爆破工程消耗量定额
- 格式:doc
- 大小:2.82 MB
- 文档页数:198
实用标准文档目 录编制概况...................................................................................................................................................... . (1)第一章 土石方工程...................................................................................................... (7)第二章 地基处理与边坡支护工程........................................................................................................22第三章 桩基础工程...................................................................................................... (31)第四章 砌筑工程...................................................................................................... (40)第五章 钢筋及混凝土工程...................................................................................................... (47)第六章 金属结构工程...................................................................................................... (58)第七章 木结构工程...................................................................................................... (65)第八章 门窗工程...................................................................................................... (69)第九章 屋面及防水工程...................................................................................................... (73)第十章 保温 、隔热、防腐工程...................................................................................................... (83)第十一章 楼地面装饰工程...................................................................................................... (92)第十二章 墙、柱面装饰与隔断、幕墙工程 (105)第十三章 天棚工程 (114)1工程造价行业"十三五"规划明确提出,到 2020 年,健全市场决定工程造价机制,建立统一的计价规则。
《山东省建筑工程消耗量定额》定额说明及计算规则、定额解释总说明一、《山东省建筑工程消耗量定额》(以下简称本定额)是在《全国统一建筑工程基础定额》的基础上,依据国家现行有关工程建设标准,结合我省的实际情况编制的.本定额共分十章,包括:土石方工程;地基处理与防护工程;砌筑工程;钢筋及混凝土工程;门窗及木结构工程;屋面防水、保温及防腐工程;金属结构制作工程;构筑物及其他工程;装饰工程;施工技术措施项目。
二、本定额适用我省行政区域内的一般工业与民用建筑的新建、扩建和改建工程及新建装饰工程。
三、本定额是完成规定计量单位分部分项工程所需人工、材料、机械台班消耗量的标准;是编制招标标底的依据;是编制施工图预算,确定工程造价以及编制概算定额、估算指标的基础.四、本定额是按照正常的施工条件,合理的施工工期、施工组织设计编制的,反映社会平均消耗水平。
五、本定额中人工工日消耗量以《全国建筑安装工程统一劳动定额》为基础计算,内容包括:基本用工、辅助用工、超运距用工及人工幅度差。
人工工日不分工种、技术等级,以综合工日表示。
六、本定额中材料消耗:(一)本定额材料(成品、半成品、配件等)按符合质量标准和设计要求的合格产品确定。
(二)本定额包括主要材料及其他材料.其他材料以占材料费百分比表示。
(三)本定额中包括材料施工损耗、材料(成品、半成品、配件等)从工地仓库至加工地点或操作地点的运输损耗等。
七、本定额中机械消耗:(一)本定额机械台班消耗量包括机械台班消耗量和机械幅度差.以不同种类的机械分别表示。
(二)本定额中其他机械(超高机械增加中的其他机械降效除外)以占机械费百分比表示。
(三)大型机械安拆及场外运输,按《山东省建筑工程费用项目构成及计算规则》中的有关规定计算.八、本定额的工作内容仅对其主要施工工序进行了说明,次要工序虽未说明,但均已包括在定额中.九、本定额中凡注有“×××以内”或“×××以下”者,均包括“×××”本身;凡注有“×××以外”或“×××以上”者,则不包括“×××” 本身.第一章土石方工程土石方工程定额说明:一、本章包括单独土石方、人工土石方、机械土石方、平整、清理及回填等内容。
山东省建筑工程消耗量定额价目表(2003版)综合工日:28元/工日序号定额编号定额名称单位基价人工费材料费11-1-1人工挖普通土10 29.4829.480 21-1-2人工挖坚土10 69.0869.080 31-1-3推土机推普通土20m内10 12.43 1.320 41-1-4推土机推坚土20m内10 14.51 1.320 51-1-5推土机推土100m内增运20m10 7.6400 61-1-6装载机装运土方20m内10 10 1.320 71-1-7装载机装运200m内增运20m10 2.7600 81-1-8铲运机铲运普通土200m内10 19.08 1.320.09 91-1-9铲运机铲运坚土200m内10 24.72 1.320.09 101-1-10铲运机500m内增运100m10 5.6400 111-1-11拉铲挖自卸汽车运普通土1km内10 64.68 1.980.2 121-1-12拉铲挖自卸汽车运坚土1km内10 77.18 1.980.2 131-1-13反铲挖自卸汽车运普通土1km内10 63.56 1.980.2 141-1-14反铲挖自卸汽车运坚土1km内10 74.68 1.980.2 151-1-15自卸汽车增运1km10 11.2900 161-1-16机械打孔爆破松石10 70.3118.726.2 171-1-17机械打孔爆破坚石10 142.5630.1448.25 181-1-18挖掘机挖渣自卸汽车运渣1km内10 132.13 2.420.2 191-1-19自卸汽车运渣增运1km10 17.2100 201-1-20机械夯填土10 26.2712.980 211-1-21光轮压路机回填碾压10 40.569.680.26 221-1-22振动压路机回填碾压10 39.819.680.26 231-2-1人工挖普通土深2m内10 50.1650.160 241-2-2人工挖普通土深>2m10 76.7876.780 251-2-3人工挖坚土深2m内10 95.795.70 261-2-4人工挖坚土深4m内10 122.32122.320 271-2-5人工挖坚土深6m内10 141.02141.020 281-2-6人工挖坚土深>6m10 153.56153.560 291-2-7人工挖淤泥.流砂10 2422420 301-2-8人工挖冻土厚0.5m内10 295.68295.680 311-2-9爆破后人工挖冻土厚0.5m内10 114.5486.927.64 321-2-10人工挖沟槽普通土深2m内10 71.2770.840 331-2-11人工挖沟槽普通土深>2m10 96.7796.580 341-2-12人工挖沟槽坚土深2m内10 140.13139.70 351-2-13人工挖沟槽坚土深4m内10 157.49157.30 361-2-14人工挖沟槽坚土深6m内10 178.1177.980 371-2-15人工挖沟槽坚土深>6m10 193.67193.60 381-2-16人工挖地坑普通土深2m内10 79.7978.540 391-2-17人工挖地坑普通土深>2m10 105.76105.160 401-2-18人工挖地坑坚土深2m内10 158.33157.080 411-2-19人工挖地坑坚土深4m内10 177.7177.10 421-2-20人工挖地坑坚土深6m内10 198.16197.780。
建筑工程消耗量定额-----------------------作者:-----------------------日期:《山东省建筑工程消耗量定额》定额说明及计算规则、定额解释总说明一、《山东省建筑工程消耗量定额》(以下简称本定额)是在《全国统一建筑工程基础定额》的基础上,依据国家现行有关工程建设标准,结合我省的实际情况编制的。
本定额共分十章,包括:土石方工程;地基处理与防护工程;砌筑工程;钢筋及混凝土工程;门窗及木结构工程;屋面防水、保温及防腐工程;金属结构制作工程;构筑物及其他工程;装饰工程;施工技术措施项目。
二、本定额适用我省行政区域内的一般工业与民用建筑的新建、扩建和改建工程及新建装饰工程。
三、本定额是完成规定计量单位分部分项工程所需人工、材料、机械台班消耗量的标准;是编制招标标底的依据;是编制施工图预算,确定工程造价以及编制概算定额、估算指标的基础。
四、本定额是按照正常的施工条件,合理的施工工期、施工组织设计编制的,反映社会平均消耗水平。
五、本定额中人工工日消耗量以《全国建筑安装工程统一劳动定额》为基础计算,内容包括:基本用工、辅助用工、超运距用工及人工幅度差。
人工工日不分工种、技术等级,以综合工日表示。
六、本定额中材料消耗:(一)本定额材料(成品、半成品、配件等)按符合质量标准和设计要求的合格产品确定。
(二)本定额包括主要材料及其他材料。
其他材料以占材料费百分比表示。
(三)本定额中包括材料施工损耗、材料(成品、半成品、配件等)从工地仓库至加工地点或操作地点的运输损耗等。
七、本定额中机械消耗:(一)本定额机械台班消耗量包括机械台班消耗量和机械幅度差。
以不同种类的机械分别表示。
(二)本定额中其他机械(超高机械增加中的其他机械降效除外)以占机械费百分比表示。
(三)大型机械安拆及场外运输,按《山东省建筑工程费用项目构成及计算规则》中的有关规定计算。
八、本定额的工作内容仅对其主要施工工序进行了说明,次要工序虽未说明,但均已包括在定额中。
《山东省建筑工程消耗量定额》定额说明及计算规则、定额解释总说明一、《山东省建筑工程消耗量定额》(以下简称本定额)是在《全国统一建筑工程基础定额》的基础上,依据国家现行有关工程建设标准,结合我省的实际情况编制的。
本定额共分十章,包括:土石方工程;地基处理与防护工程;砌筑工程;钢筋及混凝土工程;门窗及木结构工程;屋面防水、保温及防腐工程;金属结构制作工程;构筑物及其他工程;装饰工程;施工技术措施项目。
二、本定额适用我省行政区域内的一般工业与民用建筑的新建、扩建和改建工程及新建装饰工程。
三、本定额是完成规定计量单位分部分项工程所需人工、材料、机械台班消耗量的标准;是编制招标标底的依据;是编制施工图预算,确定工程造价以及编制概算定额、估算指标的基础。
四、本定额是按照正常的施工条件,合理的施工工期、施工组织设计编制的,反映社会平均消耗水平。
五、本定额中人工工日消耗量以《全国建筑安装工程统一劳动定额》为基础计算,内容包括:基本用工、辅助用工、超运距用工及人工幅度差。
人工工日不分工种、技术等级,以综合工日表示。
六、本定额中材料消耗:(一)本定额材料(成品、半成品、配件等)按符合质量标准和设计要求的合格产品确定。
(二)本定额包括主要材料及其他材料。
其他材料以占材料费百分比表示。
(三)本定额中包括材料施工损耗、材料(成品、半成品、配件等)从工地仓库至加工地点或操作地点的运输损耗等。
七、本定额中机械消耗:(一)本定额机械台班消耗量包括机械台班消耗量和机械幅度差。
以不同种类的机械分别表示。
(二)本定额中其他机械(超高机械增加中的其他机械降效除外)以占机械费百分比表示。
(三)大型机械安拆及场外运输,按《山东省建筑工程费用项目构成及计算规则》中的有关规定计算。
八、本定额的工作内容仅对其主要施工工序进行了说明,次要工序虽未说明,但均已包括在定额中。
九、本定额中凡注有“×××以内”或“×××以下”者,均包括“×××”本身;凡注有“×××以外”或“×××以上”者,则不包括“×××”本身。
11-1-1人工挖普通土29.4829.4800 21-1-2人工挖坚土69.0869.0800 31-1-3推土机推普通土20m内12.43 1.32011.11 41-1-4推土机推坚土20m内14.51 1.32013.19 51-1-5推土机推土100m内增运20m7.64007.64 61-1-6装载机装运土方20m内10 1.3208.68 71-1-7装载机装运200m内增运20m 2.7600 2.76 81-1-8铲运机铲运普通土200m内19.08 1.320.0917.67 91-1-9铲运机铲运坚土200m内24.72 1.320.0923.31 101-1-10铲运机500m内增运100m 5.6400 5.64 111-1-11拉铲挖自卸汽车运普通土1km内64.68 1.980.262.5 121-1-12拉铲挖自卸汽车运坚土1km内77.18 1.980.275 131-1-13反铲挖自卸汽车运普通土1km内63.56 1.980.261.38 141-1-14反铲挖自卸汽车运坚土1km内74.68 1.980.272.5 151-1-15自卸汽车增运1km11.290011.29 161-1-16机械打孔爆破松石70.3118.726.225.41 171-1-17机械打孔爆破坚石142.5630.1448.2564.17 181-1-18挖掘机挖渣自卸汽车运渣1km内132.13 2.420.2129.51 191-1-19自卸汽车运渣增运1km17.210017.21 201-1-20机械夯填土26.2712.98013.29 211-1-21光轮压路机回填碾压40.569.680.2630.62 221-1-22振动压路机回填碾压39.819.680.2629.87 231-2-1人工挖普通土深2m内50.1650.1600 241-2-2人工挖普通土深>2m76.7876.7800 251-2-3人工挖坚土深2m内95.795.700 261-2-4人工挖坚土深4m内122.32122.3200 271-2-5人工挖坚土深6m内141.02141.0200291-2-7人工挖淤泥.流砂24224200 301-2-8人工挖冻土厚0.5m内295.68295.6800 311-2-9爆破后人工挖冻土厚0.5m内114.5486.927.640 321-2-10人工挖沟槽普通土深2m内71.2770.8400.43 331-2-11人工挖沟槽普通土深>2m96.7796.5800.19 341-2-12人工挖沟槽坚土深2m内140.13139.700.43 351-2-13人工挖沟槽坚土深4m内157.49157.300.19 361-2-14人工挖沟槽坚土深6m内178.1177.9800.12 371-2-15人工挖沟槽坚土深>6m193.67193.600.07 381-2-16人工挖地坑普通土深2m内79.7978.540 1.25 391-2-17人工挖地坑普通土深>2m105.76105.1600.6 401-2-18人工挖地坑坚土深2m内158.33157.080 1.25 411-2-19人工挖地坑坚土深4m内177.7177.100.6 421-2-20人工挖地坑坚土深6m内198.16197.7800.38 431-2-21人工挖地坑坚土深>6m213.69213.400.29 441-2-22人工挖桩孔普通土孔深8m内236.05210.7625.290 451-2-23人工挖桩孔坚土孔深8m内383.89342.7641.130 461-2-24人工挖桩孔普通土孔深12m内319.83285.5634.270 471-2-25人工挖桩孔坚土孔深12m内505.86451.6654.20 481-2-26人工挖桩孔普通土孔深16m内415.68371.1444.540 491-2-27人工挖桩孔坚土孔深16m内657.64587.1870.460 501-2-28人工挖桩孔普通土孔深>16m479.74428.3451.40 511-2-29人工挖桩孔坚土孔深>16m758.91677.681.310 521-2-30人工凿松石方157.74157.7400 531-2-31人工凿坚石方354.64354.6400 541-2-32人工凿沟槽松石186.78186.7800 551-2-33人工凿沟槽坚石502.7502.700 561-2-34人工凿地坑松石259.16259.1600 571-2-35人工凿地坑坚石756.8756.800 581-2-36人工凿桩孔松石868.07775.0693.010601-2-38人工修整爆破后基底坚石125.84125.8400 611-2-39人工修整爆破后槽坑松石59.1859.1800 621-2-40人工修整爆破后槽坑坚石140.14140.1400 631-2-41人工修整爆破后边坡松石31.2431.2400 641-2-42人工修整爆破后边坡坚石86.2486.2400 651-2-43人工运土方20m内43.1243.1200 661-2-44人工运土方200m内增运20m9.689.6800 671-2-45人工运淤泥流砂20m内96.896.800 681-2-46人工运淤泥流砂200m内增运20m14.5214.5200 691-2-47人力车运土方50m内34.7634.7600 701-2-48人力车运土方500m内增运50m 5.5 5.500 711-2-49人力车运淤泥流砂50m内78.178.100 721-2-50人力车运淤泥流砂500m内增运50m8.368.3600 731-2-51人工清运石渣20m内102.3102.300 741-2-52人工清运石渣200m内增运20m18.718.700 751-2-53人力车清运石渣50m内92.6292.6200 761-2-54人力车清运石渣500m内增运50m12.112.100 771-2-55人工清运石渣桩孔人工出渣167.06149.1617.90 781-2-56人工装车土方34.3234.3200 791-2-57人工装车石渣45.9845.9800 801-3-1推土机推普通土20m内10.44 1.3209.12 811-3-2推土机推坚土20m内13.12 1.32011.8 821-3-3推土机推土100m内增运20m 6.4400 6.44 831-3-4装载机装运土方20m内10.78 1.3209.46 841-3-5装载机装运200m内增运20m 2.7600 2.76 851-3-6铲运机铲运普通土200m内20.83 1.320.0919.42 861-3-7铲运机铲运坚土200m内27.05 1.320.0925.64 871-3-8铲运机运土500m内增运100m 5.6400 5.64 881-3-9挖掘机挖普通土15.06 1.32013.74 891-3-10挖掘机挖坚土18.65 1.32017.33911-3-12挖掘机挖槽坑普通土14.04 2.64011.4 921-3-13挖掘机挖槽坑坚土15.18 2.64012.54 931-3-14挖掘机挖普通土自卸汽车运1km内75.14 1.980.272.96 941-3-15挖掘机挖坚土自卸汽车运1km内90.92 1.980.288.74 951-3-16挖掘机挖普通土槽坑汽车运1km内69.95 2.640.267.11 961-3-17挖掘机挖坚土槽坑汽车运1km内84.48 2.640.281.64 971-3-18人工打孔爆破松石81.9959.8422.150 981-3-19人工打孔爆破坚石165.09131.7833.310 991-3-20人工打孔爆破槽坑松石216.69161.4855.210 1001-3-21人工打孔爆破槽坑坚石425.6340.7884.820 1011-3-22机械打孔爆破松石82.9421.7828.5132.65 1021-3-23机械打孔爆破坚石169.2534.9851.8882.39 1031-3-24机械打孔爆破槽坑松石202.5553.2473.0676.25 1041-3-25机械打孔爆破槽坑坚石418.6191.96126.67199.98 1051-3-26机械打孔爆破桩孔松石375.78171.82121.5182.45 1061-3-27机械打孔爆破桩孔坚石929.53368.94263.32297.27 1071-3-28控制爆破松石237.349.72150.4337.15 1081-3-29控制爆破坚石430.3771.72249.27109.38 1091-3-30控制爆破槽坑松石410.2171.06255.5983.56 1101-3-31控制爆破槽坑坚石816.34124.96428.38263 1111-3-32静力爆破坚石3722.29377.961927.731416.6 1121-3-33静力爆破槽坑坚石4135.92419.762141.941574.22 1131-3-34风镐破碎桩孔松石3273.59742.9489.152441.5 1141-3-35风镐破碎桩孔坚石4676.881061.28127.353488.25 1151-3-36风镐破碎鼓石1433.39334.401098.99 1161-3-37液压锤破碎松石532.9113.640519.27 1171-3-38液压锤破碎坚石669.7813.860655.92 1181-3-39液压锤破碎槽坑松石642.6714.080628.59 1191-3-40液压锤破碎槽坑坚石806.8714.30792.57 1201-3-41推土机推石渣20m内30.72 1.76028.961221-3-43挖掘机挖集石渣38.14 1.76036.38 1231-3-44挖掘机挖石渣自卸汽车运1km内144.11 2.420.2141.49 1241-3-45装载机装土方10.43 1.3209.11 1251-3-46装载机装石方19.97 1.76018.21 1261-3-47挖掘机装土方9.7 1.3208.38 1271-3-48挖掘机装石方20.04 1.76018.28 1281-3-49机动翻斗车运土方100m内50.560050.56 1291-3-50机动翻斗车运土方500内增运100m 6.9500 6.95 1301-3-51机动翻斗车运石方100m内153.7800153.78 1311-3-52机动翻斗车运石方500内增运100m18.420018.42 1321-3-53拖拉机运土方1km内83.70083.7 1331-3-54拖拉机运土方增运1km9.97009.97 1341-3-55拖拉机运石方1km内172.1700172.17 1351-3-56拖拉机运石方增运1km20.150020.15 1361-3-57自卸汽车运土方1km内46.380.660.245.52 1371-3-58自卸汽车运土方增运1km 4.3600 4.36 1381-3-59自卸汽车运石方1km内82.110.660.281.25 1391-3-60自卸汽车运石方增运1km15.250015.25 1401-3-61垂直运输机械运土方22.337.26015.07 1411-3-62垂直运输机械运石方37.7512.32025.43 1421-3-63运输钻孔桩泥浆1km内(柱体积)702.69141.460561.23 1431-3-64运输钻孔桩泥浆增运1km(柱体积)39.920039.92 1441-4-1人工场地平整13.8613.8600 1451-4-2机械场地平整 2.70.220 2.48 1461-4-3竣工清理 3.52 3.52001481-4-5人工原土夯实 3.52 3.5200 1491-4-6机械原土夯实 3.33 1.980 1.35 1501-4-7原土机械碾压0.540.2200.32 1511-4-8填土机械碾压48.0510.780.2637.011531-4-10人工夯填土(地坪)35.4635.20.260 1541-4-11机械夯填土(地坪)26.4211.66014.76 1551-4-12人工槽坑夯填土44.26440.260 1561-4-13机械槽坑夯填土34.5815.4019.18 1571-4-14槽坑夯填砂502.6857.42443.24 2.02 1581-4-15槽坑夯填石屑309.4457.42250 2.02 1591-4-16槽坑夯填石渣252.2274.8174.77 2.65 1602-1-13:7灰土垫层483.08184.14288.3610.58 1612-1-2砂垫层547.63102.52443.09 2.02 1622-1-3人工级配砂石垫层692.91176.66510.48 5.77 1632-1-4天然级配砂石垫层622.54147.4469.37 5.77 1642-1-5干铺碎石垫层696.41147.84542.32 6.25 1652-1-61:3砂浆灌碎石垫层1049.79179.3840.7329.76 1662-1-7干铺碎砖垫层1202.85171.821024.78 6.25 1672-1-81:3砂浆灌碎砖垫层1514.172421248.4123.76 1682-1-9干铺地瓜石垫层772.3174.68590.98 6.64 1692-1-101:3砂浆灌地瓜石垫层1232.8237.82964.3330.65 1702-1-11干铺毛石垫层825.03188.1629.96 6.97 1712-1-121:3砂浆灌毛石垫层1272.3284.68951.8335.79 1722-1-13C154现浇无筋砼垫层1439.83224.621205.259.96 1732-1-14C154现浇毛石砼垫层1370.76212.961147.849.96 1742-2-1夯填灰土481.01178.64291.7910.58 1752-2-2人工填砂石机械振动553.4781.84470.22 1.41 1762-2-3人工填砂石机械碾压604.8497.24495.8711.73 1772-2-4推土机填砂碾压515.04 1.54495.8717.63 1782-2-5推土机挤淤碾压529.72 2.64494.9432.14 1792-2-6填铺石屑35197.24249.91 3.85 1802-2-7填铺碎石693.99145.42542.32 6.25 1812-2-8抛石挤淤510.97132.22377.6 1.15 1822-2-9填筑C154现浇毛石砼1357.56199.761147.849.961842-3-2打砼方桩18m内1550.25117.4849.751383.02 1852-3-3打砼方桩30m内1032.770.1849.75912.77 1862-3-4打砼方桩>30m891.4560.0649.75781.64 1872-3-5压砼方桩12m内1672.95157.96163.871351.12 1882-3-6压砼方桩18m内1827.1166.54163.871496.69 1892-3-7压砼方桩30m内2251.94137.94163.871950.13 1902-3-8压砼方桩>30m1997.87116.38163.871717.62 1912-3-9打砼管桩16m内11768.17223.310093.111451.76 1922-3-10打砼管桩24m内11524.1190.5210093.111240.47 1932-3-11打砼管桩32m内11435.48179.5210093.111162.85 1942-3-12打砼管桩>32m11421.78177.3210093.111151.35 1952-3-131964.96266.6435.531662.79 1962-3-141635.41220.8835.531379 1972-3-151421.12169.6235.531215.97 1982-3-161252.43148.9435.531067.96 1992-3-17打孔灌砼桩10m内3525.39712.141783.741029.51 2002-3-18打孔灌砼桩15m内2873.44430.761783.74658.94 2012-3-19打孔灌砼桩>15m2723.85365.421783.74574.69 2022-3-20夯扩成孔灌注砼桩身3906.69842.821779.321284.55 2032-3-21夯扩成孔灌注桩夯扩砼4084.31935.441722.761426.11 2042-3-22螺旋钻机钻孔12m内300.58219.56081.02 2052-3-23螺旋钻孔灌注砼桩12m内1954.1598.121838.6117.42 2062-3-24螺旋钻机钻孔>12m259.05187.66071.39 2072-3-25螺旋钻孔灌注砼桩>12m1920.1866.221838.6115.35 2082-3-26回旋钻机钻孔φ60cm内2933.74467.0635.412431.27 2092-3-27回旋钻机钻孔φ80cm内2531.89416.0233.882081.99 2102-3-28回旋钻机钻孔φ100cm内2230.84378.431.111821.33 2112-3-29回旋钻机钻孔φ120cm内1934.36282.2625.211626.89 2122-3-30回旋钻机钻孔φ>120cm1703.67255.219.141429.33 2132-3-31回旋钻机钻孔入岩φ60cm内12768.37202427.8910716.482152-3-33回旋钻机钻孔入岩φ100cm内7557.191191.327.896338 2162-3-34回旋钻机钻孔入岩φ120cm内5873.8924.8827.894921.03 2172-3-35回旋钻机钻孔入岩φ>120cm4263.37691.0227.893544.46 2182-3-36回旋钻孔灌注砼桩2366.5380.32286.230 2192-3-37人工挖孔灌注砼桩壁2120.91360.581669.8490.49 2202-3-38人工挖孔砌黏土砖桩壁1201797.85512.821271.3713.66 2212-3-39人工挖孔砌黏土砖桩壁2401797.37512.821268.5915.96 2222-3-40人工挖孔灌注砼桩芯1876.92274.341401.1201.48 2232-3-41人工挖孔灌注毛石砼桩芯1702.98191.621309.88201.48 2242-3-42打灰土挤密桩6m内1298.25306.46454.26537.53 2252-3-43打灰土挤密桩>6m1049.4194.7454.26400.44 2262-3-44打砂桩10m内1692.92380.6599.99712.33 2272-3-45打砂桩15m内1495.78266.64599.99629.15 2282-3-46打砂桩>15m1409.87213.84599.99596.04 2292-3-47打碎石桩10m内1614.16404.14497.69712.33 2302-3-48打碎石桩15m内1410.42283.58497.69629.15 2312-3-49打碎石桩>15m1320.99227.26497.69596.04 2322-3-50振冲打碎石桩1160.71158.4478.11524.2 2332-3-51钻孔压浆碎石桩2877.31363.661948.17565.48 2342-3-52打砂石桩10m内1808.47404.14692712.33 2352-3-53打砂石桩15m内1604.73283.58692629.15 2362-3-54打砂石桩>15m1515.3227.26692596.04 2372-3-55深层搅拌粉喷水泥桩(水泥10%)1062.29110.88579.49371.92 2382-3-56深层搅拌浆喷水泥桩(水泥10%)1037.73124.74584.3328.69 2392-3-57水泥桩水泥掺量每增1%50.05050.0502412-3-59双重管旋喷机高压旋喷水泥桩1472.66228.14550694.52 2422-3-60三重管旋喷机高压旋喷水泥桩2078.1253.44847.76976.92482-3-66预制钢筋砼方桩凿桩头1205.07781.880423.19 2492-3-67灌注砼桩凿桩头480.14311.30168.842512-4-1强夯<100t-m 25夯点 4击766.44119.240647.2 2522-4-2强夯<100t-m 25夯点增减1击142.1124.20117.91 2532-4-3强夯<100t-m 23夯点 4击705.35109.780595.57 2542-4-4强夯<100t-m 23夯点增减1击128.6220.020108.6 2552-4-5强夯<100t-m 17夯点 4击521.6881.40440.28 2562-4-6强夯<100t-m 17夯点增减1击94.8514.74080.11 2572-4-7强夯<100t-m 13夯点 4击398.6562.040336.61 2582-4-8强夯<100t-m 13夯点增减1击72.1611.22060.94 2592-4-9强夯<100t-m 10夯点 4击306.747.740258.96 2602-4-10强夯<100t-m 10夯点增减1击55.288.58046.7 2612-4-11强夯<100t-m 低锤满拍725.31107.140618.17 2622-4-12强夯<200t-m 25夯点 4击1529.41159.2801370.13 2632-4-13强夯<200t-m 25夯点增减1击279.3429.040250.3 2642-4-14强夯<200t-m 23夯点 4击1406.71146.5201260.19 2652-4-15强夯<200t-m 23夯点增减1击257.4726.840230.63 2662-4-16强夯<200t-m 17夯点 4击1039.67108.240931.43 2672-4-17强夯<200t-m 17夯点增减1击190.619.80170.8 2682-4-18强夯<200t-m 13夯点 4击795.3282.720712.6 2692-4-19强夯<200t-m 13夯点增减1击145.4115.40130.01 2702-4-20强夯<200t-m 10夯点 4击611.863.580548.22 2712-4-21强夯<200t-m 10夯点增减1击112.2811.660100.62 2722-4-22强夯<200t-m 低锤满拍1366.66134.4201232.24 2732-4-23强夯<300t-m 25夯点 4击1919.58188.3201731.26 2742-4-24强夯<300t-m 25夯点增减1击370.5336.080334.45 2752-4-25强夯<300t-m 23夯点 4击1766.55173.1401593.412772-4-27强夯<300t-m 17夯点 4击1305.31128.0401177.27 2782-4-28强夯<300t-m 17夯点增减1击249.5324.420225.11 2792-4-29强夯<300t-m 13夯点 4击998.5297.680900.84 2802-4-30强夯<300t-m 13夯点增减1击191.3518.70172.65 2812-4-31强夯<300t-m 10夯点 4击767.8175.240692.57 2822-4-32强夯<300t-m 10夯点增减1击147.7614.520133.24 2832-4-33强夯<300t-m 低锤满拍2281.85128.702153.15 2842-4-34强夯<400t-m 25夯点 4击4186.07358.8203827.25 2852-4-35强夯<400t-m 25夯点增减1击896.0276.780819.24 2862-4-36强夯<400t-m 23夯点 4击3850.5633003520.56 2872-4-37强夯<400t-m 23夯点增减1击824.1870.620753.56 2882-4-38强夯<400t-m 17夯点 4击2694.022*******.02 2892-4-39强夯<400t-m 17夯点增减1击608.6652.140556.52 2902-4-40强夯<400t-m 13夯点 4击2176.52186.5601989.96 2912-4-41强夯<400t-m 13夯点增减1击465.6140.040425.57 2922-4-42强夯<400t-m 10夯点 4击1674.26143.6601530.6 2932-4-43强夯<400t-m 10夯点增减1击359.230.80328.4 2942-4-44强夯<400t-m 低锤满拍2715.64219.7802495.86 2952-4-45强夯<500t-m 25夯点 4击5424.07405.4605018.61 2962-4-46强夯<500t-m 25夯点增减1击1161.1286.6801074.44 2972-4-47强夯<500t-m 23夯点 4击4988.39372.904615.49 2982-4-48强夯<500t-m 23夯点增减1击1068.0979.860988.23 2992-4-49强夯<500t-m 17夯点 4击3488.63261.1403227.49 3002-4-50强夯<500t-m 17夯点增减1击788.9958.960730.03 3012-4-51强夯<500t-m 13夯点 4击2819.8210.7602609.04 3022-4-52强夯<500t-m 13夯点增减1击603.3645.320558.04 3032-4-53强夯<500t-m 10夯点 4击2168.8162.3602006.44 3042-4-54强夯<500t-m 10夯点增减1击465.3734.760430.61 3052-4-55强夯<500t-m 低锤满拍3043.15263.7802779.37 3062-4-56强夯<600t-m 25夯点 4击5977.86458.2605519.63082-4-58强夯<600t-m 23夯点 4击5450.23372.905077.33 3092-4-59强夯<600t-m 23夯点增减1击1068.0979.860988.23 3102-4-60强夯<600t-m 17夯点 4击3490.69261.1403229.55 3112-4-61强夯<600t-m 17夯点增减1击788.9958.960730.03 3122-4-62强夯<600t-m 13夯点 4击2819.8210.7602609.04 3132-4-63强夯<600t-m 13夯点增减1击603.3645.320558.04 3142-4-64强夯<600t-m 10夯点 4击2168.8162.3602006.44 3152-4-65强夯<600t-m 10夯点增减1击465.3734.760430.61 3162-4-66强夯<600t-m 低锤满拍3321.8287.9803033.82 3172-5-1木撑木挡土疏板防护89.3436.5252.820 3182-5-2钢撑木挡土疏板防护73.1827.9445.240 3192-5-3木撑木挡土密板防护111.0247.0863.940 3202-5-4钢撑木挡土密板防护91.0835.8655.220 3212-5-5木撑钢挡土疏板防护95.2436.9658.280 3222-5-6钢撑钢挡土疏板防护77.2428.1649.080 3232-5-7木撑钢挡土密板防护113.547.0866.420 3242-5-8钢撑钢挡土密板防护93.4236.357.120 3252-5-9袋土围堰810.65381.92392.2636.473392-5-23土层喷射砼护坡 初喷50155.4532.5695.8927 3402-5-24岩层喷射砼护坡 初喷50188.0755.66103.2529.16 3412-5-25喷射砼护坡每增减10mm30.33 5.9419.17 5.22 3422-6-1抽水机基底排水 降水深1m内400.26 4.421.07374.79 3432-6-2抽水机基底排水 降水深2m内685.42 6.639.47639.35 3442-6-3抽水机基底排水 降水深3m内862.661164.88786.783713-1-1M5.0砂浆砖基础1389.81267.961107.0914.76 3723-1-2M5.0混浆矩形砖柱周长1.2m内1748.15584.321151.5712.26 3733-1-3M5.0混浆矩形砖柱周长1.8m内1705.58545.381146.5413.66 3743-1-4M5.0混浆矩形砖柱周长>1.8m1600.53441.541144.7314.26 3753-1-5M5.0混浆异形砖柱2040.96551.541472.8616.56 3763-1-6M2.5混浆单面清水砖墙 1151600.41457.61130.612.21 3773-1-7M2.5混浆单面清水砖墙 1801590.95451.881125.7113.36 3783-1-8M2.5混浆单面清水砖墙 2401514.52397.11103.3614.06 3793-1-9M2.5混浆单面清水砖墙 3601513.35375.11123.3414.91 3803-1-10M2.5混浆单面清水砖墙 ≥4901497.14360.581121.2515.31 3813-1-11M2.5混浆混水砖墙 531737.93584.321146.267.35 3823-1-12M2.5混浆混水砖墙 1151581.93439.121130.612.21 3833-1-13M2.5混浆混水砖墙 1801551.92413.381125.2313.31 3843-1-14M2.5混浆混水砖墙 2401455.78338.361103.3614.06 3853-1-15M2.5混浆混水砖墙 3651467.25328.91123.3415.01 3863-1-16M2.5混浆混水砖墙 4901461.77325.381121.0815.31 3873-1-17弧形砖墙另加工料50.243317.240 3883-1-18M5.0混浆贴砌砖墙 53107.835.4271.33 1.05 3893-1-19M5.0混浆贴砌砖墙 115196.4252.8141.57 2.05 3903-1-20M5.0混浆贴砌砖墙 240374.9788282.92 4.05 3913-1-21M5.0混浆空花砖墙 115137.6145.3291.440.85 3923-1-22M5.0混浆空花砖墙 240287.4494.82190.82 1.8 3933-1-23M5.0混浆砖平璇2160.18596.21549.6714.31 3943-1-24M5.0混浆砖拱璇2520.29849.21655.4315.66 3953-1-25M5.0混浆砖过梁1891.14462.441411.4417.26 3963-1-26M5.0混浆半砖栏板190.3156.32132.59 1.4 3973-1-27M5.0砂浆砖台阶1462.98302.51145.7214.76 3983-1-28M5.0混浆砖地沟1457.01307.121135.6314.26 3993-1-29M5.0混浆零星砖砌体1594.935061075.7213.21 4003-2-1M5.0砂浆乱毛石基础1092.26259.82807.8824.56第 13 页,共 114 页4013-2-2M5.0混浆乱毛石墙1317.68418.44874.6824.56 4023-2-3M5.0混浆乱毛石挡土墙1188.32289.08874.6824.56 4033-2-4M5.0混浆乱毛石护坡1272.94311.52934.4526.97 4043-2-5干砌乱毛石护坡931.7202.4729.30 4053-2-6M5.0混浆整毛石墙毛石背里450638.21213.62413.5311.06 4063-2-7M5.0混浆整毛石墙毛石背里±1013.15 4.188.720.25 4073-2-8M5.0混浆整毛石墙砖背里450672.12197.12466.698.31 4083-2-9M5.0混浆整毛石墙砖背里±1014.85 3.5211.180.15 4093-2-10整砌毛石表面处理158.02109.1248.904113-2-12M5.0混浆方整石柱3807.51664.183134.778.56 4123-2-13M5.0混浆方整石墙3492.27350.683132.788.81 4133-2-14M5.0混浆方整石墙毛石背里4501149.71190.74951.377.6 4143-2-15M5.0混浆方整石墙毛石背里±1013.18 4.188.750.25 4153-2-16M5.0混浆方整石墙砖背里4501205.68173.81024.887 4163-2-17M5.0混浆方整石墙砖背里±1014.85 3.5211.180.15 4173-2-18M10 混浆方整石平璇4341.28638.223694.059.01 4183-2-19M10 混浆方整石拱璇4459.5771.543678.79.26 4193-2-20M5.0混浆零星方整石砌体4242.69913.663317.9711.06 4203-3-1M5.0混浆烧结粉煤灰轻质砖墙1151708.61443.081253.3212.21 4213-3-2M5.0混浆烧结粉煤灰轻质砖墙1801692.05432.081246.6613.31 4223-3-3M5.0混浆烧结粉煤灰轻质砖墙2401589.65353.761221.8314.06 4233-3-4M5.0混浆烧结粉煤灰轻质砖墙3651602.42343.861243.5515.01 4243-3-5M5.0混浆黏土多孔砖墙1151897.89310.21578.289.41 4253-3-6M5.0混浆黏土多孔砖墙1801832.98279.621541.511.86 4263-3-7M5.0混浆黏土多孔砖墙2401843.33261.141570.3811.81 4273-3-8M5.0混浆黏土多孔砖墙3651893.5235.41645.4912.61 4283-3-9M5.0混浆煤矸石多孔砖墙902042.37325.61706.819.96 4293-3-10M5.0混浆煤矸石多孔砖墙1901991.652751706.699.96 4303-3-11M5.0混浆煤矸石多孔砖墙2401963.82270.161681.2512.41 4313-3-12M5.0混浆煤矸石多孔砖墙2901943.52245.961685.5512.01第 14 页,共 114 页4323-3-13M5.0混浆承重型黏土空心砖墙1152086.74325.61752.838.31 4333-3-14M5.0混浆承重型黏土空心砖墙1802053.19293.71751.138.36 4343-3-15M5.0混浆承重型黏土空心砖墙2402011.77274.121726.6411.01 4353-3-16M5.0混浆承重型黏土空心砖墙3651977.09247.51717.8311.76 4363-3-17M5.0混浆非承重黏土空心砖墙1151921.93338.581574.448.91 4373-3-18M5.0混浆非承重黏土空心砖墙2401865.44281.821574.419.21 4383-3-19M5.0混浆零星空心砖砌体2063.89431.641619.1413.11 4393-3-20M5.0混浆煤矸石空心砖墙1152004.69341.881653.39.51 4403-3-21M5.0混浆煤矸石空心砖墙1801985.63313.281662.2410.11 4413-3-22M5.0混浆煤矸石空心砖墙2401927.94284.461631.8211.66 4423-3-23M5.0混浆煤矸石空心砖墙3651897.4260.261624.6812.46 4433-3-24M5.0混浆加气砼砌块墙1201882.42247.061631.26 4.1 4443-3-25M5.0混浆加气砼砌块墙1801787.12227.481555.54 4.1 4453-3-26M5.0混浆加气砼砌块墙2401835.7198.661632.94 4.1 4463-3-27M5.0混浆泡沫砼砌块墙901805.96245.081551.629.26 4473-3-28M5.0混浆泡沫砼砌块墙1901824.1223.081596.32 4.7 4483-3-29M5.0混浆泡沫砼砌块墙2901785.34198.221580.92 6.2 4493-3-30M5.0混浆泡沫砼砌块墙3901765.06178.641580.22 6.2 4503-3-31M7.5混浆硅酸钙砌块墙1201859.35297.441556.96 4.95 4513-3-32M7.5混浆硅酸钙砌块墙1801843.13278.961559.22 4.95 4523-3-33M7.5混浆硅酸钙砌块墙2401812.92251.021556.95 4.95 4533-3-34M7.5混浆硅酸钙砌块墙3651784.08227.041551.29 5.75 4543-3-35石膏砌空心块墙1106926.61194.76731.910 4553-3-36石膏砌空心块墙1806933.04174.96758.140 4563-3-37石膏砌夹心块墙806938.21215.66722.610 4573-3-38石膏砌夹心块墙1006934.21209.666724.550 4583-3-39M7.5混浆粉煤灰加气砼砌块墙2001821.2196.021619.28 5.9 4593-3-40M7.5混浆煤矸石砌块墙2801927.95201.521720.03 6.4 4603-3-41M7.5混浆硅酸盐砌块墙2402613.21230.342377.82 5.05 4613-3-42M7.5混浆膨胀珍珠岩砌块墙11013003.22218.6812780.94 3.6 4623-3-43M7.5混浆砼空心砌块墙902684.97258.062420.51 6.4第 15 页,共 114 页4633-3-44M7.5混浆砼空心砌块墙1902689.42226.62457.52 5.3 4643-3-45M7.5混浆砼空心砌块墙2902631.46199.322425.147 4653-3-46M7.5混浆砼空心砌块墙3902612.87183.482422.74 6.65 4663-3-47M7.5混浆轻骨料砼空心砌块墙902007.11245.741754.97 6.4 4673-3-48M7.5混浆轻骨料砼空心砌块墙1901995.7215.821774.58 5.3 4683-3-49M7.5混浆轻骨料砼空心砌块墙2901956.47189.861759.617 4693-3-50M7.5混浆轻骨料砼空心砌块墙3901938.12174.91756.57 6.65 4703-3-51M5.0混浆砌空心砌块烟风道2404527.27750.23774.27 2.84743-3-55钢筋砼漏空花格70内1067.9830.141037.580.26 4753-3-56钢筋砼漏空花格100内1334.3143.341290.590.38 4763-3-57钢筋砼漏空花格200内2146.9986.682059.550.76 4773-3-58预制水磨石隔断板.窗台板689.9234.76655.160 4783-4-1GRC多孔板墙601949.2730.361898.7120.2 4793-4-2GRC多孔板墙802189.2633.662135.2720.33 4803-4-3GRC多孔板墙902309.8636.082253.4520.33 4813-4-4GRC多孔板墙1002429.5937.42371.7320.46 4823-4-5GRC多孔板墙1202669.7640.922608.2520.59 4833-4-6轻集料砼多孔条板墙751541.2129.92149120.29 4843-4-7轻集料砼多孔条板墙1001647.2832.561594.4320.29 4853-4-8轻集料砼多孔条板墙1201964.4335.861908.2820.29 4863-4-9轻陶粒砼实心条板墙60760.7133.66704.0223.03 4873-4-10轻陶粒砼实心条板墙80872.336.96812.3123.03 4883-4-11石膏空心条板墙60707.7427.28660.3820.08 4893-4-12石膏空心条板墙80893.4729.26844.0120.2 4903-4-13双石膏空心条板墙1307.6763.81236.17.77 4913-4-14双石膏空心条板墙填501468.4169.31391.137.98 4923-4-15双石膏空心条板墙厚±1029.340.2229.120 4933-4-16硅镁多孔板墙901201.4232.561148.5320.33第 16 页,共 114 页4943-4-17硅镁多孔板墙1001326.9633.661272.9720.33 4953-4-18木纤维增强水泥多孔板801483.3230.581430.3522.39 4963-4-19网架水泥板聚苯乙烯泡塑心76(50)888.928.82846.8513.23 4973-4-20网架水泥板岩棉夹心65(40)835.9725.3797.4413.23 4983-4-21网架水泥板岩棉夹心75(50)876.9928.6835.1613.23 4993-4-22网架水泥板岩棉夹心85(60)972.1931.68927.2813.23 5003-4-23GRC复合外墙板1201788.2240.481720.3327.41 5013-4-24GRC复合外墙板3702151.9553.92070.8927.16 5023-4-25彩钢压型板墙845.5420.46779.6945.39 5033-4-26双层彩钢压板墙聚氨酯板填601737.4834.321631.3871.78 5043-4-27双层彩钢压板墙聚氨酯板填1001931.6534.981824.8971.78 5053-4-28双层彩钢压板墙聚氨酯板填±2096.780.2296.560 5063-4-29双层彩钢压板墙岩棉板填801678.9634.761572.4271.78 5073-4-30双层彩钢压板墙岩棉板填1201795.0635.21688.0871.78 5083-4-31双层彩钢压板墙聚苯乙烯板填751610.7834.541504.4671.78 5093-4-32双层彩钢压板墙聚苯乙烯板填1501775.2335.641667.8171.78 5103-4-33双层彩钢压板墙聚苯乙烯板±2554.780.4454.3406104-1-100墙面钉钢板网70.0612.3257.7406144-2-1C204现浇桩承台独立基础1554.6155.541393.1 5.96 6154-2-2C204现浇桩承台带型基础1552.86155.541391.36 5.96 6164-2-3C204现浇毛石砼无梁式带型基础1445.72140.81299.79 5.13 6174-2-4C204现浇砼无梁式带型基础1543.58147.841390.3 5.44第 20 页,共 114 页6184-2-5C204现浇砼有梁式带型基础1551.97155.541390.47 5.96 6194-2-6C204现浇毛石砼独立基础1449.67143.441301.1 5.13 6204-2-7C204现浇砼独立基础1575.93177.981391.99 5.96 6214-2-8C204现浇毛石砼有梁式满堂基础1453.16143.661304.37 5.13 6224-2-9C204现浇砼有梁式满堂基础1590.65189.641395.05 5.96 6234-2-10C204现浇毛石砼无梁式满堂基础1441.71321304.57 5.13 6244-2-11C204现浇砼无梁式满堂基础1547.73146.521395.25 5.96 6254-2-12C204现浇砼杯型基础1562.72164.121392.64 5.96 6264-2-13C204现浇毛石砼设备基础1459.73143.661310.94 5.13 6274-2-14C204现浇砼设备基础1585.78178.21401.62 5.96 6284-2-15C202现浇砼二次灌浆2438.1803.661634.440 6294-2-16M10 砂浆二次灌浆2133.75803.661265.764.39 6304-2-17C254现浇矩形柱1954.92421.521524.399.01 6314-2-18C254现浇圆形柱1931.85399.081523.769.01 6324-2-19C254现浇异形柱2041.87508.8615249.01 6334-2-20C253现浇构造柱2064.85477.181578.669.01 6344-2-21C253现浇升板柱帽2224.5625.021576.5622.92 6354-2-22C253现浇轻体墙填充砼2046.64452.761579.8614.02 6364-2-23C253现浇基础梁1827.82238.71582.117.01 6374-2-24C253现浇单梁.连续梁1875.62286.441582.177.01 6384-2-25C253现浇异形梁1891.86302.281582.577.01 6394-2-26C253现浇圈梁2067.41475.421584.987.01 6404-2-27C253现浇过梁2132.18519.421605.757.01 6414-2-28C253现浇弧形.拱形梁2071.74475.421589.317.01 6424-2-29C253现浇毛石砼墙1732.03258.51465.028.51 6434-2-30C253现浇砼墙1968.85375.321585.028.51 6444-2-31C253现浇砼电梯井壁1968.93375.541584.888.51 6454-2-32C253现浇砼弧型墙1996.32402.381585.438.51 6464-2-33C253现浇砼大钢模板墙1921.39320.11592.788.51 6474-2-34C253现浇建筑物滑模工程2029.29278.961597.36152.97 6484-2-35C253现浇轻型框剪墙2072475.641587.858.51第 21 页,共 114 页6494-2-36C252现浇有梁板1927.57234.961684.548.07 6504-2-37C252现浇无梁板1905.83213.841683.928.07 6514-2-38C252现浇平板1942.01242.441691.58.07 6524-2-39C252现浇拱板2056.47375.981672.428.07 6534-2-40C252现浇密肋板1914.14232.761673.318.07 6544-2-41C252现浇斜板.折板1977.35260.71707.888.77 6554-2-42C202现浇直形楼梯无斜梁100434.3797.24332.84 4.29 6564-2-43C202现浇直形楼梯有斜梁100532.67118.14409.4 5.13 6574-2-44C202现浇旋转楼梯无梁385.53108.9272.97 3.66 6584-2-45C202现浇旋转楼梯有梁698.21183.04508.27 6.9 6594-2-46C202现浇楼梯板厚±1021.75 5.0616.480.21 6604-2-47C202现浇板式阳台208.3452.36154.52 1.46 6614-2-48C202现浇有梁式阳台337.8377.66257.97 2.2 6624-2-49C202现浇雨蓬201.7945.98154.55 1.26 6634-2-50C202现浇地沟及电缆沟1834.28281.381531.9820.92 6644-2-51C202现浇栏板2185.7624.81560.90 6654-2-52C202现浇扶手2682.461121.561560.90 6664-2-53C202现浇门框1994.51447.261526.3320.92 6674-2-54C202现浇柱接柱及框架柱接头2132.43610.061522.370 6684-2-55C202现浇小型构件2260.9608.31652.60 6694-2-56C202现浇挑檐.天沟2078.37501.381556.0720.92 6704-2-57C202现浇台阶1910.72335.281554.5220.92 6714-2-58C202现浇压顶2125.89527.781598.110 6724-2-59C202现浇小型池槽2164.21606.321557.890 6734-2-60C302现浇后浇带梁2412.27430.761967.4814.03 6744-2-61C302现浇后浇带楼板2370.37377.521978.8214.03 6754-2-62C302现浇后浇带墙300内2515.15536.361964.7614.03 6764-2-63C302现浇后浇带墙>3002437.16465.081958.0514.03 6774-2-64C302现浇后浇带基础底板2291.1317.241964.869 6784-2-65C202现浇阳台.雨篷每±1020.05 4.6215.280.15 6794-3-1C254预制砼方桩.板桩1702.64175.561467.3359.75第 22 页,共 114 页6804-3-2C254预制砼矩形柱1707.68178.861469.0759.75 6814-3-3C254预制砼异形柱1702.76176.441466.5759.75 6824-3-4C254预制砼框架形支架1773.02244.21469.0759.75 6834-3-5C254预制砼异形支架1814.3287.981466.5759.75 6844-3-6C302预制鱼腹式吊车梁2092.79232.761786.6873.35 6854-3-7C302预制T型吊车梁2069.19210.541785.373.35 6864-3-8C302预制托架梁2104.34247.51783.4973.35 6874-3-9C302预制拱.梯型屋架2081.08229.681778.0573.35 6884-3-10C302预制组合屋架2044.62188.981782.2973.35 6894-3-11C302预制薄腹屋架2115.06268.181773.5373.35 6904-3-12C302预制三角型屋架2093.24234.31785.5973.35 6914-3-13C302预制锯齿型屋架2117.44258.51785.5973.35 6924-3-14C302预制门式钢屋架2089.28234.521781.4173.35 6934-3-15C302预制天窗屋架2234.51377.31783.8673.35 6944-3-16C302预制平板2148315.921773.3858.7 6954-3-17C302预制升板1970.44130.461781.2858.7 6964-3-18C302预制天窗侧板2111.81244.421804.9462.45 6974-3-19C302预制天窗端壁板2111.22225.51823.2762.45 6984-3-20C302预制天窗2363.03458.041842.5462.45 6994-3-21C302预制井盖板2156.76312.41785.6658.7 7004-3-22C302预制小型构件2232.33375.11798.5358.7 7014-4-1123.0813.28.5101.38 7024-4-2142.9817.68.5116.88 7034-4-3砼运输车运砼5km内260.8100260.81 7044-4-4砼运输车运砼每增1km36.830036.83 7054-4-5机动翻斗车运砼1km内27.460027.46 7064-4-6205.5498.7816.9389.83 7074-4-7143.6582.2816.9344.44 7084-4-8151.6782.2816.9352.46 7094-4-9322.28197.5616.93107.79 7104-4-10234.94164.5616.9353.45第 23 页,共 114 页7114-4-11244.88164.5616.9363.39 7124-4-12420.4295.6816.93107.79 7134-4-13344.27246.8416.9380.5 7144-4-14357.76246.8416.9393.99 7154-4-15基础现场搅拌砼99.2850.3813.9134.99 7164-4-16柱.墙.梁.板现场搅拌砼120.8150.3813.9156.52 7174-4-17其他构件现场搅拌砼15450.3813.9189.71 7185-1-1单扇带亮带纱木门框制作442.5119.36414.398.76 7195-1-2单扇带亮带纱木门框安装87.0232.3454.540.14 7205-1-3双扇带亮带纱木门框制作322.0713.86302.35 5.86 7215-1-4双扇带亮带纱木门框安装5923.135.80.1 7225-1-5单扇带纱木门框制作415.5418.92388.258.37 7235-1-6单扇带纱木门框安装101.5737.6263.810.14 7245-1-7双扇带纱木门框制作266.9812.1250 4.88 7255-1-8双扇带纱木门框安装60.1823.3236.790.07 7265-1-9单扇带亮木门框制作311.5718.92284.528.13 7275-1-10单扇带亮木门框安装85.1332.3452.650.14 7285-1-11双扇带亮木门框制作226.5313.42207.25 5.86 7295-1-12双扇带亮木门框安装58.4323.135.230.1 7305-1-13单扇木门框制作290.5818.48263.738.37 7315-1-14单扇木门框安装99.4737.6261.710.14 7325-1-15双扇木门框制作188.6611.88171.9 4.88 7335-1-16双扇木门框安装58.7223.3235.330.07 7345-1-17单扇带亮自由门木门框制作444.0720.46415.138.48 7355-1-18单扇带亮自由门木门框安装85.0233.8850.970.17 7365-1-19双扇带亮自由门木门框制作305.613.86285.9 5.84 7375-1-20双扇带亮自由门木门框安装54.3420.933.320.12 7385-1-21四扇带亮自由门木门框制作316.317.6292.88 5.82 7395-1-22四扇带亮自由门木门框安装30.8513.6417.160.05 7405-1-23六扇带亮自由门木门框制作242.8116.28222.33 4.2 7415-1-24六扇带亮自由门木门框安装23.3311.6611.620.05第 24 页,共 114 页7425-1-25单扇自由门木门框制作398.1317.82372.767.55 7435-1-26单扇自由门木门框安装97.0734.7662.10.21 7445-1-27双扇自由门木门框制作241.9311226.46 4.47 7455-1-28双扇自由门木门框安装53.3820.4632.80.12 7465-1-29带纱连窗木门框制作382.9236.96336.489.48 7475-1-30带纱连窗木门框安装40.4618.4821.860.12 7485-1-31连窗木门框制作274.9635.42230.069.48 7495-1-32连窗木门框安装39.3418.4820.740.12 7505-1-33单扇带亮木门扇制作659.7854.12580.1625.5 7515-1-34单扇带亮木门扇安装51.8133.6618.150 7525-1-35双扇带亮木门扇制作728.6658.52643.4126.73 7535-1-36双扇带亮木门扇安装48.8230.1418.680 7545-1-37单扇木门扇制作740.2963.36649.5127.42 7555-1-38单扇木门扇安装21.1221.1200 7565-1-39双扇木门扇制作784.6366.88688.329.45 7575-1-40双扇木门扇安装22.6622.6600 7585-1-41单扇带亮玻璃木门扇制作600.243.56536.1820.46 7595-1-42单扇带亮玻璃木门扇安装61.7728.8232.950 7605-1-43双扇带亮玻璃木门扇制作627.3747.52559.2320.62 7615-1-44双扇带亮玻璃木门扇安装73.0132.5640.450 7625-1-45单扇玻璃木门扇制作659.0645.32594.9518.79 7635-1-46单扇玻璃木门扇安装39.1220.918.220 7645-1-47双扇玻璃木门扇制作676.2953.02601.0822.19 7655-1-48双扇玻璃木门扇安装52.6425.7426.90 7665-1-49单扇带亮半截玻璃木门扇制作540.5840.92479.220.46 7675-1-50单扇带亮半截玻璃木门扇安装87.6237.62500 7685-1-51双扇带亮半截玻璃木门扇制作619.7642.9556.2420.62 7695-1-52双扇带亮半截玻璃木门扇安装82.634.148.50 7705-1-53单扇半截玻璃木门扇制作576.2840.48517.0118.79 7715-1-54单扇半截玻璃木门扇安装64.2123.9840.230 7725-1-55双扇半截玻璃木门扇制作677.5147.08608.2422.19第 25 页,共 114 页7735-1-56双扇半截玻璃木门扇安装65.5127.7237.790 7745-1-57单扇带亮纤维板门扇制作505.9552.14418.2235.59 7755-1-58单扇带亮纤维板门扇安装52.1133.6618.450 7765-1-59双扇带亮纤维板门扇制作576.7956.32482.3838.09 7775-1-60双扇带亮纤维板门扇安装48.7130.1418.570 7785-1-61单扇纤维板门扇制作548.3860.72445.0442.62 7795-1-62单扇纤维板门扇安装21.1221.1200 7805-1-63双扇纤维板门扇制作627.664.46518.9844.16 7815-1-64双扇纤维板门扇安装22.6622.6600 7825-1-65单扇带亮玻璃纤维板门扇制作502.6455.22411.8335.59 7835-1-66单扇带亮玻璃纤维板门扇安装56.1428.1627.980 7845-1-67双扇带亮玻璃纤维板门扇制作573.664.9470.6138.09 7855-1-68双扇带亮玻璃纤维板门扇安装59.4231.0228.40 7865-1-69单扇玻璃纤维板门扇制作543.7463.8437.3242.62 7875-1-70单扇玻璃纤维板门扇安装32.4620.2412.220 7885-1-71双扇玻璃纤维板门扇制作631.1379.86507.1144.16 7895-1-72双扇玻璃纤维板门扇安装35.5423.9811.560 7905-1-73单扇带亮胶合板门扇制作615.3952.14527.6635.59 7915-1-74单扇带亮胶合板门扇安装52.1133.6618.450 7925-1-75双扇带亮胶合板门扇制作693.2456.32598.8338.09 7935-1-76双扇带亮胶合板门扇安装48.7130.1418.570 7945-1-77单扇胶合板门扇制作687.9260.72584.5842.62 7955-1-78单扇胶合板门扇安装21.1221.1200 7965-1-79双扇胶合板门扇制作775.8264.46667.244.16 7975-1-80双扇胶合板门扇安装22.6622.6600 7985-1-81单扇带亮玻璃胶合板门扇制作602.8955.22512.0835.59 7995-1-82单扇带亮玻璃胶合板门扇安装56.1428.1627.980 8005-1-83双扇带亮玻璃胶合板门扇制作68164.9578.0138.09 8015-1-84双扇带亮玻璃胶合板门扇安装59.4231.0228.40 8025-1-85单扇玻璃胶合板门扇制作670.263.8563.7842.62 8035-1-86单扇玻璃胶合板门扇安装32.4620.2412.220第 26 页,共 114 页8045-1-87双扇玻璃胶合板门扇制作766.9279.86642.944.16 8055-1-88双扇玻璃胶合板门扇安装35.5423.9811.560 8065-1-89半玻璃带亮自由门门扇制作775.1954.12705.6615.41 8075-1-90半玻璃带亮自由门门扇安装79.832.7847.020 8085-1-91半玻璃自由门门扇制作890.8163.36811.2516.2 8095-1-92半玻璃自由门门扇安装67.5635.232.360 8105-1-93全玻璃带亮自由门门扇制作518.0948.84459.0810.17 8115-1-94全玻璃带亮自由门门扇安装113.3435.278.140 8125-1-95全玻璃自由门门扇制作651.2652.14589.369.76 8135-1-96全玻璃自由门门扇安装108.837.6271.180 8145-1-97单扇门连窗门窗扇制作489.4236.96433.1219.34 8155-1-98单扇门连窗门窗扇安装117.5136.0881.430 8165-1-99双扇门连窗门窗扇制作461.6235.86406.4219.34 8175-1-100双扇门连窗门窗扇安装117.4741.875.670 8185-1-101三扇门连窗门窗扇制作397.7830.8347.6419.34 8195-1-102三扇门连窗门窗扇安装126.1639.16870 8205-1-103纱门扇制作(扇面积)330.4645.1268.2917.07 8215-1-104纱门扇安装(扇面积)63.9547.316.650 8225-1-105纱亮扇制作(扇面积)378.144.22310.2223.66 8235-1-106纱亮扇安装(扇面积)118.0782.0636.010 8245-1-107普通成品门扇安装(扇面积)1104.8224.421080.40 8255-1-108镶木板门扇安装小百叶108.4128.1680.250 8265-1-109胶合板.纤维板门扇安装小百叶79.8419.5860.2608285-2-1带采光窗平开木板大门门扇制作845.01100.98719.5924.44 8295-2-2带采光窗平开木板大门门扇安装76.6552.5824.070 8305-2-3不带采光窗平开木板大门门扇制作917.53100.98788.3628.19 8315-2-4不带采光窗平开木板大门门扇安装50.1650.1600 8325-2-5带采光窗推拉木板大门门扇制作810.4598.56688.2623.63 8335-2-6带采光窗推拉木板大门门扇安装154.1894.1660.020 8345-2-7不带采光窗推拉木板大门门扇制作945.81115.94800.7229.15第 27 页,共 114 页。
总说明一、《山东省建筑工程消耗量定额》(以下简称本定额)是在《全国统一建筑工程基础定额》的基础上,依据国家现行有关工程建设标准,结合我省的实际情况编制的。
本定额共分十章,包括:土石方工程;地基处理与防护工程;砌筑工程;钢筋及混凝土工程;门窗及木结构工程;屋面防水、保温及防腐工程;金属结构制作工程;构筑物及其他工程;装饰工程;施工技术措施项目。
二、本定额适用我省行政区域内的一般工业与民用建筑的新建、扩建和改建工程及新建装饰工程。
三、本定额是完成规定计量单位分部分项工程所需人工、材料、机械台班消耗量的标准;是编制招标标底的依据;是编制施工图预算,确定工程造价以及编制概算定额、估算指标的基础。
四、本定额是按照正常的施工条件,合理的施工工期、施工组织设计编制的,反映社会平均消耗水平。
五、本定额中人工工日消耗量以《全国建筑安装工程统一劳动定额》为基础计算,内容包括:基本用工、辅助用工、超运距用工及人工幅度差。
人工工日不分工种、技术等级,以综合工日表示。
六、本定额中材料消耗:(一)本定额材料(成品、半成品、配件等)按符合质量标准和设计要求的合格产品确定。
(二)本定额包括主要材料及其他材料。
其他材料以占材料费百分比表示。
(三)本定额中包括材料施工损耗、材料(成品、半成品、配件等)从工地仓库至加工地点或操作地点的运输损耗等。
七、本定额中机械消耗:(一)本定额机械台班消耗量包括机械台班消耗量和机械幅度差。
以不同种类的机械分别表示。
(二)本定额中其他机械(超高机械增加中的其他机械降效除外)以占机械费百分比表示。
(三)大型机械安拆及场外运输,按《山东省建筑工程费用项目构成及计算规则》中的有关规定计算。
八、本定额的工作内容仅对其主要施工工序进行了说明,次要工序虽未说明,但均已包括在定额中。
九、本定额中凡注有“×××以内”或“×××以下”者,均包括“×××”本身;凡注有“×××以外”或“×××以上”者,则不包括“×××” 本身。
省市政工程消耗量定额及计算规则目录第一册通用项目5工程量计算规则5第一章土石方工程7第二章打拔工具桩7工程量计算规则7第三章围堰工程8工程量计算规则9第四章支撑工程9工程量计算规则9第五章拆除工程9工程量计算规则9第六章脚手架及其他工程9工程量计算规则10第七章护坡、挡土墙10工程量计算规则10第二册道路工程10第一章路床(槽)整形11工程量计算规则11第二章道路基层11工程量计算规则12第三章道路面层12工程量计算规则13第四章人行道侧缘石及其他13工程量计算规则13第三册桥涵工程14第一章打桩工程15第二章钻孔灌注桩工程16工程量计算规则16第三章砌筑工程17工程量计算规则17第四章钢筋工程17工程量计算规则17第五章现浇混凝土工程17工程量计算规则18第六章预制混凝土工程18工程量计算规则18第七章立交箱涵工程18工程量计算规则19第八章安装工程19工程量计算规则19第九章临时工程19工程量计算规则20第十章装饰工程21工程量计算规则21第十一章金属构件制作安装工程21 第四册隧道工程21第一章隧道开挖与出碴22工程量计算规则22第二章临时工程22工程量计算规则23第三章隧道衬23工程量计算规则23第四章隧道沉井24工程量计算规则24第五章盾构法掘进24第六章垂直顶升25工程量计算规则26第七章地下连续墙26工程量计算规则26第八章地下混凝土结构26工程量计算规则26第九章地基加固、监测27工程量计算规则27第十章金属构件制作27工程量计算规则27第五册给水工程27第一章管道安装28工程量计算规则28第二章新设与原设管道安装29工程量计算规则29第三章管件及阀、栓、表类安装29工程量计算规则30第四章铸铁及钢制管件及法兰阀类接口30 工程量计算规则30第五章管道附属构筑物30工程量计算规则30第六章管道防腐30工程量计算规则31第七章取水工程31工程量计算规则31第六册排水工程31第一章定型混凝土管道基础及铺设32工程量计算规则33第二章定型井33工程量计算规则33第三章非定型井、渠、管道基础及砌筑33 工程量计算规则34第四章顶管工程34工程量计算规则34第五章给排水构筑物35工程量计算规则35第六章给排水机械设备安装36工程量计算规则38第七章模板、钢筋、井字架工程39工程量计算规则39第七册燃气与集中供热工程40第一章管道安装41工程量计算规则41第二章管件制作、安装41第三章法兰阀门安装42第四章燃气用设备安装42第五章集中供热用容器具安装43第六章管道试压、吹扫及无损探伤43工程量计算规则44第七章除锈、刷油、绝热、防腐蚀工程44 第八册路灯工程45第一章变配电设备工程45工程量计算规则45第二章架空线路工程46工程量计算规则46第三章电缆工程47工程量计算规则47第四章配管配线工程47工程量计算规则48第五章照明器具安装工程48工程量计算规则48第六章防雷、接地装置工程48工程量计算规则48第七章路灯灯架制作安装工程49工程量计算规则49第八章刷油防腐工程49第一册通用项目一、《省市政工程消耗量定额》第一册“通用项目”(以下简称“本分册”),包括土石方工程、打拔工具桩、围堰工程、支撑工程、拆除工程、脚手架及其他工程、护坡挡土墙等容。
总说明一、随着我国城市建设和基础工业的发展,工程爆破技术得到广泛应用。
为适应建设工程市场发展、工程造价管理工作的需要,规范市场行为,合理确定爆破工程造价,制定《爆破工程消耗量定额》(以下简称本定额)。
二、本定额适用于新建、扩建和改建工程中的爆破工程,包括露天爆破、地下爆破、硐室爆破、拆除爆破、水下爆破及特种爆破的各类爆破工程。
三、本定额是按爆破工程量清单的项目特征、工作内容完成规定计量单位爆破工程所需的人工、材料、施工机械台班消耗量的计量标准,是编制工程量综合单价、确定爆破工程造价的依据,是编制招标工程标底和投标报价的基础。
四、本定额突出了爆破工程行业的特点,是按照正常的施工条件,大多数施工企业的现有装备程度,合理的施工工艺,严密的施工安全防护措施和劳动组织为基础编制的,反映了社会平均消耗水平。
五、本定额是依据《民用爆炸物品安全管理条例》、爆破安全规程、国家有关现行产品标准、设计规范、质量评定标准、安全防护规定,以及建设部《全国统一建筑工程基础定额》编制若干统一性规定制定的,并参考了相关行业、地方标准和有代表性的工程设计、施工资料和其他资料。
六、本定额反映了当前设计、施工中最新技术成果,近几年推广应用的新技术、新工艺、新设备等。
七、本定额人工工日以综合工日表示。
人工不分工种、技术等级。
八、材料消耗量的确定:材料消耗包括主要材料、辅助材料、零星材料等。
其他材料费是以该项目材料费之和的百分数考虑的。
采用的爆破材料应是符合国家质量标准和相应设计要求的合格产品。
九、施工机械台班消耗量的确定:施工机械分别按机械、型号或容量,以单机台班消耗量表示。
随人工班组配备的中小型机械,其台班消耗量列入相应的定额项目内。
十、土壤及岩石分类按建设部《全国统一建筑工程基础定额》中的土壤及岩石(普氏)分类表执行。
十一、本定额工作内容中已说明了主要的施工工序,次要工序虽未说明,均已考虑在定额内。
十二、本定额适用于海拔高程2000m以下地区。
超过2000m时,可结合高原地区特殊情况,按当地建设行政主管部门制订的调整办法执行。
十三、爆炸器材的市内运输,因受工程环境、运输车辆以及有无临时贮存场地等因素影响很大,本定额未作统一规定,可根据实际情况另行计算人工、材料和机械的消耗量。
十四、关于爆破工程的安全措施项目:试验爆破工程、爆破网路试验、爆破振动与其他环境影响监测、爆破警戒与人员疏散组织工程、城区环境保护措施、爆破安全评估和爆破工程监理等,均需另行计算。
十五、本定额是按照合理的施工组织设计和正常的施工条件进行编制的。
定额中所列的项目及含量,均系按现行的标准、图纸、法规经测算分析取定的,除定额中规定允许换算者外,均不得因工程的施工组织、操作方法和材料消耗与本定额不同而换算。
十六、本定额中注有“×××以内”或“×××以下”者,均包括×××本身,“×××以外”或“×××以上”者,则不包括×××本身。
十七、本说明未尽事宜,详见各章说明。
·2·第一章露天爆破工程说明1.深孔爆破按钻孔直径分为4个等级。
其中,50mm<φ≤100mm等级的数据主要以孔径φ76mm的统计资料为基础;100mm<φ≤150mm等级的数据主要以孔径φ110mm的统计资料为基础;150mm<φ≤250mm 等级的数据主要以孔径φ200mm的统计资料为基础;φ>250mm等级的数据主要以孔径φ310mm的统计为基础。
2.光面爆破和预裂爆破以爆破的面积作为定额计量单位。
光面爆破与预裂爆破按钻孔直径分为5个等级,分别为φ≤50mm,50mm<φ≤100mm,100mm<φ≤150mm,150mm<φ≤250mm,φ>250mm。
水平预裂爆破只有两个等级,即φ≤50mm,50mm<φ≤100mm。
水平预裂爆破的工程数量定额以直斜孔光面爆破与预裂爆破定额为基数乘以系数1.2。
3.城镇及复杂环境石方爆破工程,对复杂环境应分类区别,露天石方爆破复杂环境分为A、B、C 3类:A类复杂环境指爆破范围至国家一、二级文物,极重要设施,极精密贵重仪器设备及重要建(构)筑物等距离50m以内,或至国家三级文物、省级文物、重要设施、民房、办公楼、厂房等距离10m以内;B类复杂环境指爆破范围至国家一、二级文物,极重要设施,极精密贵重仪器设备及重要建(构)筑物等距离大于50m、小于或等于100m,或至国家三级文物、省级文物、重要设施、民房、办公楼、厂房等距离大于10m、小于或等于50m;C类复杂环境指爆破范围至国家一、二级文物,极重要设施,极精密贵重仪器设备及重要建(构)筑物等距离大于100m、小于200m,或至国家三级文物、省级文物、重要设施、民房、办公楼、厂房等距离大于50m、小于100m。
城镇及复杂环境石方爆破工程数量定额中只包括爆破工作内容,不包括爆破有害效应防护内容,爆破有害效应防护措施数量根据具体项目的爆破设计另行计算。
根据测算城镇及复杂环境浅孔爆破和深孔爆破的工程数量定额,可以普通浅孔爆破和深孔爆破(50mm<φ≤100mm)定额为基数,除炸药数量外,其他人工、机械、材料数量乘以一定的系数较合适。
A类复杂环境的爆破工程量消耗乘以系数3.0;B类复杂环境的爆破工程量消耗乘以系数2.0;C类复杂环境的爆破工程量消耗乘以系数1.5。
数量定额表中工作内容为:布孔,钻孔,验孔,装药,填塞,联网路,警戒,起爆,爆后检查,二次破碎大石块。
爆破有害效应防护措施根据具体项目的爆破设计另行计算。
4.临近边坡爆破工程按边坡性质和重要性参考定为极重要设施或一般重要设施,如Ⅰ、Ⅱ级铁路、高速公路、发电厂房等可以定为极重要设施。
5.大块孤石爆破可参考浅眼爆破定额计算。
6.场平石方爆破可参照相应的深孔爆破或浅孔爆破定额。
7.考虑当前国内爆破工程已经广泛使用乳化炸药,比较不同配方的乳化炸药和2#岩石硝铵炸药的爆炸性能和破碎效果,暂以2#乳化炸药替代以往以2#岩石硝铵炸药作为定额材料炸药用量的计算量。
·4·1.1浅孔爆破工程1.1.1浅孔爆破工作内容:布孔,钻孔,验孔,装药,填塞,联网路,警戒,起爆,爆后检查,二次破碎大石块。
3定额编号1-1-1 1-1-2 1-1-3 1-1-4项目名称浅孔爆破松石次坚石普坚石特坚石名称单位数量人工综合工日工日9.850 13.450 15.840 20.200材料合金钻头个 1.000 2.000 3.000 5.000 六角空心钢kg 2.000 3.000 5.000 7.000 高压风管m 0.210 0.350 0.560 0.760 胶质导线 1.5mm2m 49.280 53.680 60.360 64.840 胶质导线 2.5 mm2m 23.990 24.140 24.800 25.440定额编号1-1-1 1-1-2 1-1-3 1-1-4项目名称浅孔爆破松石次坚石普坚石特坚石名称单位数量材料电雷管导爆管雷管个54.000 62.000 75.000 88.000 乳化炸药 2#kg 26.320 32.580 41.500 52.970 高压水管m 0.340 0.570 0.920 1.250 水m3 3.720 6.720 10.390 14.820 其他材料费% 2 2 2 2机械风动凿岩机气腿式台班 1.910 3.190 5.187 7.034 修钎机台班0.230 0.330 0.480 0.690 电动空气压缩机 10m3/min 台班0.680 1.130 1.850 2.5001.1.2基坑石方爆破工作内容:布孔,钻孔,验孔,装药,填塞,联网路,警戒,起爆,爆后检查,二次破碎大石块。
3定额编号1-1-5 1-1-6 1-1-7 1-1-8项目名称基坑爆破(上口面积>20m2)·6·3计量单位:100m3定额编号1-1-13 1-1-14 1-1-15 1-1-16项目名称基坑爆破(上口面积≤4m2)松石次坚石普坚石特坚石名称单位数量人工综合工日工日50.000 65.600 88.000 100.500材料机械1.1.3沟槽石方爆破工作内容:布孔,钻孔,验孔,装药,填塞,联网路,警戒,起爆,爆后检查,二次破碎大石块。
3定额编号1-1-17 1-1-18 1-1-19 1-1-20项目名称沟槽爆破(1m<沟底宽≤4m)松石次坚石普坚石特坚石名称单位数量人工综合工日工日23.000 26.000 32.000 38.000 材料·8·机械3定额编号1-1-21 1-1-22 1-1-23 1-1-24项目名称沟槽爆破(沟底宽≤1m)松石次坚石普坚石特坚石名称单位数量人工综合工日工日45.000 50.000 60.000 75.000材料机械1.1.4保护层开挖石方爆破工作内容:布孔,钻孔,验孔,装药,填塞,联网路,覆盖,警戒,起爆,爆后检查,二次破碎大石块。
3定额编号1-1-25 1-1-26 1-1-27 1-1-28项目名称保护层开挖爆破松石次坚石普坚石特坚石名称单位数量人工综合工日工日50.800 61.300 76.100 101.500材料机械1.2深孔爆破工程1.2.1 50mm<φ≤100mm钻孔爆破工作内容:布孔,钻孔,验孔,装药,填塞,联网路,警戒,起爆,爆后检查,二次破碎大石块。
3定额编号1-2-1 1-2-2 1-2-3 1-2-4项目名称深孔爆破(50mm<孔径φ≤100mm)松石次坚石普坚石特坚石名称单位数量人工综合工日工日 2.800 3.900 4.520 5.300材料乳化炸药 2#kg 38.500 43.260 48.830 56.650 导爆管雷管 15m脚线个 2.000 2.200 2.400 2.600 电雷管 8#个 5.200 6.220 7.240 9.260·10·1.2.2 100mm<φ≤150mm钻孔爆破工作内容:布孔,钻孔,验孔,装药,填塞,联网路,警戒,起爆,爆后检查,二次破碎大石块。
3·12·料机械1.2.3 150mm<φ≤250mm钻孔爆破工作内容:布孔,钻孔,验孔,装药,填塞,联网路,警戒,起爆,爆后检查,二次破碎大石块。
3定额编号1-2-9 1-2-10 1-2-11 1-2-12项目名称潜孔钻钻孔爆破石方(150mm<孔径φ≤250mm)松石次坚石普坚石特坚石名称单位数量人工综合工日工日 1.460 2.040 2.370 2.770材料定额编号1-2-9 1-2-10 1-2-11 1-2-12项目名称潜孔钻钻孔爆破石方(150mm<孔径φ≤250mm)松石次坚石普坚石特坚石名称单位数量材料机械3定额编号1-2-13 1-2-14 1-2-15 1-2-16项目名称牙轮钻钻孔爆破石方(150mm<孔径φ≤250mm)松石次坚石普坚石特坚石名称单位数量人工综合工日工日0.370 0.500 0.770 1.340 材料机械·14·1.2.4 φ>250mm钻孔爆破工作内容:布孔,钻孔,验孔,装药,填塞,联网路,警戒,起爆,爆后检查,二次破碎大石块。