当前位置:文档之家› 水泥混凝土路面施工图设计规划介绍

水泥混凝土路面施工图设计规划介绍

水泥混凝土路面施工图设计规划介绍
水泥混凝土路面施工图设计规划介绍

.\

xxx施工图设计说明

1设计依据和采用的规范、标准

1)“建设工程设计合同”

2)平面地形图等资料

3)《全椒县B片区详细性控制规划》

4)《全椒县xxx工程地质勘察报告》

冶金工业部华东勘察基础工程总公司 2013.06

5)《城市道路工程设计规范》(CJJ 37--2012)

6)《城市道路交叉口设计规程》(CJJ 152--2010)

7)《城镇道路路面设计规范》(CJJ169-2012)

8)《无障碍设计规范》(GB 50763--2012)

9)《公路水泥混凝土路面设计规范》(JTG D40--2011)

10)《公路水泥混凝土路面施工技术规范》(JTG F30--2003)

11)《公路路基设计规范》(JTG D30--2004)

12)《公路路基施工技术规范》(JTG F10--2006)

13)《城镇道路工程施工与质量验收规范》(CJJ1--2008)

14)《公路路面基层施工技术规范》(JTJ034--2000)

15)《公路工程抗震设计规范》(JTJ004--89)

16)《公路土工合成材料应用技术规范》(JTG/T D32--2012)

17)《道路交通标志和标线》(GB5768--2009)

18)《室外排水设计规范》(GB50014--2006)2011版

19)《给水排水工程构筑物结构设计规范》(GB50069--2002)

20)《城市排水工程规划规范》(GB50318--2000)

21)《给排水管道工程施工及验收规范》(GB50268--2008)

22)《埋地硬聚氯乙烯排水管道工程技术规程》(CECS122:2001)

23)《城市工程管线综合规划规范》(GB50289--98)

24)《城市道路绿化规划与设计规范》(CJJ75--97)

25)《城市道路照明设计标准》(CJJ 45--2006)

2设计概要

2.1 工程范围、工程规模、测设过程及主要工程内容

全椒县地处皖东,江淮分水岭南侧,滁河北岸。地理坐标为北纬31°51′~32°15′,东经117°49′~118°25′之间。全椒县域东部毗邻江苏省江浦县,南与和县、含山县隔河相望,西临巢湖市、肥东县,北与滁州市南谯区接壤。县城位于全椒东部南屏山下,襄水河畔,北距滁州市区22公里,东距南京60公里,西距合肥100公里,距全国最大的经济中心上海市390公里。

本项目位于全椒县县城西部,包含两条道路:西门街、xxx。西门街为南北走向,南起花园路,北至本次设计xxx,全长156.64m;xxx为东西走向,西起本次设计西门街,东至前进小学,全长389.379m。西门街、xxx均为城市支路,红线宽15m,为双向两车道,设计时速30km/h。道路沿线地势较为平缓,西门街现状为4米宽的水泥路,xxx现状为碎石路,道路两侧主要为房屋,同时在西门街的西侧、xxx的北侧为现状古襄河。

主要工程内容包括:道路工程、排水工程、交通工程、路灯工程、绿化工程。

2.2 技术指标及设计参数

本次设计项目包含两条道路:西门街、xxx。西门街南起花园路,北至本次设计xxx,全长156.64m;xxx西起本次设计西门街,东至前进小学,全长389.379m。两条道路均为城市支路,红线宽15m,设计时速30km/h。

根据前期方案汇报结果及与建设方沟通确认,西门街、xxx的实施路幅为:9m车行道+3m 人行道×2=15m。

技术指标及设计参数

2.2.1 平面设计

本次设计项目包含两条道路:西门街、xxx。西门街南起花园路,北至本次设计xxx,全长156.64m;xxx西起本次设计西门街,东至前进小学,全长389.379m。两条道路均为城市支路,红线宽15m,设计时速30km/h。根据前期方案汇报结果及与建设方沟通确认,西门街、xxx的实施路幅为:9m车行道+3m人行道×2=15m。

西门街:本次设计的西门街现状为4米宽的水泥路,两侧主要为房屋,道路西侧为现状古襄河,沿线地势较为平缓。道路中心线根据前期方案汇报结果及与建设方沟通确认,由两段直线和一半径为115米的圆曲线组成,全线与花园路、xxx相交,为新建工程。

设计起点处花园路现状为水泥混凝土路面,车行道宽约为9.6米。本次设计衔接现状花园路车行道边,桩号为0+04.838,施工前注意复核该处的位置及高程。在半径为115米的圆曲线段,根据规范要求,应设置全超高,并在圆曲线两侧设置10米的超高渐变段。同时根据与建设方沟通确认,因西门街道路交通量较小且主要为小型车辆,单侧车行道宽度为4.5米,本次设计考虑不设置加宽。设计终点处位于与xxx交口处,因交口北侧西门街暂不设计,该交口纳入本次施工范围,施工终点位于交口切线处,桩号为1+56.64。同时交口处注意施工时与现状水泥路的衔接。

xxx:本次设计的xxx现状为碎石路,两侧主要为房屋,道路北侧为现状古襄河,沿线地势较为平缓。道路中心线根据前期方案汇报结果及与建设方沟通确认,由两段直线和两段圆曲线组成,圆曲线半径分别为120米和500米,全线仅与西门街相交,为新建工程。

设计起点处衔接本次设计西门街施工范围,桩号为0+17.285。在半径为120米的圆曲线段,根据规范要求,应设置全超高,并在圆曲线两侧设置10米的超高渐变段。同时根据与建设方沟通确认,因xxx道路交通量较小且主要为小型车辆,单侧车行道宽度为4.5米,本次设计考虑不设置加宽。设计终点处位于前进小学附近,衔接现状xxx,桩号为3+89.379,施工前注意复核该处的位置及高程。现状xxx为水泥混凝土路面,车行道宽为9米。

本次设计道路沿线基本为商业、居住用地,本次设计不设置路段行人过街设施,行人可通过交叉口处的过街设施过街。为了方便残疾人的出行,全线均进行无障碍及盲道设计。无障碍采用单面坡型式的坡道,变坡段长10m,坡度为1.5%。盲道宽度为50cm。

本次设计道路两侧暂不设置道口,后期施工时可根据现场实际情况增设道口(道口施工前应先报建设方批准后方可实施)。

2.2.2 纵断面设计

西门街、xxx规划为城市支路,设计速度为30km/h,纵断面设计主要结合相交的现状道路高程及道路周边建筑物高程等进行设计,在道路排水及道路平面线形相协调的前提下优化纵断面设计。

纵断面设计标高:以道路中心线为纵断面设计点。

纵断面设计在依据设计规范的前提下,其设计纵向控制因素主要有:

?西门街起点处与现状花园路高程衔接(13.700);

?xxx终点处与现状xxx高程衔接(13.370);

?两侧现状地形、地物;

?满足排水需要。

纵断面设计技术指标

根据地质报告,需清除①层杂填土,道路全线平均清表厚度按2米考虑,西门街清表量约为7806.626立方米,xxx清表量约为17185.271立方米。

西门街道路全线不含交口的土方量,总填方:824.200立方米,总挖方:100.025立方米,缺土:724.175立方米。交口的总填方:198.692立方米,总挖方:759.968立方米,多土:561.276立方米。道路全线包含交口的总填方:1022.892立方米,总挖方:859.993立方米,缺土:162.899立方米。

xxx道路全线不含交口的土方量,总填方:598.900立方米,总挖方:3712.780立方米,

缺土:3113.88立方米。

注:1.本次设计土方量根据测量单位提供的数据计算所得,施工时注意校核。

2.本土方量均为未清表的土方量。

2.2.3 交叉口设计

本次设计仅包含两个交口:西门街与花园路交口、西门街与xxx交口,均采用信号灯控制的平面交叉。根据道路两侧用地规划和与建设方沟通结果,全线不考虑进行展宽设计,交口采用标线渠化。

2.3 设计横断面及地上杆线、地下管线的配合关系

根据前期方案汇报结果及与建设方沟通确认,西门街、xxx的实施路幅为:9m车行道+3m 人行道×2=15m。车行道横坡为1%,人行道横坡为2%。

综合管线断面布置具体详见排水工程相关图纸。

2.4 路基、路面、挡墙及涵洞等工程设计

2.4.1 路基设计及边沟、边坡特殊设计

一、路基设计原则

路基设计应遵循以下原则:

?路基必须密实、均匀、稳定。

?路基抗压回弹模量≥30MPa。

?路基设计应因地制宜,合理利用当地材料与工业废料。

?对特殊地质、水文条件的路基,应结合当地经验按有关规范设计。

本工程路基防护设计与水土保持、环境保护相结合,遵循“因地制宜、就地取材、以防为主、防治结合”的设计原则,综合考虑安全、美观、经济、实用和沿线地质水文条件等因素,保证边坡防护安全。填、挖方边坡均为1:1.5。

二、地质概况

以下内容摘自《全椒县xxx工程地质勘察报告》:

1、地形地貌

全椒县地处江淮平原,地形平坦,河道、沟渠多为人工开凿。拟建线路所经区域地形平坦(局部1#孔位置低洼),地面高程一般在8.98~13.55米之间。

地貌单元为老襄河河漫滩及一级阶地,微地貌为凹凸间地。拟建线路所经区域,地形平坦(局部1#孔位置低洼),地面高程一般在8.98~13.55米之间。最大高差为3.57米。

2、地层分布及特征

路线区域出露地层为:新近回填土(主要为褐色耕植土,局部为杂色杂填土)、第四

系全新统(Q

4)和更新统(Q

3

)冲洪积层,主要为褐~褐黄色低液限粘土(粉质粘土),软-

硬塑状态。根据工程地质调查、钻探及室内试验,将路线经过场地公路建设影响范围内的地层叙述如下:

①层杂填土(Q

4

pd)褐色,稍湿~湿,松散状态,含植物根茎和碎石等杂物,主要成分为粘性土,层厚为1.4-2.5米。本层广泛分布于路线经过地区,局部地段有淤泥分布。

②层淤泥质粉质粘土(Q

4

al+pl):层厚1.0~5.4m,层顶埋深1.4-2.5m,层顶高程8.39~11.53m。灰褐色,湿,软-流塑,干强度低,韧性差,压缩性高等局部夹有薄层粉砂。本层全场分布。

③层粉质粘土(Q

3

al+pl):层厚0.6~2.20m,层顶埋深2.0-7.0m,层顶高程5.09~10.82m。褐黄~黄褐色,可塑、稍湿,含铁锰氧化物,干强度一般,韧性一般,压缩性中等,压缩性中等,局部夹有碎石,粒径1-5cm。本层局部全场分布。

④层粉质粘土(Q

3

al+pl):层厚1.3~2.3m,层顶埋深3.7-5.6m,层顶高程6.61~9.35m。褐黄~黄褐色,硬可塑、稍湿,含铁锰氧化物,刀切面光滑,有光泽反应,干强度高,韧性好,压缩性中低等。本层全场分布。该层未揭穿。

3、岩土条件评价

①层杂填土的容许承载力[fa0]为90kPa。松散,含较多杂物,土质不均匀,强度低,压缩性高,工程特性差。局部堆土较大。

②层淤泥质粉质粘土的容许承载力[fa0]为70kPa。软-流塑,局部可塑,湿,干强度低,韧性差,压缩性高等。工程特性差;

③层粉质粘土的容许承载力[fa0]为120kPa。可塑,局部硬可塑,稍湿,干强度一般,韧性一般,压缩性中等,工程特性一般;

④层粉质粘土的容许承载力[fa0]为200kPa。硬可塑,局部硬塑,稍湿,干强度高,韧性好,压缩性中低等,工程特性较好;

三、道路路基处理设计

根据地质报告,分析各层土质情况,清表后路基处理方式如下:

1、车行道路基处理范围

填方高度>1.5米路段:清表后在②层土上先抛片石挤淤0.8米(暂定挤入深度0.6米,压实稳定后外露0.2米),然后在其上回填20cm的级配碎石以形成工作面,再用4%的石灰改良土(路拌)回填至路床顶下40cm处,再用6%石灰改良土(路拌)回填至路床顶。若填方高度≤1.5米或挖方段,则应先反挖至路床顶下150cm处以保证回填的4%的石灰改良土的厚度不小于70cm。

2、人行道路基处理范围

清表后在②层土上先用4%的石灰改良土(路拌)回填至路床顶下20cm处,再用6%石灰改良土(路拌)回填至路床顶。

注:(1)道路沿线对于填方高度大于3米路段,每隔1米,应增设一层土工格栅。

(2)根据地质报告,全线路基平均清表深度为2米。

2.4.2 路面结构设计

路面设计原则以交通量为基础;适应道路服务功能要求;符合当地筑路材料供应状况;适应自然条件要求;技术成熟;性能优良、造价合理;注重对新工艺、新材料的选用。由于水泥混凝土路面使用寿命长,前期养护维修费用低;施工质量容易控制;材料来源广泛。所以该路段车行道采用水泥混凝土路面。根据前期方案汇报结果及与建设方沟通确定,西门街、xxx的路面结构如下:

?车行道路面结构如下:

22cm厚C35水泥混凝土面层(设计抗弯拉强度fcm≥4.5MPa)

ES-2下封层,厚度6mm

20cm3~5.5%水泥稳定碎石基层(压实度≥98%,其7天设计抗压强度3.5~4.5MPa)

15cm10%石灰土(厂拌)底基层(压实度≥97% 其7天的设计抗压强度≥0.8MPa)

路基夯实 (重型压实度≥95%)

结构层总厚为57厘米

?人行道路面结构如下:

6cm厚纽西兰地砖(抗压强度≥25MPa)

2cm厚1:4水泥砂浆垫层

15cm3~5.5%水泥稳定碎石基层(压实度≥98%,其7天设计抗压强度3.5~4.5MPa)

路基夯实 (重型压实度≥90%)

结构层总厚为23厘米

注:1、基层水泥稳定集料的水泥剂量应根据选用材料实验确定,一般为4.5%,当达不到强度要求时应调整级配,水泥的最大剂量不应超过6%。

2.4.3 挡墙及涵洞等结构物设计

本次设计道路两侧考虑放坡设计,不考虑设置挡土墙。在西门街西侧、xxx北侧临近古襄河处考虑设置浆砌片石护坡。(注:浆砌片石护坡的设置应结合古襄河的整治方案,施工前应报建设方批准。)

2.4.4 排水工程设计

详见排水工程设计说明。

2.4.5 交通工程设计

详见交通工程设计说明。

2.4.6 路灯工程设计

详见路灯工程设计说明。

2.4.7 绿化工程设计

详见绿化工程设计说明。

2.4.8 环境工程设计

1、设计原则

(1)严格执行我国的“以防为主、防治结合、全面规划、合理布局、综合治理”的环境保护方针。

(2)坚持“以人为本”的原则,道路设计应体现对人的关怀,适当位置应有环保设施,环保设施应方便行人使用。

2、环境保护设计

本工程环保设计应着重从道路视觉环境、工程建设对周围环境和生态平衡的影响、对环境的污染、污染控制的对策措施、道路绿化等方面进行环境保护设计。本工程的施工时应重点考虑以下问题:

(1)工程建设对沿线农田水利设施与水土保持的影响,包括施工期间开挖与填筑路基对自然植被覆盖的影响;施工引起水文地质变化对农作物和对生态环境分割所带来的影响。

(2)道路建设的取、弃土场的水土保持和绿化等方案设计。

(3)路基设计应因地制宜、就地取材如采用石石灰改良土等,结合工程地质条件,作好环境保护设计。

(4)合理有效的进行环境保护和景观设计,使道路与周围环境相协调,减少对自然景观的破坏。

2.5 施工注意事项

2.5.1 施工前期准备工作

应保护好测量定桩等标志,如遇有文物古迹则应加以保护。

2.5.2 管线升降、挪移、加固、予埋与其它市政管线的协调配合

应与甲方、各设计单位一道做好各市政管线的协调配合及予埋,如:电力、供水及电信等管线。

2.5.3 新技术、新材料等的施工方法及特殊路段或构造物的做法和要求

设计施工均采用成熟工艺和方法,其施工已有成熟的经验可以借鉴。

2.5.4 施工时对重要或有危险性的现状地下管线应注意的事项

现有资料没有反映该路有重要或有危险性的现状地下管线,如施工中发现有,要及时与甲方和设计单位联系,以便于采取相应措施进行处理。

2.5.5设计与施工技术要求

1、路基

道路路基采用黄土及改良土填筑,一般路基段填方路基应分层铺筑,均匀压实。路基

填土不得使用淤泥、沼泽土、冻土、有机土、含草皮土、生活垃圾、树根和含有腐朽物的土。天然稠度小于1.1、液限大于40、塑性指数大于18的粘性土用于填方路基时,应采取技术措施使其达到以上规定。

路基施工过程中,填土须按规范分层填筑压实,特别是取土坑处。若地下水位较高或土质湿软地段的路基的压实度达不到规定时,可采用晾晒、换土、石灰处理等措施,若路堤基底范围内地表水或地下水影响路基稳定时应采取拦截、引排等措施,并在路堤底部填筑不易风化的碎石等透水性材料。

原地面横坡度陡于1:5时,原地面应挖成台阶。台阶宽度不应小于2m,坡度小于1:2.5的台阶。含水量超过规定的土,不得直接作为路基填料。

路基压实度按重型压实标准,压实度和路基最小强度要求要求为:

填方高度小于80cm及不填不挖路段原地面以下0~30cm范围内,土的压实度不应低于表列挖方要求。

表列深度范围均由路槽底算起,路槽底面土基回弹模量值应大于或等于30MPa,土路槽(路床)不得翻浆、软弹、起皮、波浪和积水等。

2、道路基层、底基层

1)水泥稳定碎石

水泥稳定碎石应采用厂拌法集中拌合,机械摊铺。

水泥稳定碎石基层应用12T以上压路机碾压,用12-15T压路机时,每层压实度厚度不大于15cm,用18-20T压路机或振动压路机碾压时,每层压实度厚度不大于20cm,严禁用薄层贴补法找平。水泥稳定碎石中的碎石应符合规定级配。

水泥可用32.5普通硅酸盐或矿渣硅酸盐水泥。

水泥稳定碎石基层7天浸水无侧限抗压强度及其压实度(重型击实标准)均应不小于下表之规定。

2)石灰土

石灰土宜采用稳定土拌合机拌合(厂拌)。石灰土中石灰掺和量为10%。

石灰土技术指标应符合规范规定,具体如下:

(1)土的有机物含量小于10%,硫酸盐含量小于0.8%,土中不得含有树根杂草等物。

(2)凡是塑性指数大于4的砂性土,粘性土塑性指数为15~20,易于粉碎及拌和,并便于碾压。

(3)石灰宜用1~3级生石灰,氧化钙、氧化铝的含量小于65%的石灰不宜采用。

(4)石灰土底基层宜在春末和气温较高的季节施工,施工期的最低气温应在5℃以上。

(5)石灰土采用集中厂拌施工,其颗粒不得大于50mm,消石灰过筛的颗粒不得大于5mm。

(6)石灰土底基层不能在低温季节施工,并不能在水文不良地段采用。

基层须保湿养生,养生期应>7天,基层未铺封层,严禁一切机动车通行(施工车辆除外)。

3)级配碎石

级配碎石其技术指标应符合规范规定,具体如下:

(1)宜采用机械摊铺符合级配要求的厂拌级配碎石。

(2)轧制碎石的材料为各种类型的岩石、砾石。轧制碎石的砾石粒径应为碎石最大粒径的3倍以上,碎石中不应有黏土块、植物根茎、腐植质等有害物质。

(3)碎石中针片状颗粒的总含量不应超过20%。压碎值不得大于40%。

(4)压实系数应通过试验段确定,人工摊铺宜为1.40~1.50;机械摊铺宜为1.25~1.35 (5)摊铺碎石每层应按虚厚一次铺齐,颗粒分布应均匀,厚度一致,不得多次找补。

(6)级配碎石混合料的级配组成应符合下表:

3、水泥混凝土路面施工

水泥混凝土的材料必须满足各自的技术要求,参照施工验收规范。水泥混凝土最大水灰比不大于0.46;塌落度一般为1~2厘米,水泥混凝土采用厂拌,采用机具震捣密实;冬季施工时,当室外日平均气温连续五天低于5℃时,应按冬季施工规定进行,同时可在混凝土中加入早强剂和抗冻剂;混凝土接缝灌缝和混凝土板养生必须严格按施工规范进行。

混凝土板的纵缝采用加拉杆的平缝,横向缩缝采用假缝。车行道上的横向缩缝不设传力杆,但在邻近胀缝的三条缩缝内设传力杆;当混凝土板块划分出现错缝时,与接缝相对应的板边加防裂钢筋;在雨水口周围及雨(污)水检查口周围混凝土板应进行加固处理。

水泥混凝土板接缝要求具体如下:

(1)、纵缝:设拉杆的贯通缝,拉杆钢筋采用Ⅱ级钢筋,直径为14毫米,长70厘米,间距60厘米;

(2)、施工缝:位于缩缝处,设传力杆的贯通缝,施工方法可采用前置钢筋支架法,详见水泥混凝土路面施工技术规范 JTG F30-2003;传力杆钢筋采用Ⅰ级钢筋,直径为28毫米,长40厘米,间距30厘米;

(3)、缩缝:为切缝,应在砼强度达到设计强度的30%时,采用切缝机切割。缝宽5毫米,缝深为砼的1/4~1/5,间距为5米(调整范围为4~6米),灌缝料为PG道路嵌缝料。

(4)、胀缝:传力杆钢筋采用Ⅰ级钢筋,直径为28毫米,长40厘米,间距30厘米,设钢筋支架固定传力杆。胀、缩缝灌缝料填充聚氯乙烯胶泥嵌缝料,胀缝板采用涂沥青聚丙烯泡沫塑料板或软木板。在水泥砼路面中的雨、污水井及各种市政公用设施(如自来水、电力、电讯等)检查井,应设置胀缝与砼板完全隔开,并在其周围加设防裂钢筋。胀缝应与路面中心线垂直,缝壁必须垂直,缝宽必须一致,缝中不得起浆。邻近胀缝或路面端部的三条缩缝应设传力杆。具体做法参见图纸。

(5)砼板表面采用刻槽机刻槽:槽宽2~5mm,槽深3mm,间距25mm。

4、水泥混凝土路面建筑材料要求

1)水泥

用于水泥混凝土板的水泥标号不应低于42.5,采用普通硅酸盐水泥。其性能应符合现行国家规定的标准。水泥应有合格证,若有疑问,出厂期超过三个月及发现受潮的水泥,必须先经实验,合格后方准使用。不同品种,不同厂家和不同出厂期的水泥应分别堆放,严禁混合搅拌或在同一仓内使用不同的水泥。

水泥化学成分、物理性能等路用品质要符合《公路水泥混凝土路面施工技术规范》(JTG F30-2003)P6表3.1.2;水泥路面的抗压、抗折强度、安定性和凝结时间必须经检验合格方可使用。

水泥砼路面采用的碎石应质地坚硬、耐磨、洁净,并应符合规定的级配,最大粒径不得超过4厘米;碎石强度≥3级。

水泥砼外加剂供应商应提供有相应资质外加剂检测单位的品质检测报告。

2)黄砂

水泥混凝土板用的砂,应选用质地坚硬,符合规定级配,细度模数在2.5以上,富有棱角的粗砂或中粗砂,当无法取得粗、中粗砂时,经配合比实验可行,可采用泥土杂物含量小于3%的细砂。砂的技术要求应满足《水泥混凝土路面施工及验收规范》(GBJ97-87)的要求。3)碎石

水泥混凝土板用的碎石应质地坚硬,符合规定级配,最大粒径不超过40mm。碎石的技术要求应满足《公路水泥混凝土路面施工技术规范》(JTG F30-2003)的要求。

4)水

混凝土搅拌用水应清洁,不得含有油、酸、碱类及其它污浊物质,一般的饮用水均可使用。若使用非饮用水时,应经过化验,符合《公路水泥混凝土路面施工技术规范》(JTG F30-2003)的要求方可使用。PH值不得小于4。

5)钢筋

水泥混凝土板用的钢筋品种、规格应符合设计要求。钢筋应顺直,不得有裂缝、断伤、刻痕、表面油污,颗粒状或片状或锈蚀应清除;用作传力杆与拉杆的钢筋所有断口毛茬须仔细磨平。

6)乳化沥青

乳化沥青下封层采用Es-2型,厚度6mm,稀浆封层施工必须采用专用的摊铺机进行摊铺,应选择坚硬、粗糙、耐磨、洁净的集料。各项性能应符合《公路沥青路面施工技术规范》有关要求。

乳化沥青用量应通过配合比设计确定。

稀浆封层施工前,应彻底清除原路面的泥土、杂物,修补坑槽、凹陷,较宽的裂缝宜清缝灌缝。最低施工温度不得低于10℃。

稀浆封层混合料技术指标详见下表。

级配如下:

7)石灰

符合GB1594规定的生石灰或消石灰的技术标准,CaO+MgO的含量≥65%。

8)土

凡塑性指数大于4的砂性土、粉性土、粘性土均可用于石灰土,塑性指数以7~17最佳,土的有机物质含量应小于8%,硫酸盐含量应小于0.8%,土中不得含有树根杂草等物。

5、弯沉测试

车行道路基、底基层、基层、面层除以压实度作为控制标准外,须进行弯沉测试,土基、路面结构层弯沉值须符合设计要求。

经计算弯沉指标如下:(单位:0.01mm)

水稳基层顶面竣工验收弯沉值 LS=61.3 (0.01mm)

石灰土底基层顶面竣工验收弯沉值 LS=221.9 (0.01mm)

土基顶面竣工验收弯沉值 LS=310.5 (0.01mm)

考虑不利季节和路基干湿类型的综合影响系数K=1.25,进行折减,折减后的土基顶面竣工验收弯沉值Ls=248.4(0.01mm)。

2.5.6 注意事项及对施工的特殊要求

(1)施工前,应完成杆线、管线的迁移工作及红线范围内建筑物拆迁工作;为施工提供足够的施工空间,创造较好的施工条件。

(2)施工放样前,应注意与测量单位完成交接工作,并建立符合精度要求的测量控制网。

(3)施工前,施工单位应做好详尽的施工组织方案及应急预案。并预留交通便道,保证施工期间的交通有序、安全。

(4)施工时应合理组织、排除安全隐患、保证施工安全。

(5)施工时必须做好施工场地内的排水工作,必须将地面积水排出路幅范围以外,将路基土疏干,以确保路基的稳定,可根据现场确定排水方式,如盲沟等形式。

(6)路槽的施工应与地下管线的施工密切配合,管线施工应按由深及浅的顺序施工,以避免管线敷设时的二次开挖。

(7)土基施工过程中若出现水稳定不良现象,应及时通知设计单位酌情处理。

(8)路基填土应不含有任何不适宜工程使用的土,如淤泥、沼泽土、含有残树根等腐质的土、建筑生活垃圾、垃圾土及含水量较大的土。

(9)路基填土必须分层压实,每层的压实厚度不得大于25cm。

(10)为了保证路基边坡的压实度,一般路段路基两侧应各加宽50cm的碾压宽度。

(11)道路基层及面层施工前应对路基作全面检查,其压实度、平整度、弯沉值等指

标应满足设计及相关规范要求,如达不到设计规定值,应查出其范围后作进一步处理。

(12)混凝土混合料从搅拌机出料到摊铺、振捣、抹面成活的允许最长时间由实验室

根据混凝土初凝时间及施工气温变化,工地应严格掌握,根据劳力组织,妥善安排一次连

续摊铺的工作量。

(13)每一建筑块的摊铺压实工作须连续进行,不应中途间隔,如遇特殊情况被迫临

时停工半小时以内,已摊铺的混合料应用麻布覆盖,以防干结,当恢复工作时,将此处混

合料耙松补浆后再继续浇注混凝土。如停工半小时以上或每日施工终了,应作施工缝处理。

(14)混凝土路面的缩缝应在混凝土强度达到设计强度的30%时用切割机切割,切割用

水冷却时,应防止切割水渗入基层和土基,切割机具及施工工艺应符合《公路水泥混凝土

路面施工及验收规范》(JTG D40-2003)中的要求。

(15)整平工作须在工作桥上进行,不得站在混凝土面层上操作。

(16)钢筋安放应符合设计要求,位置间距正确,钢筋保持平直,不变形挠曲,并防

止浇注混凝土过程中产生位移。

(17)施工过程中应注意对环境保护,尽量减小噪音及施工垃圾对环境污染。

(18)本次设计坐标系和高程系均与测量单位提供的地形图一致,施工前应与其联系

交接并复核。

(19)施工前应注意复核与现状相交道路衔接处的位置及高程,与设计不符时请及时

与设计单位联系。

设计:校对:审核:审定:

道路工程设计说明书

目录

1 设计依据和采用的规范、标准......................................................... - 1 -

2 设计概要.............................................................................. - 1 -

2.1 工程范围、工程规模、测设过程及主要工程内容 ......................................... - 1 -

2.2 技术指标及设计参数................................................................. - 1 -

2.2.1 平面设计..................................................................... - 2 -

2.2.2 纵断面设计................................................................... - 3 -

2.2.3 交叉口设计................................................................... - 3 -

2.3 设计横断面及地上杆线、地下管线的配合关系 ........................................... - 3 -

2.4 路基、路面、挡墙及涵洞等工程设计 ................................................... - 3 -

2.4.1 路基设计及边沟、边坡特殊设计.............................................. - 3 -

2.4.2 路面结构设计 ................................................................ - 4 -

2.4.3 挡墙及涵洞等结构物设计..................................................... - 5 -

2.4.4 排水工程设计 ................................................................ - 5 -

2.4.5 交通工程设计 ................................................................ - 5 -

2.4.6 路灯工程设计 ................................................................ - 5 -

2.4.7 绿化工程设计 ................................................................ - 5 -

2.4.8 环境工程设计 ................................................................ - 5 -

2.5 施工注意事项......................................................................... - 5 -

2.5.1 施工前期准备工作............................................................ - 5 -

2.5.2 管线升降、挪移、加固、予埋与其它市政管线的协调配合.................... - 5 -

2.5.3 新技术、新材料等的施工方法及特殊路段或构造物的做法和要求............. - 5 -

2.5.4 施工时对重要或有危险性的现状地下管线应注意的事项 ...................... - 6 -

2.5.5设计与施工技术要求.......................................................... - 6 -

2.5.6 注意事项及对施工的特殊要求................................................ - 8 -

水泥混凝土路面施工工艺流程

一、概述 水泥混凝土路面是指以水泥混凝土板和基(垫)层所组成的路面,亦称为刚性路面。它包括普通水泥混凝土、钢筋混凝土、碾压混凝土和连续配筋混凝土路面等。水泥混凝土路面以其抗压、抗弯、抗磨损、高稳定性等诸多优势,在各级路面上得到广泛应用,在我国高等级公路中水泥混凝土路面日渐增多,加上近年来农村公路建设中普遍采用水泥路面,使得水泥混凝土路面科学化、规范化施工成为广大公路建设者关注的问题。水泥混凝土路面施工中,核心环节是混凝土的拌和生产和混凝土的摊铺,本文仅对公路水泥混凝土路面施工工艺流程进行探讨。 二、工艺流程 1、模板安装 模板宜采用钢模板,弯道等非标准部位以及小型工程也可采用木模板。模板应无损伤,有足够的强度,内侧和顶、底面均应光洁、平整、顺直,局部变形不得大于3mm,振捣时模板横向最大挠曲应小于4mm,高度应与混凝土路面板厚度一致,误差不超过±2mm,纵缝模板平缝的拉杆穿孔眼位应准确,企口缝则其企口舌部或凹槽的长度误差为钢模板±1mm,木模板±2mm。 2、安设传力杆 当侧模安装完毕后,即在需要安装传力杆位置上安装传力杆。 当混凝土板连续浇筑时,可采用钢筋支架法安设传力杆。即在嵌缝板上预留园孔,以便传力杆穿过,嵌缝板上面设木制或铁制压缝板条,按传力杆位置和间

距,在接缝模板下部做成倒U形槽,使传力杆由此通过,传力杆的两端固定在支架上,支架脚插入基层内。 当混凝土板不连续浇筑时,可采用顶头木模固定法安设传力杆。即在端模板外侧增加一块定位模板,板上按照传为杆的间距及杆径、钻孔眼,将传力杆穿过端模板孔眼,并直至外侧定位模板孔眼。两模板之间可用传力杆一半长度的横木固定。继续浇筑邻板混凝土时,拆除挡板、横木及定位模板,设置接缝板、木制压缝板条和传力杆套管。 3、摊铺和振捣 1)摊铺前的准备工作 混凝土摊铺前的准备工作很多,主要强调一下摊铺前洒水的卸料工序。 1.1 洒水 摊铺前洒水是一个看似简单的工序,往往不被施工人员重视,但如果洒水处理不好会严重影响路面质量。 洒水量要根据基层材料、空气温度、湿度、风速等诸多因素来确定洒水量,即保证摊铺混凝土前基层湿润,而且尽可能撒布均匀,尤其在基层不平整之处禁止有存水现象。从目前施工现场来看,大多数情况下是洒水量不足,因为基层较干,铺筑后混凝土路面底部产生大量细小裂纹,有些小裂纹与混凝土本身收缩应力产生的裂重叠后使整个混凝土路面裂纹增多。 1.2 卸料 自卸车的卸料也是常常不被重视的工序,在施工中经常发生堆料过 多给施工造成困难,有时布料过少使混凝土量不足,路面厚度得不到保证。这种混凝土忽多忽少现象会严重影响混凝土路面的平整度。在施工过程中大多数施工者死板地间隔一定距离卸一车料,而忽视了基层不平整的变化,这种变化在客观上是普遍存在的。目前许多企业施工水平不是很高,尤其是对路面基层的标高控制不到位,造成基层平整度较差,加大了混凝土路面施工的难度。在实际施工中,我们可对基层表面与面层基准标高线隔段实测来决定混凝土的卸料量,这样会避免卸料不均的问题。 对于半干硬性现场拌制的混凝土一次摊铺容许达到的混凝土路面板最大板厚度为22~24cm;塑性的商品混凝土一次摊铺的最大厚度为26cm。超过一次摊铺的最大厚度时,应分两次摊铺和振捣,两层铺筑的间隔时间不得超过3Omin,下层厚度约大于上层,且下层厚度为3/5。每次混凝土的摊铺、振捣、整平、抹面应连续施工,如需中断,应设施工缝,其位置应在设计规定的接缝位置。振捣时,可用平板式振捣器或插入式振捣器。 施工时,可采用真空吸水法施工。其特点是混凝土拌合物的水灰比比常用的增大5%~10%,可易于摊铺、振捣,减轻劳动强度,加快施工进度,缩短混凝

农村公路施工图设计说明

设计总说明 一、概述 1.1工程概况 开县金峰镇青橙村村级公路硬化工程是金峰镇青橙村村民出行的主要通道。原路为泥结碎石路面,由于道路等级较低,下雨时,路面泥泞不堪,为当地人民群众的出行及物资的运送造成极大阻碍。因此,该项目的改建已势在必行。 1.2任务依据及测设经过 义乌市交通设计有限公司重庆分公司(以下简称“我公司”)受中开县金峰镇青橙村村委委托,对《开县金峰镇青橙村村级公路硬化工程》进行设计。 该项目由于任务紧张,我公司在接到委托任务后立即成立项目组开展工作,于2014年7月上旬组织相关专业人员进行现场踏勘,就项目建设方案与业主方主要负责人达成一致:利用既有公路进行建设,路线平、纵面不作大的调整,局部地段改线,调整纵坡,完善排水设施,增设挡防设施的增设、错车道的设置、安保设施的设置等工作。我公司项目组在接到任务后立即组织人员进驻现场进行勘察测量,采用现场实地选线,并结合实际地形地貌进行调整,并据此再次对路线进行局部优化调整。勘测工作中,各作业组严格控制测量精度,对资料认真进行自检、自查,确保各项资料的搜集齐全和完整。经详细的测量、实地放线、细致的资料搜集、调查,外业勘测资料精度达到勘察测量规范规定的要求。整个外业勘测工作于2014年7月中旬完成,随后项目组全面展开内业设计,内业设计工作中,工程技术人员严格把关,对项目通过认真、细致的设计,在确保结构物安全、稳定的前提下尽量做到优化设计,使设计文件更加经济、合理,可行。2014年7月下旬编制完成《开县金峰镇青橙村村级公路硬化工程》设计,并交付业主。 1.3原路状况 本项目原有公路属于农村公路,路线沿山势展开,路线曲折,弯道多、平曲线半径 小,路基宽窄不一,平纵面线形局部达不到重庆农村公路标准,存在超限问题。沿线大部分路段无边沟或排水沟,全线部分涵洞经疏通维修后能继续使用。原路防护工程大多为干砌片石,部分不满足要求的重新翻修为浆砌挡墙。 1.4建设标准 本项目原则上按设计速度15km/h,部分路段依据《重庆市农村公路建设管理办法》进行设计。 1.5 设计原则及技术标准 1.5.1 设计原则 在设计中坚持“因地制宜、量力而行、技术可行、标准合理、节约土地、保护环境、保证质量、注重安全”的原则,并按重庆农村公路建设管理办法(渝文审(2011(25号))规定中“着重提高公路的路线技术标准,完善防护排水措施,增强晴雨通车能力”的方针进行设计,使公路改建后,当地群众出行更便捷、更安全、更舒适,以适应全面建设社会主义新农村的总体要求。 1.5.2技术标准 公路等级:农村公路 设计速度: 15km/h困难段10km/h 极限最小平曲线半径: 10m 一般最小平曲线半径: 15m 不设超高的最小平曲线半径: 150m 最大纵坡: 12% 最短坡长: 40m

公路工程施工图设计

本科学生毕业论文 设计题目:黑洛公路(K590-K593+500)段施 工图设计 学院:建筑工程学院 年级:2008级 专业:土木工程 姓名: 学号: 指导教师: 2012年 5 月30 日

摘要 黑洛公路是黑龙江省公路建设的重点项目之一,它连接了黑河市和大兴安岭地区,设计行车速度40公里/小时,采用二级公路设计标准,全长740km。它的建设对完善黑龙江省内公路交通网,促进公路沿线地区经济发展,带动沿边地区早日脱贫致富,促进黑河市和大兴安岭市之间的联系,有重要意义。本设计根据沿线地质、地形、水文等自然条件,以及黑洛公路外业勘测资料,参照交通部颁发的各种技术标准、规范,完成K590—K593+500段施工图设计。 本次设计利用各种计算机软件,包括:应用纬地道路辅助设计软件HintCAD5.88、绘图软件AutoCAD2004、办公软件Offices2003等,对黑洛公路平面、横断面、纵断面、路基、路面、排水工程、附属工程、平面交叉及沿线设施等进行了施工图设计,并绘制出相应表格和图纸,确定了沥青混凝土路面和水泥混凝土路面的各结构层厚度,本着优质、高效、经济、合理的原则进行施工组织设计。 关键词 路线设计;路基;沥青混凝土路面;水泥混凝土路面;施工组织

Abstract Heiluo road is one of the key project in Heilongjiang province, it connects the Heihe city and the Daxinganling city . Its design speed is 40km/h, which adopt three-stage highway design standard. The full-length is 740 km. The meaning of its construction to the consummation of the road network, is promoting along the route area economy development, bringing poverty area to get rid of poverty and become rich soon, and promoting crosswise relation between the city group of the northeast of Heilongjiang Province, which is significant. This design is based on the field operation survey data, as well as along the route natural condition including geology, terrain, hydrology and the related technical standard, which is issued by the Ministry of Transportation & Communications. According to the above we can complete the K590to K593+500section construction drawing design. The computer technology is fully used in this design. This design uses the latitude path assistance design software HintCAD5.8, cartography software AutoCAD2004, office software Offices2003 and so on. Meantime this design also completes construction drawing design which includes the highway route, the roadbed, road surface, drainage work plan cross ,the attached project and the facility along the route and so on, and draws up the corresponding graph and form. Through to designing of the Asphaltic concrete pavement and Cement concrete pavement, I ensure that thickness on each Structural layer and design the construction organization by the high-quality, efficient, economic and rational principles. Key words Route design,Roadbed,Asphaltic concrete pavement,Cement concrete pavement, Construction organization

施工图设计说明(公路模板)

路线设计说明 一、相关批复意见及执行情况 本次设计严格按照《青海省海东工业园区临空综合经济园总体规划(2011-2020)》进行施工图设计。同时,根据多次省、市领导对该项目的指示、意见和建议以及青海省交通部门专家的咨询意见,根据青海省海东工业园区临空综合经济园区道路建设方案的会议纪要进行一阶段施工图设计。 文件的编制基本按照《市政公用工程设计文件编制深度规定》要求进行文本及设计图纸的编制。同时,考虑到本项目为青海省交通厅代建项目,所以在设计中充分征求青海省交通部门意见、相关专家咨询意见以及公路交通部门规范要求,同时参照《公路工程基本建设项目设计文件编制办法》,对设计说明及图纸进行补充。 二、路线平面、纵断面设计说明 (一)路线走向及平面布设 1、本工程为新建道路,平面线形按照总体规划进行设计,并保持道路线形顺畅,满足《城市道路设计规范》(CJJ37-90)的要求。 拟建二号路位于平安县境内,二号路与规划的兰新客运铁路专线及南绕城高速公路并行,二号路路线全长。二号路起点、终点均与现状109国道相接,道路全线线形基本与南绕城高速平行。 二号路路线走向大致呈东西向,道路全线按照城市道路Ⅱ级主干道进行设计,设计车速40km/h。本次设计西起三号路,东至一号路,全长,道路全线共设交点17个,全线设平曲线15处,最小圆曲线半径300m,缓和曲线最小长度50m,最大圆曲线半径,最小平曲线长度。 K0+000~K1+200段利用现状109国道(现状宽12m,沥青混凝土路面)向北侧进行拓宽改造,K1+200~K3+080段与南侧兰新客运专线平行,K3+080~K3+540段下穿客运专线,经政府部门与高铁相关部门协商,因高铁沿开发区中部全线穿越,孔跨跨径为30m,采用双向行车时,路幅布置在两桥墩之间,能充分保证路幅宽度及行车安全。相关同意道路选线将桥墩置于12m中央分隔带内,并考虑安全净空要求,绿化带路缘石采用连续式钢筋混凝土护栏进行防护。 高铁桥墩及高压线塔 K3+540~段平面线形基本与南侧南绕城高速平行,终点与1号路及109国道相接。K5+230~K6+000段穿越330KV的高压走廊,此段考虑到建设用地要求,经政府部门与电厂相关部门协商,同意将铁塔置于道路中央分隔带内。因中央分隔带设置宽度10m,能够保证铁塔安全净空要求,绿化带路缘石采用连续式钢筋混凝土护栏进行防护。 沿线前后跨沟五次,相应的布设桥梁。 2、路线采用坐标及高程 路线平面控制测量采用平安县城建坐标系,路线高程控制测量采用1985年国家基准 下穿客运专线 高压走廊 南绕城高速

郑开高速公路施工图设计

1 / 11

2 / 11

长沙理工大学继续教育学院自考毕业设计任务书 (2010-11-24 11:17:00) 分类:毕业设计 标签: 交通运输 北京 人民交通出版社 布置图 施工图设计 教育 长沙理工大学继续教育学院自考毕业设计任务书 一、课题名称 郑开高速公路施工图设计。 二、课题目的和意义 3 / 11

毕业设计是工科大学生实践教学的一个重要环节,是毕业前的一次综合性训练,是对学生在大学几年所学知识的全面检查。通过毕业设计,可以使学生在如何进行公路施工图设计方面进行一次全面的、系统的训练,使学生了解公路施工图设计所包含的工作内容、工作程序、施工图设计文件所包含的内容及文件的编制办法等,为今后从事公路工程设计工作打下良好的基础。通过毕业设计,既有助于提高同学们综合运用知识的能力,同时也有助于今后在工作岗位上能很快地适应工作环境。 三、施工图设计的主要工作 1.确定路线的具体位置(含平、纵、横); 2.计算路基超高、加宽,土石方工程数量计算及调配,确定取土坑及弃土堆的位置; 3.排水系统设计(含结构物类型及尺寸); 4.防护工程设计(含坡面防护、支挡工程等的结构类型及尺寸); 5.路面结构设计; 6.小桥涵结构设计及布置; 7.交叉口设计(含形式选择、结构类型及尺寸、布置图); 8.沿线设施及环境保护设施设计; 9.料场调查; 10.各项工程数量计算及统计,征地、拆迁数量计算; 4 / 11

11.施工组织设计; 12.编制施工图预算。 四、施工图设计文件的主要内容及编制办法 公路设计图设计文件通常由十三篇组成,本设计只要求完成其中主要的六篇。 第一篇总说明书 包括任务的依据及测设经过,路线起终点位置及沿线地形、地质、水文等情况的描述。对设计所采用的技术方案、技术手段以及材料、设备、工艺等说明其理由。此外还包括平纵面缩图及主要技术经济指标表等。 第三篇路线 包括路线设计说明、路线平面图、路线纵断面图、直线曲线转角表、用地图、用地及青苗补偿表、拆迁建筑物表、拆迁电力电讯及其它管线设施表、砍树挖根数量表、排水清淤及耕地填前夯实数量表、水准点表等。 第四篇路基路面及排水 包括路基路面设计说明、路基标准横断面图、路基横断面图、排水系统布置图及排水一般结构设计图、防护工程设计图、路面结构设计图、路基设计表、断面高程表、土石方数量计算表、路面工程数量表、路基路面排水及防护工程数量表等。 第五篇桥梁、涵洞 包括桥涵设计说明、桥梁布置图、桥梁结构设计图、涵洞布置图、涵洞结构图、涵洞工程一览表及工程数量一览表等。 5 / 11

道路工程施工图设计组成内容及编制深度要求

城市道路工程施工图设计文件组成内容及编制深度要求 1 设计说明书 初步设计批复等依据文件。 执行初步设计批复情况,如有改变初步设计的内容时需说明改变部分的内容、原因和依据。 采用的施工规范、规程和工程验收标准。 设计概要 工程范围、工程规模及主要工程内容。 平纵线形设计技术要点。 设计横断面及与地上杆线、地下管线的配合关系。 路基、路面、挡墙及涵洞等工程设计。 1)路基设计及边沟、边坡特殊设计。 2)路面结构设计包括:设计标准、设计弯沉值、结构组合型式及采取的技术措施(含主、辅路及人行步道)。 3)挡墙及涵洞采用通用图或特殊设计。 4)雨水口布置及道路路面排水措施。 5)交通工程设施设计。 6)照明工程设计。 7)环境工程设计。 8)其它设计情况。 9)采用新技术、新材料、新设备及新工艺等情况。 10)需要特殊说明的问题。 施工注意事项 1)施工前准备工作,包括拆迁、征地、迁移障碍物等。 2)管线升降、挪移、加固、予埋与其它市政管线的协调配合。 3)新技术、新材料等的施工方法及特殊路段或构筑物的做法和要求。 4)重要或有危险性的现况地下管线(电力、电信、燃气等应有准确位置和高程),施工时应注意的事项。 5)对施工的特殊要求。 2 施工图预算 根据实际情况编写,有无施工图预算委托。 3 工程数量和材料用量表 4 设计图纸 平面总体设计图:比尺1:2000~1:10000,内容同初步设计要求。 平面设计图:比尺1:500~1:1000,包含规划道路中线与施工中线坐标、平曲线要素、机动车道、辅路(非机动车道)、人行道(路肩)及道路各部尺寸、港湾停靠站、人行通道或人行天桥位置尺寸,道路与沿线相交道路及建筑进出口的处理方式,道路交通标志和标线及交通安全设施的位置与尺寸,桥隧、立交的平面布置与尺寸,各种杆、管线和附属构筑物的位置和尺寸,拆迁房屋、挪移杆线、征地范围等。

水泥混凝土路面施工方法及说明

6、3 水泥混凝土路面施工方法及说明 xxx改建工程,K0+000~K0+335段及K0+500~K0+985段局部路面损坏严重的需挖补原水泥面层。 路面C35 厚26cm水泥砼路面11648m2,主要为主车道路面。水泥混凝土路面施工分幅进行。路面混凝土采用有资质的C35商品混凝土。 6、3、1 路面混凝土施工方法 (1) 模板工程 ①模板的选用 路面混凝土采用26cm高定型槽钢模板。 ②模板安装 经测量放样后,路面砼模板按照单车道的宽度沿行车方向安装,安装好后刷脱模剂就可以进行路面混凝土的浇筑。模板安装如下图所示。

求进行。钢筋及扎线均不得接触模板。安装完毕的钢筋,按三检制度检查后,报请监理工程师验收。 (3)商品砼 ①搅拌设备计量误差要求 所选定的商品砼厂,其水泥混凝土搅拌设备的配套容量必须满足施工现场机具的施工要求,搅拌设备的类型必须就是强制式的,搅拌设备应能稳定可靠地供应足够的水泥混凝土拌与料、充足的供水供电。 进入搅拌设备的各种原材料须通过严格的试验检验,每个搅拌设备者须用法定计量单位对各种原材料进行计量标定,计量允许误差要求如下:水泥:±1%;砂:±2%;粗骨料:±2%;水:±1%;外加剂:±2%。 要特别注意雨天或阵雨后必须及时按砂石含水量来调整加水量与砂石料称量。混凝土坍落度应按设计要求严格控制。 ②搅拌时间 强制式搅拌设备的拌与时间不少于90秒,同时严格禁止在拌合及卸放熟料时,提前向拌合机内倾倒生料。下一拌生料必须在上一拌熟料卸完后方可进料。 ③运输 根据实验提供的新拌水泥混凝土初凝时间与施工时的气温来确定。混凝土从搅拌机出料到浇筑完毕的最大允许时间:当施工气温在5℃~10℃时,最大允许时间为2h;当施工气温在10℃~20℃时,最大允许时间为1、5h;当施工气温在20℃~30℃时,最大允许时间为1h;当施工气温在30℃~35℃时,最大允许时间为0、75h。 (4)混凝土路面施工 ①混凝土路面施工工艺流程图

公路施工图设计说明书

说明 1.0 遵循的规范、规程 (1)《公路工程技术标准》(JTG B01-2003); (2)《公路工程抗震设计规范》(JTJ 004-89); (3)《公路环境保护设计规范》(JTJ/T006-98); (4)《公路路线设计规范》(JTJ 011-94); (5)《公路路基设计规范》(JTG D30-2004); (6)《公路沥青路面设计规范》(JTJ 014-97); (7)《公路水泥混凝土路面设计规范》(JTG D40-2002); (8)《公路水泥混凝土路面施工技术规范》(JTG F30-2003); (9)《公路软土地基路堤设计与施工技术规范》(JTJ 017-96); (10)《公路排水设计规范》(JTJ 018-97); (11)《公路土工合成材料应用技术规范》(JTJ/T019-98); (12)《公路沥青路面施工技术规范》(JTG F40-2004); (13)《公路改性沥青路面施工技术规范》(JTJ 036-98); (14)《公路路基施工技术规范》(JTJ 033-95); (15)《公路路面基层施工技术规范》(JTJ 034-2000); (16)《公路工程沥青及沥青混合料试验规程》(JTJ 052-2000); (17)《公路工程水泥混凝土试验规程》(JTJ 053-94); (18)《公路土工试验规程》(JTJ 051-93); (19)《公路工程石料试验规程》(JTJ 054-94); (20)《公路工程无机结合料稳定材料试验规程》(JTJ 057-94); (21)《公路工程集料试验规程》(JTJ 058-2000); (22)《公路路基路面现场测试规程》(JTJ 059-95); (23)《公路土工合成材料试验规程》(JTJ/T060-98); (24)《公路勘测规范》(JTJ 061-99); (25)《公路工程地质勘察规范》(JTJ 064-98); (26)《公路工程质量检验评定标准》(JTG F80/1-2004); (27)国颁《道路工程制图标准》(GBJ 50162-92); 此外,参照执行我院制定的工作大纲及建设单位和地方政府的有关会议纪要、协议。 2.0 初步设计批复意见执行情况 依据初步设计的批复意见“同意采用路基两侧加宽的设计方案,每侧加宽8米。加宽后的路基宽度为42米,计算行车速度120公里/小时,双向八车道。路面结构:4厘米厚沥青玛蹄脂(SMA-13)+6厘米厚中粒式沥青混凝土(AC-20I变级配)+8厘米厚粗粒式沥青混凝土(AC-25I变级配)+36厘米厚水泥稳定碎石+20厘米厚低剂量水泥稳定粒料”进行设计。沥青混凝土表面层采用SMA,符合本项目大交通、重轴载的特点,具有较好的高温抗车辙性能、抗低温开裂性能和优异的抗滑性能;在沥青混凝土中、下面层的选择上,传统的AC-I型密级配沥青混凝土具有孔隙率较小,密实性能较好等特性,但由于细集料较多,级配呈悬浮型,高温稳定性较差,同时也易于引起泛油、涌包、车辙等破坏现象。根据我国高速公路沥青路面发展趋势并结合本项目所处的地理环境及重载交通的实际情况,虽然Superpave设计方法设计出的沥青混合料具有较好的稳定性,但该设计方法在我省应用还缺乏经验,不宜在本项目中大规模使用,而对传统AC-I型密级配进行改善,适当减少靠近最大粒径的粗集料和细集料中较细部分的比例,控制矿粉比例,适当增加中间档次的粗集料(如5~10mm、10~15mm)所形成的S型级配属于嵌挤密实型级配,具有适宜的孔隙率,渗水性小,不但有较好的高温稳定性,而且表面还具

高速公路施工图设计审查要点

. 省高速公路施工图设计审查要点 第一章总则 第1条为了加强高速公路工程勘察设计质量监督与管理,保护和人民生命财产安全,维护社会公众利益,根据和省现行有关法律、法规和标准、规,结合本省实际,特制定本审查要点。 第2条施工图审查分为政策性审查和技术性审查。技术性审查实行“双审制”,即先由行业主管部门认可的具有相应资质的设计、咨询单位进行初审并提交书面初审报告,再由业主组织有关专家进行会议审查,并形成专家审查意见。 第3条政策性审查的主要容是: 1.是否按照规定实行了勘察设计招投标; 2.设计单位承担的工程是否在其资质等级和业务许可围; 3.设计文件的有效签署是否符合规定; 4.有无出卖或出借图签、图章和印章等扰乱设计市场秩序的行为; 5.设计文件是否齐全; 6.设计合同是否有效; 7.设计方案是否符合环境保护、水土保持、文物保护、减灾防灾、土地使用等规定; 凡是不符合上述要求的图纸,一律不予受理,退回上报单位。 第4条技术性审查的主要要求: 1.主要技术标准与建设规模应符合初步设计批复意见;

2.设计文件深度及容应符合《公路工程基本建设项目设计文件编制办法》规定(以下简称《编制办法》); 3.勘察设计文件执行《工程建设标准强制性条文》及各项技术规的情况; 4.设计方案应符合安全、耐久、环保、经济、美观、节约、和谐的原则,并综合处理好相互关系; 5.工程地质勘察报告须达到《公路工程地质勘察规》要求,并能满足设计要求; 6.桥梁、隧道及立交工程主要结构物的计算结果执行现行规要求的情况; 7.工程实施方案应最大限度保护社会公众利益; 8.上级主管部门要求审查的其他容。 第5条提交施工图审查的资料必须包括: 1.政府有关部门批准的初步设计文件及批复文件; 2.完整的工程勘察报告、测量资料等基础资料; 3.全套施工图(含主要结构计算书并注明计算软件的名称); 4.环境影响评价和水土保持报告书即批复文件,其它专题报告,如:安全性分析报告、通航论证报告、行洪分析报告等及审查需要提供的相关附件、协议等资料。 5.需要提供的其它资料。 审查需要提供的其它资料,如行洪分析报告、通航论证等。 第6条审查要本着科学、客观、公正和负责的态度,通过必要的现场踏勘和设计沟通,对全套施工图文件进行系统审查,提出明确的审查意见和优化建议方案。技术复核要采用与设计不同的软件计算,优化建议要提出明确的技术措施及改进方法,作

道路施工图设计说明

道路施工图设计说明 1、概述 高铁商务区山韵佳苑D区位于山韵路、规划新锡路、镇北路和吼山浜围合的区域,D区共包括16栋18F住宅楼和4栋配套用房。其中D区一期建设10#~16#住宅、配套用房1、配套用房2、配套用房4和车库A、车库D。 根据甲要求,山韵佳苑D区一期室外市政沥青道路及小区部停车位(为沥青路面结构)属于本次设计围,绿地、硬铺装道路部分、人行道及曲径(步道)根据景观设计确定,计入景观施工围。 本图坐标为市城市坐标系,标高采用1985年高程基准。 2、设计依据规 1)《城市道路设计规》(CJJ37-2012) 2)《道路工程制图标准》(GB50162-92) 3)《市政工程勘察规》(CJJ56-2012) 4)《城镇道路路面设计规》(CJJ 169-2012) 5)《公路路基施工技术规》(JTJ G10-2006) 6)《公路路基设计规》(JTJ D30-2006) 7)《城市道路和建筑物无障碍设计规》(JGJ50-2001) 8)《透水砖》(JC/T 945-2005) 9)《城镇道路工程施工与质量验收规》(CJJ1-2008) 10)《市政公用工程设计文件编制深度规定》(建质【2004】16号) 11)《沥青路面施工及验收规》(GBJ50092-96) 12)《工程建设标准强制性条文》(建标[2000]202号) 13)《混凝土路缘》(JC899-2002) 3、路面 3.1 技术指标 (1)道路性质:场地主要道路参照城市支路标准。 (2)设计年限:沥青混凝土路面为10年 (3)设计荷载:BZZ-100 (4)路基压实度标准采用重型击实标准。 3.2 道路横坡 本工程道路横断面路拱分为单向坡和双向坡两种,6m以上(包含6m)的道路为双向坡,路拱横坡坡度1.5%,坡向向路外;6m以下的道路为单向坡,路拱横坡坡度1.5%,具体横断面坡向详见平面设计图。 3.3 路面结构 (1)完全在地下室围外路面结构: A. 6m以上(包括6m)车道结构: 3.5cm 细粒式沥青混凝土(AC-10C Ld=45 K≥95%) 粘层油 4.5cm 细粒式沥青混凝土(AC-13C K≥95%) 0.6cm 油封层 18cm 水泥稳定碎(K≥95%) 18cm 12%灰土(K≥93%) 15cm 5%灰土(Ld=380、K≥92%) 15cm 5%灰土(K≥92%) 15cm 5%灰土(K≥90%) 土基压实K≥87% B. 6m以下车道结构: 3.5cm 细粒式沥青混凝土(AC-10C Ld=62 K≥95%) 粘层油 4.5cm 细粒式沥青混凝土(AC-13C K≥95%) 0.6cm 油封层 15cm 水泥稳定碎(K≥95%) 15cm 12%灰土(K≥93%) 15cm 5%灰土(Ld=380、K≥92%) 15cm 5%灰土(K≥92%) 15cm 5%灰土(K≥90%) 土基压实K≥87% C、汽车停车位结构: 同相邻车道结构(停车位横坡坡向详见道路平面图)。 (注:按《城镇道路工程施工和质量验收规》CJJ1-2008要求,对路床顶面及各结构层弯沉进行控制。)

交通工程施工图设计说明

交通工程施工图设计说明 1设计标准 1.《城市道路工程设计规范》(CJJ 37-2012) 2.《道路交通标志和标线》(GB5768—2009) 3.《道路交通标志板及支撑件》(GB/T23827-2009) 4.《公路交通标志反光膜》(GB/T18833-2002) 5.《路面标线涂料》(JT/T280-2004) 6.《路面标线用玻璃珠》(GB/T24772-2009) 7.《道路交通信号灯安装规范》(GB14886—2006) 8.《道路交通信号灯》(GB14887—2003/XG1—2006) 9.《道路交通信号控制机》(GA25280—2010) 10.《公路交通标志和标线设置规范》(JTGD82—2009) 11.《成都市道路指路标志系统》(DB510100/T 129—2013) 12.《四川省旅游标志标牌设置标准》 13.《公共场所双语标志英文译法》 14.《成都市道路交通设施设置指南》 15.《电气装置安装工程施工及验收规范》(GBJ232082) 16.《中华人民共和国道路交通安全法》 17.《中华人民共和国道路交通安全法实施条例》 18.现行有关材料标准 2设计内容 本次设计包含:1、广州路交通工程;2、海口路交通工程;3、海南路交通工程4、兴隆湖十四号路交通工程5、广西路交通工程;以及与本项目相交道路的交叉口100m 范围内的标志牌. 道路等级:1、广州路城市主干路;2、海口路城市支路;3、海南路城市次干路4、兴隆湖十四号路城市主干路5、广西路城市次干路。主干路安全设施等级按A级配置设计。次干路、支路安全设施等级按B级配置设计。 设计车速:主干路主车道60Km/h,交织段集散车道30Km/h;次干路设计速度40Km/h;支路设计速度30Km/h。 车道宽度:主车道3。5m,集散车道3.25m,交叉口渠化段进口车道3。25m。 2.1交通标志 2.1.1设计原则 1.道路上的标志具有法律效力,应根据交通管理法规及有关标准,正确地设计与设置 标志。 2.标志的设计应根据道路的交通量及其构成,计算行车速度,平、纵面线形,桥涵、隧 道等构造物的位置,投资与自然环境等因素综合考虑。 3.标志的设置不得侵占道路建筑限界。标志牌不应侵占路肩,应确保净空高度。 4.标置的设置数量应平衡、均匀,避免信息过载或疏漏,重要信息可重复设置。在 某些情况下,应根据交通标志的重要性划分层次,保障重要标志的位置。在路况较好的长直路段也应设置一些提示性的标志。 5.以不熟悉该道路及周围路网体系的道路使用者为设计对象,交通标志的设置应充 分考虑整个路网和该道路之间的关系。 6.在设置交通标志时,应注意与交通标线的配合使用.交通标志的设置还应周围环境 等其它沿线设施的协调配合。 7.道路全线应采用统一的设置标准、版面规格,在特殊情况下,交通标志的设置位置 与统一性发生矛盾时,应优先保证交通标志的可读性和视认性。 8.交通标志的版面设计应以驾驶人员在计算行车速度下行驶时能及时辨认标志信息 为基本原则,同时力求使版面美观、醒目。 9.交通标志的结构设计应符合“充分满足功能要求、尽量考虑美观、统一规格并降 低造价”的原则. 2.1.2设计内容 2.1.2.1交通标志种类 本设计交通标志主要有四种:

城陵矶高速公路施工图勘察设计

招标编号:2018司-服务-询价-17 城陵矶高速公路施工图勘察设计 咨询技术服务 询价文件 采购人:湖南省高速公路建设开发总公司 2018年3月

总说明 一、供应商的响应文件应按照本文件的要求编制,需完整反映本文件的要求和内容。 二、询价文件中提到的时间除有特别说明外,均指北京时间;询 价文件中提到的货币单位除特别说明外,均指人民币元。 三、询价文件中所有复印件均指彩色扫描件或彩色复印件。

目录 第一章询价采购公告 附件:响应文件的评审办法 第二章询价须知 询价须知前附表 询价须知正文 一、说明 二、询价文件 三、响应文件 四、响应文件的递交 五、成交结果信息公布与授予合同 六、其他规定 第三章合同格式 第四章采购需求 第五章响应文件组成

第一章询价采购公告 湖南省高速公路建设开发总公司拟对城陵矶高速公路项目施工图勘察设计 咨询技术服务进行公开询价采购,特邀请有兴趣的潜在供应商询价。 1.项目基本情况 城陵矶高速公路已由湖南省发改委核准批复(湘发改基础[2017]521号),初步设计文件已经省交通运输厅批复,已完成施工图设计施工总承包招标。项目位于湖南省岳阳市境内,主线全长7.34km,采用四车道高速公路标准建设,设 计速度100km/h,路基宽度26m。全线共设特大桥1127.8m/1座,大桥2120m/7座,中桥42m/1座,互通式立交2处,涵洞8道,通道12道,主线收费站2处。 本次招标共一个标段,采购预算上限为27.90 万元,供应商自行报价,合 同为固定总价合同。评审办法采用最低价法。 2.供应商资格要求 2.1供应商应具有独立法人资格,持有有效的营业执照(经营范围包含公路 工程技术咨询与服务或工程技术咨询服务或技术咨询)(或事业单位法人证书) (供应商为企业的,还应具备组织机构代码证,按照“三证合一”或“五证合一” 登记制度进行登记的,可仅提供营业执照副本,下同;供应商为依法允许经营的事业单位的,应具有事业单位法人证书和组织机构代码证)、最近5年(指递交响应文件截止之日前一日回溯5年)至少完成过1条高速公路的初步勘察设计或 施工图勘察设计,或1条高速公路的初步勘察设计监理咨询或施工图勘察设计监 理咨询,或1条高速公路的初步设计或施工图设计评审,或1条高速公路的技术咨询服务(设计优化、核查)业绩(上述合同的技术服务范围必须至少同时包括 路线、路基路面、桥涵、路线交叉、安全设施等专业),并在人员、设备、资金 等方面具有相应的服务能力。 2.2本次询价不接受联合体。 2.3单位负责人1为同一人或者存在控股2、管理关系3的不同单位(即利益相 关企业),不得同时投本项目,否则其所有响应均将被否决。 1单位负责人,是指单位法定代表人或者法律、行政法规规定代表单位行使职权的主要 负责人。(招标文件中所列“单位负责人”均作本条所释) 2控股,是指出资额(持股)占股本总额50%以上或虽不足50%,但依出资额或所持股 份所享有的表决权已足以对股东会、股东大会的决议产生重大影响的,或者国有企事业单位 通过投资关系、协议或者其他安排,能够实际支配公司行为的。(招标文件中所列“控股” 均作本条所释) 3管理关系,是指不具有出资持股关系的其他单位之间存在的管理与被管理关系。(招标文件中所列“管理关系”均作本条所释)

(完整版)水泥混凝土路面施工方案

成庄提浓站站外混凝土道路施工方案 一、工程概况: 本工程位于成庄提浓站站外道路,道路总长为300米,本道路为单车道。 二、编制依据 本施工方案是根据现场勘察以及山西省《水泥混凝土路面施工及验收规范》(GBJ97-87)施工验收规范及规程进行编制。 三、水泥混凝土路面施工注意事项: 1、施工前应严格按设计要求坐标进行放样,并对全线水准控制点进行闭合校验; 2、路基工程施工期间应采取必要的排水措施以保证路基干燥; 3、路面工程 1)混凝土计算抗折强度不低于4.0MPa,加水拌合料坍落度15-25,摊铺后先用插入式振捣器振捣边角,然后用夹板振捣器纵横交错全面振捣,振捣整平后30分钟内抹压提浆,抹面是禁止撒灰、洒水,抹面后30分钟内沿道路横向压成光面,施工完毕3小时开始养护,保持湿润。 2)道路路面应满足《水泥混凝土路面施工技术规范》 4、施工允许误差 板厚±10mm 路拱标高±10mm 路面宽±20mm 相邻板高差±3mm 平整度3m直尺接触路面,空隙不大于5mm 纵横顺直度20m长误差不大于15mm。 四、材料供用 路基采用100mm厚C15商砼,面层采用250mm厚C30商砼;停车位垫层使用200厚极配碎石,面层采用250mm厚C30商砼。 五、施工工艺 1、砼垫层施工工艺流程: 施工准备→施工测量放样→平地机整平→砼垫层浇筑 2、水泥混凝土路面面层施工工艺 施工准备→测量放样、复测高程→路面基层清理→安装模板→摊铺砼→抹平→压纹→拆模板→切缝→养护 1)施工准备工作

采用商品C30混凝土: ○1在正式施工前,商品砼供应商的试验室应先按设计图纸要求的砼强度等级进行配合比设计,并按规定做好砼的试件,经有关部门审核符合要求后,才能正式在工程施工中使用。砼的运输 ○2砼供应商采用搅拌车将工程所需的砼由搅拌站运送至现场,再用泵车运输至浇捣地点作业。商品混凝土运输进入施工现场后将混凝土用泵车送到浇筑面上,连续浇筑。在施工过程中,加强通信联络和调度,确保混凝土浇筑的连续均匀性。 ○3为满足混凝土连续施工的需要,浇筑之前,应提前选择好行车路线和确定运输车数量,同时应做好沿途交通警察工作、工地附近居民工作,以防出现混凝土因交通和民扰出现问题。○4由商品混凝土搅拌站试验室确定配合比及外加剂用量。 ○5混凝土浇筑前组织施工人员进行施工方案的学习,由技术部门讲述施工方案,对重点部位单独交底,设专人负责,做到人人心中有数。 2)测量放样 测量放样是水泥混凝土路面施工的一项重要工作。首先应根据设计图纸放出中心线及边线,设置胀缝、缩缝、曲线起迄点和纵坡转折点等桩位,同时根据放好的中心线及边线,在现场核对施工图纸的混凝土分块线。要求分块线距窨井盖的边线保持至少1cm的距离,否则应移动分块线的位置。放样时为了保证曲线地段中线内外侧车道混凝土块有较合理的划分,必须保持横向分块线与路中心线垂直。对测量放样必须经常进行复核。包括在浇捣混凝土过程中,要做到勤测、勤核、勤纠偏。 3、安设模板 垫层检验合格后,即可安设模板。模板采用木模,长度3~4m。模板高度与混凝土面层板厚度相同。模板两侧铁钎打入基层固定。模板的顶面与混凝土路面顶面齐平,并应与设计高程一致,模板底面应与基层顶面紧贴,局部低洼处(空隙)要事先用水泥浆铺平并充分夯实。模板安装完毕后,再检查一次模板相接处的高差和模板内侧是否有错位和不平整等情况,高差大于3mm或有错位和不平整的模板应拆去重新安装。 4、摊铺与振捣 1)、摊铺 摊铺混凝土前,应对模板的间隔、高度、支撑稳定情况和基层的平整情况等进行全面检查。 混凝土混合料运送车辆到达摊铺地点后,直接倒入安装好侧模的路槽内,并用人工找补均匀,如发现有离析现象,应用铁锹翻拌。

道路设计总说明

东兰县中央财政预算内以工代赈项目花香乡花香村巴吉道路 一阶段施工图设计 (路线总长562.069m) 广西XX设计有限责任公司 二○一六年二月

东兰县中央财政预算内以工代赈项目花香乡花香村巴吉道路 一阶段施工图设计 (路线总长562.069m) 证书编号:审定: 资质等级:公路行业(公路)丙级审核: 法定代表人:复核: 技术负责人:设计: 项目负责人: 广西XX设计有限责任公司 二○一六年二月

总目录 总目录

第一篇总论 一、概述 (一)工程概况 (1)工程名称:XX县中央财政预算内以工代赈项目花香乡花香村巴吉道路 (2)建设单位:东兰县发展和改革局 (3)设计单位:广西建XX设计有限责任公司,证书编号:XXX;资质等级:公路行业(公路)专业丙级; (4)项目建设地点:花香乡花香村,距离县城50.0km。 (5)建设规模:道路总长562.069m,路基宽度4.5m,路面宽度3.5m。 (二)设计依据及标准 1、设计依据 (1)勘测设计委托合同; (2)《公路工程技术标准》(JTG B01-2003); (3)《公路路基设计规范》(JTG D30-2004); (4)《公路桥涵设计通用规范》(JTG D60-2004); (5)《公路桥涵地基与基础设计规范》(JTJ 024-85); (6)《公路桥涵施工技术规范》(JTJ041-2000); (7)《公路排水设计规范》(JTJ018-97); (8)《农村公路建设指导意见》(交公路发[2004]372号)。 2、主要设计指标如下: (1)公路等级—按《农村公路建设暂行技术要求》设计。 (2)计算行车速度:20km/h。 (3)路基宽度:4.5m;路面宽度3.5m。 (4)路面结构:水泥混凝土路面 (5)最大纵坡:14.98 % (6)设计洪水频率:新建桥涵及路基按25年一遇洪水标准设计。 (7)图中坐标、高程系统均为假设。 二、工程概况 路线起点位于花香乡花香村弄吉屯,终点巴吉屯。路线全长562.069m。 主要工程量:挖土石方2091m3,填土方1346m3,混凝土路面1997.2m2。详见下表: 表1主要工程数量表 三、沿线自然条件及地理特征 1、地形 本路线通过地域地形较陡,高差大。 2、地质构造 测区内多以风化石为主,地表覆盖厚0.5-1.5m,未存在不良的地质构造。 3、地震

高速公路施工图设计说明

摘要 本工程为某地区高速公路一段设计,该工程的实施将对带动该地区经济发展、方便地方人民群众生活起到积极作用;也是联系本地与外界的一条重要通道。 本次设计的路段是陕西延安至吴起高速公路A2段,全线采用双向四车道高速公路标准,全程5.5公里,设计速度为100公里/小时,路基宽度为26.0米。 依据老师所给的资料,通过对k0+000—k5+500路段的原始数据的分析,根据该路段的地质情况、地形、地物及水文等自然条件的特点,依据交通部颁发的公路工程标准、设计与施工技术规范,并运用纬地道路设计软件、AutoCAD对公路的路线平面线形、纵段面线形与横断面、路基路面进行了设计与计算,绘制出路线平面图、纵段面图、横断面图、直线曲线转角表、纵坡竖曲线表、标准横断面图、路基设计表、路面结构设计图、土石方数量表以及相关的其他图表,并且编写各部分相应的设计说明书等。通过这次设计不但了解建设公路的各个步骤, 而且也能熟练的运用AUTOCAD进行制图. 关键词:经济发展陕西延安至吴起高速公路纬地道路设计 AutoCAD Abstract This works for a while in an area highway design, implementation of the project will promote economic development in the region , to facilitate local people's lives play an active role ; is also an important channel to contact the local and the outside world. This section is designed toWu Qi highway A2 segment Yan'an , Shaanxi , across the board with a two-way four-lane expressway standard , the entire 5.5 km , the design speed of 100 km / h , roadbed width of 26.0 meters . Based on the information given by the teacher , through the k0 +000- k5 +500 sections of the original analysis of the data , according to the characteristics of the geological conditions of the road , terrain , terrain and other natural hydrological conditions , issued by the Ministry of Transportation highway engineering standards design and construction specifications , and the use of latitude to road design software , AutoCAD horizontal alignment of the road route , longitudinal section and cross-sectional surface alignment , road embankment is designed and calculated to draw out the route plan , longitudinal section view of the Hengduan surface chart , line graph corner table , longitudinal vertical curve table , the standard cross-sectional view of roadbed design tables, pavement design , earthwork number of tables and other graphics -related , and each part of the preparation of the corresponding design manual. Through this design not only understand the various steps of the construction of the road , but also be able to skillfully use AUTOCAD drawing . Keywords : Economic Development Yan'an Expressway to WuQi WeiDi in road design AutoCAD

相关主题
文本预览
相关文档 最新文档