IT项目管理案例分析The GPS Auto-navigation System Verification Project

戴小卫

Z09030928

9/25/2010

REQUIREMENT 1: Project Organization

You quickly began assembling the project planning team. The team would have responsibility for: (1) developing the project plan and schedule, (2) conducting the reliability testing of the guidance systems, (3) conducting the tear down audit and interpreting the results, and (4) reporting the results of the project to Senior Management.

This is your project. Your project team consists of Gail YU, Manager of Quality Engineering, Tom HUANG, Manager of Design and Product Engineering, Jesse LIU, a senior engineer from Product Manufacturing, and Pete DONG, a senior engineer from Administration responsible for component purchasing and incoming testing of materials. Each member of your project team has access to whatever resources they need to support the project. This is a top priority for the company and you have been assured that you will “get whatever you need to complete the project”.

You decide that a first order of business is to develop a Project Charter. You will have an initial meeting in one day with the project management team. This is where you will develop the project objectives, roles, and responsibilities. You decide to go in with a draft and have the team work from there.

In preparation for this meeting,

(a) develop an initial project charter,

项目名称:导航系统可靠性测试及模块分解审计

项目起始时间:2010-9-1 项目结束时间:2010-9-27

项目目标:通过对5套导航系统的可靠性测试和模块审计,分别从工艺评估和工程设计分析去判断那些工艺上的缺陷对产品的影响。通过测试结果的说明去说服客户公司的

产品设计和实现是可靠可信的。

项目经理:Da i xiaowei Reliability Engineering Manager

项目成员:Gail YU, Manager of Quality Engineering

Tom HUANG,Manager of Design and Product Engineering

Jesse LIU,senior engineer from Product Manufacturing

Pete DONG,senior engineer from Administration responsible for component

purchasing and incoming testing of materials

项目进程安排:1. 设计测试计划和时间安排

2. 实施导航系统可靠性测试

3. 实施模块分解审计,说明审计结果

4. 分析测试和审计结果

5. 提交项目总结报告

(b) develop a complete Linear Responsibility Chart,

2 - Supervision

3 - Must be consulted

4 - May be consulted

5 - Must be notified

6 - Approval authority

(c) complete a stakeholder analysis.

REQUIREMENT 2: Network Planning for the Reliability Testing and Workmanship Auditing

The team has quickly developed a sequence of major activities for the project. These activities are listed in the table below along with durations and predecessor relationships:

Given the table of project activities:

(a)Develop a CPM Activity on Node diagram for the project,

Determine the critical path and the duration of the critical path for the project,

CPM为AKMN,总项目时间为21天。

(c), What conclusions can you draw from the CPM diagram?,

从定义出的关键路径可以看出,整个项目的主要工作量和成本集中在可靠性测试中,只有保证可靠性测试按时完成,整个项目才不会出现延误,通过追踪关键路径可以平衡整个项目的进度。

(b)Discuss the assumptions, limitations, and implications for using the CPM as an approach for

scheduling this project?

由于该项目对成本并无要求,但是对时间和资源都有比较严格的控制要求,可以通过关键路径法对项目进度和项目所需资源进行优化,同时由于关键路径法本身的缺点所导致的局限性,诸如:各个活动的优先级并不明显,各个活动的时间经常需要利用概率分布来估计时间点,有可能会出现偏差,如果遇到确实无法确定的工作,管理团队应该在项目运作中进行充分的分析并做出相应的调整,此时的网络计划就显得非常无力。

REQUIREMENT 3: PERT as a method to schedule the Project

You want to develop a more realistic estimate for the project schedule. Therefore, you have requested that your project team develop PERT based estimates for project durations. The following table has been provided with the PERT data:

Given the table of project activities:

(a)Develop a PERT Activity on Node diagram for the project (This diagram must specify the

critical path and duration of the CP,

通过PERT分析的关键路径可知完成整个项目可能需要24个工作日

(b)Construct a table which identifies: Activity, duration, Early Start, Early Finish, Late Start,

(c)What can you conclude about the project duration from analysis of the PERT network

diagram?,

通过PERT分析关键路径我们可知对于分解模块审计决定了整个项目的进程。因此如果能够控制对分解模块审计的时间就可以有效地缩短整个项目所需要的时间

(d)What are the primary concerns that a PM must consider in using PERT for project

scheduling?

利用PERT进行项目管理调度主要考虑时间的不确定性,重点在于对时间的控制,在已知乐观时间,悲观时间和最可能时间的前提下,通过公式

计算出期望时间最后确定关键路径。

REQUIREMENT 4: Risk Management

James TAN is concerned about the failure in the project. There is a great deal at stake for the company, not to mention his career. He approaches you and says that he heard that, “Risk Management is an approach that can totally el iminate project failure.” Based on your knowledge of risk management and the case situation:

(a)discuss the statement made by James TAN,

James Tan的论断是不全面的。风险管理的主要目的是在项目管理过程中识别风险和控制风险。通过对风险的转移、防范、避免、降低和利用五种策略可以有效的进行风险管理。在任何项目中都存在着风险,风险是一种不确定性,风险可能会导致项目的失败,有效的风险管理可以降低这种可能性。但是项目失败不一定都是风险因素造成的。所以风险管理不能完全消除项目失败的可能性。但是能够有效的降低这种可能性。

(b)identify primary sources of risk inherent in this project,

该项目的风险源大致可以定义为以下几点:

1.对时间或资源可用日期的估计错误;对浮动时间或时差的分配管理不善

2.成本风险,虽然公司高管承诺了无需考虑成本,但并未明确具体成本上限

3.人力资源风险,项目组织和职责划分不科学,人员缺席等

4.技术风险,缺乏培训,对方法、工具和技术理解的不够,应用领域的经验不够,新的技术和

开发方法,不能正确工作的方法

5.沟通相关风险,包括与客户,高管和组员间的共同问题

(c)develop and discuss the role that risk management can play in successful accomplishment of

THIS project.

1.有助于项目经理制定切实可行的项目进度计划

2.有助于公司高管更好的理解项目(从成本上考虑)

3.有助于项目经理更好的进行资源管理和调配,充分发挥各组员的能力,高效率高质量完成项目

4.有助于项目经理预见项目中的技术难点并提前进行公司内部的资源调配来克服技术困难,从而使项目能够顺利的进行。

5.有助于促进项目经理与公司高管,客户和组员的沟通,明确需求,汇报进度,做到问题早发现早报告早预防早解决

软件系统项目工作总结报告

软件系统项目工作总结报告 自2月份开始,我一直在跟进xx银行w-xxND1S2.0项目的测试工作,至此为止已近6个月时间,从公司内部系统测试、验收测试,再到UAT测试,以及投产前的系统压力测试等等。从开始到项目即将结束,一步步走过来。本次项目中,我作为测试环节的主力人员之一,仅对此项目中测试工作进行总结。 一、项目测试进度控制。项目的测试进度主要是按照项目计划进行的,完全按照项目组计划要求完成测试任务、提交测试类相关文档,包括测试案例的完善、制定测试计划、执行测试、缺陷跟踪以及BUG 回归测试等。协调项目的内部测试工作,本此项目中测试小组一共组织了四轮次系统全面测试工作,认真配合项目工作,共同保证项目质量。项目测试的问题跟踪及处理采用每日进行修改问题回归测试工作,每日同步更新问题跟踪单的模式,按照规划时间完成系统更新测试。 二、项目组内部成员关系处理。在项目工作的这几个月里大家相处融洽,项目组内部共同探讨解决问题的方法,向各模块负责人学习模块功能处理方式,向业务人员了解系统中涉及的业务知识点,两者结合起来进行模块功能测试。鉴于之前辖内对公交易系统和中行对公项目的经验,也向项目组提出了一些完善性意见。 三、协调用户测试方面。用户验收测试是项目测试工作的重要组成部分之一,是项目验收阶段的最终把关阶段,业务人员结合日常业

务处理情况对系统进行的尝试性使用过程。本次项目客户测试方面也是我个人觉得不够安全感一个主要方面,客户测试介入力度太小,尽管我们已经很多次电话催促业务人员测试,每次联系相关业务人员进行测试,他们来到项目组开发现场测试,也仅仅一两个小时时间,简单的进行验证操作即可。xx银行利用两批系统培训的时间安排了两次分行集中测试,也算给项目进行了一次全面的测试,从中也暴露出不少系统存在的问题,目前项目组均已解决。[ ] 四、测试成效方面。中信X-FUNDS2.0系统测试中,共记录问题及客户新增需求825个,其中BUG数量512个、系统完善类问题225个,新增需求类问题88个。组织了四轮次内部系统全面测试工作,兼顾日常系统更新测试工作,最大限度的进行了内部质量把关。配合外包公司一同进行系统压力测试及稳定性测试,测试结果符合客户要求。现中信X-FUNDS2.0系统临近投产实施工作,测试组还将继续配合配合项目投产工作及投产后的补丁更新测试工作。 四、个人得失方面。作为此次项目测试的负责人,对于日常的测试流程、测试任务分配、测试执行、缺陷跟踪、协调内部测试及协调客户测试方面能力均得到了进一步提高,理清了项目整个过程中测试小组的工作过程以及后期的项目移交工作。同时也对各子系统相应的业务知识有了更进一步认知。相关业务知识方面还需要进一步加强,测试技能及测试管理方面还需要进一步完善学习。更好的吸收项目经验,做好以后的补丁测试工作及其他项目的测试工作。

软件项目管理与案例分析 期末复习题

《软件项目管理与案例分析》复习题 一选择题 1. 核心计划过程有明确的依赖关系,在大多数项目中要以同样的顺序必须完成。下列哪一项符合核心计划过程的正确顺序:. A. 范围规划--范围定义--活动排序--活动工期估计 B. 范围定义--范围规划--活动定义--活动排序--活动工期估计 C. 范围规划--范围定义--活动排序--活动定义--活动工期估计 D. 活动工期估计--范围规划--范围定义--活动定义--活动排序 参考答案:A 2. PERT和CPM的主要区别在于PERT: A.在计算进度时使用分布的均值(预期值) B.使用最可能估算计算浮动时间 C.侧重计算浮动时间来确定那些活动的进度没有灵活性 D.在图中包括了回路或条件分支活动 参考答案:A 3.由于你的项目的范围发生变更,因此成本基线也发生变更。你的下一步将是: A.估计范围变更的程度 B.更新预算 C.记录获得的经验 D.执行得到批准的范围变更 参考答案:D

4. 以下哪项不属于合同管理的部分? A.评估风险 B.确认已经送出建议书 C.确认已经进行了合同变更 D.回答潜在卖方的问题 参考答案:D 5. 你负责对项目进行成本估计工作。因为要求成本估计尽可能精确,所以你决定做出保守的估计。你的第一步工作是: A、确定一种计算机工具帮助进行估计成本 B、利用以前的项目成本估计 C、确定并估计项目的每项工作的成本 D、咨询各方面的专家,并在他们的建议的基础上进行成本估计 参考答案:C 6. 项目整体管理是指? A.复杂系统的软件集成管理 B.将系统开发过程的管理和项目管理结合起来 C.将系统的主机平台.网络平台.应用软件开发和系统环境建设作为一个整体来进行项目管 理 D.包括在项目生命周期中协调所有其它项目管理知识领域所涉及的过程 参考答案:B 7. 涉及多领域工作的复杂项目最好由下列哪种组织形式管理: A.项目型 B.职能型

论软件项目管理的现状分析和对策

论文关键词:软件企业;项目管理;现状;分析;对策论文摘要:本文主要分析了我国软件项目管理的现状及存在的误区,总结了软件项目管理方面的经验,提出了初步的解决方案和办法。随着计算机硬件水平的不断提高,计算机软件的规模和复杂度也随之增加。计算机软件开发从“个人英雄”时代向团队时代迈进,计算机软件项目的管理也从“作坊式”管理向“软件工厂式”管理迈进。这就要求软件开发人员特别是软件项目管理人员,要更深一步地理解和掌握现代软件工程的理论方法,完成思想观念上的转变。本人结合软件项目管理知识,对我国IT行业的特点及相关的软件项目管理工作普遍存在的问题和思想观念上容易陷入的误区进行了分析,并提出了初步解决方案和办法。一、IT行业的发展特点随着信息技术的发展,IT行业以惊人的速度逐步深入到社会各行各业,成为推动社会进步和国民经济发展的重要力量,对我国传统产业和传统的企业管理理念产生巨大的冲击,深刻地改变着人们的生产、生活和工作方式。1、高技术性IT行业是最典型的技术密集型、知识密集型的产业。人才是IT行业最宝贵的财富,具有明显的技术性、流动性和年轻化的特点。2、高渗透性IT行业具有很强的渗透性和带动作用,是国民经济发展的倍增器,IT行业已逐步渗透到我国第一、第二、第三产业以及社会生活的各个领域,有效地推动了产业结构调整和技术升级,提高了人们的生活质量,为产业发展和整个社会生活带来革命性的变化。3、高风险性IT行业在产品研发、生产和市场推广过程中,都要进行巨额的资金、设备和人力投入,由于技术的高度复杂性和市场的高度不确定性,项目风险控制难度加大,项目的成功率较低。但是一旦某个新项目或新产品获得成功,将会带来相对高额的回报。4、高竞争性IT行业是一个富有创造性和挑战性的行业,要求在有限的资源条件下,在越来越短的时间范围内,为客户提供技术创新性强、个性化程度高的信息产品和服务。在我国企业ERP系统项目建设中,项目真正的成功率一般在40%一50%之间。目前,攀钢集团公司正投入巨资进行ERP系统项目建设,项目进展虽说顺利,但如何把行业发展和项目管理的实施有机地结合起来,提高企业信息化水平和效益,仍是面临的一个重要课题。 [1][2][3][4]下一页二、软件项目管理所存在的问题及对策软件项目管理IT行业的一个富有创新意义的领域,是针对特定的项目需求,以团队运作的形式,有效地组织项目资源,通过对项目的管理和控制,实现项目的目标。在我国IT行业起步较晚,但发展迅速,项目管理在IT行业的应用还很不成熟,一般的、常规的组织管理方式已很难适应,这是软件开发中项目管理面临的最大挑战。[!--empirenews.page--] 1、对项目管理认识和重视不够项目经理或管理人员不十分了解项目管理的知识体系,所以在实际工作中没有项目管理知识的指导,完全依靠个人现有的知识技能,管理工作的随意性、盲目性比较大。在软件企业中,项目经理主要是因为他们能够在技术上独当一面,而管理方面特别是项目管理方面的知识比较缺乏。希望尽快推行和实施软件项目经理知识技能资格制度,各方面都能充分认识项目管理的重要性,让项目经理自觉学习项目管理的知识和一些常用工具和方法。2、对项目的系统性把握不够在软件企业一些项目管理人员对项目总体计划、阶段计划的作用认识不足。项目经理认为计划不如变化快,项目中也有很多不确定的因素,做计划是走过场,因此制定总体计划时比较随意,造成计划与控制管理脱节,无法进行有效的进度控制管理。其实制定计划的过程就是一个对项目逐渐了解掌握的过程,通过认真地制定计划,项目管理人员可以知道哪些要素是明确和重要的,哪些要素是要逐渐明确和次要的,通过渐近明细不断完善项目计划。制定计划的过程,也是在进度、资源、范围之间寻求一种平衡的过程。因此,提高项目管理人员的计划意识,加强对开发计划、阶段计划的有效性,并进行事前事后的评估。3、管理思想贯彻不到位项目经理如果没有从总体上去把握管理整个项目,而是埋头于具体的技术工作,造成项目组成员之间任务不均、资源浪费。在软件企业中,项目经理大多是技术骨干,技术方面的知识比较深厚,但无论是项目管理知识,还是项目管理必备的技能、项目管理必备的素

软件项目经理工作总结.doc

软件项目经理工作总结 时间飞逝,光阴如梭,晃眼20xx年就过去了。在不知不觉中,新年也过完了。只放了7天假,太短太短,还没有休息够。年度总结都还没有开始写,新年就过完了。好了下面言归正传,总结一下20xx 年,这一年我都做了些什么。 一、做了什么 20xx年11月加入新公司,同时也尝试着做全新的岗位:软件项目经理(纯管理型)。我以前主要从事技术管理工作,现在转而从事项目经理工作。20xx年底进入公司后,公司给了我一个小项目a(用java开发的mis系统),让我先适应,这个项目是一个内部项目,业务比较简单,也没用什么新技术,领导对我的指示就是让我放手用敏捷开发agile的方法去管理项目,就当是敏捷的试验田来做。有了这话我也就放开了,大刀阔斧的就干起来了。 之后接着就是我的"噩梦"了,公司新开发了一条产品线,是云计算方面的。领导找我谈话,让我结束手上所有的案子,以后全心投入云计算产品线中来。该产品线下面有许多的项目,目前正在运行的有四个项目,其中三个由我来负责,另外一个由我的一个同事负责。说是我的"噩梦",其实也是对我的一个挑战,因为云计算的项目很偏技术,业务层面相对较少。所以对于我这个技术的门外汉来说是一个很大的挑战。其次,云计算的技术也比较前沿,待解决/未解决的问题也特别的多,在开发的过程当中会碰到很多的阻碍。再次,以前只

带一个项目,现在同时带三个项目对于我来说也是一个挑战。但是我也很高兴能有这样的一个机会,接受挑战,没有挑战就不会有进步。 二、收获 1.完成了我人生中一次大的转型,从偏技术岗位成功转型到偏管理岗位上来了。 2.参加了pmp的考试,并一次通过,取得了pmp证书。(复习真的很辛苦) 3.学习了公司规范的项目管理流程,结合pmp的学习,对同事们也混熟了,结交了不少朋友,非常感谢他们给我的帮忙和支持。 三、不足 1.项目虽然都跌跌闯闯的完成了,结案了。但是总觉得有很多的不足,可以改进的地方。项目结束的太匆忙,没有太多时间去想,去总结经验和坚持下来,断断续续,总是说没有时间。 2.业余时间没有抓紧,太贪玩了。 3.来新公司1年多了,还没有加薪,有点失望。 时间飞逝,光阴如梭,晃眼20xx年就过去了。在不知不觉中,新年也过完了。只放了7天假,太短太短,还没有休息够。年度总结都还没有开始写,新年就过完了。好了下面言归正传,总结一下20xx 年,这一年我都做了些什么。 一、做了什么 20xx年11月加入新公司,同时也尝试着做全新的岗位:软件

软件项目管理及案例分析

软件项目管理及案例分析 引导语:美国项目管理专业资质认证委员会主席PaulGrace说过,在当今社会中,一切都是项目,一切也将成为项目。下面是为你带来的软件项目管理及案例分析,希望对你有所帮助。 中国科学院计算技术研究所是国家专门的计算技术研究机构,同时也是中国信息化建设的重要支撑单位,中科院计算所培训中心是致力于高端IT类人才培养及企业内训的专业培训机构。中心凭借科学院强大师资力量,在总结多年大型软件开发和组织经验的基础上,自主研发出一整套课程体系,其目的是希望能够切实帮助中国软件企业培养高级软件管理与技术人才,提升整体研发能力。迄今为止已先后为国家培养了数万名计算机专业人员,并先后为数千家大型国内外企业进行过专门的定制培训服务。 高水平项目管理是软件项目成功的关键,也是软件产品质量的根本保证,具有这方面理论和实践的人员是目前软件组织中急需的高层次人才。为建立符合中国国情的软件开发过程和组织体系,培训中心特举办“软件项目管理”培训班,具体事宜通知如下: 一、培训对象 软件开发机构高级管理人员、项目经理、系统架构师、系统分析师、资深开发人员、质量保证人员以及其他对提升软件开发质量负有责任的人员。二、学员基础 1,对软件项目的分析、设计、组织和开发具有一定实践经验;

2,有一定的软件项目管理、技术管理或质量保证的基础知识与实践经验。三、师资 由业界知名专家亲自授课: 袁老师培训中心高级讲师,CMMI、GJB5000A高级咨询顾问,具有多年成功管理大型软件项目的经验,对软件工程管理与过程具有深邃的理论见解和丰富的实践经验。四、培训要点 高质量软件于高水平的项目管理,这个观点已经成为业内的共识。软件项目成功最重要的要素是什么?大型软件项目是依靠一个组织来完成的,如果这个组织在管理上是无序的,开发过程是非正式和混乱的,计划期限和成本目标通常超限,项目的成功取决于个人英雄式的行为,在人员发生变动时项目往往陷入灾难,那么很难说这个项目会获得成功。从这个意义上说,软件项目管理是项目成功的关键因素。 所有软件开发机构都必须在今天这种技术含量高、变化速度快、资源有限的环境下,实现软件生产规模化、规范化、国际化,这也是当前我国软件行业面临的最大挑战。在这样复杂的背景下,我们该如何去思考如何去做呢?1,项目管理人员必须具备更广阔的视角,包括站在更高的角度理解企业管理的思想理念, 理解产品开发的质量、成本、效率与效益之间的关系,理解过程是如何对管理发挥作用的,理解规范化的软件工程方法。更重要的是,理解如何提升自身的领导素质,培养更好的领导力。这种宽阔的眼界,对于一个高级项目管理人员极其重要。

软件项目管理案例分析

IT项目管理案例分析The GPS Auto-navigation System Verification Project 戴小卫 Z09030928 9/25/2010

REQUIREMENT 1: Project Organization You quickly began assembling the project planning team. The team would have responsibility for: (1) developing the project plan and schedule, (2) conducting the reliability testing of the guidance systems, (3) conducting the tear down audit and interpreting the results, and (4) reporting the results of the project to Senior Management. This is your project. Your project team consists of Gail YU, Manager of Quality Engineering, Tom HUANG, Manager of Design and Product Engineering, Jesse LIU, a senior engineer from Product Manufacturing, and Pete DONG, a senior engineer from Administration responsible for component purchasing and incoming testing of materials. Each member of your project team has access to whatever resources they need to support the project. This is a top priority for the company and you have been assured that you will “get whatever you need to complete the project”. You decide that a first order of business is to develop a Project Charter. You will have an initial meeting in one day with the project management team. This is where you will develop the project objectives, roles, and responsibilities. You decide to go in with a draft and have the team work from there. In preparation for this meeting, (a) develop an initial project charter, 项目名称:导航系统可靠性测试及模块分解审计 项目起始时间:2010-9-1 项目结束时间:2010-9-27 项目目标:通过对5套导航系统的可靠性测试和模块审计,分别从工艺评估和工程设计分析去判断那些工艺上的缺陷对产品的影响。通过测试结果的说明去说服客户公司的 产品设计和实现是可靠可信的。 项目经理:Da i xiaowei Reliability Engineering Manager 项目成员:Gail YU, Manager of Quality Engineering Tom HUANG,Manager of Design and Product Engineering Jesse LIU,senior engineer from Product Manufacturing Pete DONG,senior engineer from Administration responsible for component purchasing and incoming testing of materials

建立ERP项目管理制度的重要性.

建立ERP项目管理制度的重要性 企业管理项目培训网 实施ERP是一项深刻的管理革命,是一场耗资大、实施周期长、涉及面广的系统工程,项目不仅涉及企业运营各个环节和相关的部门,同时也涉及ERP软件供应商、ERP顾问服务提供应商、硬件供应商和系统集成供应商等多个商业组织,如何在这种复杂的局面下稳步高效推进ERP实施项目,并达到预期效果?建议一套项目管理制度是项目管理的前提和基础,同时项目管理制度还必须具备“行之有效”的核心含义。本文笔者以领导的一个ERP实施项目为实例,探讨了建议行之有效的项目管理制度在ERP实施项目中的重要性。行之有效的项目管理制度不仅是项目需求和项目范围管理和项目团队组建的基础,同时也是项目计划制定的依据,是项目各项目干系人合作的基础,是先进项目管理思想在ERP实施项目上的具体体现形式,在项目的启动、计划、执行、控制、收尾等各过程组中发挥着重要的作用,行之有效的项目管理制度是ERP实施项目的纲领,是项目的“宪法”。 ERP管理系统具有双重核心,即管理思想和信息技术。ERP就是运用信息技术将企业内的资金流、物流和信息流进行有效集成,使其协调运作,从而实现整个企业绩效最优化。同时, ERP系统对信息的及时高效处理,减轻了加工负担,对数据进行统计、分析与挖掘,提炼了知识。实施ERP系统是有效解决企业的诸多困扰,提升综合管理能力的最有力的手段。 ERP实施项目是一个庞大的系统工程,是一场耗资大、实施周期长、涉及面广的系统工程,目的是要实现系统运行集成化、业务流程合理化、绩效监控动态化、管理改善持续化。但要达到这些目的,会涉及到企业管理理念的变革、流程的新建、重组与再造及企业资源的整合,因变革可能各方存在职能与观念的错位。同时面临很多不可控因素,不仅涉及到整个企业运营各业务部门,同时也涉及软件供应商、顾问服务供应商和硬件供应商及系统集成供应商,只有有效协调各项目涉及各方,协调各方能有效预防、规避或出现问题能有效进行协商解决,是成功实施ERP实

软件项目管理年度工作总结范文

( 工作总结 ) 单位:_________________________ 姓名:_________________________ 日期:_________________________ 精品文档 / Word文档 / 文字可改 软件项目管理年度工作总结范 文 Annual work summary model of software project management

软件项目管理年度工作总结范文 软件项目管理已经到了学期的最后,我们seed小组的软件项目也已完工,这一个学期真的是获益匪浅! 礼平老师曾经说我既可以走技术路线也可以走管理路线,一切都看我自己。真的很是佩服老师的看人眼光,很犀利。我知道,现在的我不是没有能力去做好,只是自己没有去做,一直在殿外徘徊,不肯付出努力向前迈进。从大一到现在,我的专业技术一直都是我的短板,理由么,很简单,就是因为自己懒,不肯花时间去做。从以前不知道自己想做什么,到现在明确目标,可以说,软件项目管理课程给了我很多灵感,让我从自己纷乱的思绪中看清楚了自己最想要的东西。一直自己很喜欢管理,我会花费很多时间在这上面,从大一到现在一直都是,一直没有改变过。在技术上,我总是给自

己找借口,总是偷懒,但我现在明确了一点,没有技术,就没有管理!脱离技术的管理是不可能的,也是不现实的。在这个行业里,技术是一切的基本,想作工程师也好,想作管理者也好,技术都是起步的根基。而我这次所经历的项目更让我明确了这一点。在这个小项目里,虽然我们两个星期就开发完成了这个软件,并交付使用,但是问题还是很多的。在这么一个小项目里,由于需求、设计、代码、文档产生的问题,每一个看似容易,却都需要实实在在的经验在里面,都需要对业务的熟悉,有语言功底作根基。 在这个项目里,我负责软件配置管理工作,在文档的整理过程中,我仔细看了他们的需求分析,概要设计,数据库设计,模块设计等文档,也参与了风险分析文档的编写,承担了用户手册和项目成本估算的编写。在这个过程中,我明确了技术的实在意义,明确了技术对我的指导作用,同时也明确了自己的学习道路应该怎么走下去! 整个项目进行的过程中,我一直在努力从中学习,我旁听开发组的会议,为组长提供管理意见,为会议、文档制定标准,整个过

软件项目管理案例教程第4版前十二章课后习题答案

第一章 一、填空题 1.敏捷模型包括(4)个核心价值,对应(12)个敏捷原则。 2.项目管理包括(启动过程组)、(计划过程组)、(执行过程组)、(控制过程组)、(收尾过程组)5个过程组。 二、判断题 1、搬家属于项目。(√) 2、项目是为了创造一个唯一的产品或提供一个唯一的服务而进行的永久性的努力。(×) 3、过程管理就是对过程进行管理,目的是要让过程能够被共享、复用,并得到持续的改进。(√) 4、项目具有临时性的特征。(√) 5、日常运作存在大量的变更管理,而项目基本保持连贯性的。(×) 6、项目开发过程中可以无限制地使用资源。(×) 7、相比传统开发的预测性过程,敏捷开发属于自适应过程(√) 三、选择题 1、下列选项中不是项目与日常运作的区别的是(C) A. 项目是以目标为导向的,日常运作是通过效率和有效性体现的。 B. 项目是通过项目经理及其团队工作完成的,而日常运作是职能式的线性管理。 C.项目需要有专业知识的人来完成,而日常运作的完成无需特定专业知识。 D.项目是一次性的,日常运作是重复性的。 2、以下都是日常运作和项目的共同之处,除了(D) A.由人来做 B.受限于有限的资源 C.需要规划、执行和控制 D.都是重复性工作 3、下面选项中不是PMBOK的知识域的是(A) A.招聘管理 B.质量管理 C.围管理 D.风险管理 4、下列选项中属于项目的是(C) A.上课 B.社区保安 C.野餐活动 D.每天的卫生保洁 5、下列选项中正确的是(C) A.一个项目具有明确的目标而且周期不限 B.一个项目一旦确定就不会发生变更 C.每个项目都有自己的独特性 D.项目都是一次性的并由项目经理独自完成 6、(B)是为了创造一个唯一的产品或提供一个唯一的服务而进行的临时性的努力。

软件项目管理计划书案例完整

学生宿舍信息管理系统项目计划书

目录 第一章前言---------------------------------------------------------2 1.1项目开发背景-------------------------------------------------2 1.2项目开发目的-------------------------------------------------2 1.3项目开发意义-------------------------------------------------2 第二章范围计划-------------------------------------------------------3 2.1项目工作分解结构--------------------------------------------3 2.2软件生命周期模型---------------------------------------------5 2.2.1软件生命周期模型图示表示-----------------------------------6 2.2.2软件生命周期模型详细文档-----------------------------------6 (一)软件规划----------------------------------------------6 (二)需求开发----------------------------------------------7 (三)软件结构设计-------------------------------------------8 (四)数据库设计-------------------------------------------10 (五)实施-------------------------------------------------10 (六)系统集成----------------------------------------------10 (七)提交-------------------------------------------------11 (八)维护-------------------------------------------------11 第三章进度计划------------------------------------------------------11 3.1甘特图-----------------------------------------------------11 3.2网络图(单代号或双代号)-------------------------------------12

软件项目管理经验总结

软件项目管理经验总结 管理分为实行计划、组织、指挥、协调、控制。优秀的管理者是可以通过努力达到的。下面是X整理个人管理经验 总结的范文,欢迎阅读! 个人管理经验总结篇一 各位领导: 今天我就自己在广利工作2个月以来的心得和体会来跟大家进行探讨和研究,在我这2个月的工作中,得到了站内各级领导的大力支持,在此深表感谢!也从公司各位领导身 上学到了很多经验和做法,比如王秀涛站长、张盛聪副站长、冯汉彪经理等,因为我觉得这些领导在各自的岗位上都有一套独特的管理方法和管理理验,而且是比较成功的,我们中国有句古话叫做“有容乃大”你们的方法与经验也是我将后工作中不断学习与总结的借鉴,“他山之石,可以攻玉”。作为广利公司管理层中的一员,我将我的管理思路和方向向各位领导作简明扼要的阐述,不周之处,望各位领导见谅指 '[正O 一、树立正确的领导管理心态,严格要求。 作为一名领导者,对每一个员工都应该做到公平、公正、客观。能够听取下属员工不同的意见,工作中的分歧不能掺杂个人感情。对下属员工的严格要求,在我看来,并不是对

他们苛刻,而是在真正的帮助他们,逼迫他们进步,能适应社会残酷的竞争,我在给机修班开会时说过:每一个行业 都逃不过市场经济发展的潜规则,高速发展期(目前混凝土行业就是这个阶段),市场饱和期、优胜劣汰期。在不久的将来,混凝土行业就会进入市场饱和期和优胜劣汰期,那时就会有部分企业被市场淘汰,行业从业人员就会超过市场需求,岗位竞争会越来越激烈,如果没有过硬的工作作风和技术,就会被市场所淘汰。而我们都是男人,男人最基本的要求是应该有种家庭责任感,要有能力养活妻子,抚养孩子,照顾父母,这些能力需要我们有较强的社会竞争力,社会竞争力要靠我们积极的心态,努力工作,不断的学习,不断的进步,跟上社会发展的步伐。我们也更应该抓住现在行业的高速发展期这个机遇,通过不断的努力进步把自己提升到一个更高的层次,我不希望你们在我手下干了三年或者五年后还是一个机修,希望你们都能有独挡一面的能力,如果你们现在都不能严格要求自己,自己范围的事都做不好,怎么能进步,又会有哪一家企业、有哪一个老板会放心让你们去带一个团队。 二、营造良好的团队工作气氛。 在我的工作中,我积极主张这样一个理念:积极的人象太阳,照到哪里哪里亮;消极的人象月亮,初一十五不一样。在团队管理中,我会通过各种途径树立一个积极的榜样,让 每个员工都有一把衡量自己的标尺,都有一个努力的方向。 在这次的员工评级制度中,我极力主张过往不究,不追究员工以往

软件项目管理案例教程(第三版)课后复习题答案40517

第一章 二、判断题 1、搬家属于项目。(√) 2、项目是为了创造一个唯一的产品或提供一个唯一的服务而进行的永久性的努力。(×) 3、过程管理就是对过程进行管理,目的是要让过程能够被共享、复用,并得到持续的改进。(√) 4、项目具有临时性的特征。(√) 5、日常运作存在大量的变更管理,而项目基本保持连贯性的。(×) 6、项目开发过程中可以无限制地使用资源。(×) 三、选择题 1、下列选项中不是项目与日常运作的区别的是(C) A. 项目是以目标为导向的,日常运作是通过效率和有效性体现的。 B. 项目是通过项目经理及其团队工作完成的,而日常运作是职能式的线性管理。 C.项目需要有专业知识的人来完成,而日常运作的完成无需特定专业知识。 D.项目是一次性的,日常运作是重复性的。 2、下列选项中最能体现项目的特征(C) A.运用进度计划技巧B.整合围与成本C.确定期限D.利用网络进行跟踪3、以下都是日常运作和项目的共同之处,除了(D) A.由人来做B.受限于有限的资源C.需要规划、执行和控制D.都是重复性工作 4、项目经理的职责不包括(D) A.开发计划 B.组织实施 C.项目控制 D.提供资金 5、下列选项中属于项目的是(C) A.上课 B.社区保安 C.野餐活动 D.每天的卫生保洁 6、下列选项中正确的是(C) A.一个项目具有明确的目标而且周期不限 B.一个项目一旦确定就不会发生变更 C.每个项目都有自己的独特性 D.项目都是一次性的并由项目经理独自完成 7、(B)是为了创造一个唯一的产品或提供一个唯一的服务而进行的临时性的努力。 A.过程 B.项目 C.项目群 D.组合 8、(B)是一系列伴随着项目的进行而进行,目的是确保项目能够达到期望结果的一系列管理行为。 A.人力资源管理 B.项目管理 C.软件项目管理 D.需求管理 9、下列活动中不是项目的是(C) A.野餐活动 B.集体婚礼 C.上课 D.开发操作系统 10、下列选项中不是项目的特征的是(C) A.项目具有明确的目标 B.项目具有限定的周期 C.项目可以重复进行 D.项目对资源成本具有约束性 第二章 二、判断题 1、项目初始阶段甲方为软件开发方,乙方为顾客。(×) 2、项目招标对于一个项目的开发是必需的,即便项目是部项目。(×)

软件项目管理案例教程(第2版)课后习题答案(详细版)

课后练习题答案 序-- 练习题 一、回答问题: 1.项目集成管理 (Project Integration Management) 是什么? 集成项目管理是项目成功的关键 ,它贯穿了项目的全过程,包括从初始、计 划、执行、管理到结束等过程。项目集成管理在项目的整个生存期内协调项 目管理其他各管理知识域,保证项目总目标的是实现。 2.项目管理九大知识域是什么? 项目管理九大知识域是项目范围管理、项目时间管理、项目成本管理、项目 质量管理、项目人力资源管理、项目采购管理、项目沟通管理、项目风险管理、 项目集成管理。 3.项目成本管理( Project Cost management)包括哪些过程? 项目成本管理( Project Cost management )包括成本估算(Cost estimating),成本预算( Cost budgeting),成本控制( Cost control)等 过程。 4.项目管理的五个过程组是什么? 项目管理的五个过程组是启动过程组、计划过程组、执行过程组、控制过程组、 收尾过程组。 5.下面活动是项目: 野餐活动 集体婚礼 开发微软的操作系统 神州飞船计划 二、判断题: 6. 项目开发过程中可以无限制地使用资源。(×) 7.项目具有暂时的特征。(√) 8.项目管理核心的三角形是范围、进度、风险。( X ) 9. 过程管理与项目管理在软件组织中是两项最为重要的管理,项目管理用于保证 项目的成功,而过程管理用于管理最佳实践。(√) 10.运作管理 (Operation Management)是从宏观上帮助企业明确和把握企业发展 方向的管理。(×) 第一章练习题 一、名词解释 1.项目章程 项目章程( project charter )是指项目执行组织高层批准的一份以书面签 署的确认项目存在的文件,包括对项目的确认、对项目经理的授权和项目 目标的概述等。

软件项目管理总结

软件项目管理过程的简单总结 学院:计算机学院 班级:软件11 姓名:雷莉莎 做任何事情都需要管理,好的管理出好的效益,开发软件项目也不例外。随着信息系统工程、网络工程、软件工程的发展,项目管理和软件工程的交汇越来越多,从而使“软件项目管理”发展起来,一个项目的成功与否,关键一点就是,看项目管理是否得当。所以,项目管理是项目的核心部分,是项目的灵魂。 软件项目管理的概述 所谓项目,就是在特定条件下,具有特定目标的一次性任务,是在一定时间内,满足一系列特定目标的多项相关工作的总称.项目具有一次性、独特性、目标的确定性、组织的临时性和开放性以及成果的不可挽回性等基本属性。 而软件项目管理是为了使软件项目能够按照预定的成本,进度、质量顺利完成,而对人员,产品,过程和项目进行分析和管理的活动。根本目的是为了让软件项目尤其是大型项目的整个软件生命周期(从分析,设计,编码到测试,维护全过程)都能在管理者的控制之下,以预定成本按期,按质完成软件交付用户使用。 软件项目的管理过程详解 在软件项目开发管理过程中,不仅要努力实现项目的范围、时间、成本和质量等目标,还必须协调整个项目过程,以满足项目参与者及其他利益相关者的需要和期望。随着软件规模和所涉及的领域不断扩大,软件项目的管理越来越困难。纵观所有失败的软件项目,基本原因是不能管理其软件过程,在无纪律、混乱的项目状态下,组织不可能从较好的方法和工具中获益。严谨的软件过程控制与管理不仅可以在每个阶段回顾和纠正项目的偏差,识别软件项目的风险甚至果断中止项目,而且可以将人才流动所带来的不利影响减少到最小。要进行有效的过程控制,必须明确软件项目管理流程。 下图即为软件项目管理流程: 接下来详细介绍项目管理过程的步骤包括: 项目立项——启动——规划——执行和控制——收尾阶段 1.软件项目立项包含5个环节:发起、评估、申请、审核、立项。 立项流程图 2. 项目的启动就是确定项目的目标范围,它主要包括开发和被开发双方的合同(或是协议),软件要完成的主要功能以及这些功能的量化范围,项目开发的阶段周期等。 PMBOK中明确指明项目启动阶段主要的工作是制定项目章程和识别项目干

软件项目管理案例分析题

软件工程管理案例分析 案例分析一 问题1: 本工程申请国家技术创新基金100万元,但国家实际批准基金额度很可能会低于100万元,“工程投资来源”中应当说明:当国家实际批准基金低于申请额度时,如何补足二者之间的差额以及由此所引起的地方匹配基金的差额。 应重新召开股东大会并讨论以下议题:当国家实际批准基金低于申请额度时,公司是否愿意补足二者之间的差额以及由此引起的地方匹配基金的差额。 如果能够通过,应在“工程投资来源”中加注:当国家实际批准基金低于申请额度时,公司承诺补足二者之间的差额以及由此引起的地方匹配基金的差额(附新的公司股东大会决议)。 问题2: A,B双方以B方现有技术成果为基础进一步合作开发,应明确以下几个主要问题: (1)B方是以现有技术成果折价入股,还是将现有技术成果转让给A方; (2)如果是“技术转让”,应明确是“专利权转让”、“专利实施许可”、还是“技术秘密转让”? (3)双方是否已就合作开发的新技术成果的所有权、使用权以及利益分成问题达成一致意见? 双方是否已正式签订“合作开发合同”或“技术转让合同”? 问题3: 应主要从以下几方面分析工程技术的成熟性: (1)关键技术成熟性分析(包括采用的现有成熟关键技术、已攻克的关键技术、待研究的关键技术等); (2)工程采用的关键技术是否获得国家、部门或地方科技计划的支持(已获得、尚未获得)及计划的名称、获得支持的时间; (3)工程采用的关键技术是否通过技术鉴定(已鉴定、尚未鉴定)及鉴定单位、鉴定意见、鉴定时间。 案例分析二 问题1: 由工程执行偏差导致工程计划变更的各种诱发因素称为工程变更的内部因素。由工程目标变化导致工程计划变更的各种诱发因素称为工程变更的外部因素。 问题2: “B方首付资金未能按时交付”、“A方盲目确定进度目标”、“A方的前期设计有疏漏”、“A方编制的需求分析说明书未能准确、全面地表达B方的实际需求”、“B方自行负责的机房装修误期”、“A方开发人员跳槽”,属于工程变更的内部因素。 “证监会要求上市公司执行新的会计制度”、“B方因机构重组改变了业务流程”、“B方提出增加合同审计功能”、“B方行业主管部门发布了新的行业ERP实施规范”,属于变更的外部因素。 问题3: “A方盲目确定进度目标”、“A方的前期设计有疏漏”、“A方开发人员跳槽”,属于A方责任。由此而增加的工程经费,由A方承担。“需求分析时,B方表达不清,A 方理解有误,双方沟通不够,A方编制的需求分析说明了书未能准确、全面地表达B方的

软件项目工作汇报

软件项目工作汇报 篇一:软件开发工作汇报 XX市XXXXXXXXXXX信息 化平台 --工作汇报 XXXXXXXXX单位 2016年4月 XXXXX市XXXXXXXX工作汇报 目录 1 开发背景............................................................... . (1) 2 工作目标............................................................... . (2) 3 工作任务............................................................... . (3) 4 工作计划...............................................................

(4) 5 信息化平台开发执行标准 (6) 6 信息化平台实施完成任务情况 (7) 7 信息化平台自测效果............................................... (9) 8 信息化平台特色............................................................... .. (13) 9 总结............................................................... . (16) 1 开发背景 根据XX市XXXXX馆《XX市XXXXX管理信息化软件开发招标文件》对XX信息化的建设要求,于XXXXX 年X月X日对项目进行进行招标,采购项目名称为“XX市XXXXX管理信息化软件开发”,招标编号为“0XXXXXX”,XXXX信息技术有限公司

软件项目管理案例教程(第三版)课后习题答案

项目管理案例教程(第三版)习题及答案 第一章软件项目管理概述 一、填空题 1、实现项目目标的制约因素有(项目范围)、(成本)、(进度计划)、(客户满意度)等。 2、项目管理包括(启动过程组)、(计划过程组)、(执行过程组)、(控制过程组)、(收尾过程组)5个过程组。 二、判断题 1、搬家属于项目。(对) 2、项目是为了创造一个唯一的产品或提供一个唯一的服务而进行的永久性的努力。(错) 3、过程管理就是对过程进行管理,目的是要让过程能够被共享、复用,并得到持续的改进。(对) 4、项目具有临时性的特征。(对) 5、日常运作存在大量的变更管理,而项目基本保持连贯性的。(错) 6、项目开发过程中可以无限制地使用资源。(错) 三、选择题 1、下列选项中不是项目与日常运作的区别的是(C) A. 项目是以目标为导向的,日常运作是通过效率和有效性体现的。 B. 项目是通过项目经理及其团队工作完成的,而日常运作是职能式的线性管理。 C.项目需要有专业知识的人来完成,而日常运作的完成无需特定专业知识。 D.项目是一次性的,日常运作是重复性的。 2、下列选项中最能体现项目的特征(C) A.运用进度计划技巧 B.整合范围与成本 C.确定期限 D.利用网络进行跟踪 3、以下都是日常运作和项目的共同之处,除了(D) A.由人来做 B.受限于有限的资源 C.需要规划、执行和控制 D.都是重复性工作 4、项目经理的职责不包括(D) A.开发计划 B.组织实施 C.项目控制 D.提供资金 5、下列选项中属于项目的是(C) A.上课 B.社区保安 C.野餐活动 D.每天的卫生保洁 6、下列选项中正确的是(C) A.一个项目具有明确的目标而且周期不限 B.一个项目一旦确定就不会发生变更 C.每个项目都有自己的独特性 D.项目都是一次性的并由项目经理独自完成 7、(B)是为了创造一个唯一的产品或提供一个唯一的服务而进行的临时性的努力。 A.过程 B.项目 C.项目群 D.组合 8、(B)是一系列伴随着项目的进行而进行,目的是确保项目能够达到期望结果的一系列管理行为。

相关主题
文本预览
相关文档 最新文档