水磨石地面施工组织设计
- 格式:doc
- 大小:399.50 KB
- 文档页数:16
目 录
1、编制依据.....................................................................................................................3
2、工程概况.......................................................... 3
2.1工程概况.....................................................................................................................2
2.2建筑设计概况.............................................................................................................2
3、施工准备.......................................................... 3
3.1材料准备....................................................................................................................3
3.2 施工机具...................................................................................................................4
3.2 施工机具...................................................................................................................4
4、操作工艺.......................................................... 5
4.1工艺流程....................................................................................................................4
4.2施工部位....................................................................................................................8
5、质量标准.......................................................... 9
5.1保证项目...................................................................................................................8
5.2 基本项目..................................................................................................................8
5.3 允许偏差项目..........................................................................................................9
6、成品保护......................................................... 10 7、应注意的质量问题................................................. 11
7.1 空鼓及处理方法.....................................................................................................10
7.2漏磨及处理方法......................................................................................................10
7.3磨纹、砂眼及处理方法...........................................................................................10
7.4倒泛水及处理方法..................................................................................................10
7.5面层石渣粒不匀及处理方法..................................................................................11
7.6强度偏低及处理方法..............................................................................................11
7.7分格条掀起,显露不清晰及处理方法...................................................................11
7.8质量保证体系..........................................................................................................11
8、安全文明施工措施...................................................................................................13
8.1施工操作人员安全管理要求..................................................................................13
8.2供电系统安全要求..................................................................................................13
8.3安全保证体系..........................................................................................................14
9、环保文明措施...........................................................................................................15
10、附图.........................................................................................................................16
1、编制依据
1.1《建筑工程质量验收统一标准》GB50300-2001
1.2《建筑地面工程施工质量验收规范》GB50209-2002
1.3《建筑机械使用安全技术规范》JGJ33-86
1.4《中小学设计规范》GB50099-2011
1.5金山小学美利山校区施工图纸
1.6 金山小学美利山校区设计变更及图纸会审记录
2、工程概况
2.1工程概况
工程名称 重庆北部新区金山小学美利山校区
质量监督单位 重庆北部新区建设工程质量监督站
建设单位 重庆首金房地产开发有限公司
设计单位 重庆卓创国际工程设计有限公司
地勘单位 四川蜀西地质工程勘测院
监理单位 重庆市建永工程监理有限公司
施工单位 北京首钢建设集团有限公司
合同范围 施工承包合同中约定范围
合同质量目标 达到国家标准、行业标准的合格标准,并符合设计图纸的要求
2.2建筑设计概况 总面积(m2) 7807.58 教学主楼
(m2) 5981.54 教学辅楼
(m2) 1156.14
室外篮球场(m2) 669.90
教学主楼 层数 地上部分 五层(含构架) 地下部分 一层(车库)
教学辅楼 层数 地上部分 二层 地下部分 0
教学主楼层数 地上部分 一层 地下部分 0
结构使用年限 50年 地震设防烈度 6度 耐火等级 一级
结构型式 教学主楼、辅楼:框架结构
3、施工准备
3.1材料准备
水磨石施工前,应做好材料准备,包括:
3.1.1 石子:所用石子必须质地坚硬的碎石(1-1cm),无风化。并根据设计要求,所选定的碎石的颜色和粒径的大小必须与封样一致。
3.1.2 分隔条
玻璃条:由设计确定或用普通3mm厚平板玻璃裁制成宽10mm左右(视石子粒径定)的玻璃条,长度由分块尺寸决定。
3.1.3 水泥
3.1.3.1 施工水磨石采用42.5级的复合硅酸盐水泥。
3.1.3.2 水泥进场使用前,应分批对其强度、凝结时间、安定性等必试项目进行检验、复试。
3.1.3.4 不同品种的水泥不得混合使用。
3.2 施工机具
3.2.1水磨石施工主要机具:磨石机、湿式磨光机、滚筒、小推车、平锹、3级配电箱、软轴磨边机、搅拌机、磅秤、垂直运输设备。 3.2 施工机具
3.3.1 顶棚、墙面抹灰已经完成,各种管线已埋设完毕,地漏口已经遮盖。
3.3.2 混凝土已浇筑完毕,按标高留出水磨石底灰与面层的厚度,并经养护达到设计要求。
3.3.3 弹好墙身+50cm水平控制线
3.3.4 工程材料已经备齐,运到现场,经检查质量符合要求。数量满足连续作业条件的需要。
3.3.5 石粒应分别过筛,去掉杂质并洗净晾干备用。
3.3.6基层已验收合格,无空鼓、裂纹、起砂等现象。
4、操作工艺
4.1 工艺流程
弹分格线→镶分格条→拌制水磨石拌合料→涂水泥浆结合层→铺水磨石拌合料→滚压抹平→试磨→粗磨→细磨→磨光→草酸清洗→打蜡上光
4.1.1 弹分格线
根据设计预设的分格尺寸,如果设计未要求一般采用lm×lm的分格尺寸,在房间中部弹十字线,计算好周边的镶边宽度后,以十字线为准可弹分格线,如果设计有图案要求时,应按设计要求弹出清晰的线条。