脚手架JHA危险性分析

  • 格式:doc
  • 大小:92.50 KB
  • 文档页数:4
3.设红白警示线;
And the red white band should be use to caution.
脚手架拆除
scaffold dismantling
架杆、扣件砸伤非脚手架施工人员
hurt non-scaffold man by scaffold pole or clips
1.设立专人在脚手架周围警卫,过往人员不能进入作业区,设红白警示线;
The scaffolds that erected first should be dismantled last. And they cannot be dismantled vertically at one time
3.作业过程中作业人员递送扣件,不能抛掷;
Construction staff is not permit to delivered the clips with the method of throwing.
3.不能站在已经松绑的架板上作业;
Not permit to work on the untied scaffold plank.
4.作业过程中互相照应,动作一致,架杆不能搁在已经解开螺撕的扣件上。Staffs care fore each other and consistent activity. The scaffold poles are not permit to put on the clips whose sail has been untied.
3.脚手架板及时绑扎牢固,作业面随时加设防护栏杆;
Fix and tightenctive handrail timely.
4.脚手架搭设过程中和在管架上行走必须将安全带扣在设置好的横杆或生命线上.
During the scaffold erection and when walking on the pipe rack, safety harness must be secured to the life line on the pope rack.
3.作业过程中作业人员互相关照,动作一致,递送扣件不能抛掷;
The staffs care for each other and consistent activities .Pro habit delivery clips with method of throwing.
4.工作时,使用工具袋存放工具;
板手钢管跳板踢脚板管扣垫板
Revision No
版次
Date of Revision
修订日期
Sequence of Basic Job Steps
基本工序
Identified HSE Hazards
确定的HSE危险
Precautions / Controls / By Whom
预防/控制措施/执行人
2.安全带不允许挂在施工中还没有用卡件固定好的脚手架上,应挂在设置的生命线或固定好的脚手架钢管上;
The safety harness is not allowed to secure on the scaffold which is not fixed with coupler. The harness should be secured on the safety line on the pipe rack.
The height of scaffold should not surpass the length of truck and the minimum length of truck is 6 meters, The height of scaffold should not surpass the height of the truck .
4.进入施工现场限速15Km/小时;
The maximal speed is15Km/hin the site.
5.运输架杆的车上严禁乘人。
The truck which used to carry piles should not carry
humanbeing.
脚手架的搭设
Scaffold installation
脚手架钢管装车
steel tubeof Scaffold loading
手、脚砸伤
Spueeze hand andfeetsand injured
1.正确使用个人防护用品。Use PPE strictly.
2.装车过程中作业人员互相关照,动作一致。
Construction staff care for each other and consistent activities
材料垂直运输
material vertical transportation
架杆、扣件砸伤脚手架施工人员及周边人员
hurtscaffoldman by scaffold pole or clips
1.材料的垂直运输要通过用麻绳提升和降落;
Vertical transport ion of material should be carried out by manila rope.
脚手架材料的运输
Scaffold material conveyance
装车的架杆超长、超高,在行驶中容易发生交通事故、人员伤害
Overlong and height scaffoldpole cancause to Traffic accidents.
1.装车的架高不能超过车厢长度;运输车辆的车厢长度要大于6米,架杆的高度不能超过车厢的高度;
脚手架的搭设
Scaffold installation
作业者高处坠落
fall from high
1.高空作业人员必须始终挂好双钩五点式安全带,穿好防滑鞋;
harness and wear safety anti-slippery shoes when working at height. And the workers must wear a five point harness with shock absorber and two lanyards.
4.拆除的架杆、扣件由下方的人员随时接递并码放整齐。
The dismantled scaffold poles and clips should be taken and stored in order by the following staff.
脚手架拆除
作业者高处坠落
fall from height
签名日期
Location位置
Approved By
批准人:
SignatureDate
签名日期
Analysis By准备人
Name姓名:Position职位:Signature签名:
Revision By
修订人:
SignatureDate
签名日期
Equipment / Tools / Material to be used使用的工具/设备/材料
2.按照方案架设剪刀撑和斜撑,吊架按照方案架设脚手架承重横杆和立杆及防滑扣。Cross bracing shall be erected as per the erection plan. Bearing transverse pole, vertical pole and anti-skid coupler shall be used as per the erection plan.
架杆、扣件砸伤手、砸伤脚
hurt hand s or feet by scaffold pole or clips
1.作业人员戴好防护手套,穿好防护鞋。
Wear protective gloves and safety shoes
2.架子搭设必须由持有特殊工种上岗证的架子工专人搭设;
Only qualified scaffold erectors are permitted to erect ,modify or dismantle scaffolds.
Job Hazard Analysis Worksheet工作危险性分析报告
Project / Company
项目/公司
MDI联合装置硝酸单元项目/
Date submitted
提交日期
Date Issued
签发日期
Job Description
工作描述
脚手架搭设/拆除
Reviewed By
审核人:
SignatureDate
Put the tools in the tool bags when working.
5.设踢脚板,不准遗留工具等杂物;
Establish kick-off board and not permit to leave tools etc.behind.
6.严格执行编制、审批好的搭设方案,脚手架搭设应挂红牌,脚手架搭设完毕需经检验合格挂上绿牌后方可施工。
脚手架的搭设
Scaffold installation
脚手架搭设倾覆
scaffolding collapse during erection
1.脚手架严格按照已批准的施工方案搭设;
The scaffold shall be erected strictly as per the approved erection plan.
The established method should be carried out ,Red tag should be put up when we are erecting the scaffold, the completed scaffold should be check up byscaffoldsupervisor and all scaffold must have a green tag in place prior to use .