How to start the Takt Time Calculation Based On Product and Process Design怎样根据产品和制程设计计算节拍时间
Scenario 1: Product design is 6 pcs per one PCB panel. The Process Takt Time will be every 12 second a panel. Besides, your process design is using a pallet to place 4 panels, then your Process Takt Time is 48 second a pallet. If 2 line running, process Takt time will be 96 sec. 情节1:产品设计为每块PCB板由 6 块小板组成,节拍时间是每块PCB板 12 秒; 制程设计治具 同时放置 4 块PCB板,则制程的节拍时间是 48 秒/治具。如果同时有 2 条生产线生产, 制程的节拍时间则为 96 秒。
Key Note from Sensei: 老师的重要提示: • To understand the above WIP definitions, go to The Genba and perform your own work towards Establishing the right WIP quantities. This is the Only way you can understand the definition. 要理解WIP定义,你需要去到现场在工作中实践正确的WIP数量。 这是让你理解这个定义的唯一方法。
9
What is Standard WIP 什么是标准WIP • WIP means INVENTORY. INVENTORY is Basically ‘bad’.