目录

1编制说明 (2)

2工程概况 (2)

3施工部署 (3)

3.1现场施工条件 (3)

3.2施工进度安排 (3)

3.3劳动力及机械设备安排 (4)

4施工方法 (4)

4.1施工通道连接方式 (4)

4.2施工缝处理 (5)

4.3市政雨水管道临时支撑及节点处理 (6)

4.4钢筋、模板、混凝土施工 (11)

5地铁站内防护结构设置 (7)

6安全、文明施工措施 (12)

5.1安全施工措施 (12)

5.2文明施工措施 (12)

7雨水管道支撑体系计算书 (13)

41编制说明

本工程地下一层结构(标高范围-5.900~-1.600m)1/A~A轴交13~14轴与成都地铁世纪城站3、号出入口之间设计为混凝土结构通道连接。结合现场实际情况,场地西侧有一直径1.4m市政雨水管穿过,通道施工时需采取临时支撑加固措施,保证雨水管不被破坏。按照业主要求,通道在土方回填完成后开始施工,为了保证通道施工优质、高效、安全的顺利进行,根据国家及地方现行有关规范标准、法规规定和现场实际情况,编制专项施工方案指导现场施工。

2工程概况

本工程1/A~A轴交13~14轴区域地铁通道位于工程西侧地下一层,为单层框架结构,标高范围-5.900~-1.600m,层高4.3米,宽11.6米。通道底部为300厚抗水板,侧壁为400厚挡土墙,顶部同地下室顶板。距地下室外墙约1.7米处为φ1.5m市政雨水管穿过,壁厚150,施工阶段存在少量积水。

通道平面图

通道剖面图

3施工部署

3.1现场施工条件

按照业主要求,地铁通道需在地下室防水施工完成且回填后进行,现场施工需具备以下施工条件:

1、地下室外墙施工完成,场地西侧外墙防水及防水保护层施工,灰土回填密实且沉降稳定。

2、与地铁接口处原地铁混凝土结构部分破除。

3、通道范围(约12m)场地西侧市政雨水管道临时加固固定完成。

3.2施工进度安排

按照业主要求,通道施工于地下室土方回填后完成,计划开工时间为2011年5月11日,施工工期50日历天。

3.3劳动力及机械设备安排

序号

1

2

3

4

5

6

名称

钢筋工

木工

电焊工

混凝土工

架子工

杂工

数量

30

30

4

20

15

10

备注

钢筋绑扎

模板施工

电焊、氧割、支撑焊接

混凝土浇筑

模板支撑架搭设

辅工、文明施工等

4施工方法

4.1施工通道连接方式

根据设计要求,连接通道与地铁接口处及地下室车库连接方式如下:

1、与地铁结构处连接方式

破除原地铁已施工完成的扶壁柱及500mm范围剪力墙,保留原结构钢筋,通道钢筋锚入原扶壁柱内锚固区域后进行混凝土浇筑。如下图所示:

2、与地下室结构连接方式

通道与地下室结构连接一侧采取留设施工缝的方式进行处理,待土方回填完成后再进行车道施工,如下图所示:

地铁通道施工缝留设示意图

4.2施工缝处理

1、与地铁结构处施工缝处理

在与地铁站侧墙连接施工缝位置,在地铁站侧墙及结构柱破除后、通道混凝土浇筑前先将地铁侧墙混凝土破除面清理干净,祛除松动石块,在混凝土破除面刷一道素水泥浆,沿整个施工缝在破除面中部埋设40×40的遇水膨胀止水条,然后才能进行混凝土浇筑。遇水膨胀止水条施工方法见下图:

2、与地下室结构连接施工缝处理

在与地下室结构连接施工缝位置,在地下室结构施工过程中预留通道连接处墙、板、及梁钢筋,通道结构钢筋在施工缝处与预留钢筋搭接连接,施工缝处焊接止水钢板。混凝土浇筑前,施工缝处的原结构混凝土人工剃凿出露出混凝土新面,清楚杂质与松动石块,清水冲洗干净,并刷一道素水泥浆后方可进行混凝土的浇筑。

3、施工缝处防水加强

整个通道结构应外满包防水卷材,在施工缝布置加设一道防水卷材,附加卷材宽度不小于500,施工缝两侧各250。防水卷材具体施工方法参照《地下室防水施工方案》。

4.3市政雨水管道临时支撑及节点处理

根据现场实际情况,通道区域有一直径1.4m市政雨水管道穿越,雨水管距离地铁外墙约600mm,通道施工阶段无法进行拆除,通道施工时需进行临时加固处理及在墙体上预留洞口。雨水管道改道完成并拆除后进行通道预留洞口封堵及防水加强处理。该处详见下图:

地铁通道区域各部分关系图

1、雨水管道支撑体系施工

雨水管加固采用钢结构支撑架进行加固,土方回填至与冠梁面平齐后开始施工钢结构支撑架。钢结构支撑架采用18#工字钢连接成支撑体系,如下图所示:

雨水管道钢结构支撑示意图

因雨水管道较重(约1.65t/m),雨水管道支撑系统的施工存在较大难度,需按照下列步骤进行施工:

(1)地铁站内防护结构设置

地铁通道施工过程中,首先在地铁站内部通道施工部位设置临时围挡,围挡设置范围见下图:

围挡的设置需要从地下室通道开始施工一直延续到最后投入使用,时间长达数月(预计5月10日~精装修完成)。围挡采用方钢支架,外挂30厚压型彩钢板,为了防止在地铁结构破除厚雨水进入地铁站内,在围挡内侧砌筑200高挡水坎。详见下图:

(2)地铁站内临时围挡设置完成且土方回填至冠梁面后,挖除雨水管道上部原护壁土方。然后破除原地铁侧墙部分结构,破除面低于雨水管道底部不小于250mm,并在管道底部掏出间距1.5米的250高150宽洞口。详见下图:

(3)雨水管道上部原护壁土方清除完成,管道底部及原地铁站结构250高150

宽洞口成型后,采用18#工字钢搭设雨水管道支撑架。12厚钢板采用膨胀螺栓分别固定在冠梁上及地铁站底板上,工字钢支撑立杆与钢板焊接,立杆间距2米设置。立杆顶部采用工字钢水平拉杆焊接连接,冠梁处立杆及地铁站底板处立杆各设置一道。水平拉杆上搁置雨水管道支撑水平杆,支撑水平杆按间距1.5米设置,与水平拉杆焊接连接。详见下图:

(4)支撑体系完善后挖出雨水管道下方土方,破除原地铁站剩余结构,详见下图:

雨水管道下方土方清除完成,原地铁站结构破除完成后,即进行地铁通道结构施工。

2、雨水管穿墙处节点处理

由于雨水管从该通道侧墙位置穿过,因此,在侧墙施工时,穿越位置留设2.2米×2.2米的洞口,待后期雨水管拆除后再进行该洞口的封堵。考虑到侧墙外侧为回填土,需加强防水处理,侧墙洞口时候时沿洞口四周埋设300宽止水钢板。后期施工缝外侧设置防水附加层进行处理。

雨水管穿墙处理节点详图

3、开设预留洞口时预留原剪力墙钢筋,后期封堵时采用双面5d搭接焊修复,洞

口封堵处混凝土浇筑如下图所示:

侧墙雨水管洞口后期混凝土封堵做法大样图

4、通道内雨水管拆除以后,需要对通道两端的雨水管端头进行封堵处理,封堵方法如下图:

雨水管端头封堵处理大样

4.4钢筋、模板、混凝土施工

地铁通道该部分做法为常规做法,具体参照地下室结构各专项施工方案。

5安全、文明施工措施

5.1安全施工措施

1、通道施工时周围设置防护栏杆及标语提醒施工人员注意安全;

2、现场围护栏杆和安全网的搭设必须稳固、严密;

3、安排施工任务时应对施工人员进行安全交底,交底的内容要有针对性,针对重点问题提出安全可靠的防护措施;

4、落实安全责任,明确责任人,严格实行安全奖罚制度;

5、进入施工现场必须正确戴好安全帽,不允许赤脚或穿拖鞋、高跟鞋进入施工现场;

6、施工时不允许相互打闹,严禁酒后进行施工;

7、使用塔吊转运钢筋时,必须将需要转运的钢筋捆绑牢固,且应有专业塔吊指挥人员指挥转运;

8、人工搬运较长的钢筋时,搬运人员要前后呼应、相互配合;

9、夜间施工时,必须有明显的警示标识和足够的照明设施。施工现场照明灯具的架设高度要符合有关安全规程的要求,不应低于2.5m;

10、加强施工现场用电管理,经常检查各种配电设备的安全可靠性,如有损坏,应及时更换;

11、严禁私自检修各类电器设备或接、拉各种电线,如有需要,应及时提出申请,由专业机修工或电工进行操作;

12、特殊工种必须持证上岗,严禁非正式特殊工种代替正式特殊工种上岗作业;

13、钢筋绑扎过程中要注意骨架自身的稳定,特别是高大的结构,要有防止骨架倾覆、扭转失稳的支撑措施,操作人员应避免直接踩在钢筋骨架上作业;

14、钢筋焊接时要清理工作面上的易燃物品、要有防止焊接火花四处飞溅的措施、必要时要有专人对工作面监控,要有必要、有效的消防设施。

5.2文明施工措施

1、有计划的组织钢筋进场,做到既能满足现场施工的需要,又可避免因长时

间堆放而造成的钢筋油污和锈蚀;

2、合理安排施工作业时间,钢筋加工应尽量安排在白天进行,避免发生噪音扰民的情况;

5、夜间施工时,灯光应集中照射,避免灯光扰民;

6、完成各项施工任务后,要做到工完场清;

6雨水管道支撑体系计算书

1、自重计算

雨水管直径D=1.4米;壁厚d=0.15米

单位长度重量为V=πD×d×p=3.14×1.4×0.15×25KN/m3=16.5KN.

型钢自重V=205N/m

2、型钢截面性能

型钢:18#工字钢;E=2.06×105N/mm2;I=1660cm4;W=185cm3。

3、计算模型

其中L根据现场实际情况取L=4m。

P=V×1.5m=16.5KN×1.5m=24.75KN(其中1.5米为管道支撑型钢间距)

4、抗弯承载力计算

计算得Mmax=PL/4=24.75KN.m

最大应力为Mmax/W=133.8N/mm2<205mm2满足要求。

5、挠度计算

挠度r=PL3/48EI=24750×40003/48×2.06×105×1660×104=9.65mm.

青岛地铁施工方案

青岛地铁测量施工方案 目录 第一章.工程概况 第二章.测量作业任务和内容 第三章.作业依据 第四章.施工测量技术方案 第五章.测量人员组织 第六章.使用仪器设备 第七章.测量精度质量保证措施

第一章、工程概况 本标段主要工程内容有清江路站、清江路站~双山站区间,1站1区间。清江路站位于清江路与哈尔滨路交汇附近,是3号线的中间站,车站主体位于哈尔滨路下方,车站为地下二层10米岛式暗挖车站,地下一层为站厅层,站厅由中部的公共区及两端的设备管理用房两部分组成;地下二层为站台层,由设备管理用房区、乘车区及轨道区三部分组成。车站中心里程为K12+395.000,车站规模189.00×20.158m。车站共设3处出入口、2处风亭、1处无障碍出入口、1处消防专用出入口。 区间起讫里程K12+516.350~K13+480.500,区间长964.15米,区间隧道采用矿山法施工,断面形式为马蹄形,复合衬砌暗挖结构,区间沿哈尔滨路转入黑龙江路,穿福州路莱钢立交桥,地面为商业、商务办公、居住和商住用地,沿黑龙江路进入双山站。该区间地面覆土9.3m~22.6m,区间线间距13m~18m。区间在K12+899.765处设施工竖井(兼做活塞风道和联络通道)一座,向清江路站和双山站两个方向左右线四个工作面同时施工;在轨面高程最低处设置排水泵房及横通道,在靠近双山站附近右线设停车线一处,停车线为单洞双线马蹄形断面,长228.435米,其他断面为单洞单线隧道,在靠近清江路站附近设置人防门。

第二章、测量作业任务和内容 测量工作是土建工程的重要组成部分,为工程施工提供准确的定位信息、在本次工程项目中,测量作业的任务主要分为三部分:1∶地面控制测量;2∶地面、地下竖井联系测量;3∶施工放样测量。其主内容: ①地面测量控制网的检测; ②施工平面控制网的加密测量; ③施工高程控制网的加密测量; ④地面至隧道的联系测量,包括竖井定向测量、高程传递测量; ⑤地下施工控制测量、施工放样测量; ⑥隧道贯通测量; ⑦竣工测量(包含线路中线测量、隧道静空断面测量)。 第三章、测量作业依据 1、《城市轨道交通工程测量规范》GB50308-2008 2﹑《工程测量规范》GB 50026-2007

地铁车站主体结构施工方案

目录 1编制依据 (1) 2工程概况 (2) 2.1工程概况 (2) 2.2地质概况 (2) 2.3车站结构设计概况 (3) 3施工准备 (5) 3.1施工场地准备 (5) 3.2技术准备 (6) 3.3施工组织 (6) 3.4物资设备计划 (8) 3.5物资材料吊装 (9) 4工期计划 (10) 4.1施工进度管理 (10) 4.2施工进度计划 (10) 4.3工期保证措施 (10) 5总体施工方案 (13) 5.1施工方案概述 (13) 5.2施工顺序安排 (15) 5.3车站主体结构施工工艺流程 (16) 6结构工程施工方法 (16) 6.1单段施工步序 (16) 6.2接地网施工 (18) 6.3垫层施工方法 (18) 6.4底板施工方法 (19) 6.5侧墙施工方法 (20) 6.6结构立柱施工方法 (22)

6.7顶板、梁施工方法 (22) 6.8盾构洞门环的安装方法 (23) 6.9部结构施工 (24) 7结构工程施工技术措施 (25) 7.1模板工程施工 (25) 7.2预埋件及预留孔洞施工技术措施 (27) 7.3钢筋工程施工技术措施 (27) 7.4砼施工技术措施 (29) 7.5车站结构测量措施 (33) 7.6顶板回填及路面恢复 (34) 8质量保证措施 (35) 8.1质量保证体系 (35) 8.2检测试验方法及措施 (37) 8.3施工控制措施 (40) 9安全保证措施 (51) 9.1安全监管机构 (51) 9.2安全保证体系 (52) 9.4具体安全措施 (55) 10环境保护措施 (59) 10.1建立环境保护体系 (59) 10.2主要环境影响的控制保证措施 (60) 11施工应急预案 (62) 11.1应急原则 (62) 11.2应急组织及职责 (62) 11.3应急处理程序 (64) 11.4常见事故的预防及应对措施 (66) 1编制依据 (1) 《施工图-第四篇-车站工程-第二十五册-三江口站-第二分册-结构与防水-第一部分车站围护结

地铁车站主体结构施工方案

目录 一、编制原则 (5) 二、编制依据及编制围 (5) 2.1编制依据 (5) 2.2编制围 (6) 三、工程概况 (6) 3.1建筑概况 (6) 3.2周边环境 (7) 3.3结构概况 (7) 3.4主要工程数量表 (8) 3.5车站设计标准 (9) 3.6车站平面及剖面图 (9) 3.7主要材料及混凝土保护层 (9) 3.7.1 主要材料 (9) 3.7.2 保护层厚度 (10) 四、施工管理组织机构与职责 (10) 4.1工程项目管理组织机构 (10) 4.2岗位职责 (11) 4.2.1 项目领导班子岗位职责 (11) 4.2.2 职能部门岗位职责 (14) 五、施工总体部署 (17) 5.1施工准备 (17) 5.2施工管理目标 (18) 5.2.1 工程质量目标 (18) 5.2.2 工期目标 (18) 5.2.3 安全生产目标 (19) 5.2.4 文明施工与环境保护目标 (19) 5.3机械设备与劳动力投入计划 (19) 5.3.1管理人员配置 (19) 5.3.2作业人员配置 (19) 5.3.3机械设备投入计划 (20) 5.3.4材料使用计划 (20) 5.4施工测量 (21) 5.4.1 平面控制测量 (22)

5.4.2高程控制测量 (22) 5.5主体结构施工单元划分 (22) 5.5.1 施工单元划分原则 (22) 5.5.2车站施工段划分 (23) 5.6主体结构施工工艺流程图 (23) 5.7主体结构施工顺序 (24) 5.7.1 车站纵向分段施工顺序 (25) 5.7.2 车站竖向分层施工 (25) 六、施工现场平面布置与管理 (27) 6.1一期施工 (27) 6.1.1 施工围 (27) 6.1.2 场地平面布置及管理 (27) 6.2三期施工 (28) 6.2.1 施工围 (28) 6.2.2 场地平面布置及管理 (28) 6.3三期施工 (29) 七、分项工程施工工艺 (29) 7.1钢筋工程 (29) 7.1.1技术准备 (29) 7.1.2钢筋的进场验收 (30) 7.1.3钢筋加工 (30) 7.1.4钢筋接头 (33) 7.1.5钢筋的锚固 (36) 7.1.6钢筋安装 (37) 7.1.7钢筋绑扎质量通病控制措施 (43) 7.1.8钢筋安装质量检查控制标准 (44) 7.2模板工程 (45) 7.2.1 模板设计的主要原则 (45) 7.2.2 模板方案 (45) 7.2.3 施工技术准备 (46) 7.2.4 模板支撑与安装 (46) 7.2.5 模板工程质量检验标准 (48) 7.3混凝土工程 (49) 7.3.1底板垫层 (49) 7.3.2 底板砼施工 (50) 7.3.3 侧墙混凝土施工 (50) 7.3.4 板梁混凝土的浇筑 (51)

地铁施工方案及人员配置

地铁机电安装施工专业施工队劳动力的配置根据施工进度计划优化配置人力、机械、材料、技术等生产要素,并根据施工阶段性要求,保证各生产要素及时进退场,实现施工资源的动态管理,特别是劳动力的动态管理。 为了保证该工程高速、优质地完成,我们将选择具有丰富施工经验的工人,按专业组成专业施工队伍,以充分发挥其专业特长,共组建5个施工队进行该工程的安装,即:通风空调施工队、管道施工队、电气施工队、防腐保温施工队、调试施工队,各系统设备安装纳入相应专业施工队。 各施工队骨干力量保持稳定,一般技术工人以公司为强大后盾,随工程需要实行动态管理,即保证工程高峰期用人需要,又不至于造成现场窝工,从而提高工作效率。 1.施工机械设备一览表 根据总体进度计划的安排,结合各专业工程特点和实际情况,由各专业工程师编制施工机具设备需用计划,在既满足整体施工需要,又保证机械设备利用率的前提下,编制汇总施工机械设备总需用计划。我们将按该计划进行配置,并做好各专业之间的协调工作。 机电安装主要施工机械设备表

2.通风空调系统安装工程 车站通风空调系统由公共区空调系统和设备、管理用房空调系统,区间隧道

通风系统设在车站的事故风道内。 设备及管理用房空调系统(车站小系统)根据地铁设备管理用房的工艺要求和运营管理要求设置通风和防排烟系统,正常运行时为设备正常工作提供必需的运行环境和为运营人员提供舒适的工作环境,事故状态时迅速组织排除烟气。2.1风管主要施工方法及技术要求 1)风管施工主要程序 2)施工准备 (1)人员进场后,组织主要施工技术人员熟悉图纸,解决建筑、结构和电气、暖卫施工图中的管路走向、坐标、标高与通风管道之间跨越交叉出现的问题。 (2)组织施工人员学习有关规范和规程,对施工人员进行技术交底,对风管的制作尺寸,采用的技术标准、咬口及风管的连接方法进行明确。 (3)按照总图对预制加工场地进行布置,根据风管制作的工序合理布置风管加工设备。 (4)风管预制场垫置橡胶板,以减少风管在下料、拼接等过程中的划痕。4)风管及部件的制作 本工程空调风管采用镀锌钢板和玻璃钢风管两种。分别就两种风管的制作方法按工序进行叙述。 (1)镀锌钢板风管的制作 ①风管制作的主要工序:

地铁主体结构施工方案..

浙江交工集团股份有限公司杭海城际铁路工程第十一标段项目部浙大国际学院车站主体结构 施 工 组 织 方 案 王保书 2016年5月24日

目录 第一章工程概况 第二章施工准备 第三章施工工艺 第四章质量体系与保证措施 第五章安全保证措施 第六章工期保证措施 第七章环境保护、水土保持,后期恢复及文明施工措施第八章雨季施工措施 第九章人员、机械、材料配备附表 第九章支付保障措施

第一章、工程概况 杭海城际铁路工程第十一标段浙大国际学院车站主体结构工程。 浙大国际学院站位于海州东路与碧云南路交叉路口,沿海州东路呈东西向布置。路口东北侧为在建别墅区,西北侧为东方艺墅,东南侧为金钻天地在建楼盘,西南侧为海宁市教育园区。 车站为地下两层双柱三跨明挖结构(交叉渡线附近及停车线附近为单柱双跨结构),本站共设有共设置9个出入口、4组风亭及2个安全出入口,其中B号出入口与2号风亭组合建,2号安全出入口与3号风亭组合建。车站主体长446.6m,标准段宽21.3m,标准段基坑深16.11~16.94m,覆土厚度2.99~4.67m。车站西端设置盾构始发井,东端设置预留盾构接收井。 本站采用地下二层双柱三跨结构(交叉渡线附近及停车线附近为单柱双跨结构),典型横剖面详见主体结构横剖面图。主体结构侧墙为地下连续墙加内衬墙的复合结构,地下连续墙是施工期间的基坑支护结构,同时也兼作永久结构受力构件,地下连续墙与内衬墙之间设置防水隔离层,主体结构设全包防水层。 车站主体主体结构顶部设置压顶梁,利用地下连续墙自重及与周边土层摩阻力以满足抗浮要求。主体结构接外挂开口较大处,为满足抗浮要求,底板下设置Φ1000mm抗拔桩立柱桩,桩长30米。 1、施工工期 施工计划工期:主体结构计划开工日期:2017 年9 月 1 日 主体结构计划完工日期:2018 年2 月1 日 共计153天,实际工期以签订合同时为准。 2、安全目标

地铁车站主体结构施工方案

广州市轨道交通十二号线及同步实施工程总承包项目(第八项目部)槎头车辆段工程 槎头车辆段B区盖体结构工程 施工方案 编制单位:(盖单位章) 年月日

目录 目录 (1) 一、编制依据 (3) 二、工程概况 (4) 三、施工总体筹划 (4) 四、施工方案及技术措施 (5) 4.1测量方案 (6) 4.2钢筋工程 (8) 4.3 混凝土工程 (11) 4.4模板工程 (12) 五、质量保证措施 (13) 5.1钢筋质量保措施 (13) 5.2混凝土质量保措施 (15) 5.3质量针对性措施 (16) 六、安全、文明施工保证措施 (18)

一、编制依据 (1)广州市轨道交通十二号线主体结构设计图纸; (2)施工组织设计; (3)中华人民共和国《工程建设标准强制性条文》(城市建设部分)(2000年版) (4)广州市《工程建设地方标准强制性条文》(2000年版) (5)《建筑工程施工质量验收统一标准》(GB50300-2001) (6)市政地下工程施工质量验收规范(DGTJ08-236-2006) (7)广州地基基础设计规范(DBJ08-11-99) (8)《地下工程防水质量验收规范》(GB50208-2002) (9)《地下工程防水技术规范》(GB50108-2001) (10)《钢筋焊接及验收规程》(JGJ18-2003) (11)《钢筋机械接头施工验收规范》 JGJ107-2003 (12)《混凝土结构工程施工质量验收规范》(GB50204-2004) (13)《建筑变形测量规程》(JGJ8-2007) (14)《施工现场安全生产保证体系》(DBJ08-903-2003) (15)《建筑施工安全检查标准》(JGJ59-99) (16)《建筑机械使用安全技术规程》(JGJ33-2001) (17)《施工现场临时用电安全技术规范》(JGJ46-2005) (18)《电气装置安装工程接地装置施工及验收标准》(GB50169-2006)

地铁主体结构顶板回填土施工方案

地铁主体结构顶板回填土施工方案

地铁10号线二期工程角门东站主体结构顶板回填土施工方案

目录 一、编制依据 (1) 二、工程概况 (1) 三、施工总体部署 (1) 3.1施工平面布置及分段划分 (1) 3.2 工程数量 (2) 3.3 人员设备配置 (2) 四、施工准备 (2) 4.1、材料准备 (2) 4.2、作业条件 (3) 五、施工工艺 (3) 5.1、工艺流程 (3) 5.2、操作工艺 (3) 六、质量标准 (7) 6.1、主控项目 (7) 6.2、一般项目 (7) 七、施工注意事项 (7)

八、成品保护 (8) 九、安全措施 (9) 十、环境保护 (9)

一、编制依据 (1)角门东站车站主体结构施工图(B版) (2)角门东站主体围护结构施工图(B版); (3)《建筑工程冬期施工规程》(JGJ 104-97); (4)《轨道交通工程施工质量验收标准》(JQB-049-2008); (5)《建筑地基基础工程施工质量验收规范》(GB 50202-2002)。 二、工程概况 角门东站(西马场站)有效站台中心里程为K34+448.169~K34+654.069,总长度205.9m,总建筑面积约12480.4m标准段总宽度20.8m,基坑深度17.1m,覆土厚度3.7m。车站共设3个出入口,2组风亭,1个消防疏散口。角门东站主体及附属均采用明挖法施工。围护结构采用钻孔灌注桩+内支撑,主体结构采用钢筋混凝土箱型结构,标准断面为地下两层三跨,纵向柱跨9.75m。主体结构外侧设全包防水层,与钻孔桩一起组成复合墙体系。 三、施工总体部署 3.1施工平面布置及分段划分 为方便施工安排及施工操作,顶板土方回填采取分层分步回填,先回填1-4流水段(1-13轴)顶板回填土,5-8流水段(14-25轴)待其结构施工完毕顶板结构强度达到85%后回填,在预留顶板孔洞位置处应施作挡土墙,分步回填断面处应做好接槎,修筑阶梯形边坡,每台阶可取50cm,宽100cm。回填土施工平面布置图详见附图1角门东站顶板回填土施工平面布置图,回填施工计划表见表3-1。 表3-1 角门东站顶板回填土施工计划表 项目 土方 量(m3) 填方高 度(m) 计划开始 时间 计划结束 时间 3-6轴顶板回填土1339 2.6 2010年12 月12日 2010年12 月14日 6-13轴顶1245 0.9 2010年122010年12

地铁站主体施工方案

目录 1.编制依据 ·············································································································1 2.编制原则 ·············································································································1 3.工程概况 ·············································································································13.1.设计概况·········································································································1 3.1.1设计概况································································································1 3.1.2结构材料································································································2 3.1.3钢筋保护层·····························································································2 3.1.4结构防水································································································23.2.工程地质与水文地质··························································································2 3.2.1 工程地质 ·······························································································2 3.2.2 水文地质 ·······························································································3 4.资源配置 ·············································································································34.1.劳动力配置······································································································3 4.2.机械设备配置···································································································4 5.主要施工方法及技术措施 ························································································45.1.混凝土垫层施工································································································45.2.钢筋混凝土结构施工··························································································6 5.2.1钢筋工程································································································6 5.2.2模板及支撑系统····················································································11 5.2.3混凝土工程··························································································14 5.2.4预留孔洞及预埋件的施工········································································17 5.2.5楼梯、电梯井、站台板及轨顶风道施工 ·····················································175.3.杂散电流防护钢筋··························································································185.4.结构防水施工 ·····························································································18 5.4.1结构自防水·······················································································18 5.4.2缝的防水 ··························································································18 5.4.3底板防水 ··························································································20 5.4.4 降水井封堵防水···················································································21 5.5.钢支撑拆除···································································································21 6.质量保证措施 ····································································································226.1.质量目标······································································································226.2.质量保证体系································································································226.3.质量保证措施 ·····························································································22 6.3.1技术复核、隐蔽工程验收········································································22 6.3.2 施工阶段“砼浇筑令”制度····································································23 6.3.3技术、质量控制措施··············································································23 7.安全保证措施 ····································································································247.1.安全生产目标 ·····························································································247.2.安全管理制度 ·····························································································24 7.3安全技术措施 ······························································································24 8.文明施工、职业健康安全及环境保护措施································································278.1.文明施工····································································································27

地铁施工方案

第一章工程概况 1.工程概况 1.1 工程简介 哈尔滨地铁1 号线一、二期工程东起哈东站,南到哈南站,全长 17.48 公里,设18座车站,分别为哈尔滨东站站、桦树街站、交通学院站、太平桥站、工程大学站、烟厂站、医大一院站、博物馆站、铁路局站、哈工大站、西大桥站、和兴路站、学府路站、理工大学站、医大二院站、哈达站、哈尔滨南站站。本次投标为哈尔滨地铁一号线第十标段工程大学站。 1.2 工程质量标准 工程质量国家优良等级,并须遵守国家有关建筑安装和装饰工程施工和验收规范,以及其他有关规定。符合设计施工图纸和规范要求。1.3 工程工期 (1)计划工程工期:119 日历天 (2)计划开工日期:2013年2月1日 (3)计划竣工日期:2013年5月30日 1.4 施工范围 1.4.1 本规范适用于哈尔滨地铁1号线一、二期工程车站(除博物馆站)出入口外露雨棚、风亭及消防出入口、残疾人电梯装饰装修工程施工及管理。 1.4.2 工程在施工中使用的原材料、半成品或成品,隐蔽工程以及施工原始资料和记录,均应按本规范要求进行一系列的控制与检查,使工程质

量符合规定的质量标准。在每一章节的各项目中均对施工要求、质量检验 内容和方法等提出了要求。如有未写明之处,应按照国家、建设部和黑龙江省现行有关规范规定且经监理工程师批准后执行。 1.4.3 本标段工程投标人实施永久性工程, 为避免对附近不属于地铁公司的既有建筑物、构筑物等产生影响,应征得该建筑物、构筑物等招标人的同意。 1.4.4 本标段工程实施过程中如涉及到哈尔滨市相关政府主管部门和其它企业、团体,本标段投标人应就其建议的施工方法,征求他们的咨询意见,并在自己的计划中为此留出时间。 1.4.5 投标人应在本合同实施过程中对场地管理负全责,并不得干扰周围居民的正常生活,因场地管理不善引发的一切纠纷由投标人自行解决,招标人不承担责任。 1.4.6 投标人在合同期满一个月内或招标人规定的时间内,应无条件清退所有施工场地。如不及时清退,招标人除向投标人收取租金(租金为人民币10元/M2/天)外,招标人将暂停计价支付、工程结算等工作,本合同投标人应承担由此产生的一切后果,比如造成招标人被第三方索赔的事宜。 1.5 工程承诺 1.5.1 工程总体承诺我们完全响应招标文件关于本工程有关的质量标准、施工工期的要求,完全响应招标文件关于文明施工、环境保护和安全生产的 要 求,全力实现工程质量好、工期短、配合佳和业主满意、用户满意、社会满

地铁车站主体结构工程施工组织设计方案

目录 一、编制原则 (6) 二、编制依据及编制围 (6) 2.1编制依据 (6) 2.2编制围 (7) 三、工程概况 (7) 3.1建筑概况 (7) 3.2周边环境 (8) 3.3结构概况 (9) 3.4主要工程数量表 (10) 3.5车站设计标准 (10) 3.6车站平面及剖面图 (11) 3.7主要材料及混凝土保护层 (12) 3.7.1 主要材料 (12) 3.7.2 保护层厚度 (13) 四、施工管理组织机构与职责 (13) 4.1工程项目管理组织机构 (13) 4.2岗位职责 (14) 4.2.1 项目领导班子岗位职责 (14) 4.2.2 职能部门岗位职责 (17) 五、施工总体部署 (21) 5.1施工准备 (21) 5.2施工管理目标 (21) 5.2.1 工程质量目标 (21) 5.2.2 工期目标 (21) 5.2.3 安全生产目标 (22) 5.2.4 文明施工与环境保护目标 (22) 5.3机械设备与劳动力投入计划 (22) 5.3.1管理人员配置 (22) 5.3.2作业人员配置 (23) 5.3.3机械设备投入计划 (23) 5.3.4材料使用计划 (24) 5.4施工测量 (25) 5.4.1 平面控制测量 (25)

5.4.2高程控制测量 (25) 5.5主体结构施工单元划分 (26) 5.5.1 施工单元划分原则 (26) 5.5.2车站施工段划分 (26) 5.6主体结构施工工艺流程图 (28) 5.7主体结构施工顺序 (29) 5.7.1 车站纵向分段施工顺序 (30) 5.7.2 车站竖向分层施工 (30) 六、施工现场平面布置与管理 (32) 6.1一期施工 (32) 6.1.1 施工围 (32) 6.1.2 场地平面布置及管理 (32) 6.2三期施工 (33) 6.2.1 施工围 (33) 6.2.2 场地平面布置及管理 (33) 6.3三期施工 (34) 七、分项工程施工工艺 (34) 7.1钢筋工程 (34) 7.1.1技术准备 (34) 7.1.2钢筋的进场验收 (35) 7.1.3钢筋加工 (35) 7.1.4钢筋接头 (38) 7.1.5钢筋的锚固 (41) 7.1.6钢筋安装 (42) 7.1.7钢筋绑扎质量通病控制措施 (49) 7.1.8钢筋安装质量检查控制标准 (50) 7.2模板工程 (51) 7.2.1 模板设计的主要原则 (51) 7.2.2 模板方案 (51) 7.2.3 施工技术准备 (52) 7.2.4 模板支撑与安装 (52) 7.2.5 模板工程质量检验标准 (57) 7.3混凝土工程 (58) 7.3.1底板垫层 (58) 7.3.2 底板砼施工 (58) 7.3.3 侧墙混凝土施工 (59) 7.3.4 板梁混凝土的浇筑 (59)

地铁主体和附属工程施工方案

目录 第一章总说明 (1) 第二章工程概况 (2) 一、工程概况 (2) 第三章施工总体方案及施工组织安排 (6) 一、车站主体及附属附属结构施工方案概述 (6) 三、车站主体及附属结构施工工艺流程 (7) 四、车站主体及附属结构进度安排 (8) 五、施工设备与劳动力安排 (9) 六、施工组织管理 (10) 第五章结构工程施工方法 (15) 一、单段施工步序 (15) 二、接地网施工 (18) 三、垫层施工方法 (19) 四、底板施工方法 (20) 五、侧墙、端墙施工方法 (20) 六、结构立柱施工方法 (21) 七、楼(顶)板、梁施工方法 (22) 八、抗浮压顶梁 (22) 九、内部结构施工 (23) 第六章结构工程施工技术措施 (24) 一、模板工程施工 (24) 二、预埋件及预留孔施工技术措施 (33)

三、钢筋工程施工技术措施 (34) 四、混凝土施工技术措施 (38) 五、车站结构抗浮措施 (44) 六、车站结构测量措施 (44) 七、顶板回填及路面恢复 (45) 第七章结构工程施工质量保证措施 (47) 一、施工控制 (47) 二、裂缝控制 (49) 三、防渗漏保证措施 (50) 四、对预埋件、预留孔洞的保证措施 (51) 五、结构模板与支架施工质量措施 (52) 六、结构混凝土的质量保证措施 (53) 第八章结构工程施工工期保证措施 (55) 第九章结构工程施工安全保证措施 (58) 一、施工现场规范要求 (58) 二、进入基坑要求 (58) 三、高处作业安全措施 (59) 四、支架和支架工程安全措施 (59) 五、满堂支架搭设安全措施 (60) 六、支架和支架拆除安全措施 (60) 七、模板工程安全措施 (61) 八、加强监控量测,确保安全 (62)

地铁土方施工方案内容

目录 一、工程概况 (1) 二、编制依据 (1) 1、施工图纸 (1) 2、主要规范、规程、地方标准 (2) 三、施工部署安排 (2) 1、工期安排 (2) 2、技术准备 (2) 3、物资准备 (3) 4、人员准备 (3) 5、作业条件准备 (3) 四、施工方法及工艺流程 (3) 1、施工工艺流程 (3) 2、施工方法 (3) 3、路基压实标准 (4) 4、试验方法 (4) 五、季节性施工 (5) 六、质量保证措施 (5) 七、文明施工及安全生产要求 (6)

成华大道站土方回填及路面恢复施工方案 一、工程概况 成华大道站为成都地铁7号线工程的一个中间站,站前接成都理工站, 站后接崔家店站和出入崔家店停车场的配线。本站起讫里程:YDK8+358.250~YDK8+730.726,外包总长372.476m(含配线长度),站台中心里程YDK8+441.000,车站有效站台140×12m。车站南北端均为盾构接收。车站采用明挖法+局部盖挖法施工。顶板混凝土及防水层验收合格后,应及时回填土方。 二、编制依据 1、施工图纸

2、主要规范、规程、地方标准 三、施工部署安排 1、工期安排 根据施工总进度计划,土方回填分3个节点,第一个节点为小里程盖挖段土方回填,第二个节点为中间盖挖段土方回填,第三个节点为剩余主体结构顶板土方回填。按顺序土方回填的时间分别为2014年6月,2014年9月,2015年6月至8月。人员组织详见下表: 2、技术准备 (1)项目部专业技术人员应充分熟悉施工图纸,同时编制详细的施工技术方案。 (2)按照设计要求,将材料送试验室做击实试验,确定最大干密度时的最优含水量,最优含水量为:11.8%,最大干密度为1.95g/cm3。 (3)在土方施工队伍进场后,项目部专业技术人员应积极的做好土方工程施工技术交底。由项目技术部门及专业工长对进场人员进行安全技术交底,并对机械操作人员进行专门交底。 (4)根据设计图纸在防撞墙及围护桩上测放出回填土顶标高、控制线及清理基槽杂物,复核合格方可进行施工。

地铁车站主体结构施工方案培训资料(doc 58页)

地铁车站主体结构施工方案培训资料(doc 58页)

目录 1 编制依据 0 2 工程概况 (1) 2.1工程概况 (1) 2.2地质概况 (1) 2.3车站结构设计概况 (2) 3 施工准备 (4) 3.1施工场地准备 (4) 3.2技术准备 (5) 3.3施工组织 (5) 3.4物资设备计划 (9) 3.5物资材料吊装 (13) 4 工期计划 (14) 4.1施工进度管理 (14) 4.2施工进度计划 (14) 4.3工期保证措施 (14) 5 总体施工方案 (17) 5.1施工方案概述 (17) 5.2施工顺序安排 (18) 5.3车站主体结构施工工艺流程 (19) 6 结构工程施工方法 (20)

6.1单段施工步序 (20) 6.2接地网施工 (23) 6.3垫层施工方法 (24) 6.4底板施工方法 (25) 6.5侧墙施工方法 (26) 6.6结构立柱施工方法 (27) 6.7顶板、梁施工方法 (28) 6.8盾构洞门环的安装方法 (29) 6.9内部结构施工 (29) 7 结构工程施工技术措施 (30) 7.1模板工程施工 (30) 7.2预埋件及预留孔洞施工技术措施 (32) 7.3钢筋工程施工技术措施 (32) 7.4砼施工技术措施 (34) 7.5车站结构测量措施 (37) 7.6顶板回填及路面恢复 (38) 8质量保证措施 (39) 8.1质量保证体系 (39) 8.2检测试验方法及措施 (41) 8.3施工控制措施 (44) 9安全保证措施 (52) 9.1安全监管机构 (52)

9.2安全保证体系 (53) 9.4具体安全措施 (55) 10环境保护措施 (58) 10.1建立环境保护体系 (58) 10.2主要环境影响的控制保证措施 (59) 11施工应急预案 (61) 11.1应急原则 (61) 11.2应急组织及职责 (61) 11.3应急处理程序 (62) 11.4常见事故的预防及应对措施 (64)

地铁车站主体结构支架模板工程专项施工组织方案

某地铁车站主体结构支架模板工程专项施工方案 第1章工程概况 某地铁车站位于民田路下,呈南、北向布置,北端位于民田路与福华路口交叉路口,南端位于民田路与福华三路交叉路口,民田路道路红线宽为15m。车站西侧主要建筑有中海大厦、中海华庭,东侧为Coco Park购物公园。 车站为地下三层岛式站台无柱车站。车站全长148m,标准段宽19.1m,车站有效站台中心里程处底板埋深为30.6m,顶板覆土厚度平均约为3.5m。 车站为现浇钢筋混凝土矩形框架结构。 车站主体结构主要尺寸的设计如下: 顶板厚500mm,中板厚分别为300mm和700mm,底板厚1000mm+990mm,衬墙厚度300mm,且与连续墙形成叠合结构。地下一、二层无衬墙。主要构件尺寸见下表:

1、设计依据及参考文献 (1)《地铁龙岗线西延段工程某地铁车站车站主体结构施工图》(及相关设计文件)。 (2)本工程土建工程相关合同文件、招标文件、投标文件。 (3)国家现行有关施工及验收规、规则、质量技术标准,以及地区在安全文明施工等方面的规定。 (4)《混凝土结构设计规》(GB50010-2002)。 (5)《混凝土结构工程施工质量验收规》(GB50204-2002)。 (6)《建筑施工扣件式钢管脚手架安全技术规》(JGJ130-2001)。 (7)我单位在地铁工程结构方面的施工经验。 (8)《建筑施工手册》(第四版),中国建筑工业。 (9)江正荣编《建筑施工计算手册》,中国建筑工业。 2、模板与支架系统设计检算说明 2.1 设计检算围 标准段主体结构工程包括:顶板、中板、侧墙、横梁等容。 由于底板采用直接在垫层施作结构砼,底板的模板与支撑形式相对简单,根据施工经验进行模板与支撑施工,不再做设计检算。 本方案仅对顶板、中板、梁、侧墙的模板及支架进行设计检算,确保模板与支架系统的强度、刚度及稳定性等满足要求。 2.2 设计检算原则 1)在满足结构受力的前提下考虑挠度变形控制。

地铁施工安全管理方案

安全技术管理方案 1 总说明: 以保证施工工期为核心,理顺质量、安全和进度的关系,在保证施工质量、施工安全的前提下,合理组织施工,组织流水作业,做到均衡生产,保证各项总体目标的实现。 针对本工程的特点、施工重点、难点,项目部配置了满足本工程施工需要的先进施工机具和设备,保证按业主要求的工期、安全、优质地完成施工任务。 确保“安全第一”是永恒的主题,施工生产永远将安全放在第一位。所有技术措施、施工方案、现场调度指挥等一切以安全为主旋律。 1.1 编制依据 JGJ59-99 《建筑施工安全检查标准》 JGJ80-91《建筑施工高处作业安全技术规范》 JGJ33-2001《建筑机械使用安全技术规程》 JGJ46-2005《施工现场临时用电安全技术规范》 JGJ30-2001《建筑施工扣件式钢管脚手架安全技术规范》 1.2 编制原则 为使我项目部施工现场的安全管理更加规范化、标准化,进一步提高本工程项目部安全管理水平,更好地遵守国家、地方以及公司有关安全生产的法令、法规、规章要求。依据相关规范及法律法规,结合我项目部实际情况,编制本方案。 通过贯本管理方案,使我项目部能充分有效地识别、评价施工现场所有施工过程和场所存在的危险源和不利环境因素,采取适当的技术和管理措施,控制和减小项目部施工现场的安全风险和不利环境因素,并持续改进安全业绩,为工程施工创造良好的条件,最大限度地预防和减少安全事故的发生。 1.3 工程概况 上海市轨道交通2号线东延伸段工程为既有2号线(淞虹路站~张江高科站)向东延伸线。2号线东延伸段工程(龙阳路站~浦东国际机场站)线路起自既有龙阳路站-张江高科站区间高架段,经由张江高科技园区、唐镇新市镇及川沙新市镇等地区,至浦东国际机场站止。线路正线全长29.580km(上行线),其中高架线为9.687km,地下线为19.893km(包括单圆盾构段10.191km,双圆盾构段6.352km,明挖段3.350km)。共设11座车站,其中高架站2座,地面站1座(站

地铁动照施工方案.

天津地铁6号线工程机电系统设备安装施工一标段 电 气 施 工 方 案 编制: 审核: 批准: JLA(地铁)/MS3-SGFA-03-2015

目录 一、编制依据 (2) 二、工程概况 (2) 三、施工组织流程图: (3) 四、工程特点 (4) 五、编制原则 (4) 六、施工工艺及方法 (4) 七、调试阶段 (14) 八、质量控制措施 (15) 九、吊装安全措施 (15) 十、施工现场临时用电安全措施 (15) 十一、安全用电技术措施和电气防火措施 (15) 十二、文明施工措施 (16)

一、编制依据 《地铁设计规范》 GB50157-2013 《城市轨道交通照明》 GB/T16275-2008 《建筑设计防火规范》 GB50016-2006 《消防联动控制系统》 GB16806-2006 《重要电力用户供电电源及自备应急电源配置技术规范》 GB/Z 29328-2012 《逆变应急电源》 GB/T 21225-2007 《集中式蓄电池应急电源装置》 JG/T371-2012 《工商业电力用户应急电源配置技术导则》 DL/T268-2012 《外壳防护等级(IP 代码)》 GB4208-2008 《电气装置安装工程蓄电池施工及验收规范》 GB50172-2012 《阀控式密封铅酸蓄电池订货技术条件》 DL/T637-1997 《交流输出稳定电源》 JB/T7397-1994 《低压直流电源设备的性能特性》 GB17478-2004 《电磁兼容试验和测量技术静电放电抗扰度试验》 GB/T 17626.2-2006 《电磁兼容试验和测量技术射频电磁场辐射抗扰度试验》 GB/T 17626.3-2006 《电磁兼容试验和测量技术电快速瞬变脉冲群抗扰度试验》 GB/T 17626.4-2006 《电磁兼容试验和测量技术浪涌(冲击)抗扰度试验》 GB/T17626.5-2008 二、工程概况 动力照明系统主要内容包括动力配电箱(柜)、照明配电箱(柜)、应急电源配电柜(EPS)、插座箱、手操箱、智能疏散指示系统、电气火灾监控系统、照明灯具、插座、照明开关、接地系统等电气设备的采购、安装、调试;配电电缆、电线的采购、敷设;电缆桥架及电缆支架的采购、安装及接地;动力照明负荷的供电及控制的系统调试等。本工程施工范围应包括动力照明配电系统的设备、材料的采购、运输、保管、设备安装、线缆敷设、设备调试及竣工验收等,即从施工准备至施工完毕达到工程验收的全部工程。施工项目包括以下主要内容:

相关主题
文本预览
相关文档 最新文档