Frozen brine flow reactor to reduce event tree
B High temperature D Restore the coolant flow rate
①Continue to
alarming device
0.75 E Shut down the
operate
Safety training professional ability
Safety training-2013
2、Event tree analysis steps (1)Determine the system and its components; (2)Analysis of each subsystem; (3)Prepare the event tree; (4)Quantitative calculation;
Safety training professional ability
Safety training-2013
3、Typical cases Frozen brine flow reactor to reduce event tree analysis
The reaction is exothermic, therefore in the jacketed reactor into the frozen brine to remove heat of reaction。If frozen brine flow rate reduce, can make the reactor temperature rise, reaction speed, so that the reaction is out of control。There are installed in the reactor a temperature measurement control system, and with the frozen brine inlet valve connection, according to the temperature control of frozen brine flow rate。