Project Budget Monitor and Control

Author:Yin Guo-li

Nationality:American

Derivation:Management Science and Engineering.Montreal: Mar 20, 2010 .

With the marketing competitiveness growing, it is more and more critical in budget control of each project. This paper discusses that in the construction phase, how can a project manager be successful in budget control. There are many methods discussed in this paper, it reveals that to be successful, the project manager must concern all this methods.

1. INTRODUCTION

The survey shows that most projects encounter cost over-runs (Williams Ackermann, Eden, 2002,pl92). According to Wright (1997)'s research, a good rule of thumb is to add a minimum of 50% to the first estimate of the budget (Gardiner and Stewart, 1998, p251). It indicates that project is very complex and full of challenge. Many unexpected issues will lead the project cost over-runs. Therefore, many technologies and methods are developed for successful monitoring and control to lead the project to success. In this article, we will discuss in the construction phase, how can a project manager to be successful budget control.

2. THE CONCEPT AND THE PURPOSE OF PROJECT CONTROL AND MONITOR

Erel and Raz (2000) state that the project control cycle consists of measuring the status of the project, comparing to the plan, analysis of the deviations, and implementing any appropriate corrective actions. When a project reach the construction phase, monitor and control is critical to deliver the project success. Project monitoring exists to establish the need to take corrective action, whilst there is still time to take action. Through monitoring the activities, the project team can analyze the deviations and decide what to do and actually do it. The purpose of monitor and control is to support the implementation of corrective actions, ensure projects stay on target or get project back on target once it has gone off target。

3. SETTING UP AN EFFICIENT CONTROL SYSTEM

For the purpose of achieving cost target, the manager need to set up an efficient management framework including: reporting structure, assessing progress, and communication system. The employees' responsibility and authority need to be defined in the reporting structure. The formal and informal assessing progress can help getting a general perspective between reality and target. It is significant to help identify what is the risk and should be monitored and controlled. Project success is strongly linked to communication. The efficient communication system benefit for teamwork and facilitate problem solving ( Diallo and Thuillier, 2005 ).

4. COST MONITOR AND CONTROL

4.1 Ranking the priority of monitoring

In construction phase, many activities are carried out based on the original plan. It is need to know what kind of activities or things are most likely to lead the project delay and disruption. Therefore, the first step is ranking the priority of the activities. Because the duration of a project is determined by the total time of activities on critical path, any delay in an activity on the critical path will cause a delay in the completion date for the project (Ackermann Eden, Howick and Williams,2000,p295). Therefore, the activities on critical path should firstly to be monitored and controlled. Secondly, monitoring the activities with no free float remaining, a delay in any activity with no free float will delay some subsequent activity inevitably. These subsequent delays will discomfit the resource schedule significantly. Some resources are unavailable because they are committed elsewhere. Thirdly, monitoring the activities with less than a specified float, because if an activity has very little float, it might use up the time before control decision is made once such an activities has a variance with the target. Fourthly, managers should monitor high risky activities. High risky activities are most likely to overspend. Fifthly, managers should monitor the activities using critical resource. Some resource is critical because they are very expensive or limited (Cotterell and Hughes, 1995).

4.2Methods of cost control

The main cost of a project includes staff cost, material cost and delay cost. To control these cost, managers should first set up a cost control system to: a) Allocate responsibilities for administration and analysis of financial data

b) Ensure all costs are properly allocated against project codes

c) Ensure all costs are genuinely in pursuit of project activities

d) Check that other projects are not using the budget.

Then, managers should monitor and control change to the project budget. It means the following things:

a) Concerned with key factors that cause changes to the budget

b) Controlling actual cost changes as they occur

- Monitor cost performance to detect variances

- Record all appropriate changes accurately in the cost baseline

- Preventing incorrect, unauthorized changes being included in the cost baseline

- Determine positive and negative variances

- Integrated with all other control processes (scope, change, schedule, quality) As a project is dynamic, sometimes the project managers know the project is going out off target by monitoring, but don't know the best action to take. In this circumstance, net present value (NPV) should be used as an ongoing monitor and control mechanism, because NPV takes account of the time element and discounts future cash flows, it is the result of the time effect on cash

4.3 Change monitor and control

Voropajev (1998) states that dynamic changes of project environment will influence the process of project implementation, the project itself and may cause heightened risk. When carried out some activities, the methods different from that in the original plan must be used to keep the process moving forward (as experienced under practice). Therefore, changes are inevitable and need to be managed during project life-cycle (Voropajev. 1998,p 16- 17) .An effective change control system should be established to ensure change procedure is clear and unambiguous and easy for employee to request a change. And the following things need to be concerned:

a) Monitoring and forecasting most probable changes Key factors that generate change to ensure good results; make sure that change must be checked by suitable person.

b) Changes should take place once it is approved and be monitored to check whether it worked as expected

c) All changes in project should be recorded in the project documentation (Voropajev, 1998,pl8).

5. CONCLUSION

This article shows the best methods of budget control. First, an efficient control system must be set up. Secondly, It is required to recognize and rank the important factors affecting budget target. Thirdly, manager should combine different control techniques to reach the success of a project.

项目成本减少与控制

作者:Yin Guo-li

国籍:美国

出处:管理科学与工程.2010.03.20

随着市场竞争的激烈性越来越大,在每一个项目中,进行成本控制越发重要。本文论述了在施工阶段,项目经理如何成功地控制项目预算成本。本文讨论了很多方法。它表明,要取得成功,项目经理必须关注这些成功的方法。

1.简介

调查显示,大多数项目会碰到超出预算的问题(Williams Ackermann, Eden, 2002,pl92)。据Wright(1997)的研究,一个好的经验法则就是相比首次成本预算至少会增加50%(Gardiner and Stewart, 1998, p251)。这表明,项目是非常复杂并且充满挑战的。很多意想不到的因素会导致项目成本的增加。因此,许多科学技术和方法被应用于监测和控制成本来促使项目的成功。在这篇文章中,我们将讨论在施工阶段,项目经理如何才能成功控制预算成本。

2.项目控制和监测的概念和目的

Erel and Raz (2000)指出项目控制周期包括测量成本是实际情况,将施工成本的实际值和计划值进行比较,对比较结果进行分析,并采取适当的措施来纠正偏差。项目在施工阶段的监测和控制对于项目的成功是至关重要的。为了采取正确的纠偏措施需要建立项目监测机制,同时这样做也可以有时间来采取措施。通过监测手段,项目团队可以分析偏差产生的原因以及决定纠偏措施并采取行动。监控的目的就是纠偏措施的实施,确保项目控制在计划目标内或者使已经偏离计划的回到目标范围内。

3.建立一个有效的控制体系

为了实现预算成本的目标,项目管理者需要建立一个高效的管理框架,包括:报告的结构,评估的进展情况以及沟通体系。在报告结构中,雇员的责任和权力应该要清楚地被定义。正式的和非正式的评估可以帮助实际和目标之间大体上保持一致,且这对于确定什么是风险以及哪些需要被监测和控制是非常有帮助的。项目成功与良好的沟通密切相关,一个高效率的沟通体系有利于团队协作并促进问题的解决( Diallo and Thuillier, 2005)。

4.成本费用的检测和控制

4.1对检测的优先顺序进行排序

在施工阶段,很多施工活动是基于原来的计划。它需要清楚什么样的活动或者哪些东西是最有可能导致项目延误和不受控制的。因此,第一步就是要对这些

活动进行优先排序。由于项目的工期是由关键路径上的关键工作的总时间决定的,任何关键路径上工作的延迟将导致项目工期的拖延(Ackermann Eden, Howick and Williams,2000,p295)。因此,关键路径上的工作应该首先进行检测和控制。其次,检测没有自由时差浮动的工作,任何没有自由时差工作的延误将导致其后续工作的拖延,这些后续工作的延误将对资源分配安排带来影响,有些资源被分配到特定的工作是不可以变更利用的。第三,检测具有较少浮动时间的工作,因为,如果一个工作具有非常少的浮动时间,那么当它偏离目标的时候很有可能在还没有采取控制措施前就将浮动时间用完了。第四,项目管理者应该检测高风险活动,高风险活动最有可能超支。第五,管理者应该检测项目活动中使用的关键资源,有些资源由于是非常昂贵和有限的而至关重要(Cotterell and Hughes, 1995)。

4.2成本控制的方法

一个项目的主要费用包括员工成本、材料成本以及工期延误的成本。为了控制这些成本费用,项目管理者首先应该建立一个成本控制系统:

a)为财务数据的管理和分析工作落实责任人员

b)确保按照项目的结构来合理分配所有的成本

c)确保所有成本都是项目进展过程中各项活动的真实支出

d)检查其它工程项目没有使用此项目预算

然后,项目管理者应该对项目预算进行监督和控制变更。这意味着以下几点:

a)关注可以引起成本变化的主要因素

b)控制实际成本的变化

--监测成本发生情况来发现它的变化

--在成本控制线上准确地记录所有恰当的成本变动

--为防止出现错误,没有经过允许的成本变化也应该体现在成本控制线上

--确定积极地和消极的成本变化

--与其它控制目标(范围、变更、进度、质量)相结合

由于一个工程项目是动态变化的,有时项目经理通过监测知道项目成本正在偏离预算,但是却不知道采取什么措施来控制。在这种情况下,净现值(NPV)能够被用来作为一种持续监控的方法,因为净现值考虑了时间的因素来对未来现金流折现,它是现金流考虑时间价值影响后的结果。

4.3变化的检测和控制

Voropajev (1998)指出,施工环境的动态变化将会影响项目的实施过程、项目本身以及增加项目风险的可能性。当在开展施工活动的时候,不同于原计划的各种方法必须被应用来保持项目向前推进(根据实践经验)。因此,变化是不可

避免的,需要在项目的整个生命周期过程中管理和控制变化(Voropajev. 1998,p 16- 17)。为了确保变更程序是明确和毫不含糊的以及方便施工人员提出要求发生改变,应该建立一个有效的变更控制体系。可以从以下几个方面考虑:

a)为确保良好的结果,应检测和预测最有可能发生变更的主要因素,应该保证变更必须由合适的人员检查

b)一旦被批准,变更应该发生并对此进行监测以检查是否按预期工作

c)项目的所有变更应该被记录在项目文件资料中(Voropajev, 1998,pl8)

5.结论

本文介绍了控制预算的最佳方法。首先,必须建立一个高效率的监管控制体系;其次,它必须包括影响成本预算目标的主要因素并将它按照重要性排序;第三,项目管理者应该结合不同的科学控制方法以达到项目的成功。

世界贸易和国际贸易【外文翻译】

外文翻译 原文 World Trade and International Trade Material Source:https://www.doczj.com/doc/2512495646.html, Author: Ted Alax In today’s complex economic world, neither individuals nor nations are self-sufficient. Nations have utilized different economic resources; people have developed different skills. This is the foundation of world trade and economic activity. As a result of this trade and activity, international finance and banking have evolved. For example, the United States is a major consumer of coffee, yet it does not have the climate to grow any or its own. Consequently, the United States must import coffee from countries (such as Brazil, Colombia and Guatemala) that grow coffee efficiently. On the other hand, the United States has large industrial plants capable of producing a variety of goods, such as chemicals and airplanes, which can be sold to nations that need them. If nations traded item for item, such as one automobile for 10,000 bags of coffee, foreign trade would be extremely cumbersome and restrictive. So instead of batter, which is trade of goods without an exchange of money, the United State receives money in payment for what it sells. It pays for Brazilian coffee with dollars, which Brazil can then use to buy wool from Australia, which in turn can buy textiles Great Britain, which can then buy tobacco from the United State. Foreign trade, the exchange of goods between nations, takes place for many reasons. The first, as mentioned above is that no nation has all of the commodities that it needs. Raw materials are scattered around the world. Large deposits of copper are mined in Peru and Zaire, diamonds are mined in South Africa and petroleum is recovered in the Middle East. Countries that do not have these resources within their own boundaries must buy from countries that export them. Foreign trade also occurs because a country often does not have enough of a particular item to meet its needs. Although the United States is a major producer of sugar, it consumes more than it can produce internally and thus must import sugar.

国际贸易中的企业【外文翻译】

外文翻译 原文 Firms in International Trade Material Source: https://www.doczj.com/doc/2512495646.html, Author: Andrew B. Bernard For most of its lengthy history the field of international trade largely ignored the role of the firm in mediating the flow of goods and services. Traditional trade theory explained the flow of goods between countries in terms of comparative advantage, that is, variation in the opportunity costs of production across countries and industries. Even the research focusing on differentiated varieties and increasing returns to scale that followed Helpman and Krugman continued to retain the characterization of the representative firm.?However, the assumption of a representative firm, while greatly enhancing the tractability of general equilibrium analysis, is emphatically rejected in the data. My research over the past decade has been an attempt to explore international trade from below: to understand the decisions of heterogeneous firms in shaping international trade and their effects on productivity growth and welfare. Firm Heterogeneity and Trade My early work with J. Bradford Jensen was motivated by a simple question: what do we know about firms that trade? The answer at the time was "very little" and our initial efforts focused on locating firm-level data and describing the world of exporting firms. Our first study compared exporters and non-exporters for the entire U.S. manufacturing sector and established a set of facts about exporting plants and firms.?Two major results stand out. First, only a small fraction of firms are exporters at any given time. Even in sectors where the United States is thought to have comparative advantage, such as Instruments, a majority of firms produce only for the domestic market. Similarly, some firms are exporting even in net import sectors such as Textiles and Apparel. Second, exporters are substantially and significantly different than non-exporters, even in the same industry and region. Exporters are dramatically larger, more productive, pay higher wages, use more skilled workers, and are more technology- and capital-intensive than their non-exporting counterparts. In related

酒店服务质量管理外文文献翻译

文献出处:Borkar S, Koranne S. Study of Service Quality Management in Hotel Industry [J]. Pacific Business Review International, 2014, 6(9): 21-25. 原文 Study of Service Quality Management in Hotel Industry Borkar; Sameer Abstract It is an attempt to understand the role of quality improvement process in hospitality industry and effectiveness in making it sustainable business enterprise. It is a survey of the presently adopted quality management tools which are making the hotels operations better focused and reliable and meet the customer expectations. Descriptive research design is used to know the parameters of service quality management in hospitality industry. Exploratory research design is undertaken to dig out the service quality management practices and its effectiveness. Data analysis is done and presented; hypothesis is tested against the collected data. Since the industry continuously tries to improve upon their services to meet the levels of customer satisfaction; Study presents tools for continuous improvement process and how it benefits all the stake holders. It can be inferred from the study that the hotel implement continuous improvement process and quality management tools to remain competitive in the market. The study involves hotels of highly competitive market with limited number of respondents. This limits the study to hotel industry and has scope of including other hospitality service providers as well. Keywords:Customer Satisfaction, Perception, Performance Measurement, Continuous, Improvement Process. Introduction It has brought paradigm shifts in the operations of hospitality industry. The overall perspective of the industry is changed due to introduction of new techniques

国际贸易、市场营销类课题外文翻译——市场定位策略(Positioning_in_Practice)

Positioning in Practice Strategic Role of Marketing For large firms that have two or more strategic business units (SBUs), there are generally three levels of strategy: corporate-level strategy, strategic-business-unit-level (or business-level) strategy, and marketing strategy. A corporate strategy provides direction on the company's mission, the kinds of businesses it should be in, and its growth policies. A business-level strategy addresses the way a strategic business unit will compete within its industry. Finally, a marketing strategy provides a plan for pursuing the company's objectives within a specific market segment. Note that the higher level of strategy provides both the objectives and guidelines for the lower level of strategy. At corporate level, management must coordinate the activities of multiple strategic business units. Thus the decisions about the organization's scope and appropriate resource deployments/allocation across its various divisions or businesses are the primary focus of corporate strategy.Attempts to develop and maintain distinctive competencies tend to focus on generating superior financial, capital, and human resources; designing effective organizational structures and processes; and seeking synergy among the firm's various businesses. At business-level strategy, managers focus on how the SBU will compete within its industry. A major issue addressed in business strategy is how to achieve and sustain a competitive advantage. Synergy for the unit is sought across product-markets and across functional department within the unit. The primary purpose of a marketing strategy is to effectively allocate and coordinate marketing resources and activities to accomplish the firm's objectives within a specific product-market. The decisions about the scope of a marketing strategy involve specifying the target market segment(s) to pursue and the breadth of the product line to offered. At this level of strategy, firms seek competitive advantage and synergy through a well-integrated program of marketing mix elements tailored to the needs and wants of customers in the target segment(s). Strategic Role of Positioning Based on the above discussion, it is clear that marketing strategy consists of two parts: target market strategy and marketing mix strategy. Target market strategy consists of three processes: market segmentation, targeting (or target market selection), and positioning. Marketing mix strategy refers to the process of creating a unique

工程管理专业毕业设计外文翻译(外文+翻译)

Study on Project Cost Control of Construction Enterprises By: R. Max Wideman Abstract With the increasing maturity of construction market, the competition between construction enterprises is becoming fierce. The project profit is gradually decreasing. It demands that all construction enterprises enhance their cost control, lower costs, improve management efficiency and gain maximal profits. This paper analyses the existing problems on project cost control of Chinese construction enterprises, and proposes some suggestions to improve project cost control system. Key Words :Construction enterprises, Project management, Cost control After joining the WTO, with Chinese construction market becoming integrated, the competition among architectural enterprises is turning more intense. Construction enterprises must continually enhance the overall competitiveness if they want to develop further at home and abroad construction market. Construction Enterprises basically adopt the "project management-centered" model, therefore, it is particularly important to strengthen project cost control. 1.The Current Domestic Project Cost Classification and Control Methods Cost refers to the consumption from producing and selling of certain products, with the performance of various monetary standing for materialized labor and labor-consuming. Direct and indirect costs constitute the total cost, also known as production cost or manufacturing cost. Enterprise product cost is the comprehensive indicator to measure enterprise quality of all aspects. It is not only the fund compensation scale, but also the basis to examine the implementation of cost plan. Besides, it can provide reference for product pricing According to the above-mentioned definition and current domestic cost classification, construction project cost can be divided into direct costs and indirect costs. Direct costs include material cost, personnel cost, construction machinery cost, material transportation cost, temporarily facility cost, engineering cost and other direct cost. Indirect costs mainly result from project management and company's cost-sharing, covering project operating costs (covering the commission of foreign projects), project's management costs (including exchange losses of

外文翻译---国际贸易单证的作用

附录 F.1英文参考资料及中文翻译 F. 1 .1international trade documents role General international trade documents (international trade documents) is the international trade of use all the documents, documents and certificates collectively. Usually with international trade documents to deal with in and out of delivery of the goods El, transportation, insurance, inspection and quarantine, customs declaration, the settlement of exchange, etc. Special international trade documents usually refers to the settlement documents, especially the l/c under the way of settlement of documents. International trade documents and the use of import and export trade program closely related, the documents in the import and export enterprise work throughout the export, purchase, transportation, the whole process of the proceeds, the effort is big, timeliness strong, is broad, in addition to import and export enterprise internal between various departments the cooperation with the outside, still must and bank, customs, transportation department, insurance companies, the inspection and quarantine agencies and the relevant administrative authorities happen various contact, linked together, mutual influence, also are conditions. International trade documents for the performance of a contract is necessary means International trade is the transnational goods business, due to the particularity of the multinational business, which is the purchase and sale of the different departments are located in different countries, are remote, in most cases, the goods and payment can't perform simple direct exchange, but only as the medium of exchange with documents means. The international trade of the documents that sales of goods through the documents realization sale, the seller should not only will the actual delivery of goods export shipment, and should submit to the buyer include the title to the goods vouchers, complete documents to show real assignment. The seller/p means that the delivery of the goods, and the buyer payment is get to buy goods on behalf of property rights certificate, the deal is no longer with the goods as the core, but with documents as the core. Documents and payment of the convection principle has become the international trade of general principles of the commodity business. As international trade experts "; m Cardiff in the export trade in his book mentioned: "from a business perspective, can say CIF the purpose of the contract is not the buying and selling of goods itself, but the documents relating to the goods business." What say here "documents" is the international trade of documents. International trade documents many kinds, every kind of documents has its

供应商质量管理文献翻译(外文翻译-中英对照)

互利共赢的供应商质量控制 前言 近年来,随着对供应链的重视,供应商管理正逐渐成为企业和学术界的关注对象,IS09000族标准以及QS 9000标准都对供应商的管理提出了相应的要求,与供应商管理有关的研究成果正逐渐增多,一些软件巨头也推出了供应商关系管理的软件,但是在这些研究成果和应用软件中,涉及到的供应商质量控制的内容只是一些最基本的要求,而供应商质量控制恰恰是供应商管理的最基本、最重要的内容。另一方而,质量管理界对质量控制的研究取得了大量的成果,遗憾的是这些成果大多依然局限于企业的内部控制,仅仅研究从企业内部各环节如何改善产品的质量,而基于供应链的角度来研究质量控制的成果尚不多见。因此,系统地研究经济全球化形势下供应商质量控制的理论与方法,将有助于推动我国企业产品质量的快速提高和供应链竞争优势的形成与巩固。 1、质量与企业共存 质量一直是一个随着时代的变化而不断变化的概念,人们对质量的认识也往往因关注点不同而有所不同。如,早在1908年,通用汽车公司的工程师们在皇家汽车俱乐部会员们的面前拆解了3辆凯迪拉克轿车,并把这些零件混在一起,而后从中选择零件重新组装成车,然后驾车绝尘而去。这令在场的会员极为震惊,认为凯迪拉克车质量之高令人惊叹。显然在当时,汽车零件具有互换性是一种了不起的质量特性,这也是福特公司的N型车和T型车取得辉煌成功的重要原因.时至今日,即使农用三轮车的零部件也具有极高的互换性,零部件的标准化和互换性已经是理所当然的事情,不再是吸引顾客的重要质量特性.可见质量的内涵是不断变化的.那么究竟什么是质量呢? (1)市场竟争就是企业间对“顾客”的争夺,在日益激烈的“顾客"争夺战中,质量、价格、交付(交付日期、方式和手段)和服务是企业常用的四个法宝,其中质量是根本,离开质量其他三项将变得毫无意义,因此可以说质量己成为市场竞争的焦点.它反映了产品是否能够反映顾客需求、能否满足顾客需求,从面决定了产品的市场前途。有鉴于此,质量己成为一项全球性运动,世界上所有优秀企业无一不把质量作为企业战略的关键内容,从战略的角度来规划质量。 (2)对于企业经营者来说,认识到质量对企业的重要意义只是经营企业的第一步,重要的是如何利用科学的方法来保证产品和服务的质量,使顾客满意,来保证过程和工作的质量来获互利共炭的供应商质量控制得良好的业绩。 众所周知,企业管理是社会生产力发展到一定程度的历史产物,质量管理作为企业管理的组成部分,同样也是社会发展的客观要求,特别是顾客处于主导地位的今天,要使顾客满意,就必须有过硬的产品质量和服务质量,这就要求企业积极推行先进的质量管理理论与方法,不断进行质量管理创新. 2、企业与供应商质量控制 随着生产社会化的不断发展,企业的生产活动分工越来越细,专业化程度越来越强,促使生产技术水平越来越高,产品质量得到大幅度改善。通常,某一产品不可能由一个企业从最初的原材料开始加工直至形成顾客最终使用的产品,往往是通过多个企业分工协作来完成.另外,先进生产方式的广泛应用,如准时生产、敏捷制造、零库存等,使企业与供应商的关系愈加紧密,企业与供应商的关系也由单纯的买卖关系向互利共底的合作关系演变。 ISO 9000族标准自1987年诞生以来受到了世界各国的一致追捧,全球约50多万家企业通过ISO9001质量管理体系认证足以说明这套管理标准在引领国际管理潮流方面的巨大成功。在备受企业欢迎的新版标准ISO9000:2000中,互利的供应商关系被作为八项质量管理原则之一,充分体现了供应商关系管理在企业经营实践中的作用和价值。企业要贯彻这一原则,就必须

跨境电商外文文献综述

跨境电商外文文献综述 (文档含英文原文和中文翻译) 译文: 本地化跨境电子商务的模型 摘要 通过对国际供应链的B2B电子商务交易量的快速增长和伊朗快速增加的跨境交易业务,跨境电商过程的有效管理对B2B电子商务系统十分重要。本文对局部模型的结构是基于B2B电子商务的基础设施三大层,消息层、业务流程层和内容层。由于伊朗的电子商务的要求,每一层的需要适当的标准和合适的方案的选择。当电子文件需要移动顺利向伊朗,建议文件的标准为文件内容支持纸质和电子文件阅读。验证提出的模型是通过案例研究方法呈现一到四阶段的情景。本文试图通过交换商业文件在贸易过程中这一局部模型,实现在全球电子贸易供应链更接近区域单一窗口建设的关键目标。 关键词:电子商务;跨境贸易;电子文档管理;国际供应链

1.简介 电子商务是关于在互联网或其他网络电子系统购买和销售产品或服务。术语B2B(企业对企业),描述了企业间的电子商务交易,如制造商和批发商,或批发商和零售商之间。本文的研究目标是上两个不同国家贸易商之间的通信。今天的世界贸易组织的主要目标之一是建立区域单一窗口,可以提高世界各地的贸易便利化。建立区域单一窗口需要跨境海关,可以有效地交换贸易文件。因此,首先,简化跨境贸易文件的关键在于朝着国家单一窗口移动。然后,区域单一窗口可以授权国家之间的通信。电子商务模型是基于三个主要逻辑层的研究。这三个层消息传输层,业务处理层和内容层。本文的局部模型是一种能够自动交换读取文件的过程。通过与东亚和中东国家的建立区域单一窗口可以在将来得到改善的更多的互操作性,从而建立伊朗国家单一窗口 在本文的第二部分讨论引进国际供应链中的跨境B2B模式所需的基本概念和标准。第三部分介绍在大的模型中引入的组件功能和范围。第四部分讨论了B2B交易层模型的定位,最后结束本文。 2.背景 在本节中,除了了解B2B电子商务在伊朗的情况,还有参考模型的背景等概念以及讨论B2B电子商务跨境模式的本土化。 2.1 B2B电子商务在伊朗 如今伊朗在贸易进程的变现是一个关键的贸易成功点。伊朗和许多其他国家接壤,它的进口和出口过程可以通过公路,铁路,海上和空中的方式来完成。因此,这个国家的中部和战略作用,使得它在亚洲和中东地区货物运输的主要贸易点。今天,在伊朗海关几乎所有的贸易过程通过纸质表格完成,由商务部提供的电子服务仅限于谁该国境内交易的商人。今天,伊朗海关几乎所有的贸易流程都是通过纸质表格来完成的,商务部给出的电子服务只限于该国的商人。介绍了模型试图简化在伊朗交易的跨境电子商务供应链交换电子文件的过程。这里提到的一些系统,由商务部在伊朗的电子服务被提及:进口订单管理系统。贸易统计制度。伊朗法典伊朗。这些电子系统的主要使用,以促进在伊朗贸易过程。这里提到的系统作为独立的贸易者可与建议本文模型在未来的作用。在亚洲的区域性单

工程管理工程造价中英文对照外文翻译文献

中英文资料对照外文翻译 Design phase of the project cost management Abstract Project cost management is the basic contents to determine reasonable and effective control of the project cost. Described the current stage of the project cost management situation on the strengthening of the various stages of construction cost management of the importance of and raised a number of key initiatives. Keywords:cost of the construction project cost management status investment decision phase of the design phase of the implementation phase of the cost management in a market economy, Even under the WTO and China's accession to the world community, China's construction industry how to effectively control construction cost of the construction and management of an important component part. However, the current budget for the construction projects - estimate, budget, Super budget accounts for the "super three" is still widespread and that eventually led to a serious loss of control of project investment. Project cost management is the basic contents to determine reasonable and effective control of the project cost. As the project cost to the project runs through the entire process, stage by stage can be divided into Investment Decision stage, the design and implementation phases. The so-called Project Cost effective control is the optimization of the construction plans and design programs on the basis of in the building process at all stages, use of certain methods and measures to reduce the cost of the projects have a reasonable control on the scope and cost of the approved limits.

质量管理文献综述

关于企业质量管理文献综述 摘要:随着新世纪的到来,特别是我国加入WTO后,中国将进一步融入世界经济的主流,质量将成为我国广大企业抓住机遇、迎接严峻挑战的关键。要拓展海外市场,必须靠有竞争力的质量;要保护国内的市场,不再有高关税和政府的过渡保护,也要靠质量的较量。随着科学技术的进步,质量管理的理论和方法有了更大发展。本文综合了质量管理的发展历程,并简要评价,提出看法,以便为企业的质量管理和理论研究提供参考。 关键词:质量管理、管理改进 21世纪是质量的世纪”。随着经济全球化和信息革命的迅猛发展,竞争日益加剧。在“数量”问题已解决的今天,人们将越来越追求和依赖于高质量的产品和服务,而且质量的领域不断拓宽,生活的质量、环境的质量、文化的质量、经济增长的质量更加受到全社会的关注。质量已成为竞争的焦点,不仅关系到企业的生存发展,而且影响到国家经济实力的增强和民族的形象。质量已成为全球经济发展战略的核心问题。 一、质量管理理论的回顾 (一)、质量管理的发展阶段 (1)质量检验阶段(20世纪20-30年代) 生产力迅猛发展,生产过程分工细化、日益复杂,许多美国企业按照泰勒的管理模式,纷纷设立检验部门,使检验与生产分离开来,其最大特点为“事后把关”。(2)统计质量阶段(20世纪40-50年代) 早在20世纪20年代,美国贝尔实验室工程师休哈特就提出“控制与预防缺陷”的概念。主要是利用数理统计原理,预防产生废品并检验产品质量,在方式上由专业质量控制工程师和技术人员承担。但这种方法只是保证生产过程中的产品质量,而不能提高产品本身的质量。 (3)全面质量管理阶段(20世纪60年代至今) 美国的费根堡姆提出,“全面质量是为了能够在最经济的水平上,并考虑到充分满足顾客要求的条件下进行生产和提供服务,将企业各部门研制质量、维持质量和提高质量的活动构成为一体的一种有效体系”。 (二)、质量管理的理论流派 1、事后检验 20世纪,美国工程师泰勒提出“科学管理理论”,1911 年泰勒出版了专

相关主题
文本预览
相关文档 最新文档