带式输送机安装工艺指导书工艺名称Process name工艺要求Process request公差Tolerance质量问题Quality Question解决办法Solution地基Foundation按照带式输送机的安装尺寸,核实安装基础是否符合要求,测量安装基础是否在同一水平面上(指横向)According to theinstallation sizeof the beltconveyor,Verifyinstallation baseis in line with therequirements,Whethermeasuringinstallationbased on thesame horizontalplane(Refers tothe horizontal)水平面公差1/1000Level oftolerance1/1000地基水平Foundation Level可用垫片调整到水平为止Availableshimadjustment atthe level带式输送机安装中心线The center line of the belt conveyor installation按总装图的安装尺寸要求,将其尺寸复制到地基上,划完线后,再由工程质检进行检验确认According to therequirements ofassemblydiagram ofinstallationdimension,Its滚筒及托辊轴线对输送机机架中心线的垂直度2/1000,两相邻托辊对角线≤3mmPulley androller line tothe centerline of theconveyor先将头尾架划好中心,再用软线弹出带式输送机的中心线,根据中心线两侧分画中间架及支脚线Center headtail rack rowfirst,Pop upthe centerline of beltsize is copied to the foundation,After draw the line,Confirmed by the test engineering quality inspection again frameverticaldegree2/1000,Twoadjacentrollersdiagonal≤3mmconveyor witha soft lineagain,According to thecenter line onboth sides ofthe pictureframe andthe leg line头尾架Head and tail frame在经检验合格后的安装中心线上,进行头尾架的安装所用工具千坠、水平尺、差尺,主要测量头、尾架、滚筒座是否在同一水平面上(要求1/1000),尔后测出滚筒轴线对输送机中心线的垂直度(要求2/1000)In the inspectionqualified afterthe installation ofthe centerline,The headand tail rackinstallation toolsused forthousandpendant, spiritlevel, ruler,mainlymeasuring headand tail frame,pulley is in thesame horizontalplane(request1/1000),Then水平公差1/1000垂直公差2/1000The level oftolerance1/1000The verticaltolerance2/1000地基不平,头尾架变形The foundationuneven,Head to tailframedeformation①地基不平可用垫片进行调整;②机架变形可调整机架(1) thefoundationunevengasketavailable toadjust(2)the framedeformationadjustableframemeasure theverticality of cylinder axis of the center line ofthe conveyor(request 2/1000)支腿landing leg首先检测支腿是否变形,方法是测量两立柱的对角线,观测两立柱是否在同一平面上,确认无质量问题后,按地脚线进行安装,安装后确保支腿两侧立柱的直线度在任意25m长度内,公差为5mm,输送机长度≤100m,直线度10mm>100-300m,直线度30mm以内The firstDetectingwhether the legtransformation,Methods are thetwo pillar ofdiagonalmeasurement,Ifobserved twocolumns on thesame plane,Afterconfirmed withno qualityproblem,According to the anchorlineinstallation,Afterinstallation to对角线≤4,在任意25m直线度5mm≤100m直线度10mm,>100-300m直线度30mm以内Diagonal≤4,In any25 mstraightness5 mm or less100 mstraightnessis 10 mm, >100-300 - mstraightnesswithin 30mm地基不平,支腿变形The foundationuneven,Head to tailframedeformation①用垫片调整地脚;②修正支腿或变换(1) with thegasket toadjust theanchor(2) correctionof leg orchangeensure that the leg on either side of the column the straightness in arbitrary length of 25 m,tolerance of 5 mm,Conveyor length 100 m or less,straightness 10mm>100-300m,Straig htness of 30 mm中间架Middle Frame按图确定好下料点位置,首先安装与其对应的中间架,尔后按中间架排号进行安装,边安装边测量孔的对角线≤4mm,安装完后必须经质检人员签字合格后方可进行下一步工序According to thefigure fineblanking pointlocation isdetermined,First installationand itscorresponding tothe middle of theframe,Thenaccording to thenumeral middleframe forinstallation,Instal两侧中间架水平度2/1000,安装托辊横梁孔的对角线公差≤4mmOn bothsides of themiddle2/1000levelness,Install idlerbeam holediagonaltolerance of4 mm or less两中间架不在同一水平面上,对角线超差Two the middleframe is not inthe samehorizontal plane,diagonal error应认真调整、测量,注:这是对输送机跑偏与否起到关键性的工艺Should becarefullyadjusted,measurementNote:This iskeytechnology interms ofconveyorrunningdeviation ornotl while measuring hole diagonal 4 mm or less,After the installation must be done by the quality inspection personnel qualified rear can carries on the next working procedure滚筒pulley 头尾滚筒的安装要求转动灵活,垂直度要符合2/1000的公差要求The request ofinstallation abouthead and returnpulley is flexiblerotation水平度1/1000Levelness1/1000垂直度2/1000Vertical 2/1000①滚筒转动不灵活;Pulley’s rotationis not flexible②垂直度超差Vertical beyondtolerance①滚筒两侧瓦合用垫片进行调整到转动灵活为止;Adjustboth sides ofpulley’s tilecombinationwasher toflexiblerotation②检查划线是否有误,Check the dashwhether havemistake用调整螺栓进行调整be adjusted byadjusting thescrew托辊横梁及托辊convey frame and roller 认真查阅总装配图,注意缓冲托辊、前倾横梁及过渡横梁、调心托辊横梁的安装位置(两边的调心托辊先不上)Carefully reviewthe generalassembly drawing,Notice the installation location of impact rollers, forward beams and excessive beam,sphericalroller beams(spherical rollers both side can’t install firstly)输送带Conveyorbelt输送带安装前必须严格检查转动件转动是否灵活可靠,确认无问题后,可安装输送带,输送带的吊装严禁用带锐角的工具或钢丝绳直接接触带来吊运,可用>80mm直径的圆管等穿入带心进行吊装,输送带接头贴接采用硫化贴接,需专业技术人员完成Conveyor must bestrictly checkedbefore installationto confirm turningwhether flexibleandreliable.Installationconveyors afterconfirmed.Transporting conveyor beltsuse With sharptools or directcontact with wirerope isforbidden.Liftingcan usepenetration with aheart tube (pipediameter>带边撕裂Band edge tear吊装工具不对,更换工具Lifting tools iswrong,changetools80mm).Connector of conveyor belt use then pastesulfide byprofessionalworkers.跑偏开关、拉绳开关Deviation switch,Ro pe switch 输送带安装完毕后,在试运行前必须安装好跑偏开关及拉绳开关,否则禁止试车运行After installing conveyor belts ,andBefore commissioning,deviation switch and rope switch must be installedsuccessful.or commissioning isforbidden驱动装置Drive means 驱动装置安装时与传动滚筒对接,其两联轴器的标志一定对齐(此件为柱销联轴器)安装同心度≤0.7mm,安装完后按设备要求加足润滑油Install buff driveand drive pulley,the log of twocouplings mustalignment.(Thispiece is pincoupling)Installationconcentricity≤0.7mm,AddLubricating oil asequipment requestafter installation.同心度≤0.7mmConcentricity≤0.7mm转动时颤动或两相邻的轴承发热Rotation fibrillationor two adjacentbearings heating重新调整驱动装置位置,上下不同心可在驱动架下垫片,解决前后不同心,可移动驱动装置解决,以达到理想效果为止Re-adjust theposition of drivemeans .Drivingunder thegasket in theframe whileDown differentheart,Mobiledrive unit toslave Beforeand afterdifferentheart.The aimis to achieve the desiredeffectPloughunloader 犁式卸料器在下料口处安装犁式卸料器,安装后要进行调整,①胶板探出刮板10-15mm,②刮板要与输送带调至无间隙为止,在试运行前,把犁头抬起以减小开车阻力Install plough unloader at feed opening,after installing, adjust it.①rubber board is longer than scraper,about10-15mm.②Scraper and conveyor belt should be adjusted with no gap,before commissioning,lift the pough to reduce driving resistance.试运行Commissi oning 运行前准备工作:preparation beforeoperating一、检查驱动装置各润滑处所注入的润滑油牌号、数量是否符合要求;㈠Check thedriving devicelubricationpoint,the injectedoil grade and①启动电机后减速机不转动;①After startingthemotor,reducerdoesn’trotate.②整机无法启动;②②the conveyorcan’t beoperated.③启动后联轴器振动,轴承位发热升温超过40°C①液力偶合器是否加够了介质数量,①Fluidcoupling addenoughquantity ofoperationmedium②有逆止器的带式输送机是否转向不对,②checkquantity to meet the requirements.二、检查液力偶合器中注入的介质(油式水)质量、数量是否与传动功率相匹配(应加入介质量占总容积的75-80%);二、Check injected operationmedium(oiled water) of fluid couplingquality,quantity,wh ether match the transmission power(should be added to the total volume of operation medium quality 75%-80%)三、检查制动器闸瓦与制动轮间隙是否符合1.5-3mm的要求;三、Check the brake shoe and brake wheel gap,whether meets the requirements of 1.5-3mm.四、检查减速器输入轴的转向,逆止器的转向是否符合要求;点动试车四、Check the the steering of the gearbox input shaft,steering of inverted (含环境温度)③couplingvibrationstarts,bearingpositionheatingtemperaturerising over 40degrees.(including ambienttemperature)the beltconveyorwithinvertedvalve isturningright.③如联轴器振动或轴承位发热,应重新调整联轴器的同心度或轴承是否缺油。