目 录
一、 监理工作的内容及范围·····························2
二、 监理的依据·······································3
三、 监理工作程序·····································3
四、 监理工作目标·····································4
五、 施工现场监理对质量管理的要求·····················4
六、 施工现场监理工作材料设备管理的要求···············5
七、 水暖工程施工过程的质量监理要求···················5
八、 室内给水系统安装·································9
九、 室内排水系统安装·································11
十、 室内热水供应系统安装·····························13
十一、室内卫生器具安装································14
十二、采暖辐射塑料管安装要求··························15
十三、室外给水管道安装································16
十四、室外排水管道安装································18
十五、室外供热管道安装································19
十六、自动喷水灭火管道安装····························20
十七、通风系统安装····································24
XXXXXXXXXXX工程给排水、暖气、通风
监理实施细则
本工程为XX公司XXX工程;包括商品房6栋集资房3栋;总工期600天..
炎黄科技园监理细则(给排水专业) 河南清鸿建设监理有限公司
第 1 页 共 11页
目 录
一、监理实施细则的编制依据 ................................. 2
二、专业工程概况 ........................................... 2
三、监理工作程序 ........................................... 2
四、监理工作质量控制要点及目标值 .......................... 10
五、监理工作方法与措施 .................................... 10
炎黄科技园监理细则(给排水专业) 河南清鸿建设监理有限公司
第 2 页 共 11页 一、监理实施细则的编制依据
(1)炎黄科技园工程监理规划。
(2)炎黄科技园工程施工图纸及有关资料说明。
(3)炎黄科技园工程施工承包合同
(4)炎黄科技园工程委托监理合同
(5)本项目有关的施工规范、标准和规定
二、专业工程概况
三、监理工作程序
(一)施工前准备阶段
1、施工前质量控制实施
1.1设计交底和图纸会审
1.1.1设计交底:施工图纸是监理单位、设计单位和施工单位进行质量控制的重要依据,设计交底应在施工前由建设单位组织各方有关人员参加设计单位设计交底工作。主要包括:水文、地质、地形、设计意图、施工注意事项。要了解各专业与本专业的关系。
1.1.2图纸会审:施工图会审是各方进行质量预控的重要手段。图纸会审之前,各方对施工图纸、设计说明,组织专业技术人员熟悉施工图,进行图纸会审,审查内容包括:图纸设计资格、设计资料是否齐全;施工图中有无遗漏;中心、标高是否相符;给排水专业与相关专业配合关系;施工图中所涉及的各种标准;图集规程炎黄科技园监理细则(给排水专业) 河南清鸿建设监理有限公司
目 录
一、给排水工程特点及其技术、质量标准 ......................... 1
二、监理工作范围及重点 ....................................... 1
三、监理工作流程 ............................................. 1
四、监理工作控制要点、目标及手段 ............................. 2
1、监理控制目标: ................................................................................... 2
2、监理控制要点: ................................................................................... 2
2.1室内给水系统安装 ......................................................................... 2
2.2.室内排水系统安装 ....................................................................... 34
2.3.室内热水供应系统安装 ............................................................... 41
2.4.室内卫生器具安装 ....................................................................... 47
2.5.室外给水管网安装 ....................................................................... 53
给排水.暖通工程监理实施细则最终版
一、 工程概况 (一)建筑概况 (二)暖通概况
1、本工程周边没有可利用的集中热源,住宅采暖采用家用燃气壁挂炉(热效率不低于88%),采暖供回水温度为80/60℃。 2、采暖室内外计算参数:冬季采暖室外计算干球温度:-7.6℃,平均风速:2.6m/s。冬季采暖室内设计参数:卧室、起居室、餐厅、卫生间:18℃,厨房:15℃。地下一、二层非燃烧品库房及设备房间不采暖。
3、本建筑各户型最大热负荷为:A1户型5.5kW,A2户型5.2kW ,A3户型5.2kW ,A4户型5.5kW 。B1户型5.5kW ,B2户型5.2kW ,B3户型5.2kW ,B4户型5.5kW ,B5户型5.5kW 。
4、住宅户内采暖系统采用水平串联单管跨越式系统,管道埋设在建筑垫层内。
5、散热器选型:散热器选用钢制高频焊翅片管散热器。GC6-25/300-1.0型,散热器高度600m ,标准散热量2156W/m,散热器底进底出接管,接管口径DN20。
6、燃气壁挂炉参数:选用两用型燃气壁挂炉,最大输出负荷18kW ,膨胀水箱容积7L ,最大功率110W ,电源220/50Hz,额定热效率93%,循环水泵扬程5MH 2O 。 7、通风、空调
7.1住宅每户房间预留分体空调器的位置,冷凝水管有组织排放; 7.2厨房自然通风,电气专业预留排油烟机插座。卫生间机械排风,电气专业预留排气扇插座。
7.3地下一、二层非燃烧品库房自然通风,电气房间机械排风。 7.4各电梯机房设机械排风。 8、通排风烟
8.1住宅、卫生间由用户自备排油烟机、排风扇,由建筑专业预
留竖向通风竖井,排放支管上应有逆止阀。配电室设排风,无外窗的水泵房、卫生间设排风。地下车库,排放兼排烟系统,排风管道上设有70℃熔断防火阀,一旦防水火灾。防护服、阀关闭,打开相应区域的排烟口进行排烟。同时送风兼补风系统开启,补风量不少于排烟量的50%;加压送风:消防电梯前室设置加压送风系统,防烟楼梯间自然排烟。