工程量计算书

  • 格式:doc
  • 大小:189.50 KB
  • 文档页数:7

工程量计算书

项目

编码 项目名称 单位 数量 计算公式及过程

1 建筑面积 m2 3752.60 S1=3.14×1.77²×0.5+5.19×8.3+24.24×6.54+18×7.1+0.5×3.14×1.47²+14.94×4.54+1.2×14.64+14.4×7.1=525.353

S2~S6= S1+0.95×2+0.5×(1.8×1.2+1.2×0.6+0.25×3.14×1.2²)+0.5×3.14×1.12²=531.228

S7=531.228+L梯×0.12+S梯=571.098

S总=S1+5×S2+S7=3752.60

一 土石方工程

2 人工综合土方

三类 湿土 m3 327.61 B=1.2 C=0.3 H湿=0.60

L=38.4+14.6+38.4+18.9-2.7+1.35×3.14+2.4+4.3+23+3.95+21.95+13.7+13.4+5.3×7+4.1×6+1×11+5.3×4+3.3×4+1.7=303.339

V=(1.2+2×0.30)×0.60×303.339=327.60612

3 人工综合土方

三类 干土 m3 300.31 B=1.2 C=0.3 H干=0.55

L=38.4+14.6+38.4+18.9-2.7+1.35×3.14+2.4+4.3+23+3.95+21.95+13.7+13.4+5.3×7+4.1×6+1×11+5.3×4+3.3×4+1.7=303.339

V=(1.2+2×0.30)×0.55×303.339=300.30561

4 湿土排水 m3 327.61 B=1.2 C=0.3 H湿=0.60

L=38.4+14.6+38.4+18.9-2.7+1.35×3.14+2.4+4.3+23+3.95+21.95+13.7+13.4+5.3×7+4.1×6+1×11+5.3×4+3.3×4+1.7=303.339

V=(1.2+2×0.30)×0.60×303.339=327.60612

二 桩基础与加固工程

5 C20 沉管灌注桩 m3 474.39 V=180×3.14×0.213²×18.5=474.39

6 桩尖埋设 个 180

三 砌筑工程

7 碎石垫层 m3 38.36 S=(3+3.3-1.2-0.24)×(12-0.24)-(3+3.3-1.2-0.24)×2

×0.24=54.8

V=54.8×0.1×7=38.36

8 标准砖基础 m3 90.6 VA=(125.57+6.3+3-2×0.37-3)×0.74×0.37=35.9

VB=(4×12.8-4×0.37+5×13.4-5×0.37+8.3-0.185+6.3

-0.185+3×18+12+1.95-22×1.37)=51.5

VDL1=0.24×0.75×6.195=1.1

VDL2=0.37×0.75×7.58=2.1

V=VA+ VB+VDL1+VDL2=90.6

9 M5 混合砂浆多孔砖内外墙(2~4层) m3 448.8 L外=0.5×3.14×2.7+0.5×3.14×3.3+12+6.3+5+38.4

+18.9+4.95+1.2+18+1.3+4.3=119.56

L内=(6.3-0.24)×11+(4.3-0.24)×4+(24-0.24)+(6.1-0.24) ×6+24+2.4-0.24+18+0.24+4.95-0.24=184.0

V窗=2×1.5×2.1+2×1.5×2.7+2×1×2.7+18×1×2.7+0.9

×1.8+3×1.5×1.8+2×0.6×1.5+1.5×1.8+2.76×1.2+3

×1.22+18×1.82=148.6

V梁=V圈+V矩=2.62+15.36=17.98

V过=0.36 , V柱=11.47

V=0.24×[(119.56+184.0)×(3.2-0.16)-148.6]-17.98-0.36

-11.47=156.0

V`=3×(156.0-6.4)=448.8

10 M5 混合砂浆多孔砖弧形内外墙(2~4层) m3 19.2 L弧=9.42

V窗=2×0.6×0.15=1.8

V过=0.24×0.12×(0.6+0.24)=0.05

V=0.24×[9.42×(3.2×0.16)-1.8]-0.05=6.4

V`=3×6.4=19.2

11 M7.5 混合砂浆多孔砖内外墙(5~7层) m3 452.72 V窗=2×1.5×2.1+2×1×2.1+2×1.5×2.7+18×1×2.7+2×1

×2.7+2×0.6×1.5+0.9×1.8+3×1.5×1.8+1.5×1.8

+2.76×1.2+3×1.22+18×1.82=152.8

L(3.2m)=38.4+24+1+8+184.97-4.95-2.1-4.3-2.4=242.59

L(4.3m)=6.3+2+3+6.3+2+4.3=23.9

L(6.6m)=4.95×2+3.3+4.3×2+2.7+0.5×3.14×6=33.92

V梁=V圈+V矩=22.41, V过=0.34, V柱=12.85

V=0.24×[242.59×(3.2-0.16)+23.9×(4.3-0.16)+33.92×(

6.6-0.16)-152.77]-(3.68+18.73)-0.34-12.85=181.0

V`=181.0+2×149.3=479.6

V``=479.6-26.88=452.72

12 M7.5 混合砂浆多孔砖弧形内外墙(5~7层) m3 26.9 V=0.24×[9.42×(6.6-0.16)-1.8]-0.24×0.12×2×(0.6+0.24

)=14.1

V`=14.1+2×6.4=26.9

13 M10 混合砂浆多孔砖内外墙(底层) m3 450.6 V窗=2×1.5×2.1+2×1.5×2.7+18×1×2.7+2×1×2.7+2.76

×2.7+1.5×1.2+0.9×1.8+3×1.5×1.8+2×0.6×1.5+1.5

×1.8+3×1.22+18×1.82=154.5

V梁=V圈+V矩=17.98, V过=0.32, V柱=11.47

V=0.24×[(119.56+184.0)×(3.2-0.16)-154.51]-17.98

-0.32-11.47=154.6

V`=(152.6-4.4)×3=450.6

14 M10 混合砂浆多孔砖弧形内外墙(底层) m3 13.2 V=0.24×[0.5×3.14×3.3×(1.6-0.16)+0.5×3.14×2.7×(3.2

-0.16)-1.8]-0.24×0.12×(0.6+0.24)=4.4

V`=3×4.4=13.2

四 混凝土和钢筋混凝土

15 C10混凝土垫层砼 m3 36.84 V基=1.2×275.02×0.1=33

V厕=54.82×0.07=3.84

V=33+3.84=36.84

16 钢筋混凝土带形基础m3 138.0 VA=(1×0.3+0.5×0.3)×131.13=59.0 砼 VB=(1×0.3+0.4×0.3)×188.11=79.0

V=59.0+79.0=138.0

17 基础梁砼 m3 4.9 V=[(4.95-1.2×0.6)×2+3+(1.8-0.6-0.3)]×(0.3×1+0.45

×0.4)=4.9

18 C20矩形柱砼 m3 81.9 V1~6=3.2×(9×0.24×0.24+0.5×9×0.24+29×0.24×0.24+3

×0.35×0.3)=11.5

V7=6.6×(3×0.24×0.24+3×0.24×0.24+0.35×0.3×2)+(21

-6×3.2)×2×0.24×0.24+3.2×(6×0.24×0.24+9×0.5

×0.24+24×0.24×0.24+1×0.3×0.35)=12.9

V=11.5×6+12.9=81.9

19 C20矩形梁砼 m3 19.4 V1~6=1.58+0.23+0.34+0.1+0.37=2.62

V7=1.58+0.44+0.34+0.5+0.16+0.66=3.68

VL1=11×0.3×0.24×2=1.58

VL2=1×0.7×0.24×2=0.34

VL3=1×0.58×0.24×3.14×1×1=0.44

VL4=(1×0.47)/(0.7×0.24×2)=0.23/0.34

VL5=(1×0.47)/(0.7×0.24×3)=0.34/0.5

VL6=(1×0.47)/[0.7×0.24×(1.05-0.12)]=0.1/0.16

VL6`=(1×0.33)/[0.58×0.24×(4.95-0.24)]=0.37/0.68

20 圈梁砼 m3 111.0 VQL1=(0.122+0.242)×(6.3×3+2+4.3)=1.8

VQL2=0.242×[(6.3-0.12)×11+(4.3-0.12)×4+4.3+4.95+(

4.95-0.12)+(5.1-0.12)×6]=7.4

VQL3=0.24×0.33×(38.4+12+1+17.7)=5.5

VQL4=0.24×0.3×(4.95+3.3)×2+0.24×0.3×(4.3+2.7)×2

=2.2

V梯1=0.24×0.3×3.14×1.65=0.4

V梯2=0.24×0.3×3.14×1.35=0.3

V1~6=1.8+7.4+5.5+0.4+0.3=15.4

V7=1.8-2×(0.122+0.242)+7.4+5.5-14.4×0.24×0.33+14.4

×0.24×0.62+0.4+0.3+2.2=18.8

21 楼梯砼 m3 193.1 楼梯1: S底=2.97×1.45=4.3

S标=3.14×0.25×(3.3-0.24)2+0.12×(3.3-0.24)+(

9×0.27+0.24)×(3.3-0.24)=15.9

S顶=3.14×0.25×(3.3-0.24)2+0.12×(3.3-0.24)+(

9×0.27+0.24)×(2.7-0.24)=12.2

S=4.3+15.9×6+12.2=111.9

楼梯2: S标=3.14×0.25×(2.7-0.24)2+0.12×(2.7-0.24)+(

9×0.27+0.24)×(2.7-0.24)=11.6

S=11.6×7=81.2

S总=111.9+81.2=193.1

22 雨篷1砼 m2 2.29 S1=2.76×(0.95-0.12)=2.29

23 雨篷2砼 m2 3.83 S2=(1.8-0.12)×(2.4-0.12)=3.83

24 雨篷3砼 m2 1.97 S3=0.5×3.14×(1+0.12)2=1.97