深挖路堑安全专项施工方案
- 格式:doc
- 大小:306.00 KB
- 文档页数:41
目 录
1 编制说明 ................................................................ 1
1。1编制依据 .......................................................... 1
1.2编制原则 ........................................................... 1
1。3适用范围 .......................................................... 2
2工程概述 ................................................................ 2
2。1工程概况 .......................................................... 2
2。2工程地质特性 ...................................................... 2
2。3自然气候 .......................................................... 3
3 深路堑施工人员、设备配备 ................................................ 3
3.1人员配备 ........................................................... 3
3.2设备配备 ........................................................... 4
4、施工工艺及方法 ......................................................... 5
4.1路堑开挖 ........................................................... 5
4.1。1土质路堑开挖施工工序 ........................................ 5
4.1。2施工工艺及技术要求 .......................................... 5
4.2路堑挡土墙 ......................................................... 7
4。2。1工艺流程 ................................................... 8
4。2。2基坑开挖 ................................................... 8
4。2。3安装模板 ................................................... 8
4.2。4混凝土浇筑 .................................................. 8
4。2。5沉降缝设置 ................................................. 9
4。2.6泄水孔设置及墙背回填 ....................................... 10
4.3路堑桩板墙 ........................................................ 10
4。3.1工艺流程 ................................................... 10
4.3。2准备工作 ................................................... 10
4.3。3锚固桩施工 ................................................. 10
4。3。4灌注锚固桩身砼 ............................................ 11
4。3。5桩间挡板施工 .............................................. 12
4。3.6墙后回填 ................................................... 12
4.3.7路堑桩板墙施工注意事项 ...................................... 13
4.4框架锚杆 .......................................................... 14
4.4。1技术要求 ................................................... 14
4.4.2施工要求 .................................................... 14
4.4。3 施工安全措施 ............................................... 16
4.5预应力锚索 ........................................................ 17
4.5。1材料 ....................................................... 17
4.5.2施工准备 .................................................... 17
4.5。3锚索施工工艺流程 ........................................... 18
4。5。4锚索施工 .................................................. 18
4.6深挖方路堑边坡监控 ................................................ 21
4.7路堑开挖的注意事项 ................................................ 21
5安全组织机构 ........................................................... 23
6危险因素及应对措施 ..................................................... 25
6。1重大危险源的识别 .................................................. 25
6.2重大危险源预防措施 ................................................. 25
7 特殊季节和夜间施工安全措施 ............................................. 33
7.1雨季施工 ........................................................... 33
7.2高温季节 ........................................................... 33
7.3夜间施工 ........................................................... 34
8 文明施工与环保措施 ..................................................... 34
9 应急预案 ............................................................... 34
9。1应急指挥机构 ...................................................... 34
9。2下设机构及职责 .................................................... 35
9.3事故应急救援程序 ................................................... 36
9.3。1事故报告与报警 ............................................. 36
9。3.2应急程序 ................................................... 36
9。4对应急救援工作的要求 .............................................. 37
9。5施工现场的应急处理设备和设施管理 .................................. 37
9.5。1应急电话 ................................................... 37
9。5.2急救箱 ..................................................... 38
9。5.3其他应急设备和设施 ......................................... 38中交三航局 深路堑专项施工方案
1 深路堑专项施工方案
1 编制说明
1.1编制依据
1.1《危险性较大工程安全专项施工方案编制及专家论证审查办法》(建质【2004】213号)
1。2《建设工程安全生产管理条例》中华人民共和国国务院令第393 号;
1。3《铁路路基工程施工安全技术规程》(TB10302—2009);
1。4《铁路路基工程施工质量验收标准》(TB10414-2003);
1.5《铁路混凝土工程施工质量验收标准》(TB 10424—2010);
1。6深茂铁路JMZQ—1标合同段路基施工设计图纸;
1.7深茂铁路有限责任公司下发的标准化文件汇编;
1.8我单位对施工现场实际情况踏勘、调查资料;
1。2编制原则
(1)遵循国家和地方政府现行有关的土地、环境保护、水土保持、水利与水资源、矿产资源等方面的法规、条例和国家及铁道部关于安全生产、技术标准、工程质量等方面的规定要求。
(2)充分满足建设单位要求的竣工工期和工程质量的要求.
(3)结合工程特点,统筹安排,本着突出重点难点,方案、措施得力的原则,建立良好的施工顺序,优化人、物、材等资源配置,实现最佳综合效益。