.4.2 廊道系统 (61)5.4.2.1 坝基灌浆廊道 (61)5.4.2.2检查和坝体排水廊道 (62)5.4.3 横缝构造 (62)6 结语 (63)7 致谢 (64)8 参考文献 (65)前言本次毕业设计是根据根据教学要求,对水利水电专业本科毕业生进行的最后一项教学环节。
王圪堵水库枢纽布置及泄水建筑物设计毕业设计王圪堵水库枢纽布置及泄水建筑物设计毕业设计目录第1章工程概况 (7)第2章设计任务及依据 (8)2.1 设计任务及设计阶段 (8)2.2 工程等别及防洪标准 (10)2.3 设计依据 (10)第3章基本资料 (11)3.1 水文 (11)3.1.1流域水文概况 (11)3.1.2 气象 (12)3.1.3 洪水 (13)3.2 工程地质 (16)3.2.1 地形地貌 (16)3.2.2地层岩性 (16)3.2.4 水文地质条件 (17)3.2.8坝基处理 (22)3.3水库设计标准、特性指标及调洪计算条件 (22)3.3.1 设计标准 (22)3.3.2 库容曲线 (23)3.3.3 水库死水位 (25).WORD版本.3.3.4调洪计算条件 (25)第4章枢纽布置设计 (27)4. 1 坝址选择 (27)4. 2 坝轴线选择 (29)4.3坝型的选择及方案比较 (29)4.3.1 土石坝与重力坝 (30)4.3.2 均质土坝与斜墙坝、心墙坝 (31)4.3.3 结论 (31)4.4 调洪计算 (32)第5章建筑物设计 (45)5.1 坝体设计 (45)5.1.1坝体断面尺寸的拟定 (45)5.1.2渗流计算 (49)5. 2 溢洪道设计 (55)5.2.2 水力计算 (56)5.3泄洪排沙洞 (67)5.3.1总体布置及主要结构型式 (68)5.3.2水力计算 (69)5.3放水洞 (69)第6章构造设计 (71)6.1护坡 (71)6.2坝顶 (72).专业.专注.6.3马道 (72)第7章地基处理 (73)7.1基础处理 (73)7.2帷幕灌浆与固结灌浆 (73)7. 3 绕坝渗漏处理 (75)第8章总结与讨论 (76)参考文献 (77)第1章工程概况王圪堵水库坝址位于市横山县城关镇西北12km,榆靖高速公路无定河大桥以上2.5km、芦河入无定河口以上5.5km处的无定河干流上,距市区60km。
王圪堵水库枢纽工程大坝填筑施工质量控制摘要:文章结合王圪堵水库枢纽工程大坝填筑工程实例,重点分析了坝体填筑施工方法以及坝体填筑质量控制措施。
关键词:水利工程,大坝填筑,施工方法,质量控制Abstract: combining with the king Ge plugging reservoir project engineering project example of dam filling, and analyses the dam filling construction method and quality control measures of the dam filling.Keywords: water conservancy project, dam filling, construction method, quality control1.概况王圪堵水库枢纽工程大坝填筑包括坝体填筑458.7万m3、右坝肩管理区5.3万m3,总计464.0万m3,左坝肩削坡78.2万m3,利用76.2万m3,总计划填筑521天,则坝体填筑月最大强度32万m3/月,日强度达12577m3/天。
坝体填筑计划工期17个月,2010年8月开始填筑至2012年的6月底。
2011年6月底全坝段填筑到1028m高程,满足1028m高程的度汛要求。
2012年6月底大坝填筑设计高程1054.0m后,预留预沉降高度0.4m,主河床坝段填筑至1054.4m高程,2012年底前修筑坝顶道路等工程。
坝体填筑按区、段、单元划分进行,坝面分三区,即:左岸坝肩填筑区、右岸坝肩填筑区、河床段区,每区分为三个独立工作面。
先施工左、右坝肩段,再施工河床段。
按照不同高程设上坝道路。
2坝体填筑施工方法2.1坝体填筑施工道路布置2.1.1上坝道路布置采用岸坡与坝坡相结合的布置方式,上坝道路按双车道设计,两岸上坝主干道路面宽7m,最大纵坡控制在10%左右;坝体下游坡面的临时上坝道路路面宽7m,最大纵坡控制在10%以下。