顶管施工组织设计施工方案
- 格式:docx
- 大小:64.38 KB
- 文档页数:18
.................................................................................
....................................................................... 2
2.1 测量定位 ................................................................... 2
2.2 基坑开挖、垫层浇筑。 ....................................................... 2
2.3 模板、支撑 ................................................................. 2
2.4 钢筋绑扎 ................................................................... 3
2.5 沉井混凝土浇捣 .............................................................. 3
2.6 沉井下沉、封底 .............................................................. 3
2.6.1 沉井下沉 ............................................................. 3
2.6.2 封底 ................................................................. 4
2.6.3 沉井预留孔进、出口封堵处理 ...........................................
4
....................................................................... 4
3.1 顶管采用工艺 ................................................................ 4
3.2 顶管机头主要技术参数及配套设备 ................................................................................... 5
3.3 顶力估泥水算 ................................................................ 5
3.4 顶进设备安装 ................................................................ 6
3.5 管道顶进施工 ................................................................ 7
3.6 顶管纠偏 ................................................................... 7
3.7 顶进测量及 控制 ............................................................ 8
3.8 触变泥浆减阻 ................................................................ 9
3.8.1 注浆量计算 ........................................................... 9
3.8.2 触变泥浆的施工方法要点 ............................................... 9
3.8.3 注浆设备的配置 ...................................................... 10
3.8.4 泥浆配制 ............................................................ 10
3.8.5 压浆方法 ............................................................. 11
4 管道安装 ........................................................................ 11
4.1 钢管焊接 .................................................................. 11
4.2 钢管接口补防腐 ............................................................
12
............................................................... 13
5.1 劳动力安排 ................................................................ 13
5.2 主要机械配置 ...............................................................
13
.................................................................. 14
6.1 保证土体稳定层、防止土体挪移 .............................................. 14
6.2 减小顶管阻力、防止土体挪移 ................................................ 14
6.3 减少纠偏、保持土体稳 ...................................................... 14
6.4 保证注浆压力、控制地面沉降 ................................................ 15
6.5 质量标准 ..................................................................
15
........................................................... 15
7.1 安全防护 .................................................................. 15
7.2 安全用电 .................................................................. 16
7.3 文明施工 .................................................................. 16
1.1 工程概况:该施工专项方案为 XX 市 XX 供水环线工程 XX 顶管施工,顶管位置
位于 XX 大桥西侧,管材主要采用DN1000 钢管,壁厚为 14mm,长度为 225 米,设计工
作压力为 0.5Mpa。工作井采用钢筋混凝土施工,位置位于 XX 南面花坛内,接收井采
用钢筋混凝土施工,位于南面河道工程施工场地内。顶管施工采用泥水平衡法,顶管
管中心标高为-4.00,管顶覆土深度为 3.5 米。
1.2 设计单位: XXXX 设计院有限公司
1.3 主要工程量
1.3.1 结构沉井工程:钢筋混凝土顶管工作井 (内)6.5m×4.0m1 座,接收井
(内)4.0m×4.0m1 座。
1.3.2 顶管: DN1020×14mm 钢管 1 处,鉴湖大桥顶管 225 米。
1.4 工程特殊性:沉井、顶管均处在淤泥质黏土层,适合顶管施工;沉井高程较
深,沉降时机械挖土较艰难,须加长挖机臂长,同时在沉降过程中容易产生偏斜,须
加以控制,井壁后座土质须作加固处理。
1.5 施工实施
1.5.1 钢筋混凝土沉开:钢筋混凝土工作井和接收井,采用沉井施工、以商品混
凝土现场制作;长臂挖机挖土自重下沉;排水封底。
1.5.2 顶管:采用封闭式水力机械机头;顶进时注入触变泥浆减阻,长距离顶管
备用中继间。
1.6 施工执行规范和技术标准:
给水排水管道工程施工及验收规范 GB50268
工业金属管道工程施工及验收规范 GB50235
现场设备、工业管道焊接工程施工及验收规范 GB50236
给排水构筑物施工及验收规规范 GBJ1410090
施工现场暂时用电安全技术规范 JGJ46
地方政府的有关规范、标准
现按现场实际交底和满足顶管要求拟设施工方案。
本工程工作井、接收井各 1 座,分 1 处顶管段设置,工作井平面尺寸均为(外)
8.1m×5.6m,接收井平面尺寸均为(外) 5m ×5m。
各沉井施工采用商品混凝土现场制作, 以机械挖土自重下沉, 排水封底施工方法。
如遇地质流砂层则采取井点降水措施。 工作井将分三次浇筑三次下沉方法, 施工程序:
测量~基坑开挖~垫层铺设;刃脚制作,一次下沉;井壁制作 (厚壁段);二次下沉;
再次井壁制作;三次下沉;封底;养护,湿井待顶管和管线连接完毕后进行。
根据施工图中总平面布置要求,按甲方给定沉井中心的位置,在不受沉井下沉时
土体挪移影响的地方,设立观测沉井曲线移偏观察、复核十字轴线桩,然后按沉井所
需尺寸,用白灰划定沉井基坑开挖线。
由于各处地下管道、电缆埋设情况不明确,为防止沉井座落在原管道、电缆上或者 在沉井沉降过程影响原管线, 所以在沉井基坑放样后, 须对周围原管线进行挖土寻觅, 确定原管线不受影响后方可挖土施工。
沉井基坑大于井, 外形坑底尺寸为按图, 外边留工作面 1.5m,深 1.8m,放坡开挖。
(见附图 9.2)
沉井刃脚基础垫层为砂层、素砼层。粗砂垫层全底厚 0.7m,素砼 C15 为带垫层厚
0.5m,宽 1.5m。(见附图 9.1)
沉井内外壁模板均采用硬质层压模板,脚手架支架动撑用Φ 48 A3 钢管、方木。