EPC总承包项目固定总价包干合同预结算管理
- 格式:docx
- 大小:30.19 KB
- 文档页数:5
epc 总价包干合同条款英文回答:EPC, which stands for Engineering, Procurement, and Construction, is a type of contract commonly used in construction projects. In an EPC contract, the contractoris responsible for the entire project, from design and engineering to procurement of materials and construction. The total price of the project is included in the contract, and the contractor is required to complete the project within the agreed-upon budget.One of the key advantages of an EPC contract is that it provides a single point of responsibility. This means that the client only needs to deal with one contractor throughout the project, simplifying the communication and coordination process. The contractor is responsible for managing all aspects of the project, including subcontractors, ensuring that everything is completed on time and within budget.Another advantage of an EPC contract is that it allows for better cost control. Since the total price is fixed in the contract, the client knows exactly how much the project will cost from the beginning. This eliminates the risk of cost overruns and provides greater certainty in budget planning.Furthermore, an EPC contract can provide faster project delivery. With a single contractor responsible for the entire project, there is less potential for delays and conflicts between different parties. The contractor can streamline the construction process and ensure efficient project execution.To illustrate the benefits of an EPC contract, let's consider an example. Imagine a client who wants to build a new power plant. By entering into an EPC contract, the client can hire a contractor who will handle everything from designing the plant to procuring the necessary equipment and constructing the facility. The client doesn't need to worry about coordinating different contractors ormanaging the procurement process. The contractor takes care of all these tasks, ensuring that the project is completed on time and within the agreed-upon budget.中文回答:EPC,即工程设计、采购和建设,是建筑项目中常用的一种合同类型。
从施工角度EPC工程总承包项目应关注的商务管理摘要随着国内工程建设项目高速度高质量发展要求,近年EPC模式项目承接的增加,EPC类项目成为了下一步建筑业发展的重要支撑,此类项目的商务管理工作如何开展及成本如何有效的管控、风险如何防范、商务策划如何创效一直是施工企业需要面对的新课题,比如项目的超概、过程中大量的设计变更及签证,阻碍着项目最终的结算工作。
关键词:一、与传统施工总承包区别工程总承包项目是没有招标清单、没有施工图纸的,取而代之的为发包人要求和方案设计等项目前期立项批复、投资估算、概算等内容。
EPC项目是固定的总价+固定的工期,投标报价时要考虑的是项目的成本+利润+风险。
在传统的施工总承包模式下,按图施工并依据施工合同条款变更由业主主导的设计以寻求更多的利润,是施工现场的重要商务管理工作。
但从EPC项目的合同承包范围就可以知道,施工图设计阶段是对整个项目成本影响最大的阶段,施工阶段的一些设计变更(发包另行要求除外)是工程总承包人应当承担的义务和风险。
因此施工阶段的二次经营不属于工程总承包项目的管理重点。
二、EPC(工程总承包)项目的计价方式按照现行清单和定额计价下浮的方式;按照模拟清单自主报价的方式;按照建设面积单方造价的方式。
无论采用任何一种计价方式,建设过程中严禁超工程总承包合同范围,工程预算或预计结算总价严禁超签约合同价、严禁超批复的投资概算价(调概手续齐全的除外)。
三、EPC(工程总承包)项目各阶段商务管理的重点(一)项目跟踪阶段项目立项以后,依据可靠的营销资源,取得项目推进过程中各个阶段的推进信息。
随时掌握项目招标是否具备条件,项目是依据可研进行招标或是依据初设方案进行招标。
通过取得的可研报告或初设方案及概算为下一步工作的推进提供支持。
(二)投标前期的资源整合通过前期的项目跟踪形成高端对话的良好通道,取得阶段性营销主动权。
即对话关键人物、策划关键路线和事件。
获取项目动态消息,并针对关键问题及时做出应对策略。
epc总价包干最高法随着我国经济的快速发展和城市化进程的加速推进,大量的基础设施建设项目如雨后春笋般涌现。
然而,这些项目的建设往往需要耗费大量的资金和人力资源,因此,如何合理控制项目成本、确保工程质量成为了一个亟待解决的问题。
为解决这一难题,我国引入了EPC总价包干模式,并将其纳入了最高法的相关法律法规中。
EPC(Engineering, Procurement and Construction)总价包干模式是指工程总承包商承担工程设计、采购和施工等全过程的责任,并按照合同约定的总价进行施工。
这一模式的引入,旨在通过一站式服务,提高项目建设的效率和质量,降低投资风险,保证工程的顺利进行。
EPC总价包干模式能够有效降低项目建设的成本。
在传统的分包模式下,各个环节由不同的承包商负责,协调工作难度大,容易导致成本控制不力。
而EPC总价包干模式则由同一家承包商负责全过程的工作,可以更好地协调各个环节,减少资源浪费和成本增加。
总价包干模式下的承包商在工程设计、采购和施工等方面都能够发挥自身优势,从而提高工程的效率和质量,降低建设成本。
EPC总价包干模式能够提高工程建设的质量。
在总价包干模式下,承包商对工程全过程负责,可以更好地控制工程质量。
承包商在进行工程设计时,可以充分考虑工程施工的实际情况,提出合理的设计方案;在采购环节,承包商可以选择优质的材料和设备,确保工程的质量;在施工过程中,承包商可以对施工进度和质量进行全面监控,及时解决问题。
总价包干模式下的承包商拥有全面的控制权,能够更好地保证工程建设的质量和安全。
EPC总价包干模式能够降低投资风险。
在传统的工程建设模式下,由于工程分包给不同的承包商,工期和成本往往难以控制,容易导致投资风险加大。
而总价包干模式下,承包商承担了全部的责任,可以更好地控制投资风险。
承包商在签订合同时,需要对工程成本进行全面的评估和预测,并为工程建设提供相应的担保措施,以确保项目的顺利进行和投资回报。
EPC工程总承包模式下的招标、计价和定标规则解析EPC工程总承包的定义EPC(Engineering-Procurement-Construction),,即“设计采购和施工”模式,又称交钥匙工程总承包模式。
业主与工程总承包商签定工程总承包合同,把建设项目的设计、采购、施工和调试服务工作全部委托给工程总承包商负责组织实施,业主只负责整体的、原则的、目标的管理和控制。
设计、采购和施工的组织实施采用统一策划、统一组织、统一指挥、统一协调和全过程控制。
EPC 工程总承包的投标条件目前EPC工程总承包招标适用依据主要《关于培育发展工程总承包和工程项目管理企业的指导意见》(建市[2003]30号)。
在设置投标条件时可淡化资质管理,实行能力认可,在工程实施时回归资质管理,由有相应资质的单位分别承担设计、施工任务。
招标人可按下列方式之一设置投标条件:具有工程总承包管理能力的企业,可以是设计、施工或项目管理单位;具有相应资质等级的设计,施工或项目管理单位或组成联合体投标,由于目前建筑市场上具有工程总承包业绩单位比较少,在招标时不宜将工程总承包业绩作为投标条件,以促进工程总承包行业的发展;EPC工程总承包一般应明确招标要求EPC招标可以在完成概念方案设计之后进行,也可以在完成设计方案之后进行,既方案未定的EPC工程总承包招标和已定方案EPC工程总承包招标。
无论是哪一种招标,一般应明确招标的需求。
细化建设规模:房屋建筑工程包括地上建筑面积,地下建筑面积、高层、户型及户数,开间大小比例,等车位数量或比例等,市政工程包括道路宽带,河道宽度,污水处理能力。
精细化建设标准:房屋化建设工程包括墙、地各种各种装饰材料的材质种类,规格和品牌档次,机电系统包含的类别,机电设备材料的主要参数,指标和品牌的档次各区域末端设施的密度,家具配置和数量和标准,以及室外工程,园林绿化标准,市政工程包括各种结构层,面层的构造方式,材质厚度等。
划分工作责任:除设计施工以外的其他服务工作的内容、分工与责任。
XX有限公司开发(投资)项目工程预结算管理暂行办法第一章总则第一条根据XX集团《房地产业管理暂行办法》,为提高专业化管理和强化成本(投资)控制,加强工程预结算管理,特制定本办法。
第二条本办法适用于集团公司范围内的固定资产投资项目和集团房地产开发管理中心及所属各项目部(公司)的房地产开发项目。
第三条本办法工程预结算管理的内容主要是指开发(投资)项目的投资估算、设计概算、施工图标准预算和竣工结算。
第二章工程预结算管理原则、机构及审批权限第四条工程预结算管理原则:(一)实行三级管理,即:项目部(公司)编报和被授权执行;房地产开发管理中心审核;成本(投资)控制中心评审,集团核准。
预结算管理实行会审会签制。
(二)集团对工程预结算造价实行事前审计核准、事后督查考评。
(三)集团房地产开发管理中心负责对工程成本(投资)实行全过程控制。
项目部(公司)负责项目建造及营销成本的实施与控制,并建立目标责任制,实施奖罚。
第五条成本(投资)控制中心负责集团公司范围内固定资产投资项目和房地产开发项目的成本控制监督与管理。
工作职责是:(一)审核项目“三算”的总成本和单位成本经济指标;(二)审核项目标准预算、零星工程造价、正式工程总价或单价,审核施工合同中的经济条款;(三)审核竣工结算;(四)审核项目工程和大宗设备材料招标计划书和方案,并组织和督导有关招标工作;(五)参与项目投资阶段的可行性分析报告,设计阶段的规划(建筑)设计方案,工程建设阶段的项目总体开发方案,房屋营销阶段的营销策划与执行方案的评审,发表成本控制方面的意见.(六)参与项目开发中临设方案,单项(专项)设计方案的评审会,发表成本控制方面的意见。
(七)依据新修订的《内部项目及大宗机电设备材料招标管理办法》中的相关规定,组织、参与、指导各项目的招投标工作,做到规范工作程序、保证工程质量,实现提高投资效益的目标。
(八)参与项目成本控制执行结果评价分析.第六条房地产开发管理中心是成本管控的主体责任者,负责集团房地产业的专业管理与督导。
epc 总价包干合同条款英文回答:EPC (Engineering, Procurement, and Construction) is a type of contract commonly used in the construction industry. It is a comprehensive agreement that covers the entire project, from design and engineering to procurement of materials and construction. The main characteristic of an EPC contract is that the contractor takes fullresponsibility for the project, including its cost and schedule.The total lump sum price is a key term in an EPC contract. It means that the contractor agrees to complete the project for a fixed price, regardless of any cost overruns or delays. This provides certainty to the project owner and ensures that the contractor bears the risk of any unforeseen circumstances.The EPC contract typically includes various clauses andprovisions that define the rights and obligations of the parties involved. These may include:1. Scope of work: This section outlines the specific tasks and deliverables that the contractor is responsible for. It includes details such as design specifications, construction plans, and quality standards.2. Schedule: The contract should specify the project timeline, including milestones and completion dates. It may also include liquidated damages provisions in case of delays.3. Payment terms: The contract should clearly state how and when the contractor will be paid. This may include progress payments based on completed work or specific milestones.4. Change orders: Inevitably, changes may arise during the course of the project. The contract should outline the process for handling change orders, including how they will be priced and approved.5. Dispute resolution: To avoid costly litigation, the contract should include a mechanism for resolving disputes, such as mediation or arbitration.EPC contracts are commonly used in large-scale infrastructure projects, such as power plants, refineries, and transportation systems. They provide a comprehensive framework for managing complex projects and ensure that all parties are aligned in terms of project scope, cost, and schedule.中文回答:EPC(工程、采购和施工)是建筑行业常用的一种合同类型。
工程预结算管理办法一、总则为加强公司工程预结算的规范化管理,提高工程预结算工作的效益,保障公司合法权益,合理地确定工程造价和有效地控制工程造价,并结合工程造价形成的特点,制定本管理办法。
二、预结算管理原则1、实事求是原则:工程预结算工作必须以客观事实、工程经济合同和有关规定为依据,从严把关。
2、审核原则:工程预结算及进行总价包干的工程预算在最终实际价款确定前需经过核算部全面详细的审核,并经财务部及相关领导审核后最终确定。
3、合理低价原则:工程预结算工作应以客观事实、工程合同为依据,充分理解、灵活运用当地造价管理规定,在执行国家及当地有关规定的同时,充分利用市场竞争情况、甲方自有资源等因素,处理好质量、工期、成本的关系,坚持以合理最低价格的原则确定工程造价。
4、准确高效原则:工程预结算工作中的各项计算应准确、清晰、合规;同时工程预结算工作应保持较高良好的工作效率,及时做到事完清帐,以适应工程招投标工作、成本核算、工程管理等多方面的需求。
5、手续齐全原则:工程预结算工作中必须严格执行公司的有关规章制度,资料应具备签字、盖章等,手续务必齐全,否则不得办理预、结算。
三、工程预算的编制与审核程序1、新项目在正式开工前原则上应完成施工图预算,为在施工过程中材料采购和成本控制提供可靠依据。
对于规模较大的或复杂的项目至少要在开工前完成即将先开工的重要分部或分项工作的施工预算;2、工程施工图齐备后,应立即要求承包商编制施工图预算,同时公司预算部或负责该项目的项目经理应督促项目专职预算人员编制施工图预算,在编制完毕后,由项目经理审核签字后报公司预算部,公司预算部对施工图预算进行核对并签署意见,由公司预算部报公司分管副总经理,公司分管副总签字后报送公司总经理,由公司总经理批准执行。
工程建设项目整体预算以及个别特殊情况的单项、单位、分部分项工程预算额较大的还应召开总经理办公会议(监事会列席)最终决定工程造价,报董事会批准执行。
EPC总承包项目的成本控制和结算管理发布时间:2021-05-17T10:27:16.977Z 来源:《基层建设》2021年第2期作者:胡名霞[导读] 摘要:随着社会经济的发展,我国的EPC总承包项目建设越来越多。
常德市天城规划建筑设计有限公司湖南常德 415000摘要:随着社会经济的发展,我国的EPC总承包项目建设越来越多。
EPC总承包项目成本管理的主要目的是为了提高整个工程项目的经济效益,其内容涉及到一项工程项目的资金运转、税务、财务等诸多方面。
基于此,对EPC总承包项目进行了概述,然后对其财务管理中存在的不足进行了详细分析,最后对如何提高其财务管理水平提出了几点措施,以供参考。
关键词:EPC;总承包项目;成本管理引言通过对相关研究资料分析可知,EPC总承包是先进性的项目承包方式,根据合同内容对若干施工环节进行思考,将不同项目施工环节进行承包,从而让工程项目得到更好的质量控制。
基于这样的情况,承包商应该重视项目管理质量的提升,促使项目建设得到更高层面的施工质量保障,以利于EPC总承包得到更好的应用。
1EPC模式的概念EPC模式指的是工程总承包产业,其被广泛应用于国际通用工程中,各字母对应的具体内容为:E-设计、P采购、C-建设。
具体而言,设计指的是形成内容总体策划并细分至各设计工作中;采购指的是材料以及设备的选择与入场;建设指的是创建工程实体的环节,如施工、安装等。
顺利开展EPC模式的核心体现在两方面,除分包商专业资质外,还要求将标准化过程控制工作落实到位,从而创造高品质、高效率的工程项目。
2EPC工程总承包项目成本管理存在的问题2.1缺乏先进的管理理念,成本和进度管理粗放和发达国家相比,我国EPC工程总承包起步较晚,所参与的国际EPC工程总承包项目不多,因此,在这方面累积的经验和发达国家相比有一定的差距,导致我国企业在EPC工程总承包成本管理方面经验欠缺,成本管理粗放,成本控制力度不足。
2.2内部掌控体系有待完善当前,EPC总承包项目财务管理相关的工作并没有得到承包企业的重视,因此,造成内部掌控系统建立并不是非常完善,如此一来,极有可能导致工程项目开展过程中出现不科学、不合理的设置,在预算管理、财务管理等方面缺乏一个统一的标准,使得执行与实际需求二者产生分歧,甚出现背离现象。
EPC总承包项目固定总价包干合同预结
算管理
摘要:目前,在对EPC总合同采用固定总价包干方面存在许多问题,该合同适用于前期条件清晰、建设内容明确、技术方案成熟的项目。
但是,在实施过程中,EPC合同往往是在初步设计批复后签订的,方案和图纸都是初步设计深度,不够深入,工程量可能存在很大误差,进而给施工图预结算编制审核带来困难和争议。
关键词:EPC总承包;固定总价;预结算
引言
EPC总承包商是设计、采购和施工的总承包商,负责设计、采购、施工、测试等服务,并对项目的质量、安全和工期负全部责任。
EPC总承包商为了在市场上具有竞争力,必须严格控制项目成本。
对建设单位来说,基于固定总价模式,需要确保项目顺利实施,减少工程变更,完成既定工期、投资等目标。
1EPC总承包模式的特征
(1)在EPC总承包模式下,建设单位(同时委托监理单位)对施工图纸进行审查,对建筑工程的关键质量点进行验收,对建筑工程的进度、安全等方面进行检查,建设结果是否与合同规定相符合。
(2)EPC总承包项目的总承包商需要对建筑工程的设计、采购和施工三个环节负责,同时也需要加强对建筑工程的质量以及涉及所有专业的分包商进行管理。
换句话而言,在EPC总承包项目中总承包商占据着十分重要的地位。
(3)EPC总承包模式下,在建筑工程的方案设计、材料选购、施工环节以及项目合同管理全部需要总承包商负主要责任,总承包商将面临各种问题,并承担EPC总承包项目中的所有风险。
2EPC总承包项目固定总价合同预结算存在问题
2.1项目范围的不确定性
从合同签订、设计、采购、交付到项目接收和验收的整个实施过程的管理水
平影响EPC项目预结算工作,根据总价包干合同原则,合同双方的价格计算主要
依据的是工程范围和工程质量标准的定义,而合同范围的确定往往没有可靠的依据。
初步设计文件作为EPC总承包商投标方案及投标报价的基础,建设单位与EPC总承包商应严格按初步设计内容和《发包人要求》执行和深化施工图设计,
从类似工程项目实践看,未按初步设计内容深化施工图设计或未按《发包人要求》实施的,将造成项目范围的不确定性,进而给后续工程合同管理和变更管理造成
困难并导致合同价格的混乱,引起合同双方纠纷,影响项目顺利实施。
2.2 EPC总承包项目预结算问题
对于EPC总承包项目,由于项目体量大、专业多、复杂等特点,施工图预算
普遍存在滞后情况或未按合同约定时间与施工图同步提交。
对于需要送交政府财
政部门审核的施工图预算,建设单位应明确施工图预算送审时间及相应措施,比
如可在招投标及合同阶段设置施工图预算送审延期的惩罚性条款,以确保施工图
预算能够及时送审,避免项目已开甚至已完工、但施工图预算仍未送审的情况出现。
现有部分EPC总承包项目已完工(或接近完工),但施工图预算仍未送审情况。
如果合同约定以施工图预算包干作为合同价,且结算时不再重复计量计价计算。
故建设单位在施工图预算审核时,应该结合现场实际进行审核(预算按结算
标准审核),防止出现施工图纸与现场不一致时的计价错误。
例如松木桩梢径、
水泥搅拌桩水泥掺入量、土石方开挖回填等,审核人员应深入施工现场进行工程
量的核对,复核关键工序、隐蔽工程的佐证材料,实事求是地审核。
对于以初步设计批复概算作为固定总价包干合同的EPC总承包项目,如果项
目实施阶段出现大量针对于初步设计方案和《发包人要求》的调整,且这些调整
都将对工程组织、工程计划、工程进度及工程成本产生严重影响。
由于采用固定
总价包干的合同模式,大量的设计调整将导致整个EPC总承包合同体系的混乱,
进而给项目预结算带来困难。
3EPC总承包项目固定总价合同预结算管理对策
3.1明确建设单位与EPC总承包商之间的责任划分
建设主体各方的权力、责任与义务在合同中均应有明确约定,建设单位与总
承包商应严格按各自责任与义务完成相关工作,避免越权行为或工作缺失、不作
为现象发生。
从类似工程项目实践看,越权行为主要表现在建设单位管理上,而
工作缺失和不作为主要表现在总承包商。
不同的工程项目、不同的合同条件有着
不同的工程管理逻辑,尤其是EPC总承包项目,建设单位管理人员如果沿用其他
建设模式项目管理思路(如平行发包模式),将造成总承包商的不作为,形成对
建设单位管理的依赖性,以建设单位的管理代替本职管理工作。
3.2总承包商做好项目完工结算工作,减少回款风险
总承包商在EPC总承包项目完成之后,需要加强完工财务结算工作的实效性,以及需要开展工程验收工作和完工结算工作,做好项目完工验收对应的合同款项,并明确完工验收的时间,确定质保金回款时间,从而可以有效减少质保金回款风
险问题的发生。
除此之外,也需要在EPC总承包项目完工结算资料的收集、汇总
和存储,尤其是工程变更以及索赔等问题的记录。
另外,总承包单位也需要遵守
合同规定的时间,完成相关审批手续,并融入阶段性结算范畴内,进而保障在规
定的时间内完成结算工作,达到理想的结算效果。
同时,也需要保质保量履行
EPC总承包合同约定的义务和责任,以此获得合同约定的赶工措施费、质量奖等
奖励费用。
此外,通过质保金保函代替质保金的方式,减少资金占用,从而可以
保障质保金的提前回收。
3.3工程变更、签证与索赔
调整是指通过书面通知或经发包人批准对工程所做的修改,通常反映在施工
过程中的设计修改中,增减是合同价格调整的一个重要组成部分。
如果发包人的
指令要求进行设计变更,则总承包商必须首先进行成本计算。
如果需要增加费用,则必须及时报告变更预算,在安排执行之前获得书面批准。
未经批准,不得安排
变更的执行,否则结算将是被动的。
签证是发包人代表和承包商代表就某些责任
事件签署的证明,通常指非市场零星工作、零星工作、使用零星机器、施工的增加等。
但建设单位在处理工程变更问题上往往存在变更程序缺失、变更手续滞后等问题,未能严格按相关变更管理办法执行,上述做法往往给合同执行埋下隐患。
此外,部分建设单位工程变更管理意识淡薄,对相关变更要求理解不到位。
且由于EPC总承包合同下的工程变更与优化定义模糊、难以界定,建设单位在工程进度和投资控制压力下,往往趋向于将工程变更按优化程序处理,则工程调整书面指令不能及时下达,导致后续建设单位调整合同变更价格时缺乏必要程序和合法依据,难以区分合同双方的责任和义务,更在结算审核时无法计取相关费用,造成后续结算争议。
3.4总承包商做好税务筹划管理工作,减少涉税风险发生
对发票开具时间进行统一管理,应要尽可能接近收款时间,进而能够有效减少未收到工程款而导致税款提前流出问题的发生。
除此之外,也需要对分包发票的取得时间进行统一管理,应要匹配总包分包开票时间以确保分包发票的税额抵扣。
对EPC总承包项目所在区域的税收相关政策有详细的了解,按照当地税收相关法律法规,合理缴纳各项税款。
财务管理人员应要对相关税收法律法规有一定的了解,及时掌握最新的税收政策,在符合相关税收政策的基础上,享受国家所下发的各项税收减免优惠,从而能够有效降低企业税负,使企业获得更多的经济收益。
3.5总承包商加强分层预算编制管理
项目接管后,总承包商造价人员应与设计人员合作编制设计预算,并根据合同界限设计完成施工组织设计。
造价人员应与设计人员积极合作,努力实现设计-施工的深度融合,计算设计图纸的价格,共同审阅图纸,完成技术交付。
在实践中,设计上的某些缺陷可以通过对工程预算过程的逐案审查加以纠正和补充。
结束语
鉴于上述情况,建设单位和总承包单位都希望EPC总承包合同采取总价包干方式,从而实现各自的目标诉求,但由于EPC总承包项目固有的特点和工作进展情况,项目在招标、合同订立、建设实施和结算过程等几个阶段都有争议,需要各方加以重视。
同时,建设单位在确定合同形式时,应结合EPC总承包项目情况加以考虑,合理确定合同价格形式。
参考文献
[1]魏燕文.EPC总承包项目的成本控制和结算管理[J].建筑技术开发,2019
[2]费亮嵘.EPC总承包项目价款结算管理的特点及管控建议[J].上海建设科技,2019
[3]齐海帆,李超,汪芸.EPC总承包项目成本控制和结算管理[J].现代国企研究,2018
[4]刘奕农.简述EPC总承包项目成本控制和结算管理[J].中外企业家,2018
[5]段梅,叶武.EPC总承包项目成本控制和结算管理[J].绿色环保建材,2018。