装箱标准-立卷
- 格式:pdf
- 大小:537.13 KB
- 文档页数:2
1.3 卷眼朝上
(立卷
) eye up
coil
序号 品名
规格
说明
1
支撑木条
Wooden bars
10cm * 10cm * L
每个卷左右两侧用1组木架子横向支撑both sides of each coil were separately chocked with a set of timberwork. Top side of the coils was group covered by a set of timberwork. 3.
三角木 wooden wedges
10cm * 10cm * 15cm 第一个卷和最后一个卷的两侧底部各需4个三角木固定,当中的卷两侧底部各需2个三角木固定,所有三角木均需钉在箱底板上;The first and last coil each should be chocked with 4 pcs of wooden wedges at each side, the coils at middle part each should be chocked with 2 pcs of wooden wedges at each side; all wooden wedges should be nailed on the floor against the pallet.
4. 钢丝绳 steel wire rope 直径dia: 12mm 所有卷先用2跟钢丝绳整体绑扎成一组,每个卷各用一根钢丝绳通过顶部的木架加以垂直固定,对称绑扎,两头固定在箱底板上的令环上。
钢丝绳卡扣在每端不低于2个。
All coils should group lashed by 2 lines of steel wire rope firstly, then each coil should be further tie up lashed by a line of steel wire rope through the top side timberwork and connected to the lashing rings at both sides on the floor, and tightened by turnbuckles. Clips at each end should be not less than 2 pcs.
5.
卡扣 clips
6号
6. 松紧螺丝
turnbuckle 标准16号全新(turnbuckle should be new, rust or second
hand is prohibited)。