PMP项目管理:项目成本管理练习题3
1.Looking across the majority of industries, during which phase in a project life cycle are most of the project expenses incurred?
A.Concept phase
B.Development or design phase
C.Execution phase
D.Termination phase
对于大多数的产业, 项目费用大多发生在项目生命周期中的哪一阶段?
A.构思阶段
B.开发或设计阶段
C.执行阶段
D.结束阶段
2.Using the table below, the schedule performance index (SPI) for WBS Element P is:
A.1.10
B.0.90
C.0.956
D.1.15
WBS Element BCWS BCWP ACWP
P $1,000 $1,100 $1,150
Q $2,000 $1,800 $2,100
R $1,000 $1,200 $1,050
S $2,000 $1,900 $1,800
用下表数据计算, 工作分解结构WBS要素P的进度绩效指数(SPI)是:
A.1.10
B.0.90
C.0.956
D.1.15
工作分解结构WBS 要素计划执行预算成本BCWS 已执行工作预算成本BCWP 已执行工作实际成本ACWP
P $1,000 $1,100 $1,150
Q $2,000 $1,800 $2,100
R $1,000 $1,200 $1,050
S $2,000 $1,900 $1,800
3.You have estimated and scheduled your project based on the team members you have been assigned and developed the BCWS baseline.However, you have now been assigned new team members who are more experienced and higher salaried than those on which you based your initial estimate.The most
probable impact on project performance would be: A.Negative CV, negative SV
B.Negative CV, positive SV
C.Positive CV, negative SV
D.Positive CV, positive SV
你对项目进行了估算和进度安排,根据团队成员情况, 分配了任务并且制定了计划执行预算成本的基准.然而,分配了新的项目团队成员, 他们比初始估算的成员更有经验,薪水更高.这对项目绩效最可能的影响会是:
A.负的成本偏差CV, 负的进度偏差SV
B.负的成本偏差CV, 正的进度偏差SV
C.正的成本偏差CV, 负的进度偏差SV
D.正的成本偏差CV, 正的进度偏差SV
4.The most precise and accurate technique for determining project costs is the technique.
A.Bottom-up
B.Analogy
C.Budget
D.Modified standards
决定项目成本的最精确的和最正确的技术是什么技术
A.由下而上
B.类比
C.预算
D.修正标准
5.The four types of cost data that are normally accumulated and reported as part of a cost control system are: A.Labor, material, other direct charges, management reserve
B.Labor, material, management reserve, overhead
C.Management reserve, labor, other direct charges, overhead
D.Labor, material, other direct charges, overhead
作为成本控制系统的一部份,要收集并且报告的四类成本数据是: A.人工,原材料,其它直接费用, 管理储备
B.人工原材料,管理储备,管理费用
C.管理储备人工, 其它直接费用, 管理费用
D.人工原材料, 其它直接费用,管理费用
6.The techniques commonly used to determine the profitability of a project include all of the following, except: A.Net present value (NPV) B.Internal rate of return (IRR) C.Payback period
D.Risk assessment model (RAM)
通常用来计算决定项目的获利力的技术包括所有的下列项,除了: A.净现值(NPV)