主井井筒施工组织设计(毕业设计)

  • 格式:doc
  • 大小:1.78 MB
  • 文档页数:96
由于矿井所处地层含水量相对较大,所以井筒表土段采用冻结法进行施工,基岩段采用钻爆法进行凿井,起爆方式在远离煤层基岩段选择导爆管起爆法,在接近煤层处选择闭合反向大并联起爆法。对井筒施工的辅助设备进行了选择计算,能够高效有序地完成凿井任务。
主井井筒施工后,进行临时改绞,对提出方案进行对比,确定更为经济合理的施工方案。确定并完成井底车场和相应硐室、巷道布置及施工组织设计。对全矿井进行提升,运输,通风,排水方式的确定及所用设备选型计算与相关的硐室布置等。编制工业场地施工总平面图,合理利用工业场地进行矿井施工组织。科学管理,加快矿井建设。确定施工进度,合理进行施工组织设计,完成矿井的施工计划网络图。在本次毕业设计中,采用AutoCAD2004辅助设计,增强了图示的可读性和准确性。
Field of mine, is the geographical position, hydrogeology, basic situation of coal.
As the mine situated relatively rich ground water content, so shaft freezing method used in surface soil construction, rock drilling and blasting method used in paragraph sinking, far away from the initiation method choice for base rock section Nonel law, close to the seam and select the closed reverse large parallel initiation method. Construction on the auxiliary shaft device of choice calculated to efficient and orderly completion of drilling tasks.
After the main shaft construction,change to temporary lift, compared to the proposed program to determine a more economical construction program. Identify and complete the Shaft station and the corresponding chamber, roadway layout and construction organization design. To upgrade the whole mine, transport, ventilation, drainage ways and used to determine equipment selection calculation and layout of the relevant chamber. Construction Map prepared industrial sites, industrial sites for rational use of mine construction organization. Scientific management, speed up the mine construction. Determine the construction schedule, construction organization design and reasonable to complete the mine's construction plans network diagram. In this graduation design, with AutoCAD2004 aided design, enhancing readability and accuracy of the icon.
1.1.1.2资源量
矿井地质资源量1224.20Mt,其中33
1.1.1.3煤层及煤质
井田内共含煤4层,4 、4 煤属零星分布,不能连成片。4-1是4煤的分岔煤层。4-1号煤层为局部可采煤层,4煤层属全区大部可采煤层。煤层厚度0~38.66m,平均厚度15.23m,属特厚煤层。在井田范围内属稳定煤层,全区可采。
1.1.2.5通风系统
本矿井属高瓦斯矿井,煤尘具有爆炸危险性,属不自燃~很易自燃煤层。矿井投产后,形成主立井、副立井进风,回风立井回风的中央分列式通风系统。
按用风地点确定矿井总风量为340m³/s。
回风立井选用MAF-3150/1780-1E型矿井轴流式通风机2台,1台工作,1台备用。每台风机配1台Y710-8型高压异步电动机(1800kW,10kV,744r/min)。
Keywords:Freezing method;Drilling and blasting;Change to temporary lift;Shaft station;Network graph construction scheme

1.1
1.1.1井田概况
1.1.1.1井田境界
小庄井田位于陕西省咸阳市彬县东北向约18km,距咸阳市约148km。行政区划属彬县管辖。井田西以泾河河道为界,东以彬慧渠27号、31号拐点为界,南以泾河,阎子川及3890500座标线为界,北以28号、29号、30号、31号拐点为界。分别与孟村井田、亭南井田、大佛寺井田、文家坡井田、官牌井田和胡家河井田毗邻。井田东西长9.8km,南北宽9.5km,面积约57k㎡。
关键词冻结法钻爆法临时改绞井底车场施工计划网络图
Abstract
The content of graduation Mining Group Co., Ltd. Shanxi Binchang xiao zhuang main shaft and mine construction organization design, xiao zhuang Mining Group located in Xianyang City, Binxian northeast to about 18km, from Xianyang city about 148km. Binxian are under the jurisdiction of administrative divisions. Include Ida profile, wellbore construction, shaft station design and construction, underground site zoning and roadway development, equipment selection, industrial site plan layout of the total construction.
根据煤层的赋存条件和煤的硬度、厚度及产量要求,回采工作面采用MGTY-400/930/3.3D型电牵引双滚筒采煤机,2台SGZ830/1000型可弯曲刮板板输送机,ZF7000/19.5/38四柱支撑掩护式放顶煤支架,支撑高度1.95~3.8m,支护强度0.972 MPa,工作阻力7000kN,支架中心距1500mm。
盘区排水设备选用3台PJ200×3型高扬程多级离心泵,1台工作,1台备用,1台检修。每台泵配YB560㎡-4型(500kW、10kV、1480r/min)矿用隔爆电动机。正常涌水时1台水泵工作,最大涌水时2台水泵同时工作。排水管路选用Ф325×10无缝钢管,沿西翼进风大巷敷设。
1.1.2.7压缩空气系统
摘要
本次毕业设计内容是陕西彬长矿业集团有限公司小庄矿主井井筒及矿井施工组织设计,小庄井田位于陕西省咸阳市彬县东北向约18km,距咸阳市约148km。行政区划属彬县管辖。主要包括井田概况,井筒施工,井底车场设计施工,井下盘区划分和巷道开拓,设备选型,工业场地施工总平面图布置等。
井田概述,是对矿井的地理位置,水文地质,煤层等基本情况的概述。
1.1.2建设规模及主要技术特征
1.1.2.1建设规模、服务年限及工作制度
矿井建设规模6.00Mt/a,服务年限79.3a。
设计矿井年工作日为330d。井下每天4班作业,其中3班生产,1班准备。每天净提升时间为16h;地面每天3班作业。
1.1.2.2井田开拓
在鸭河湾工业场地内布置2个立井,主立井、副立井,主、副立井落底标高均为+480m,主立井担负全矿井的原煤提升任务兼进风,装备JKMD-4×4(Ⅲ)E型落地式多绳摩擦式提升机2台,2对20t箕斗;副立井担负全矿井的人员、设备和材料的提升任务兼做主要进风井、安全出口,装备一对单层加宽罐笼。副立井井底车场布置在4号煤层顶板岩石中,通过主立井井底清理斜巷与主立井井底沟通。
矿井的总用气量为153.4m³/min,选用5台㎡50-2S型两级压缩喷油螺杆式空气压缩机,4台工作,1台备用;排气量47.4m³/min,排气压力0.85MPa,风冷型;每台空压机随主机配IY400-4型异步电动机,250kW、1475r/min、10kV。压缩空气站设5个C-5.0/0.8型立式储气罐(5m³,0.8MPa)。
主立井井筒净直径7.5m,净断面44.2㎡,井深417m,井筒担负全矿井煤炭提升兼进风,装备二对20t箕斗;副立井井筒净直径8.2m,净断面50.3㎡,井深417m。井筒担负全矿井井下人员、材料、设备、矸石提升及进风任务。装备一对双层加宽罐笼,设有玻璃钢梯子间。井筒内布置两趟排水管,敷设动力电缆及弱电电缆。白家宫回风立井井筒净直径7.5m,净断面44.2㎡,井深616m。担负全矿井回风任务,设有玻璃钢梯子间。井下煤炭运输全部采用胶带输送机运输;辅助运输采用无轨胶轮车。
1.1.2.4提升系统
A.主立井提升设备
主立井担负全矿原煤提升任务,装备二对20t曲轨卸载箕斗,选用JKMD-4×4(III) /4型落地式摩擦轮提升机1台,配交-交变频同步电动机(3000kW、52r/min)2台,提升速度10.47m/s。