The n of Advertising Billboards
To prepare for n。the corresponding steel materials should be
used according to the n drawings。with a quality certificate。When there is doubt about the quality of the steel。sampling n
should be carried out according to the XXX used in the steel
structure project should also have a quality certificate and meet the
design XXX used should also meet the design XXX as rulers。stone pens。chalk lines。marking needles。compasses。and tin
snips needed for layout should be XXX。The layout should be
drawn on a sample board at a scale of 1:1 (with a 5mm cutting
allowance)。The quality of the weld seam should meet the
requirement of Class III。
When there are no specific XXX drawings。mechanical rust
removal should be used。with all grease。oxide scale。rust and
other impurities removed from the metal surface to ensure that the
surface is clean XXX。The second coat cannot be applied before the us XXX。natural drying for at least seven days is required
before use。XXX。foggy。or XXX
After each layer of n is applied。XXX。bubbles。flowing。wrinkles。or damage。If there are any。they should be dealt with
XXX。with each layer applied in a crosswise manner。The
coating should be even and no XXX
For the n of the billboard truss。the angle steel should be cut
with an oxygen-acetylene flame according to the 1:1 layout。The
surface of the cut should be free of oxide scale。slag or any other
XXX the quality。The cut pieces should be assembled into large
panels at the n site。and then lifted to the XXX。
For n。the sequence should be as follows: column lifting →
billboard truss on-site assembly → billboard truss lifting →
welding of the billboard truss and column → n of the lamp holder
and other components。For single-XXX。the sequence should be:
column XXX → billboard truss XXX → XXX → XXX。
Before XXX。the n should be checked and the centerline
should be marked。The surface of the n should be flat without any
cracks。bs。or XXX to each other。with a n of no more than
±20mm for the external ns and no more than 20mm for the XXX
from the reference line。
Before n。the technical personnel should analyze the
workshop structure and plan the XXX。shackles。rings。and
cable wind ropes for lifting should be preparedXXX according to
the following method:
公式T=(d/10)^2表示钢丝绳扣起吊能力,单位为t,其中d为钢丝绳扣直径,单位为mm。需要注意的是,这个估算方法只适用于新绳扣,不适用于断丝、断股现象。
在吊装现场,需要注意以下事项:吊车和运输车需要占用单车道,必须提前向相关部门办理手续。吊装过程中可能会破坏部分草坪和小树,也需要提前向相关部门办理手续。在占用道路时,需要在两端立好醒目的标志,并派专人看守。
对于立柱吊装,卷管按6米一段在卷制车间拼装焊接,然后利用10吨半挂车运输至安装位置。到达现场后,再将其组对成整体,利用16吨汽车吊进行装卸。吊装位置应选择在安装位置旁的空旷地带。
由于广告牌安装位置站车条件较好,回转半径为7米,起吊高度为19米,卷管立柱重约8吨。这时可以利用25吨汽车吊将卷管立柱整体吊装到位。在吊装过程中,需要调整缆风绳以确保立柱的垂直度,并使用经纬仪校验安装垂直度,误差不超过10mm。单面广告牌立柱重量较小,吊装相对容易,但仍需要保证其安装垂直度。
广告牌骨架到达现场后,需要再次组对成整体。吊装位置应选择在单车道上,以减少对草坪的破坏。立柱吊装好后,将广告牌骨架和支撑A、B、C在安装位置地面组装成整体,利用3个10吨倒链将广告牌骨架和支撑缓慢、均匀地提升到位。在提升过程中,每200mm稍停,检查广告牌骨架是否倾斜,调整后继续提升,直至到达安装位置。整个提升过程需要由专人指挥,并配以哨子统一作业。
最后,对于三面广告牌骨架的吊装,需要在整体提升到位后立即进行广告牌骨架与卷管立柱的焊接,确保焊接牢固后方可松钩。对于单面广告牌骨架的吊装,则需要对绑扎点角钢进行加固。