卓唐液压站出厂检验报告-英文版
- 格式:doc
- 大小:178.73 KB
- 文档页数:7
Pre-shipment Inspection Report Service Number: Summary SectionProductNameTrolley BagItemnumberN/AP/OnumberN/AQuantity 1185 piecesClientname。
Suppliername。
Inspectiondate2008-10-18Arrivaltime09:30Departuretime18:00Inspection location QUANZHOU,FUJIAN, ChinaInspector David WangNingbo IntegrityINT’LSERVICE CO.,LTDCategory Conform CommentQuantity YesProduct description / style / color No please refer to special attention Point #1, #2,Workmanship NoTesting/ checking YesData measurement YesPackaging YesShipping mark YesInspection Standard: ANSI/ASQZ1.4 (MIL-STD-105E) DEFECTSCritical Major Minor Sampling plan: Single, Normal AQL 0.0 2.5 4.0Inspection Level: II Defects Found: 0 9 13QuantityProduct description / style / colorspecificationCheck against sample submitted by client:Discrepancy was found on inspection samples, please refer to Special Attention point # 1 & #2.WorkmanshipDefectives ListDefectivesListDefectivesCRI MAJ MIN PictureDescription0 0 8Wrinkle markon fabricDirty stains 0 0 5DefectivesListDefectives ListDefectivesDescriptionCRI MAJ MIN PictureHandle standslant ( can beused)0 9 0TESTING /CHECKINGFunction test on handle, wheel, zip and Velcro.Performed on all seletced samples, the result was passed.Function checking for Velcro tape/zip Performed all selected samples, the result was acceptablePull test at handle strap by hand normal force Performed on S-3 samples, the result was passed.Adhesive test by tapes Performed on S-3 samples, Noprinting peel off, the result waspassedSize measure performed on 5 pcs samples,result is below measurement table.Internal Check performed on 5 pcs samples,Discrepancy was found oninspection samples, please refer toSpecial Attention point # 1 & # 2.(Page 2).Mass productions Approved sampleGap locationCarton Drop Test from 76cmheight, drop 10 times at 1 corner, 3edges and 6 faces.Performed on 3 cartons, the resultwas passedDATA MEASUREMENTSize MeasurementItems Spec.(cm)Samples1 2 3 4 5Product size (L * W * H) N/A 36 * 26.5* 4036 * 26.5* 4036 * 26.5* 4036 * 26.5* 4036 * 26.5* 40Side pocket23*25 23*24.5 23*24.5 23*24.5 23*24.5 23*24.5 Logo printing(L * W)N/A 11 * 2.6 11 * 2.6 11 * 2.6 11 * 2.6 11 * 2.6PE boardthickness onbottom and backpart4.0mm 4.0mm 4.0mm 4.0mm 4.0mm 4.0mmPE boardthickness around3 sides3.0mm 3.0mm 3.0mm 3.0mm 3.0mm 3.0mmGross Weight ofexport cartonN/A 5.0 KGS 5.1 KGS 5.2 KGS 5.0 KGS 5.0 KGSSize of Export carton N/A 39 * 32 *44cm39 * 32 *44cm39 * 32 *44cm39 * 32 *44cm39 * 32 *44cmPackagingUnit packingEach product was packed into anindividual poly bag ,sealed onopeningOuter packing Carton size: 39 * 32 * 44cm1 pc with an instruction sheet packed ina carton which fixed by 1 nylon strap.Shipping markShipping MarkFront mark Side markOther markingBar code label on CartonPrinting logo on bag Other PicturesSewn label Sewn label (back)Instruction sheet Bottom viewString on zipper puller Compare with approved sample (rightside one)CartonsTotal cartons Inspected cartons。
液压站出厂检验报告一、引言液压站是一种利用液体来传递动力的设备,常用于工业生产中的液压系统。
为了确保液压站的质量和性能,我们对其进行了出厂检验。
本报告旨在汇总和总结液压站的出厂检验结果,并提供相关的评估和分析。
二、检验内容1. 外观检验:- 检查液压站整体结构是否完好无损;- 检查密封件是否完好且无泄漏;- 检查各连接部位是否紧固可靠。
2. 性能检验:- 检查液压站的压力是否符合设计要求;- 检查液压站的流量是否符合设计要求;- 检查液压站的工作温度是否在规定范围内。
三、检验结果1. 外观检验结果:根据检验,液压站的外观结构完好无损,密封件完好,各连接部位紧固可靠。
2. 性能检验结果:- 压力检验结果:液压站的压力符合设计要求,平均压力稳定在规定范围内;- 流量检验结果:液压站的流量符合设计要求,并且流量稳定;- 温度检验结果:液压站的工作温度在规定范围内,无异常情况。
四、评估和分析1. 外观检验评估:液压站的外观结构完好无损,密封件完好,各连接部位紧固可靠,表明液压站在运输和安装过程中未受到损坏,各部件安装正确。
2. 性能检验评估:- 压力检验评估:液压站的压力符合设计要求,表明液压站能够产生足够的压力来驱动液压系统;- 流量检验评估:液压站的流量符合设计要求,表明液压站能够提供足够的液压功率;- 温度检验评估:液压站的工作温度在规定范围内,表明液压站能够在正常运行条件下保持稳定的温度。
五、结论通过出厂检验,我们可以得出以下结论:液压站的外观结构完好无损,各部件安装正确,密封件完好,各连接部位紧固可靠。
性能检验结果显示液压站的压力、流量和工作温度符合设计要求,能够提供稳定的液压功率和工作温度。
最后,我们建议购买液压站的用户在安装和使用前仔细阅读并遵守操作手册中的要求,以确保液压站能够稳定、高效地运行,并延长其使用寿命。
如有任何问题或需要进一步咨询,请随时与我们联系。
出厂质检报告模板英文IntroductionThis report presents the findings of the quality inspection conducted at the factory. The purpose of this inspection is to ensure that the products meet the required standards and specifications before they are shipped to the customers. The inspection was carried out on [date] by a team of experienced inspectors.Product Information- Product Name: [Name of the product]- Product Model: [Model number]- Batch Number: [Batch number]- Quantity Inspected: [Number of units]Inspection CriteriaThe inspection was conducted based on the following criteria:- International standards and regulations- Customer specifications and requirements- Industry best practicesInspection Process1. Initial assessment of product documentation2. Visual inspection of the products3. Measurement of product dimensions and specifications4. Testing of product functionalities and performance5. Assessment of packaging and labelingFindingsBased on the inspection conducted, the following findings were identified:1. Visual Inspection- The overall appearance of the products is in conformity with the specified requirements.- No visible scratches or damages were observed on the surface of the products.- The color consistency across the products is satisfactory.2. Measurement of Dimensions and Specifications- All the measured dimensions are within the specified tolerances.- The weight of the products matches the required specifications.- The materials used in the products are of the specified quality.3. Testing of Functionalities and Performance- The products function satisfactorily according to the specified requirements.- All the functions and features of the products were tested and found to be in working order.- The safety features incorporated in the products operate as intended.4. Assessment of Packaging and Labeling- The products were packed securely to prevent any damage duringtransportation.- The labeling on the packaging is clear, accurate, and in accordance with the customer requirements.- The packaging materials used are of good quality and provide adequate protection.ConclusionBased on the findings of the inspection, it is concluded that the products meet the required standards and specifications. The quality of the products is satisfactory and they are suitable for shipment to the customers.RecommendationsNo major issues were identified during the inspection. However, minor improvements in packaging design and labeling clarity are suggested to enhance the overall customer experience.AcknowledgmentWe would like to express our gratitude to the factory management and staff for their cooperation and support during the inspection. Appendix- Photographs of the inspected products- Test results and measurements data。
工厂中英文对照检讨报告中英文对照检讨报告1成品平均肉厚为0.82左右.The average thickness is about 0.82mm.2成品平均肉厚为0.6mm.The average thickness of part is 0.6mm.3成品内厚均匀.The thickness of part is even.4此处肉厚不均,成品易缩水.共六处.请修改.As the figure shows, the thickness is uneven, so it is easy to shrink. Please modify it, 6 areas in total.5成品太薄,成型比较困难,请修改成品.The thickness of part is too thin, so it is difficult to be molded, please modify it.6如图所示,塑件太薄请修改成品,厚度至少0.80mmAs the figure shows, the thickness is too thin, please modify it to 0.8mm at least.7如图所示,塑件太薄,不易充填,请将此处肉厚从0.40mm增加至0.50mm.As the figure shows, the thickness of part is too thin to fill enough, please adding material from 0.4mm to 0.5mm.8如图所示肉厚过厚,容易导致成品缩水.As the figure shows, the thickness is too thick that cause shrinking easily.9此处可能缩水,因此处肉厚较厚.There may be shrinkage, because the thickness is too thick.10平均肉厚0.53mm,最薄处仅0.2mm,有可能滞流,不易成型.The average thickness is 0.53mm, but the thinnest area is only 0.2mm, where the hesitation would exist and the part can’tbe molded easily.11请将周围红色面向公模侧拔模2.0度.Please draft the red surface 2.0 degrees along the core.12为防止成品粘母模,请将图示红色面向公模方向增加拔模到3度.As the figure shows, please draft the red surface 3-degree along the core side to prevent it (from) sticking to the cavity.13以红色线为基准,黄色面向母模侧3度拔模,蓝色面向公模侧2度拔模.Keep the red line as datum, please draft the yellow surface 3-degree along the cavity, and the blue surface 2 degrees along the core.14建议将红色面以蓝色线为基准做公模2度拔模.Keep the blue line as datum, suggest drafting the red surface 2 degrees along the core side.15.请将绿色面向母模侧拔模3度Please draft the green surface 3 degrees along the cavity side.16请将红色面做公模侧拔模!Please draft the red face along the cavity side.17如图:图中红色面,请沿斜销后退方向做3度拔模.As the figure shows, please draft the red surface 3 degrees along the backward direction of the lifter (using the arrow as the direction of lifter)18如图所示,请将红色面拔模在公模侧(全周),以防止粘母模.As the figure shows, please draft the red surface along the core side to prevent the product sticking to the cavity.19请将图示绿色面沿滑块后退方向3度拔模,用红色箭头表示其后退方向.As the figure shows, please draft the green surface 3 degrees along the releasing direction of the slider. ( using the red arrow as the releasing direction of slider.)20请将红色面向公模侧增加拔模,从0.5度加大到2.0度.Please increase the draft angle of the red surface from 0.5 to 2 degrees along the core21如图所示:请将红色面沿滑块后退方向拔模3度!As the figure shows, please draft the red surface 3 degrees along the releasing direction of slider.22为避免模仁尖角,请修改红色面拔模至公模侧.Please draft the red surface along the core side to avoid sharp corner. 23请将此处拔模3.0度,因角度太小会粘滑块. (左右共二处)Because the draft angle is too small, the part would stick to slider, so please draft this surface 3 degrees. (both sides).24红色框内区域必须沿斜销方向拔模0.5~1.0度,以防铲胶.To prevent cutting plastic , the area as the red frame shown must be drafted 0.5~1.0 degree along the lifter’s direction.25请将红色面拔模角度增加至4度以增加模仁插破角度!To increase the shut- off angle between cavity and core, please draft the red surface 4 degrees.26将红色面向母模侧拔模3度(第二次指出)Draft the red surface 3-degree along the cavity side (point out again) 27绿色面未拔模,请确认是否以0度抛光,否则向母模侧增加拔模角5度.As the figure shows, please check whether the green surface must be on zero draft for good polishing , otherwise add 5 degrees on the cavity side.28.绿色面在公模侧未拔模,建议将其做公模2度拔模.The green surface hasn’t been drafted along the core side. Suggest drafting it by 2-degree.29.如图所示,红色面为母模侧.As the figure shows, the red surface is in cavity side.30.如图所示,此处均为铁件与模仁插破封胶,易跑毛边,请将此处插破角增加至5度以上.As the figure shows, it is easy to occur flash, please add drafting angle to 5 degrees.31.建议将红色面公模拔模8度,以便于斜销成型.Suggest drafting the red surface 8 degrees along the core side for being molded by the lifter easily.32.请将图示绿色面沿斜销后退方向2度拔模,用红色箭头表示其后退方向. Please draft the green surface 2 degrees along the backward direction of lifter (using the red arrow as the direction of lifter)33.请将桔色面作斜销后退方向拔模5度.Please draft the orange surface 5 degrees along the backward direction of lifter.34.如图:现有成品外观面在红线处有分模线痕迹.建议将蓝色公模面向母模侧拔模3.0度,这样PL线下移到圆角处.As the figure shows, there will be visible mark on the appearance surfaces, suggest drafting blue surface 3.0 degrees along the cavity side (both sides) to change the PL to the place of radius.35.产品一周红色面在母模侧未拔模,建议将其做母模3度拔模.The red surface around product hasn’t been drafted on the cavity side, suggest drafting it by three degrees.36.红色面在公模侧未拔模,建议将其做公模3度拔模.The red surface hasn’t been drafted on the core side, suggest drafting it by 3- degree.37.请取消断差!Please cancel this step.38.请去掉此断差,避免模仁此处插破!Please delete the step to avoid the shut-off between the cavity and core.39.请照右图取消C角Please modify model according to the right figure.40.方案1: 取消全周R角Proposal 1:Cancel the R(all round)41.方案2: 全周增加断差Proposal 2:add the step(all around)42.建议此边倒圆角Suggestion: blend the edge43.请将红色线倒圆角0.20mm!Please round 0.2mm at the red line.44.如图所示: 请照右图修改!As the figure shows, please modify the model according to the right picture.45.滑块后退方向the releasing direction of slider46.如图示,用红色箭头表示滑块后退方向As the figure shows, use the red arrow as the releasing direction of slider.47.滑块分模线如图所示,箭头所示方向为滑块后退方向The parting line of slider is as the figure shown, the red arrow shows the direction of the slider’s movement.48.成品采用牛角进胶,胶口位置如图所示.Banana-gate is adopted as the figure shown.49.成品采用边式浇口进胶,浇口位置如图所示.To adopt the side gate, and the gate location is as the figure shown 50.成品采用边浇口进胶, 浇口位置如图所示.请确认!Gate type is edge gate and the location is as the figure shown, please confirm it.51.其效果见模流分析,建议采用阀胶口,省料头!Suggest adopting the valve gate to save the material, and refer to the mold flow analysis to see its effect.52.成品采用潜进胶,胶口位置如图所示.Gating type is submarine gate, and the gate location is as the figure shown.53.采用阀针浇口,位置如上图红色圈所示,该方案需修改成品.As the figure shows, to adopt valve gate, please confirm it.54.建议在成品上做于此类似的肋利于进胶,且牛角胶口如图所示.For injecting fluently, suggest adding a rib like this, and using banana gate as shown.55.浇口在成品厚度方向的中间不会影响成品外观.The gate is in the middle of the thickness, which will not affect the appearance of the product.57.成品采用点进浇(进胶位置如图),建议取消胶口处肋,并在浇口处做一小凹坑.To adopt pin gate as the figure shows, suggest canceling the rib in the area of the gate and adding a concave.58.如图示采用点进浇,请确认,如果采用此方案,请照图示修改成品Adopt pin gate as the figure shows, please confirm it. If accept, please t modify the product as shown.59.成品采用边进胶,建议在成品上做5.0~2.0凹槽.To adopt side gate, suggest adding a concave by 5.0mm~2.0mm.60.7支套筒顶针,其余圆顶针和扁销Seven sleeves as the highlighted yellow areas shows, others are ejector pins and flat pins.61.为了保证成品的外观,PL线修改方案→取消一周的红色圆角The first solution is to cancel the red round for getting a good appearance of the product.62.为了保证成品的外观,PL线修改方案二是从最大轮廓减胶产生一个0.03mm的断差.The second solution is adding a step (0.03mm) along the circle of the red round for getting a good appearance of the product.63.采用隧道滑块成型,滑块的分模线如图示.Adopt tunnel slider molding, and the slider’s parting line is as shown.64.由于分模线都在一周的圆角上会影响成品外观,建议修改的二种方案详见P12和P13.The parting lines will affect appearance of the product, there are two methods in P12 and P13.65.如图所示;此处为铁件与模仁插破封胶,易跑毛边,请个修改如右图所示.As the figure shows, it is easy to occur flash, please modify model.66.如图所示;此处铁件与塑件两连接孔错位,请修改As the figure shows, the holes on the steel don’t align with the holes on the plastic, please modify model.67.如图所示;因铁片加铁,此处边接孔需移位(共两处),请修改.As the figure shows, move the holes (two places), please modify model.68.成品此处间隙太小,建议将红色所示特征单边加大0.85mm,以便用斜销成型. The gap is too small, suggest enlarging the red feature by 0.85mm per side for molding by angular lifter.69.成品此处分线不顺滑,建议修改.The parting line here is not smooth, suggest modifying it.70.如图所示,红线处孔用于定位,需精确加工.建议将铁件2的定位孔尺寸做得比铁件1的定位孔大(以免1和2焊接后有微动的错位导致铁位定位不准).The hole of the red zone is precision-machined for locating, suggest enlarging orientation holes of the steel 2, and it is bigger than the steel 1 as shown.71.为避免注射时铁件变形,建议修改成品,如图所示.Suggest modifying the model as shown to reduce warp during injecting process.72.为避免注射时铁件变形,建议修改塑件( 前后加二对应的定位孔),如图所示. Suggest modifying the model as shown to reduce warp during injecting process.73.铁件蓝色面太长侧壁无法定位,建议修改铁件使蓝色面不得超出铁件红色面的延伸面,如图所示.The blue surface is too long to locate, suggest modifying the blue surface of the steel not to overstep the extend surface of the red as shown.74.成品如图所示部位空间太小,所拆滑块强度太弱,请加大到至少1.5mm以上并在上图中圆圈处倒R角.As the figure shows, the space is too small, so intension of the slider will be infirm, please add the dimension to 1.5mmt at least, and add the round in the circle marked.75.请在图示位置加两肋使其强度增加,以免被滑块拉伤.As the figure shows, to avoid dragging the part, please add two ribs on the product to be stronger.76.如图红色面,分模时在模仁上会有倒勾.As the figure shows, there will occur undercut in the red surface of the cavity.77.成品修改尺寸参考Reference of modification78.沿开模方向的拔模分析.Drafting analysis of mold opening directing.79.建议用成品上蓝色面取代红色面.Suggest replacing the red surface with the blue surface.80.利于封胶.The convenience of sealing.81.此处将采用母模入子.Cavity insert will be adopted here.82.此处分模线为曲线,较复杂,请修改成直线.The parting line as shown is curved line, please change it toa straight line.83.为避免模仁尖角,请参照右图修改成品分模线.To avoid the weak-steel, please modify the parting line according to the right figure.84.为避免模仁尖角,请修改如右图所示.The area shown is weak steels in the core. Please modify the model. 85.成品此处太穿孔,有尖角,请修改,共2处.The product has the large bore and tine. Please check it, 2 areas in total.86.如图所示,成品此处有尖角,请修改.As the figure shows, there is sharp corner on the product, please modify it.87.红色箭头为斜销运动方向.The red arrow shows the direction of the lifter.88.顶针位置如图所示.The location of the ejectors is as shown.89.产品顶出位置如上图所示。
液压站出厂检验报告
一、检验目的
液压站是一种用于输送液体的工程装置,广泛应用于各行各业的工农业生产中。
为确保液压站在出厂前的质量合格,本次检验旨在对液压站进行全面检测和评估。
二、检验范围
本次液压站出厂检验主要涉及以下方面:
1. 液压站的结构和外观检查;
2. 液压站的油路系统检验;
3. 液压站的动力系统和控制系统检验;
4. 液压站的安全保护装置检验。
三、检验内容及结果
1. 结构和外观检查
通过对液压站的结构和外观进行详细检查,确认液压站的各部件安装完好,外观无明显损伤、锈蚀和变形等情况。
2. 油路系统检验
使用液压油进行液压站的油路系统检验,包括油泵、油箱、管路、滤清器等部件的检查。
确保油路畅通无阻、无泄漏,并验证液
压站的流量和压力性能是否符合设计要求。
3. 动力系统和控制系统检验
检验液压站的动力系统和控制系统,包括电机、液压控制阀、
传动装置等。
确保动力系统正常工作,控制系统灵活可靠,对液压
站的启停、流量调节和压力控制等操作能够准确实施。
4. 安全保护装置检验
对液压站的安全保护装置进行检验,包括压力开关、溢流阀、
过载保护装置等。
确保液压站在使用过程中能够及时发现并处理异
常情况,保证操作人员和设备的安全。
四、检验结论
根据本次液压站出厂检验的结果,结合液压站的设计要求和相
关技术标准,评估液压站的质量合格情况。
经过全面的检测和评估,。
HYDRAULIC SYSTEM INSPECTION REPORTDoc. NO:CSD/PE 0202Version No: V1.0Compiled by:Date:client's name project nameDevice Name Hydraulic station DeviceModelZT41856-GO38-XR300-Y3C21Contract No C201604068SerialnumberZTY160517No Test items standard requirement test result1 Assemblyandcleaning ofhydraulicmanifoldblockassemCleaninghydraulicoil block1.The oil on the road P, T test and drain cleaningstation is turned on, pipe or flushing plate A, Bport is turned on.2. The P port pressure at 16MPa, constantlyswitching solenoid valve manifold to be washedon the oil flow wash each oil passage, about15-20 minutes.blyHydraulic circuit blocks Functiontest 1. 1. After flushing hydraulic manifold fitted withclean hydraulic valve mounted on the hydraulic station.2.The test circuit temporarily blocked with ablanking plate.3.By order of the inlet pressure P test circuitadjusted to the working pressure, test the operation of each circuit function.4. 4. requiring accurate and reliable operation ofthe circuit, the external regulator under load changes, overshoot value should meet the specified value of the product. When the control valve, throttle valve, proportional valve, servo valve rated load, adjusting the valve, the output flow should not change significantly.5.Hydraulic circuit block after the function test ineach of the openings sealed with plastic dust cover.Check before assemblyand assembly 1.Hydraulic components 1. Press the drawingproofreading needs to be installed on the valve block, size, quantity, meets the requirements, and must have product certification.2.The respective hydraulic valve block valve,flange connection screws, screw fittings and plug are applied measured torque wrench to tighten.3. Hydraulic valve must be installed on thepositioning pins locating pins.Tightnessan examination 1. 1. Press the line pressure 1.5 times the designpressure will be pressure experiments.2. 2. The return lines, drain line at 3MPa pressureor pressure design requirements, test 5-10minutes, does not allow leakage.3.In the hydraulic circuit block, tonal systempressure relief valve or relief valve when the relief valve seal test or unloading valves shut, re-transferred to the system pressure after sealing test; if the safety valve, then press the indicated pressure adjustment system.2 Cleaningdebuggingandtest ofhydraulicstationOverallcirculationhydrauliccleaning1. 1. Press hydraulic operating requirements, thehydraulic system load running for 30 minutes,checking the entire piping joints shall not leak.Slowly loading pressure not exceeding 18MPa,washing temperature does not exceed 65 ℃.2.Washing process, may be appropriate conversionsystem valve location, change the direction offlushing.3. 3. Drain cleaning fluid injected fluid to meet therequirements. Starting system according to thesystem rules, under no-load hydraulic oil filterfurther purification station itself flush for 2hours. In the washing process, the need tochange the state of the operating system to flushto ensure all parts of the hydraulic station.4.Washing process, pay attention to the senderfilter apparatus, filter clogging occurs when thenow clean or replace the filter. After all flushingis completed, replaced with a new filter.StaticSealstest1.Static seal test subjects should be preceded bythe system may leak site clean, check with aclean absorbent paper attached to the static seal,then remove, absorbent paper, if any traces of oilis oil leakage.Pressuretest1.pressure oil pipeline pressure test, pressureby 1.25 times the working pressure.1. 2. Remove the temporary return oil pipes, drainpipes to 16MPa pressure for pressure test, suchas the back, rated working pressure of a drain pipe element (or set-in pressure) less than 16MPa, the test time this isolates the element or elements to the channel block in place (or isolated blocks separated) test.2.The test pressure should be gradually increased,the regulator should be increased by a 2-3 minutes. Test pressure 10 minutes packing leakage and other abnormal phenomenon does not occur.Functional test 1. All hydraulic motors and pumps should start smoothly without abnormal noise and heat.2. The operation of various valves, check loop function, in line with the requirements of the schematic, the setting value range of each valve in the hydraulic station should be repeated three times required function correctly. I found a valve has a mistake, you should repair or replacement of components, so the drop test was repeated six times to exclude backward function correctly.3.Tank level gauge automatic control, alarm and display test. Set-control points, each point of the test at least three times, and the operation control signal is sent correctly. If one does not meet the requirements, shall repair or replacement element, the points should be retested 6 correct.4. The oil temperature display meter test. Set-control points, each point of the test at least three times, and the operation control signal is sent correctly. If after a period not meet the requirements, repair or replacement of components, the points should be retested 6 correct.5. respectively for each control point of each pressure relay, each point test at least five times, and signals and correct action. If one does not meet the requirements after the repaired or replacement ofcomponents, test points 10 times, should be correct.Noise Test 1.Hydraulic station work properly rated pressureand rated load from the hydraulic station 1.5m to test for noise with noise tester. Gear pumps and hydraulic vane pump station does not exceed 85 decibels, the hydraulic ram pump station does not exceed 100 decibels.Pump running-tes t1. This test shall be conducted all hydraulic pressure test station.2. between pumps reached their maximumpressure, displacement and rated maximum operating speed of work, 8 hours of operation, the output power of more than 30KW hydraulic pump, running-in test can be reduced to two hours, no abnormal phenomenon during operation occur.3testresultInspectorsAuditorInspection dateRem ark。