管架预制程序(中英)
- 格式:doc
- 大小:98.00 KB
- 文档页数:10
CONTENTS目录1 Scope范围2 References And Applicable Codes 参考文件3 Working procedure管道工作程序4 Preparation施工准备5 Recheck & marking of Material材料复验、标记6 Painting 管子防腐和刷漆7Pipe Prefabrication And Installation 管道预制和安装8Piping Clean And Purging 系统清洗和吹扫9Pressure Test 压力试验10Blow down and Drying管道排放和干燥11Reinstatement Of Piping System 管道系统复位12Piping Joint Coating And Insulation 管道防腐补口13Construction Quality Records And Inspection Reports 施工质量记录和检查报告14 Safety Requirements安全要求15 Revision Note 修订注释1 Scope范围This procedure shall apply to material handling & transportation, prefabrication, installation, examination, pressure testing, cleaning, painting of piping in Nanhai HDPE/PP plant.本程序适用于南海石化项目PP+HDPE装置管道现场装卸、倒运、预制、安装、检验、试验、清扫、防腐的施工。
2 References And Applicable Codes参考文件2.1 NH-HDPE+PP-QCPR-331 Material Handling, Delivering and Storage Procedure材料装卸及发放程序2.2 NH-HDPE+PP-QCPR-333 Coating pipe load/unload&storage procedure涂层钢管装卸、储运及检验程序2.3 NH-HDPE+PP-QCPR-307 Pipelines welding procedure管线焊接程序2.4 NH-HDPE+PP-QCPR-324 Piping Quality Control Procedure管线质量控制程序2.5 NH-HDPE+PP-WPR-228 Surface Preparation And Painting Procedure表面准备和防腐施工程序2.6 NH-HDPE+PP-QCPR-322 Procedure for Dimensional Control尺寸控制程序2.7 NH-HDPE+PP-WPR-211 Procedure for Hydrostatic Testing and Flushing of Piping管道水压试验及冲洗程序2.8 NH-HDPE+PP-QCPR-324 Piping Quality Control Procedure管线质量控制程序2.9 ASME B31.3 Process piping 工艺管道2.10 CSPC and TCM’s specifications. CSPC和TCM 规范2.11 GB50235-97 Code for construction and acceptance of industrial metallic piping工业金属管道工程施工及验收规范2.12 GB50236-98 Code for construction and acceptance of field equipment, industrial pipewelding engineering 现场、工业管道焊接工程施工及验收规范2.13 SH3501-97 Specification for construction and acceptance of hypertoxic andcombustible medium piping engineering in petrochemical industry石油化工剧毒、可燃介质管道工程施工及验收规范3 管道工作程序Working procedure施工准备→材料复验、标识→管道预制→管子除锈防腐和刷漆→安装→管道冲洗与吹扫→管道压力试验→管道排放和干燥→管道复位→管线防腐补口→施工质量记录和检查报告整理提交Preparation →Material recheck & marking →Pipe prefabrication →Sandblasting & painting →Pipe installation →Pipeline flushing & blowing →Hydrotest →Blow down & drying →Reinstatement →Piping joint paintting →Preparation & submission of records & inspection reports.4 施工准备CONSTRUCTION PREPARATION施工准备包括施工技术准备、特殊作业人员上岗培训准备、现场准备。
Xx罐区工程脚手架搭设程序ScaffoldingInstallationProcedure目录1X围Scope12目的Purpose13定义Definition14依据Reference25脚手架搭设前准备Preparation Before Scaffold Installation26脚手架搭设措施Scaffold Installation Measures37安全文明措施HSE Safety Measures81X围Scope1.1本程序适用于xx罐区工程施工脚手架的安装、改变或拆除,主要用于储罐安装。
The procedure applies to the installation, alteration or removal of scaffolds for the intermediate product of the xx Project and its tank project, mainly for tank installation.2目的Purpose2.1为xx罐区工程施工一共提供脚手架安装、拆除,建立统一检查标准。
It is to establish a unified inspection standard for installation and removal of scaffolds for the intermediate product of the xx Project and its tank project.3定义Definition3.1脚手架:脚手架定义为一个临时结构,提供通道、施工或用于支撑材料、装置或设备。
分为两种类型:Scaffold:Scaffold is defined as a temporary structure providing pass for construction or being used for supporting material, apparatus or equipment. It is classified as two types:3.1.1单体形式、梯子、圆形或所有其它用途的框架或整体结构;Single-form, ladder, circular or other useful frames or whole structure.3.2管道和扣件:不同长度的单根管子用一个个连管节(连接,旋转,直角)连接在一起。
Piping Prefabrication PlanContent一、工程概况General (2)二、编制依据Reference (3)三、管道预制车间Pipe Fabrication Workshop (4)四、安全管理措施Safety Management Measures (5)五、管道预制施工Pipe Fabrication (8)六、材料管理Material Management (10)七、材料验收与存放Material Acceptance and Storage (12)八、喷砂防腐sandblasting and anti-corruption (15)九、阀门试验Valve Test (17)十、管道预制的施工程序Construction Process of Pipe Prefabrication (18)十一、管道预制进度计划Pipe Fabrication Schedule (44)十二、机具动员计划Equipment Mobilization Plan (45)十三、危险分析Job Hazard Analysis (45)一、工程概况General本工程位于马来西亚关丹吉本工业园的柠檬香精项目。
业主方为巴斯夫马来西亚国油化学公司(简称BPC),管理公司由FLOUR负责,综合专业工程C420区域由中国化学工程马来西亚公司(以下简称―CCEM‖)承建。
The project is BPC Lemongrass Project which is located in Gebeng Industrial Park of Kuantan Malaysia. The Owner is the BASF-PETRONAS Chemicals (BPC) Complex. Management Company is FLUOR. Multi-discipline work (Area C400 Citral Unit) is contracted and constructed by China Chemical Engineering Malaysia Company. (Hereinafter referred to as CCEM)㈠、工程简介Project description1、本项目地上工艺管道主要由管廊管道和装置区域管道工程组成。
管道预制和安装程序1、总则(1)管道施工执行业主提供的总的技术要求规范和CPECC规范,二者如有冲突,应以业主要求的规范为主。
(2)管道预制和安装的焊工必须按照批准的程序通过考核并获得相应的证书才能上岗。
(3)所有管材及管配装卸、保管和领取应遵循材料装卸、保管和发放程序—MBOD/EPCⅠ—MU—QC Ⅲ.8。
(4)预制按照已批准的单线图进行预制,并由技术员在单线图上标出预制范围。
(5)管道焊接应遵循工艺管道焊接程序-MBOD/EPC1-RP-WLD-06。
2、管道预制(1)管道的预制仅限于2″以上的管,除撬装设备管道在车间预制外,其余在现场预制。
(2)管材、管件领取由施工班组提前三天提出所需材料计划,由技术人员核实,班组派专人领取,领料单应保存,材料应分类放好。
下料和组对之前,应仔细检查管材和管件,确认材质、壁厚和规格,对管材变形、严重划伤、法兰及阀门密封面损坏、管件有裂纹等不符合规范的材料应更换,并作好记录,对不符合规范的材料应作明显的标记,以防下次被误用。
3、管材切割(1)管道切割可采用机械和火焊切割,2″以下碳钢管道可以用切割机切割,不锈钢管道不能用火焊切割,2″以下的不锈钢管可以用切割机切割,2″以上的不锈钢管用等离子切割机或机械方法切割,切割后应清除表面氧化物和金属熔渣。
镀锌管应用切割机切割。
(2)管材切割时,考虑到切割打磨和焊接造成收缩,管道下料时应留1-2mm余量,安装固定口处应留100mm以上的余量。
(3)切割后,每段切割料上应作标记移植,标明材质、壁厚和规格。
切割后对未作标记的管材,没有经过鉴定,暂不能使用。
4、坡口加工(1)坡口用机械方法或采用火焊切割加工坡口,但必须用角向磨光机磨平,除去氧化渣,坡口角度达到焊接要求,焊前应对坡口内、外表面及两侧各25mm进行清理,应用棉纱头和钢丝刷除去水、油污、飞溅和油漆,不锈钢必须使用不锈钢刷清扫。
(2)坡口加工后作外观检查,不得发现有裂纹,夹渣等缺陷,清理和检查合格的坡口,应及时完成焊接工作,并作好记录。
建筑专业词汇《中英文对照》~~建筑专业词汇建设,建筑,修建 to build, to construct建筑学 architecture修筑,建筑物 building房子 house摩天大楼 skyscraper公寓楼 block of flats (美作:apartment block) 纪念碑 monument宫殿 palace庙宇 temple皇宫,教堂 basilica大教堂 cathedral教堂 church塔,塔楼 tower十层办公大楼 ten-storey office block柱 column柱列 colonnade拱 arch市政 town planning (美作:city planning)营建许可证,建筑开工许可证 building permission 绿地 greenbelt建筑物的三面图 elevation设计图 plan比例尺 scale预制 to prefabricate挖土,掘土 excavation基 foundations, base, subgrade打地基 to lay the foundations砌好的砖列 course of bricks脚手架 scaffold, scaffolding质量合格证书 certification of fitness 原材料 raw material底板 bottom plate垫层 cushion侧壁 sidewall中心线 center line条形基础 strip footing附件 accessories型钢 profile steel钢板 steel plate熔渣 slag飞溅 welding spatter定位焊 tacking引弧 generating of arc熄弧 quenching of arc焊道 welding bead坡口 beveled edges外观检查 visual inspection重皮 double-skin水平方向弧度 radian in horizontal direction成型 molding直线度 straightness accuracy焊缝角变形 welding line angular distortion水平度 levelness铅垂度 verticality翘曲变形 buckling deformation角尺 angle square对接焊缝 butt weld母材 parent metal法兰密封面 flange sealing surface夹层 interlayer表面锈蚀浓度 surface corrosion concentration挠曲变 bending deformation超声波探伤 ultrasonic testing/ ultrasonic examination 压力容器 pressure vessel预制下料 prefabrication baiting排版直径 set-type diameter焊缝 welding line中幅板 center plate测量方法 measuring method基准点 datum mark跳焊 skip welding允许偏差 allowable variation补强板 stiffening plate开孔 tapping对接接头 banjo fixing butt jointing角钢 angle iron安装基准圆 installation fundamental circle 吊装立柱 hoisting upright column焊接钢管 welded steel pipe向心斜拉筋 centripetal canting pull rope 带板 band plate槽钢胀圈 channel steel expansion ring环口 collar extension局部变形 local distortion环缝 circumferential weld顶板 top plate拱顶 vault顶板加强肋 stiffening rib对接 butt joint胎具 clamping fixture卷板机 plate bending rolls中心支架 center bearing bracket椭圆度 ovality等分线 bisectrix搭接宽度 lap width点焊 spot welding搭接焊 overlap welding对称 symmetrically螺旋爬梯 cockle stairs放料阀 baiting valve液位计 content gauge芬兰维萨拉 Vailsla OY美国美科 "Met-coil, USA"集中式空调系统 centralized air conditioning system 裙房 annex热源 heat source平面位置的空间 space of planimetric position密封性能 sealing performance机房 machine room节点 timing专业 "profession or discipline 都可以,要根据上下文"连体法兰 coupling flange垂直井笼 vertical well cage变风量 variable air rate施工面展开 construction unfolds违约行为 noncompliance合同交底- contract presentation管理承包商 Management Contractor party工程量 work amount实施的形象进度 progress of implementation完工资料 as-built documentation文整 clear-up审核 review汽车式起重机 Autocrane深化图纸 deepen drawing设备配置计划 equipment furnishment plan结构预埋配合阶段 Structure pre-embedment assistance stage精装修阶段 Fine fitment stage工程施工阶段 Construction stage工程竣工阶段 Completion stage台钻 Bench drill冲击钻 Churn drill手电钻 Electric portable drill砂轮切割机 Abrasive cutting off machine角钢卷圆机 Angle iron rolling machine管道切断器 Pipe cutting machine铜管调直机 Copper pipe straightening machine管道压槽机 Book joint setting machine for pipes管道压槽机 Book joint setting machine for pipes角向磨光机 Angle polishing machine电动套丝机 Electric threading machine电动卷扬机 Electric winch电动试压泵 Motor-driven pressure test pump手动试压泵 Manual pressure test pump阀门试压机 Valve pressure test device阀门试压机 Valve pressure test deviceTDC(F)风管加工流水线 TDC(F)air ductwork fabricationstream line等离子切割机 Plasma cutting machineTDC(F)法兰条成型机 TDC(F) flange strip shaping mill 勾码成型机 Forming machine for flange clampTDC(F)风管加工成型机 TDC(F) duct fabrication shaping mill多普勒超声波流量检测仪 Doppler ultrasonic flow detector 温、湿度传感器 "Temperature, humidity senor"精密声级计 Precision sound level meter风管漏风量测试仪、风室式漏风测试装置 "Duct air leakage tester, airchamber air leakage testing device"风罩式风量测试仪 Air hood air rate tester微压计、毕托管、热球(电)风速仪 "Micromanometer ,pitot tube, hot bulb(electrical) anemoscope"潜水泵 Submerged pump电动弯管机 Electric pipe bender铜管弯管机 Copper pipe bender液压弯管机 Hydraulic pipe bender电动剪刀 Electric clipper液压铆钉钳 Hydraulic riveting clamp线槽电锯 Trunking electric saw开孔器 Tapper电动空压机 Electric air compressor液压千斤顶 Hydraulic jack液压手推车 Hydraulic trolley焊条烘干箱 Welding rod drying box手拉葫芦 Chain block道(垫)木 Sleeper转速表 Tachometer电流钳型表 Clip-style ammeter压力表 Pressure gauge接地电阻测试仪 Earthing resistance testing device氧气表 Oxygen gauge乙炔表 Acetylene gauge对讲机 Walkie talkie文件和资料 documents and information建设单位 Construction unit安装单位 Installation unita. DESIGN BASIS 设计依据b. DESIGN STAGE 设计阶段c. CLIMATE CONDITION 气象条件d. GENERAL ROOM NAME 常用房间名称e. ROOFING & CEILING 屋面及天棚f. WALL(CLADDING) 墙体(外墙板)g. FLOOR & TRENCH 地面及地沟h. DOORS 、GLASS、WINDOWS & IRONMONGERY(HARDWARE)门、玻璃、窗及五金件I. STAIRCASE、LANDING & LIFT(ELEVATOR)楼梯、休息平台及电梯j. BUILDING MATERIAL WORDS AND PHRASES 建筑材料词汇及短语【 Bricks and Tiles 砖和瓦】【Lime, Sand and Stone 灰、砂和石】【Cement, Mortar and Concrete 水泥、砂浆和混凝土】【Facing And Plastering Materials 饰面及粉刷材料】【Asphalt (Bitumen) and Asbestos 沥青和石棉】【Timber 木材】【Metallic Materials 金属材料】【Non-Ferrous Metal 有色金属】【Anti-Corrosion Materials 防腐蚀材料】【Building Hardware 建筑五金】【Paint 油漆】k. OTHER ARCHITECTURAL TERMS 其它建筑术语【Discipline 专业】【Conventional Terms 一般通用名词】【Architectural Physics 建筑物理】【Name Of Professional role 职务名称】【Drafting 制图】a. DESIGN BASIS 设计依据计划建议书 planning proposals设计任务书 design order标准规范standards and codes条件图 information drawing设计基础资料 basic data for design工艺流程图 process flowchart工程地质资料 engineering geological data原始资料 original data设计进度 schedule of designb. STAGE OF DESIGN 设计阶段方案 scheme, draft草图 sketch会谈纪要summary of discussion谈判 negotiation可行性研究 feasibility study初步设计 preliminary design基础设计 basic design详细设计 detail design询价图 enquiry drawing施工图 working drawing, construction drawing竣工图 as built drawingc. CLIMATE CONDITION 气象条件日照 sunshine风玫瑰 wind rose主导风向 prevailing wind direction最大(平均)风速 maximum (mean) wind velocity 风荷载 wind load最大(平均)降雨量 maximum (mean) rainfall雷击及闪电 thunder and lightning飓风 hurricane台风 typhoon旋风 cyclone降雨强度rainfall intensity年降雨量 annual rainfall湿球温度 wet bulb temperature干球温度 dry bulb temperature冰冻期 frost period冰冻线 frost line冰冻区 frost zone室外计算温度 calculating outdoor temperature 采暖地区 region with heating provision不采暖地区 region without heating provision 绝对大气压 absolute atmospheric pressure相对湿度 relative humidityd. GENERAL ROOM NAME 常用房间名称办公室 office服务用房 service room换班室 shift room休息室 rest room (break room)起居室 living room浴室 bathroom淋浴间 shower更衣室 locker room厕所 lavatory门厅 lobby诊室 clinic工作间 workshop电气开关室 switch room走廊 corridor档案室 archive电梯机房 lift motor room车库 garage清洁间 cleaning room会议室(正式) conference room会议室 meeting room衣柜间 ward robe暖风间 H.V.A.C room饭店 restaurant餐厅 canteen, dining room厨房 kitchen入口 entrance接待处 reception area会计室 accountant room秘书室 secretary room电气室 electrical room控制室 control room工长室 foreman office开关柜室 switch gear前室 ante cabinet (Ante.)生产区 production area马达控制中心 Mcc多功能用房 utility room化验室 laboratory room经理室 manager room披屋(阁楼) penthouse警卫室 guard housee. ROOFING AND CEILING 屋面及天棚女儿墙 parapet雨蓬 canopy屋脊 roof ridge坡度 slope坡跨比 pitch分水线 water-shed二毡三油 2 layers of felt & 3 coats of bitumastic 附加油毡一层 extra ply of felt檐口 eave挑檐 overhanging eave檐沟 eave gutter平屋面 flat roof坡屋面 pitched roof雨水管 downspout, rain water pipe)(R.W.P)汇水面积 catchment area泛水 flashing内排水 interior drainage外排水 exterior drainage滴水 drip屋面排水 roof drainage找平层 leveling course卷材屋面 built-up roofing天棚 ceiling檩条 purlin屋面板 roofing board天花板 ceiling board防水层 water-proof course检查孔 inspection hole人孔 manhole吊顶 suspended ceiling, false ceiling 檐板(窗帘盒) cornicef. WALL (CLADDING) 墙体(外墙板)砖墙 brick wall砌块墙 block wall清水砖墙 brick wall without plastering 抹灰墙 rendered wall石膏板墙 gypsum board, plaster board 空心砖墙 hollow brick wall承重墙 bearing wall非承重墙 non-bearing wall纵墙 longitudinal wall横墙 transverse wall外墙 external (exterior) wall内墙 internal (interior) wall填充墙 filler wall防火墙 fire wall窗间墙 wall between window空心墙 cavity wall压顶 coping圈梁 gird, girt, girth玻璃隔断 glazed wall防潮层 damp-proof course (D.P.C)遮阳板 sunshade阳台 balcony伸缩缝 expansion joint沉降缝 settlement joint抗震缝 seismic joint复合夹心板 sandwich board压型单板 corrugated single steel plate 外墙板 cladding panel复合板 composite panel轻质隔断 light-weight partition牛腿 bracket砖烟囱 brick chimney勒脚(基座) plinthg. FLOOR AND TRENCH 地面及地沟地坪 grade地面和楼面 ground and floor素土夯实 rammed earth炉渣夯实 tamped cinder填土 filled earth回填土夯实 tamped backfill垫层 bedding course, blinding面层 covering, finish结合层 bonding (binding) course找平层 leveling course素水泥浆结合层 neat cement binding course混凝土地面 concrete floor水泥地面 cement floor机器磨平混凝土地面 machine trowelled concrete floor水磨石地面 terrazzo flooring马赛克地面 mosaic flooring瓷砖地面 ceramic tile flooring油地毡地面 linoleum flooring预制水磨石地面 precast terrazzo flooring硬木花地面 hard-wood parquet flooring搁栅 joist硬木毛地面 hard-wood rough flooring企口板地面tongued and grooved flooring防酸地面 acid-resistant floor钢筋混凝土楼板 reinforced concrete slab (R.C Slab)乙烯基地面 vinyl flooring水磨石嵌条 divider strip for terrazzo地面做2%坡 floor with 2% slope集水沟 gully集水口 gulley排水沟 drainage trench沟盖板 trench cover活动盖板 removable cover plate集水坑 sump pit孔翻边 hole up stand电缆沟 cable trenchh. DOORS, GLASS, WINDOWS & IRONMONGERY(HARDWARE)门、玻璃、窗及五金件木 (钢)门 wooden (steel) door镶板门 panelled door夹板门 plywood door铝合金门 aluminum alloy door卷帘门 roller shutter door弹簧门 swing door推拉门 sliding door平开门 side-hung door折叠门 folding door旋转门 revolving door玻璃门 glazed door密闭门 air-Tight door保温门 thermal insulating door镀锌铁丝网门 galvanized steel wire mesh door防火门 fire door(大门上的)小门 wicket门框 door frame门扇 door leaf门洞 door opening结构开洞 structural opening单扇门 single door双扇门 double door疏散门 emergency door纱门 screen door门槛 door sill门过梁 door lintel上冒头 top rail下冒头 bottom rail门边木 stile门樘侧料 side jumb槽口 notch木窗 wooden window钢窗 steel window铝合金窗 aluminum alloy window百叶窗 (通风为主) sun-bind, louver (louver, shutter, blind) 塑钢窗 plastic steel window空腹钢窗 hollow steel window固定窗 fixed window平开窗 side-hung window推拉窗 sliding window气窗 transom上悬窗 top-hung window中悬窗 center-pivoted window下悬窗 hopper window活动百叶窗 adjustable louver天窗 skylight老虎窗 dormer window密封双层玻璃 sealed double glazing钢筋混凝土过梁 reinforced concrete lintel钢筋砖过梁 reinforced brick lintel窗扇 casement sash窗台 window sill窗台板 window board窗中梃 mullion窗横木 mutin窗边木 stile压缝条 cover mould窗帘盒 curtain box合页(铰链) hinge (butts)转轴 pivot长脚铰链 parliament hinge闭门器 door closer地弹簧 floor closer插销 bolt门锁 door lock拉手 pull链条 chain门钩 door hanger碰球 ball latch窗钩 window catch暗插销 insert bolt电动开关器 electric opener平板玻璃 plate glass夹丝玻璃 wire glass透明玻璃 clear glass毛玻璃(磨砂玻璃) ground glass (frosted glass)防弹玻璃 bullet-proof glass石英玻璃 quartz glass吸热玻璃 heat absorbing glass磨光玻璃 polished glass着色玻璃 pigmented glass玻璃瓦 glass tile玻璃砖 glass block有机玻璃 organic glassI. STAIRCASE, LANDING & LIFT (ELEVATOR) 楼梯、休息平台及电梯楼梯 stair楼梯间 staircase疏散梯 emergency stair旋转梯 spiral stair (circular stair)吊车梯 crane ladder直爬梯 vertical ladder踏步 step扇形踏步 winder (wheel step)踏步板 tread档步板 riser踏步宽度 tread width防滑条 non-slip insert (strips)栏杆 railing (balustrade)平台栏杆 platform railing吊装孔栏杆 railing around mounting hole扶手 handrail梯段高度 height of flight防护梯笼 protecting cage (safety cage)平台 landing (platform)操作平台 operating platform装卸平台 platform for loading & unloading楼梯平台 stair landing客梯 passenger lift货梯 goods lift客/货两用梯 goods/passenger lift液压电梯 hydraulic lift自动扶梯 escalator观光电梯 observation elevator电梯机房 lift mortar room电梯坑 lift pit电梯井道 lift shaftj. BUILDING MATERIAL WORDS AND PHRASES 建筑材料词汇及短语Bricks and Tiles 砖和瓦红砖 red brick粘土砖 clay brick瓷砖 glazed brick (ceramic tile)防火砖 fire brick空心砖 hollow brick面砖 facing brick地板砖 flooring tile缸砖 clinkery brick马赛克 mosaic陶粒混凝土 ceramsite concrete琉璃瓦 glazed tile脊瓦 ridge tile石棉瓦 asbestos tile (shingle)波形石棉水泥瓦 corrugated asbestos cement sheet Lime, Sand and Stone 灰、砂和石石膏 gypsum大理石 marble汉白玉 white marble花岗岩 granite碎石 crushed stone毛石 rubble蛭石 vermiculite珍珠岩 pearlite水磨石 terrazzo卵石 cobble砾石 gravel粗砂 course sand中砂 medium sand细砂 fine sandCement, Mortar and Concrete 水泥、砂浆和混凝土波特兰水泥(普通硅酸盐水泥) Portland cement硅酸盐水泥 silicate cement火山灰水泥 pozzolana cement白水泥 white cement水泥砂浆 cement mortar石灰砂浆 lime mortar水泥石灰砂浆(混合砂浆) cement-lime mortar保温砂浆 thermal mortar防水砂浆 water-proof mortar耐酸砂浆 acid-resistant mortar耐碱砂浆 alkaline-resistant mortar沥青砂浆 bituminous mortar纸筋灰 paper strip mixed lime mortar麻刀灰 hemp cut lime mortar灰缝 mortar joint素混凝土 plain concrete钢筋混凝土 reinforced concrete轻质混凝土 lightweight concrete细石混凝土 fine aggregate concrete沥青混凝土 asphalt concrete泡沫混凝土 foamed concrete炉渣混凝土 cinder concreteFacing And Plastering Materials 饰面及粉刷材料水刷石 granitic plaster斩假石 artificial stone刷浆 lime wash可赛银 casein大白浆 white wash麻刀灰打底 hemp cuts and lime as base喷大白浆两道 sprayed twice with white wash分格抹水泥砂浆 cement mortar plaster sectioned 板条抹灰 lath and plasterAsphalt(Bitumen) and Asbestos 沥青和石棉沥青卷材 asphalt felt沥青填料 asphalt filler沥青胶泥 asphalt grout冷底子油 adhesive bitumen primer沥青玛啼脂 asphaltic mastic沥青麻丝 bitumastic oakum石棉板 asbestos sheet石棉纤维 asbestos fiberTimber 木材裂缝 crack透裂 split环裂 shake干缩 shrinkage翘曲 warping原木 log圆木 round timber方木 square timber板材 plank木条 batten板条 lath木板 board红松 red pine白松 white pine落叶松 deciduous pine云杉 spruce柏木 cypress白杨 white poplar桦木 birch冷杉 fir栎木 oak榴木 willow榆木 elm杉木 cedar柚木 teak樟木 camphor wood防腐处理的木材 preservative-treated lumber胶合板 plywood三(五)合板 3(5)-plywood企口板 tongued and grooved board层夹板 laminated plank胶合层夹木材 glue-laminated lumber纤维板 fiber-board竹子 bambooMetallic Materials 金属材料黑色金属 ferrous metal圆钢 steel Bar方钢 square steel扁钢 steel strap,flat steel型钢 steel section (shape)槽钢 channel角钢 angle steel等边角钢 equal-leg angle不等边角钢 unequal-leg angle工字钢 I-beam宽翼缘工字钢 wide flange I-beam丁( 之)字钢 T-bar (Z-bar)冷弯薄壁型钢 light gauge cold-formed steel shape 热轧 hot-rolled冷轧 cold-rolled冷拉 cold-drawn冷压 cold-pressed合金钢 alloy steel钛合金 titanium alloy不锈钢 stainless steel竹节钢筋 corrugated steel bar变形钢筋 deformed bar光圆钢筋 plain round bar钢板 steel plate薄钢板 thin steel plate低碳钢 low carbon steel冷弯 cold bending钢管 steel pipe (tube)无缝钢管 seamless steel pipe焊接钢管 welded steel pipe黑铁管 iron pipe镀锌钢管 galvanized steel pipe铸铁 cast iron生铁 pig iron熟铁 wrought iron镀锌铁皮 galvanized steel sheet镀锌铁丝 galvanized steel wire钢丝网 steel wire mesh多孔金属网 expanded metal锰钢 managanese steel高强度合金钢 high strength alloy steelNon-Ferrous Metal 有色金属金 gold白金 platinum铜 copper黄铜 brass青铜 bronze银 silver铝 aluminum铅 leadAnti-Corrosion Materials 防腐蚀材料聚乙烯 polythene, polyethylene尼龙 nylon聚氯乙烯 PVC (poly vinyl chloride)聚碳酸酯 polycarbonate聚苯乙烯 polystyrene丙烯酸树酯 acrylic resin乙烯基酯 vinyl ester橡胶内衬 rubber lining氯丁橡胶 neoprene沥青漆 bitumen paint环氧树脂漆 epoxy resin paint氧化锌底漆 zinc oxide primer防锈漆 anti-rust paint耐酸漆 acid-resistant paint耐碱漆 alkali-resistant paint水玻璃 sodium silicate树脂砂浆 resin-bonded mortar环氧树脂 epoxy resinBuilding Hardware 建筑五金钉子 nails螺纹屋面钉spiral-threaded roofing nail环纹石膏板钉 annular-ring gypsum board nail 螺丝 screws平头螺丝 flat-head screw螺栓 bolt普通螺栓 commercial bolt高强螺栓 high strength bolt预埋螺栓 insert bolt胀锚螺栓 cinch bolt垫片 washerPaint 油漆底漆 primer防锈底漆 rust-inhibitive primer防腐漆 anti-corrosion paint调和漆 mixed paint无光漆 flat paint透明漆 varnish银粉漆 aluminum paint磁漆 enamel paint干性油 drying oil稀释剂 thinner焦油 tar沥青漆 asphalt paint桐油 tung oil, Chinese wood oil红丹 red lead铅油 lead oil腻子 puttyk. OTHER ARCHITECTURAL TERMS 其它建筑术语Discipline 专业建筑 architecture土木 civil给排水 water supply and drainage总图 plot plan采暖通风 H.V.A.C (heating、ventilation and air conditioning) 电力供应 electric power supply电气照明 electric lighting电讯 telecommunication仪表 instrument热力供应 heat power supply动力 mechanical power工艺 process technology管道 pipingConventional Terms 一般通用名词建筑原理 architectonics建筑形式 architectural style民用建筑 civil architecture城市建筑 urban architecture农村建筑 rural architecture农业建筑 farm building工业建筑 industrial building重工业的 heavy industrial轻工业的 light industrial古代建筑 ancient architecture现代建筑 modern architecture标准化建筑 standardized buildings 附属建筑 auxiliary buildings城市规划 city planning厂区内 within site厂区外 offsite封闭式 closed type开敞式 open type半开敞式 semi-open type模数制 modular system单位造价 unit cost概算 preliminary estimate承包商 constructor, contractor现场 site扩建 extension改建 reconstruction防火 fire-prevention防震 aseismatic, quake-proof防腐 anti-corrosion防潮 dump-proof防水 water-proof防尘 dust-proof防锈 rust-proof车流量 traffic volume建筑模型 building model Architectural Physics 建筑物理照明 illumination照度 degree of illumination亮度 brightness日照 sunshine天然采光 natural lighting光强 light intensity侧光 side light顶光 top light眩光 glaze方位角 azimuth辐射 radiation对流 convection传导 conduction遮阳 sun-shade保温 thermal insulation恒温 constant temperature恒湿 constant humidity噪音 noise隔音 sound-proof吸音 sound absorption露点 dew point隔汽 vapor-proofName Of Professional role 职务名称项目经理 project manager (PM)设计经理 design manager首席建筑师 principal architect总工程师 chief engineer土木工程师 civil engineer工艺工程师 process engineer电气工程师 electrical engineer机械工程师 mechanical engineer计划工程师 planning engineer助理工程师 assistant engineer实习生 probationer专家 specialist, expert制图员 draftsman技术员 technicianDrafting 制图总说明 general specification工程说明 project specification采用标准规范目录 list of standards and specification adopted 图纸目录 list of drawings平面图 plan局部放大图 detail with enlarged scale...平面示意图 schematic plan of......平剖面图 sectional plan of...留孔平面图 plan of provision of holes剖面 section纵剖面 longitudinal section横剖面 cross (transverse) section立面 elevation正立面 front elevation透视图 perspective drawing侧立面 side elevation背立面 back elevation详图 detail drawings典型节点 typical detail节点号 detail No.首页 front page图纸目录及说明 list of contents and description 图例 legend示意图 diagram草图 sketch荷载简图 load diagram流程示意图 flow diagram标准图 standard drawing...布置图 layout of ...地形图 topographical map土方工程图 earth-work drawing展开图 developed drawing模板图 formwork drawing配筋 arrangement of reinforcement表格 tables工程进度表 working schedule技术经济指标 technical and economical index建、构筑物一览表 list of buildings and structures 编号 coding序列号 serial No.行和栏 rows and columns备注 remarks等级 grade直线 straight Line曲线 curves曲折线 zigzag line虚线 dotted line实线 solid line影线 hatching line点划线 dot and dash line轴线 axis等高线 contour Line中心线 center Line双曲线 hyperbola抛物线 parabola切线 tangent Line尺寸线 dimension Line园形 round环形 annular方形 square矩形 rectangle平行四边形 parallelogram三角形 triangle五角形 pentagon六角形 hexagon八角形 octagon梯形 trapezoid圆圈 circle弓形 sagment扇形 sector球形的 spherical抛物面 paraboloid圆锥形 cone椭圆形 ellipse, oblong面积 area体积 volume容量 capacity重量 weight质量 mass力 force米 meter厘米 centimeter毫米 millimeter公顷 hectate牛顿/平方米 Newton/square meter 千克/立方米 kilogram/cubic meter 英尺 foot英寸 inch磅 pound吨 ton加仑 gallon千磅 kip平均尺寸 average dimension变尺寸 variable dimension外形尺寸 overall dimension展开尺寸 developed dimension内径 inside diameter外径 outside diameter净重 net weight毛重 gross weight数量 quantity百分比 percentage净空 clearance净高 headroom净距 clear distance净跨 clear span截面尺寸 sectional dimension开间 bay进深 depth单跨 single span双跨 double span多跨 multi-span标高 elevation, level绝对标高 absolute elevation设计标高 designed elevation室外地面标高 ground elevation室内地面标高 floor elevation柱网 column grid坐标 coordinate厂区占地 site area使用面积 usable area辅助面积 service area通道面积 passage area管架 pipe rack管廊 pipeline gallery架空管线 overhead pipeline排水沟 drain ditch集水坑 sump pit喷泉 fountain地漏 floor drain消火栓 fire hydrant灭火器 fire extinguisher二氧化碳灭火器 carbon dioxide extinguisher 卤代烷灭火器 halon extinguisher。
Contents1. 预制梁柱的制作Precasting of Columns and Beams (2)2. 预制管架运输Precast pipe rack handling (2)3. 预制管架堆放Storage of precast pipe racks (3)4. 预制管架柱吊装Installation of precast columns (4)5. 柱子垂直度校正Adjustment of the verticality of columns (5)6. 柱子的最后固定Final securing of columns (6)7. 预制管架梁吊装Lifting and installation of precast beams (7)1. 预制梁柱的制作Precasting of Columns and Beams1)预制现场在施工前应进行硬化处理,压实和整平好地基后,用砼进行铺筑,并应设计排水坡度。
Precast yard shall be paved with concrete after it is leveled and compacted,leaving a slope for dewatering.2)根据现场的面积布置柱梁的预制位置,并画出布置图。
Arrange precast positions as per the area available and make a layout accordingly.3)模板按清水砼面准备材料,表面应光滑,均匀;施工前应涂刷脱模剂。
Formwork used for precast columns and beams shall be smooth and even on the surface and release agent shall be applied to it prior to construction.4)模板尽量避免小面积拼凑,接缝处应进行刨光处理,防止接痕。
CONTENTS目录1.0 SCOPE 范围2.0 SPECIFICATIONS,CODES AND STANDARDS规格、规范和标准3.0 INSTALLATION OF STEEL STRUCTURE 钢结构的管架安装4.0 PREFABRICATION、INSTALLATION AND PAINTING FOR LADDERS、PLATFORMS OFEQUIPMENT设备梯子、平台预制、安装和刷漆5.0 STRUCTURE STEEL BUILDING钢结构建筑物6.0 QUALITY RECORDS AND INSPECTION REPORTS质量记录和检查报告7.0 REVISION NOTES修订1.0 SCOPE 范围This Procedure shall apply to installation and painting of steel structures, prefabrication, installation and painting of stairs/ladders and platforms of equipment.本程序用于钢结构安装和刷漆、设备梯子、平台的预制、安装和刷漆。
2.0 Specifications, Codes and Standards规范、规范和标准SP-8310-7000-0006 SPECIFICATION FOR STEEL STRUCTURE SITE ERECTIONSP-8310-7000-0005 ; “Steel Structures - Shop Fabrication”SP-8440-7100-0001; ”Specification for Painting”SP-8440-7100-0002 ; “Painting cycle”GB/T1231-91: Technical Code for the High Strength Hexagon Bolts, Nuts,Washers applied to Steel StructureJGJ81-2002: Specification for Welding of Steel StructureJGJ82-91: Specification of Design, Construction and Acceptance for High-Strength Bolt Connection of Steel StructureGB50205-2001: Code for Construction and Acceptance of Steel StructuresMaterial Handling, Delivering and Storage Procedure材料装卸及发放程序In cases where more than one code, regulation or standard apply to the same condition, the most stringent shall be followed. In the event of a conflict between this specification and other specifications or correspondence, TCM shall be consulted and a ruling, in writing, shall be obtained before any work is started.当一个工程内容适用几个规范标准,则施工时将遵守最严格的一个,如果规范之间发生冲突,则任何工作启动之前,将同TCM协商,并得到TCM的书面裁决。
建造工艺流程3.3 建造步骤3.3.1材料采办、接收3.3.2放样、划线、切割总体建造程序第 1 页共 15页放样、划线、切割详见《划线程序》。
3.3.3制管制管按照API Spec 2B和业主规格书执行,详见《导管架制管程序》。
3.3.4分片预制需要预制立片、水平分片。
预制的附件包括:靠船排、抗冰锥、梯子栏杆、泵护管及支撑、吊点等。
1)ROW A和ROW B 立片预制ROW A、ROW B立片预制时,立管卡子、靠船排横承、牺牲阳极等安装到立片上。
第一步:固定垫墩详见垫墩布置图,摆放主导管(立片外侧一面朝下)临时垫墩示意图第二步:点焊固定中间水平层水平撑管第三步:点焊固定中间水平层和防沉板层之间拉筋管。
第四步:点焊固定防沉板水平撑管。
第五步:点焊固定走道水平撑管。
第六步:整体焊接固定。
第七步:焊接靠船排支撑、牺牲阳极、走道支撑等附属结构。
第八步:立片预制完成后,整体运输到涂装车间进行喷涂。
详见《涂装程序》。
2)走道、中间层水平片预制。
第一步:固定水平片的内部支撑管。
固定垫墩详见垫墩布置图第二步:点焊固定井口基盘的撑管,按照以下步骤组装。
第三步:点焊固定水平片的拉筋管。
第四步:焊接井口片。
焊接时,采用由里向外、由中间向两边并交叉组对的方法预制焊接。
走道水平片和中间层水平片焊接顺序应保持一致。
第五步:走道水平片完工后,整体运输到涂装车间进行喷涂详见《涂装程序》。
3.5 场地组装第一步:清理场地,摆放滑靴。
滑靴布置详见滑靴布置图道路灭火器照明灯项目建造区域线滑靴第二步:防沉板水平片建造防沉板水平片直接在滑道上建造。
第三步:吊装ROW“A”立片。
第四步:吊装防沉板和中间水平层之间的拉筋管。
防沉板水平片ROW“A”立片拉筋管第五步:吊装中间水平片。
中间水平片临时支撑第六步:吊装走道水平片。
走道水平片临时支撑第七步:吊装ROW“B”立片。
ROW B立片第八步:安装抗冰锥。
先安装下半部分,再安装上半部分。
抗冰锥抗冰锥第九步:安装靠船件,完善顶层走道。
目录Contents1 适用范围Scopes2 相关规范The Relevant Standards3 施工程序The Construction Procedure3.1混凝土管架梁柱预制程序The Prefabrication Procedure of The Beams and Columns of The Concrete Pipe Racks3.2混凝土管架安装施工程序The Installation Procedure of The Concrete PipeRacks4 主要工作内容The Working Contents4.1 施工准备The Construction Preparation4.2混凝土管架梁柱的预制The Prefabrication of Beams and Columns of The Concrete Pipe Racks4.3杯型基础施工The Construction of The Cup Type Foundation4.4混凝土管架安装施工The Installation of The Concrete Pipe Racks4.5回填土Backfilling1 适用范围Scopes本程序适用于建设项目厂区内钢筋混凝土管架预制和安装的施工。
This procedure is to be used for the prefabrication and installation of the reinforcing concrete pipe racks in the plant area of HDPE/PP project. 2 相关规范The Relevant StandardsGB 50202-2002 建筑地基基础工程施工质量验收规范Quality Acceptance Code for Construction of Foundations for BuildingsGB 50204-2002 混凝土结构工程施工质量验收规范Code for construction and acceptance of concrete structure engineering JGJ18-96钢筋焊接与验收规范Specification for welding and acceptance of reinforcing steel bar GB 50300-2001 建筑工程施工质量验收统一标准Standard for quality inspection and assessment of building construction 3 施工程序The Construction Procedure 3.1混凝土管架梁柱预制程序The prefabrication procedure of the concrete pipe racks beams and columns3..2混凝土管架安装施工程序The installation procedure of the concrete pipe racks4 主要工作内容The Working Contents4.1 施工准备The construction preparations4.1.1 技术准备The technique preparations4.1.1.1 图纸会审及设计交底The joint examination of drawings and design explanations对施工图进行图纸会审,做好图纸会审记录。
Joint examine the drawings and record.4.1.1.2 技术交底The technique explanations在施工前,向班组进行技术交底,明确施工程序及技术质量要求,施工重点、难点及相应措施。
准备好施工记录表格。
Before start the work, carry out the technique explanations to the constructing teams and define the construction procedure, technique quality requirement, the working emphases and working difficulties with their relevant treatment to the constructing teams.4.1.2 现场准备The jobsite preparations4.1.2.1 现场临时设施:材料仓库,加工予制场地,工具房,生活用房等生产生活临时设施。
The jobsite temporary facilities: the material storehouses, prefabrication ground, tools houses and living houses.4.1.2.2 准备有关施工机具:将施工所需各种施工机具和手段等按进场计划组织进场。
The tools and equipment preparations: organize the construction equipment, tools and instruments to enter the jobsite according to the time schedule.4.1.2.3 建立现场测量控制网Set up the site measurement control network根据TCM提供的测量基准,测设现场测量控制网(坐标和标高),设置并保护好标桩。
各建、构筑物单体放线可依据控制网标桩测设。
Set up the site measurement control network (coordinates and elevations) according to the benchmarks provided by TCM. Setup and protect the mark-pile. Set out lines of the mono buildings according to the mark-pile.4.1.3 材料准备The material preparation4.1.3.1材料进货及进场检验The checking out of the material orders and deliveries 所有进场材料必须具有产品质量证明书或出厂合格证,其各项品质指标应满足设计和规范要求。
主要材料应按材料检验程序进行外观和物理化学性能现场抽检,合格后报TCM审查认可才能使用。
All the materials entering the site should have quality certificate or factory certificate and their character indexes should accord to the design and criterion requirement. The main material should be checked out their appearance and physical chemistry characters on site and report to the TCM for approval before use.4.1.3.2 分类存放及标识Store by their sorts and tag them各种材料按品种、规格分类存放,并做好明显标识,以防混用。
易受潮变质的材料如水泥等材料必须入库存放,防雨防潮。
All sorts of materials should be stored by their sorts and specs and tag to avoid misuse. The material liable to transformation by the moisture such as cement should store in storehouses to prevent from rain and moisture.4.2混凝土管架梁柱的预制The prefabrication of concrete pipe racks beams andcolumns.4.2.1管架预制采用单梁柱预制平铺浇筑方案,以方便吊运。
因此要求管架设计方案能单根梁柱预制后再组装。
Prefabricate the racks by the method of level paving and grounding one by one so that they can be lifted and transported conveniently. So the design scheme is suitable to prefabrication in one by one and then assembly.4.2.2预制场须做地面硬化,表面抹光,作为预制构件的底模。
梁、柱按相同规格成组侧立支模,6~10根为一组。
每组构件砼浇筑完成后,应及时进行浇水养护。
The surface of the prefabrication ground should be hardening and finishing to use as the bottom formwork of the prefabricating components. The same sort of the beams and columns should made side-erected formwork in groups and 6-10 as a group. S praying water to maintain them after the components are to be completed.4.2.3管架预制钢筋混凝土作业步骤Work procedure for C.R. pipe rack一般按模板、钢筋、混凝土浇筑、养护、拆模的次序施工。
Normally the procedure is:formwork rebar casting curing demolition of formwork.4.2.3.1模板施工Formworks1)模板采用组合木模板,表面涂刷由润滑油、轻机油按3:7比例混合的脱模剂。
The formworks are wooden-array formworks and painting stripping oil mixed by lubricant and light machine oil with the rate of 3:7.2)按结构形状尺寸、施工荷载进行模板设计,确定拼板方案。