雁栖湖示范区再生水管线水源连通工程(主体工程)

洞挖工程监理实施细则

编制人: 审批人:

北京正细工程监理有限公司 2020年3月31日 目录 1.总则 ........................................................................................................................................ 1 1.1 范围 ................................................................................................................................ 1 1.2 编制依据 ........................................................................................................................ 1 1.3 施工准备工作监理 ........................................................................................................ 1 1.4 承包人的责任 ................................................................................................................ 2 1.5施工作业准备 ................................................................................................................. 2 2.暗挖土方 ................................................................................................................................ 4 3.开挖测量控制 ........................................................................................................................ 5 3.1 开挖面的欠挖清理 ........................................................................................................ 5 3.2 局部伸入设计开挖线的处理 ........................................................................................ 5 3.3 施工措施不当引起的超挖 ............................................................................................ 5 3.4 为施工需要增加的开挖 ................................................................................................ 5 4.洞口开挖 .............................................................................................................................. 5 4.1 掘进前围岩稳定性的勘察 ............................................................................................ 5 4.2 竖井开挖 ........................................................................................................................ 5 5 地下开挖土方的利用 ............................................................................................................ 6 5.1 地下工程开挖土方的利用 ............................................................................................ 6 5.2 地下工程开挖土方的弃置 ............................................................................................ 6 6.地下开挖超前勘探 ................................................................................................................ 6 6.1 根据监理人指示进行超前勘探 .................................................................................... 6 6.2 超前勘探孔规格 ............................................................................................................ 6 6.3 及时报送超前勘探资料 ................................................................................................ 6 6.4 超前预报的补偿 ............................................................................................................ 7 7.地下照明和通风 .................................................................................................................... 7 7.1 地下照明 ........................................................................................................................ 7 7.2 通风与防尘 .................................................................................................................... 7 8.质量检查与验收 .................................................................................................................... 7 8.1 地下洞室开挖前的检查和验收 .................................................................................... 7 8.2 地下洞室开挖质量的检查和验收 ................................................................................ 7 8.3 地下洞室的完工验收 .................................................................................................... 7 北京正细工程监理有限公司 1

1.总则 1.1 范围 本细则为雁栖湖示范区再生水管线水源连通工程(主体工程)再生水管穿越

现况京密引水渠施工监理工作实施编制,主要为更好的开展监理质量控制工作。 1.2 编制依据 (1)雁栖湖示范区再生水管线水源连通工程(主体工程)招投标文件 (2)本工程施工图 (3)《水利水电建设工程验收规程》(SL223-2008) (4)《水工混凝土施工规范》(SL677-2014) (5)《水利工程施工监理规范》(SL288-2014) (6)《水利水电工程单元工程施工质量验收评定标准》(SL631~637-2012、SL638~639-2013) (7)《水利水电工程施工质量检验与评定规程》(SL176-2007) (8)《给水排水管道工程施工及验收规范》(GB50268-2008) (9)《工程建设标准强制性条文》(水利工程部分2020年版) (10)《给排水水构筑物工程施工及验收规范》(GB 50141—2008) (11)相关规定的法律、法规 1.3 施工准备工作监理 在地下工程开挖前,承包人应根据施工图纸及本技术条款的规定,提交一份

包括下述内容的施工措施计划,报送监理人审批。 1)地下工程开挖及施工支洞布置图;2)开挖设备和辅助设施的配置;3)钻孔爆破技术和方法以及控制超挖的措施;4)出渣和弃渣及渣料利用措施;5)洞口保护和围岩稳定的支护措施以及处理塌方的应急措施;6)通风和散烟、除尘及空气监测安全措施;7)照明设施;8)排水措施;9)通信、信号和报警设施;10)施工进度计划及劳动力安排;11)开挖质量和安全保证措施;12)施工期地下洞室的围岩稳定临时监测措施。 在施工过程中,承包人不得随意改变经批准实施的开挖及支护程序,确因特殊原因需要修改时,必须论证其对围岩稳定及施工进度的影响,报监理人批准后