XXXXXXXX工程 临时用电施工组织设计

第 1 页 目 录

编制依据 ······························································································ 2

第一章 工程概况与部署 ········································································· 3

第二章 负荷计算 ·················································································· 6

一、计算原则 ·················································································· 6

二、总用电量(P)计算 ···································································· 6

三、各配电箱负荷计算 ·····································································

10

四、绘制电路图 ·············································································· 11

第三章 配电线路设计 ··········································································· 12

第四章 接地与防雷设计 ········································································ 13

第五章 用电措施和电气防火措施 ···························································· 14

附:

施工用电平面布置图XXXXXXXX工程 临时用电施工组织设计

第 2 页 编制说明

1、编制依据

1.1 《低压配电设计规范》GB50054-95中国建筑工业出版社

1.2 《建筑工程施工现场供电安全规范》GB50194-93中国建筑工业出版社

1.3 《通用用电设备配电设计规范》GB50055-2011中国建筑工业出版社

1.4 《供配电系统设计规范》GB50052-2009中国建筑工业出版社

1.5 《施工现场临时用电安全技术规范》JGJ46-2005中国建筑工业出版社

1.6《建筑施工安全检查标准》JGJ59-2011

1.7公司管理手册

2、编制人员

XXXX 技术负责人XXXXXXXX工程 临时用电施工组织设计

第 3 页 第一章 工程概况

1.1工程概况

XXXXXXXX工程是XXXXXXXX公司开发的大型中高档楼盘。建筑基地周边道路:XXXXXXXX路,交通较为便利。

XXXXXXXX工程: 建筑面积约为107216.25m2,3#栋地下室为2层,其余地下室为1层。地下车库有停车位692个,地上有停车位212个,共计904个。

工程建设概况一览表

序号 内 容 说明与要求

1 工程名称 XXXXXXXX工程

2 建设地点 xxxxx

3 业主 XXXXXXXX有限公司

4 设计单位

5 建设规模

6 建设工期

7 工程质量 优良工程

8 承包方式 工程总承包

9 主要用途 商住

1.2主要机械设备投入情况

由于该工程具有体量大、所投入的设备多、用电总功率大等特点。因此,对整个工程现场用电应该实行统一管理,统一布设的用电控制措施。根据本工程具体情况及项目策划,拟将投入使用的设备主要有塔式起重机5台、人货电梯5台、输送泵4台(1台备用)、对焊机3台以及其它施工用的小型设备若干。如:切断机、弯曲机、水泵、振动泵、木工机械等。为安全顺利地施工,对上述这些用电较大的设备按区段采取分线路供电方法进行用电控制。

1.3主要设备布置

主要施工设备、机具的布置详见《施工用电平面布置图》。

二、施工用电部署

2.1临时配电房 XXXXXXXX工程 临时用电施工组织设计

第 4 页 现场有总配电柜1个,位于场地的东北角,主要对施工现场、办公区进行供电,详见临时用电平面布置图(民工生活区另行布置)。布线均采用三相五线制。将施工现场分为3个回路,共设3个一级配电箱,1#配电箱负责生产一区用电,2#配电箱负责生产二区用电,3#配电箱负责生产三区及办公区用电。

2.2现场主要用电设备(见表1)

表1 现场主要用电设备统计

用电区域/设备 名称 规格 数量 额定功率

区 空调 挂式 20 0.88×20=17.6kW

空调 柜式 5 2.21×5=11.05kW

电脑 20 0.4×20=8kW

复印机 2 1.5×2=3kW

打印机 3 0.1×3=0.3kW

饮水机 8 0.4×8=3.2kW

冰柜 1 0.5kW

热水器 2 3×2=6kW

照明 60 0.04×60=2.4kW

小计 52.05 kW

生产一区 塔吊 TC5610/5013 3 42×3=612kW

镝灯 3.5kW 6 3.5×6=21kW

人货电梯 / 3 40×3=120kW

电渣压力焊 ENS 2 40kW

振动棒 1.5kW 4 1.5×4=6kW

输送泵 HBT60 1 75kW

圆盘锯 φ300 3 4.4×3=13.2 kW

交流电焊机 3 21×3=63kVA

钢筋切断机 GT-40-1 1 7.5kW

钢筋弯曲机 GW-40 1 3kW

钢筋调直机 TQ4-14 1 9kW

钢筋对焊机 1 100kVA

小计 541.7kw

生产二区 塔吊 TC5610/5013 1 42×1=42kW

镝灯 3.5kW 2 3.5×2=7kW

人货电梯 / 2 40×2=80kW

电渣压力焊 ENS 2 40kW

振动棒 1.5kW 4 1.5×4=6kW

输送泵 HBT60 1 50kW

圆盘锯 φ300 3 4.4×3=13.2kW

交流电焊机 3 21×3=63kVA

钢筋切断机 GT-40-1 1 7.5kW XXXXXXXX工程 临时用电施工组织设计

第 5 页 钢筋弯曲机 GW-40 1 3kW

钢筋调直机 TQ4-14 1 9kW

钢筋对焊机 1 100kVA

小计 541.7 kW

2.3电缆线的敷设

业主提供的变压器至一级配电屏的导线通过电缆沟埋地敷设,配电屛至二级配电箱的导线一般也通过电缆沟埋地敷设。临时用电线路在场内加塑料套管沿建筑物四周暗敷埋设,再设支路引入需用地点。楼层用电采用垂直布线,室内临时照明附墙(柱)安装,均采用塑料管保护电缆。进配电箱的电缆须穿管保护。XXXXXXXX工程 临时用电施工组织设计

第 6 页 第二章 负荷计算

一、计算原则

1.1 施工现场供电系统采用TN-S(三相五线制),根据《施工现场临时用电安全技术规范JGJ46-2005》的规定,配电系统实行三级配电,三级保护。

1.2建筑工地临时供电,包括动力用电与照明用电两种,在计算用电量时,从下列各点考虑:

1)各生产区所使用的机械动力设备,其他电气工具及照明用电的数量;

2)施工总进度计划中施工高峰阶段同时用电的机械设备最高数量;

3)各种机械设备在工作中需用的情况。

二、用电量(P)计算

1、生产一区

1)一区总配电

由于工地分为施工动力与照明相对错开,各栋楼施工器具综合考虑,因此开关需用系数综合考虑为KX总=0.5

开关选择:

I总=∑Ij=0.5*(195+195+149+142+145)=413A

负荷开关:NS500NA /3P;断路器:NS500NA /500A3P

电缆选择:

查表初选:VV-3*120+2*70

2)1#楼、5#楼

开关选择:

Pj1=0.65*(5.5+45+40+7+20+20)=90kw

Sj1= Pj1 /cos总=128KVA

Ij1=Sj1/Ue√3=195A

查表初选

负荷开关:NS250NA /3P;漏电断路器:NSE250N4P/250EL 漏电动作电流200mA

电缆选择:

查表初选VV-3*70+2*50

3)输送泵

开关选择:

Pj1=75kw

Sj1= Pj1 /cos总=95KVA XXXXXXXX工程 临时用电施工组织设计

第 7 页 Ij1=Sj1/Ue√3=142A

查表初选

负荷开关:NS200NA /3P;漏电断路器:NSE200N4P/200EL 漏电动作电流200mA

电缆选择:

查表初选VV-3*50+2*16

4)钢筋加工棚

内包含一台闪光对焊机,由于对焊机工作短时性,暂载率考虑75%,因此按75%考虑负荷。

Pj1=0.7*(3+7.5+7.5+2+0.75*100)=67kw

Sj1= Pj1 /cos总=95KVA

Ij1=Sj1/Ue√3=145A

查表初选

负荷开关:NS200NA /3P;漏电断路器:NSE200N4P/200EL 漏电动作电流200mA

电缆选择:

查表初选VV-3*50+2*16

5)预留:

负荷开关:NS250NA /3P;漏电断路器:NSE250N4P/250EL 漏电动作电流200mA

2、生产二区

1)二区总配电

由于工地分为施工动力与照明相对错开,各栋楼施工器具综合考虑,因此开关需用系数综合考虑为KX总=0.5

开关选择:

I总=∑Ij=0.5*(195+195+149+142+145+21)=434A

负荷开关:NS500NA /3P;断路器:NS500NA /500A3P

电缆选择:

查表初选:VV-3*120+2*70

2)2#楼

开关选择:

Pj1=0.65*(5.5+45+40+7+20+20)=90kw

Sj1= Pj1 /cos总=128KVA

Ij1=Sj1/Ue√3=195A

查表初选

负荷开关:NS250NA /3P;漏电断路器:NSE250N4P/250EL 漏电动作电流200mA 电缆选择: 查表初选VV-3*70+2*50