Form-08-联合起重吊装作业计划Complex Lifting Plan
- 格式:doc
- 大小:70.76 KB
- 文档页数:2
Location
Company Name
RME
Date
Description of the Lift
Load Details
Type of Lift:Single LiftTandem (Double) Lift
Details of Crane
Crane One
Crane Two
YesNo
Responsibilities
1.ALL CRANES MUST HAVE A VALID IN DATE TEST CERTIFICATE BEFORE OPERATIONS BEGIN.
2.CRANE INSPECTION CHECKLIST MUST BE COMPLETED BEFORE LIFTING COMMENCES.
In Case of Night Shift, Do You have Approval and all Safety Arrangements? YesNo
Tag Lines Required
Wind Speed < 9.8m/s
Any Electrical Hazards
Type
Yes
No
Type
Maximum Weight of the Load (A)
Weight of Rigging/Lifting Equipment & Hook Block (B)
Total Weight of Load to be Lifted (C ) = (A+B)
Crane Capacity at Maximum Radius of Lift (SWL) (D)
Type of Crane / Capacity
Maximum Boom Length
Counterweight
Boom Length – Luffer/Fly
Maximum Radius of Lift
Outrigger Centres
Load Calculation
Crane One
Crane Two
CRANE OPERATOR
Signed
RIGGER(S)
Signed
Site Manager or Competent Designated Person
Name:
Signature:
Date:
Any questions or queries for the above Lifting schedule, please consult the Lifting Operations Manager
Percent Crane Capacity at Maximum Lift Radius (C/D)%
No. of Lifting Points (in case of Tandem Lift)
Types of Lifting Gears to be used: (Spreader Bar, Shackles & Slings)
Yes
NoБайду номын сангаас
Type
Yes
No
Structural Hazards
Load < 85% of Rated Load Capacity (BS7121)
Crane and all Lifting Gears Certified by 3RDParty?
Type
Yes
No
Type
Yes
No
Type
Yes No
Limit Switches, SLI, Brakes, Angle Indicator is Working? YesNo
Flag Man, Banks Man, Barricades, Safety Signs in Place? YesNo
Energized Power Lines Within Boom Radius? YesNo
3.LIFTING EQUIPMENT MUST BE CHECKED, CERTIFIED AND COLOUR CODED BEFORE USE.
4.LIFT SPECIFIC TOOLBOX TALK TO BE CONDUCTED BY ALL INVOLVED IN THE LIFT
APPOINTED PERSON/RIGGER 1 -prepares lift plan.
AP or Rigger 1, Lift Supervisor, Slinger Signaler/Rigger and Crane Operator sign on to the lift plan
A/P OR RIGGER 1
Name
Signed
LIFT SUPERVISOR
Name
Signed
Ground Firm & Level
Any Underground Hazards
Crane and Lifting Gears Inspection Sticker not Expired?
Type
Yes No
Type
Yes
Type
Yes
No
No
Risk Assessment and Marked Plot Plan attached (required)
LIFT SUPERVISOR -receives lift plan and checks the crane(s) are configured as per the lifting plan.
SITE MANAGER OR HIS COMPETENT DESIGNATED PERSON -are involved in the planning process i.e. identification of load weights, lifting points etc.