施工组织设计方案(新修改)

  • 格式:doc
  • 大小:323.50 KB
  • 文档页数:67

---

--- 汇园国际会所铝合金门窗、幕墙工程

东莞市华锋幕墙装饰工程有限公司

---

--- 目 录

目 录·····················································2

第一章 总则·····················································4

一、工程概况··················································4

二、招标标段工程范围··········································4

三、工程承包方式··············································4

四、工期目标··················································4

五、质量目标··················································4

六、安全、文明目标及其它目标··································4

七、编制依据··················································4

第二章 施工方案、施工方法·······································5

一、铝合金门窗加工、安装施工工艺······························5

二、隐框玻璃幕墙施工工艺······································10

三、金属幕墙施工工艺··········································29

四、铝塑板幕墙施工工艺········································37

五、钢结构施工工艺············································44

六、防雨、防台风、防雷击等具体施工措施························47

1、防雨施工措施···········································47

2、防台风施工措施·········································47

3、防雷击的施工措施·······································47

4、防雷施工具体做法·······································47

第三章 施工进度计划·············································48

一、确保工期的技术、组织和经济措施····························48

1、技术措施···············································48

2、组织措施···············································48

3、高素质劳动人队伍·······································49

4、质量保证体系···········································49

5、经济措施···············································49

二、各工序的开竣工时间和搭接··································49

第四章 工程质量的技术组织措施····································50

一、质量保证体系··············································50

1、质量手册···············································50

2、程序文件···············································50

3、作业指导书·············································51

二、质量控制办法··············································51

1、技术管理措施···········································51

2、生产质量管理措施·······································51

3、工厂加工质量管理措施···································51 ---

--- 4、半成品包装质量管理措施·································52

第五章 组织机构及劳动力计划····································52

一、项目管理机构和管理人员职责·······························52

二、项目经理职责·············································54

三、施工主管职责·············································54

四、质量员职责···············································54

五、安全员职责···············································54

六、材料员职责···············································55

七、劳动力需用计划···········································55

第六章 材料供应计划············································56

一、主要材料需求计划·········································56

二、加工生产计划·············································56

第七章 安全文明施工············································57

一、安全保证体系及责任制度···································57

1、严格执行ISO14001:1996和OHSAS18001体系标准··········58

2、安全保证体系··········································58

3、安全责任制度··········································59

二、安全文明施工的目标·······································59

1、安全施工目标··········································60

2、文明施工目标··········································60

三、环境保护的措施···········································61

四、安全文明施工技术组织措施·································61

1、文明施工技术组织措施··································61

2、文明施工现场管理措施··································62

3、施工文明保证措施······································63

4、现场材料管理制度······································64

5、材料摆放管理制度······································65

6、储存地点环境要求······································65

7、安全施工技术组织措施··································66

8、现场安全生产技术措施··································66

9、现场设施检查··········································66

10、施工设备检查·········································66

11、人身安全防护措施·····································66

12、防火安全措施·········································67

五、安全档案资料制度··········································67

第一章 总 则 ---

--- 一、工程概况

1、工程名称:汇园国际会所铝合金门窗、幕墙工程

2、建设单位:惠州市建汇地产有限公司

3、设计单位:深圳市中泰华翰建筑设计有限公司

4、施工单位:博罗县圆洲建筑工程公司

5、工程地点:博罗县园洲镇园洲大道

6、建设概况:汇园国际会所铝合金门窗、幕墙约2375.53㎡。其工程主要包括玻璃隐框幕墙、铝塑板墙面、铝塑板包钢结构、屋顶铝塑板收口、铝塑板吊顶、50系列铝合金上悬窗、50*25铝方通固定窗

二、招标标段工程范围

1、汇园国际会所铝合金门窗、幕墙安装工程。

2、以上范围铝合金门窗、幕墙工程的全部工作:包括施工准备、施工图的深化设计、制作加工、包装防腐、装、卸、水平运输、安装、清洁、临时设施搭设、水电费、应纳税金、包验收。

三、工程承包方式

承包方式为大包干,即包工、包料、包质量、包工期、包安全、包文明施工。

四、工期目标

开工:乙方按甲方要求配合工程进度,乙方按甲方现场代表通知(具备安装条件)。

五、质量标准

质量标准:符合中华人民共和国《建筑装饰装修工程质量验收规范》(GB50210-2001)、《铝合金门窗工程设计、施工及验收规范》(DBJ15-30-2002)、《玻璃幕墙工程技术规范》(JGJ102-2003)的合格标准。

六、安全、文明目标及其它目标

1、安全目标:实现“五无”目标(无死亡、无火灾、无重伤、无中毒、无倒塌),严格按照建设部“一标四规范”组织施工。

2、文明施工:严格执行惠州市和建设部发布的文明施工管理的有关规定。达到惠州市文明标化工地标准要求。