惠生工程(中国)有限公司

EU Furnace 310-H-109 for Ethylene Expansion Project

扬巴二期新增乙烯裂解炉项目

Non-Destructive Testing Construction Plan

无损检测施工方案

文件编号:011060062-QM-0101-001

03 011060062-QM-0101-001 Li Weihua Zhu Wenjing Chen Ruming 2009-12-22

Rev. File name Prepared Checked Approved yyyy-mm-dd 版本号文件编号起草人审核人批准人发行日期

目次

1PREPARATION BASIS 编制依据 (3)

2GENERAL 工程概况 (4)

3PROJECT ORGANIZATION SYSTEM AND DUTIES 项目组织机构及岗位职责 (5)

4QUALITY ASSURANCE AND QUALITY CONTROL 质量管理与控制 (7)

5SCHEDULE CONTROLLING 进度控制 (23)

6TESTING PROCEDURE检测流程 (27)

7NON-DESTRUCTIVE TESTING TECHNICAL MANAGEMENT MODE 无损检测技术管理模式 (31)

8APPLICABLE NATIONAL STANDARDS AND SPECIFICATIONS 检测实施执行的国家标准和规范 (34)

9TESTING RESOURCE MOBILIZATION PLAN 检测资源配置计划 (34)

10TESTING PLAN 检测工艺方案 (37)

1 Preparation basis 编制依据

1.1 NDT Quality Control System Issued by Nanjing Enpake Testing Company., Ltd;

南京英派克检测有限责任公司无损检测质量体系文件;

1.2 NDT HSE Control System Documents Issued by Nanjing Enpake Testing Company., Ltd;

南京英派克检测有限责任公司无损检测HSE体系文件;

1.3 NDT for Pressure Equipments

JB/T4730-2005《承压设备无损检测》

1.4 Specifications for Construction and Acceptance of Industrial Metal Pipeline Project

GB50235-97《工业金属管道工程施工及验收规范》

1.5 Specifications for Construction and Acceptance of Welding of Field Equipment and

Industrial Pipeline

GB50236-98《现场设备、工业管道焊接工程施工及验收规范》

1.6 Specifications for Construction and Acceptance of Flammable Media and Toxic Pipeline

in Petroleum and Chemical Industrial Plant

SH3501-2002《石油化工有毒、可燃介质管道工程施工及验收规范》

1.7 Specifications for Construction and Acceptance of Structrural Steel Project

GB50205-2001《钢结构工程施工验收规范》

1.8 Regulations for Technical Documents of Petrochemical Engineering Construction Project

Handover

SH3503-2007《石油化工工程建设交工技术文件规定》

1.9 Examination and Supervision Management Rules for Special Equipment non-Destructive

Inspection Personnel GZGJ (2003) 248 of General Administration of Quality Supervision, Inspection and Quarantine of The People's Republic of China

《特种设备无损检测人员考核与监督管理规则》国家质量监督检验检疫总局国质国检字〔2003〕248号

1.10 ASME Boiler and Pressure Vessel Codes, Section V: Nondestructive Examination,

Including RT, UT, PT and MT

ASME Section Ⅴ ASME 锅炉压力容器规范无损检测包括射线探伤、超声波探伤、渗透探伤、磁粉探伤

1.11 Standard Test Method for Vickers Hardness of Metallic Materials

ASME E92 金属材料的维氏硬度的标准试验方法

1.12 Technologic Supervision Regulations on Safety of Pressure Vessels ZJJQGF (1999)154

质技监局锅发(1999)154号压力容器安全技术监察规程

1.13Management and Supervision Regulations on Safety of Pressure Pipeline Ministry of

Labor (1996) 140

劳动部(1996)140号压力管道安全管理与监察规定

1.14 Manual Ultrasonic Flaw Detection Methods and Detection Result Classification for

Steel Welded Joints

GB11345-89《钢焊缝手工超声波探伤方法和探伤结果分级》

1.15 Piping Welding

50-010-00-0-0-00-024《管道焊接》

1.16 Structural Steel

10-010-00-0-0-0019《钢结构》

1.17 General Requirements for Welding

40-010-00-0-0-00-016《焊接通用要求》

1.18 Approval Illuminations for Welding Implementation and Welding Quality

40-010-00-0-0-00-022《焊接实施和焊接质量的验收说明》

2 General 工程概况

2.1 Client 建设单位

BASF-YPC Company, Limited (BYC) 扬子石化—巴斯夫有限责任公司

2.2 EPC总承包单位

Wison (Shanghai) Chemical engineering Co., Ltd 惠生(上海)化工工程有限责任公司

2.3 Construction company 施工单位

The Second Construction Company of Sinopec 中石化二公司

2.4 Project location 地理位置

The cracking furnance project is located in ethylene plant of BYC in Dachang, Nanjing of Jiangsu province.

新建裂解炉位于江苏省南京市大厂区BASF-YPC的乙烯装置内。

2.5 Natural conditions in Nanjing 地区自然条件

Temperature温度Annual average temperature年平均气温15.4℃

Mean temperature of the hottest month 最热月平均气温28.2℃

Extreme maximum temperature 极端最高气温43℃

Extreme minimum temperature 极端最低气温-14℃

Average temperature of the coldest month 最冷月平均气温 1.9℃

Rainfall降雨量Average annual rainfall年平均降雨量1094.98mm

Maximum monthly average rainfall 月平均最大降雨量181.7 mm

Average daily maximum rainfall 日平均最大降雨量226.3 mm

Snowfall降雪量Maximum snow depth最大积雪深度51cm

Wind speed风速Annual average wind speed年平均风速 3.4m/s

Maximum wind speed at 10 meters high above ground 地面上层10米高处极限最大风速 38.8m/s

2.6 The main testing tasks of this project includes: 本工程主要检测任务量 Ray, ultrasonic, magnetic powder, penetration detection, hardness and PMI testing 射线,超声波,磁粉,渗透等无损检测及现场硬度检测。 3 Project organization system and duties 项目组织机构及岗位职责

3.1 We shall set up the project management department as per practices on projects as follows:

南京英派克检测有限责任公司按惯例组建项目经理部,其组织机构图如下:

3.2 Responsiblities and Obligations of Key Positions in the Organization System 组织机构关键岗位的职责

3.2.1 Project Manager (PM) 项目经理

PM shall be in charge of all the project jobs entrusted by Legal representative.

Project manager: Zhu Weixing

Working teams/groups

Reviewer Document controller

Test operators

Technical&quality leader:Li Weihua

Construction leader: Shi Jianzhong

HSE leader: Zhang Weiguo

项目经理:朱卫星

作业班组

审核员 资料员

检测员

技术质量负责人:李伟华 施工负责人:施建中 HSE 负责人:张维国

项目经理受公司法人代表的委托,全权处理本项目上一切事务。

a) Organization of the project management team, staff deployment, draft of rules and regulations, arrangement of the responsibilities of each project member, work progress;

负责项目部管理机构的构成、人员配备、规章制度的制定,明确有关人员的职责,组织项目部开展工作;

b) Establish the general target, stage target and breaking down progress targets;

负责制定承建项目的管理总目标、阶段目标,进度目标分解;

c) Accomplishment of the goal on Safety, Quality, Progress and Cost;

负责公司对本项目的“安全、质量、进度、成本”目标的完成;

d) Execution of quality plans set up by the project;

负责组织项目质量计划的实施;

e) Coordination of daily construction works, and improvement of quality system performance;

负责项目日常施工生产的协调平衡工作,改善项目质量体系运行条件。

3.2.2 Technical & Quality Leader is responsible for:项目技术质量负责人

a) Performing technical & quality functions on behalf of PM.

代表项目经理在工程上行使技术质量职权。

b) Establishment and effective execution of NDT quality management system; organizing testing jobs to meet requirements of codes and standards on testing quality;

负责无损检测质量管理体系的建立和有效运行,确保工程检测质量达到规范标准要求;

c) Preparing technical jobs to ensure complete documentation and management system as support such as: project resource distribution plan, testing codes and standards, test cards, quality manuals, procedure documents, job descriptions, operation specifications, management rules; implementing daily technical system, quality plans and control;

认真做好技术准备工作,确保检测工作有完整的技术文件和管理标准支持,如:项目源配置计划、检测标准、检测工艺卡、质量手册、程序文件、岗位工作标准、操作规程、管理制度等;负责技术体系的日常运行和实施质量计划。

d) Coordinating with EPCM, supervision company and inspection bureau on quality jobs. If no inspection occurs, take self inspection to ensure the conformity of testing process and results. Confirming technical questions and approving rectification measures;

严把质量关,配合好甲方监督、现场监理、监检等工作。在无上述监督检查的工程中,必须进行自检复查工作,以确保检测过程和结果的真实符合性,并确保检测质量(“四率”)达标;对技术问题予以确认、批准纠正措施。

e) Leading quality inspection jobs; responsible for PM in the project; performing quality

management jobs to avoid any quality accidents to the greatest degree;

具体领导工程质量检查工作,在工程上向项目经理负责;认真做好质量管理工作,最大程度避免质量事故发生;

f) Coordination of quality system audit and improvement of auditing results; establishment

and supervision of precaution measures;

负责项目质量体系审查的配合工作及审查结果的整改和纠正措施的制定、实施;预防措施的制定、监督管理

3.2.3 Construction Leader is responsible for: 项目施工负责人

a) Controlling of the progress targets, compiling of mobilization plan of staff, equipments

and materials; arrangement an organization of construction personnel;

负责现场施工进度目标的控制,负责人员、设备、物资计划的编制和施工现场人员的组织和安排。

b) Receiving site authorization, communicating and coordinating with the client, supervision

company, EPCM and construction companies;

负责现场委托的接受和配合项目经理与业主、监理、总包单位、施工单位的沟通协调。

c) Procurement, transportation, storage, distribution of materials, the allocation and

maintenance of equipment and tools;

负责物资采购、运输、贮存、发放、工机具的调配、维护等。

3.2.4 HSE Leader is responsible for: HSE负责人

a) HSE management on site, have the right to punish the departments or personnel violating

Safety, Health, Environmental protection and FF regulations; take the liaison with the client, supervision company and EPCM to guarantee the achievement of HSE goals;

负责现场的HSE管理。有权对违反安全、健康、环保、消防管理规定的部门和人员进行处罚,与业主、监理、总承包单位联络,保持密切联系,确保项目施工HSE目标的实现。

b) Working as the liaison with the departments concerned; HSE internal management,

monitoring HSE system establishment and performance; compiling HSE inspection plans and execution, confirmation and approval; possessing the veto on project safety.

对外代表项目部与有关单位联系,对内负责工程HSE管理,监督HSE体系的建立与运行,编制HSE检查计划并按其要求组织实施、确认和放行,在工程安全上有否决权。

4 Quality assurance and quality control 质量管理与控制

4.1Quality policy质量方针

Quality policies for non-destructive detection of this project are Objective, impartial, scientific and efficient, the creator and carrier of excellent products.

本项目无损检测质量方针是:客观、公正、科学、高效,优质产品的载体。

We will take “creating excellent works” as the goal of this project by adopting scientific management manner, such as strengthening testing quality control programs; strengthening testing process control; strengthening commission-testing-feedback procedure control and intensifying testing guidance by proper correction and prevention measures, to ensure an excellent testing work is achieved.

本项目的检测过程将以全新创优为目标,运用科学管理的方法,即:强化检测质量控制程序;强化检测过程的控制;强化委托—检测—反馈的程序交接;强化纠正和预防措施等手段来指导检测实施,达到保证检测质量创优的目的。

4.2Quality targets 质量目标

4.2.1 General quality targets for non-destructive detection of this project are: adhering to the principle of testing quality first, supply fair, accurate and reliable data and effective and excellent services by impartial attitude, rigorous work style, scientific methods and advanced technologies, and protect the legitimate interests of the clients all the time.

本项目无损检测总体质量目标:坚持检测质量第一,以公正的态度、严谨的作风、科学的方法、先进的技术,提供公正、准确、可靠的数据和高效优质的服务,并保护受检单位的合法利益。

4.2.2 The target values for this project are as follows:

本项目检测目标值:

——negative quality qualification rate: above 96%

底片质量合格率:96%以上

——film evaluating accuracy rate: above 98%

底片评定准确率:98%以上

——testing proportion coincidence rate: 100%

检测比例符合率:100%

——testing instruction fulfillment rate: 100%

检测指令执行率:100%

——ultrasonic testing accuracy rate: above 98%

超声波检测准确率:98%以上

——surface detecting accuracy rate: above 98%

表面检测准确率:98%以上

4.3QC organization system 质量管理体系机构

4.3.1 NDT QC organization system of the project department 项目部无损检测质量管理体系机构图:

4.3.2 Responsibility and obligations of QA system 质量保证体系责任

a) The guideline for quality management of this project is to give first place to and lay extreme stress on prevention; we not only shall improve the work quality of various departments and personnel in charge, but also shall guarantee the testing quality. The responsible personnel at all levels of QA organization system must come on their duties and go down to the construction site and testing teams or groups to inspect and supervise such works as joint checkup of drawings, drafting and verifying of testing plans, technical explanation and clarification, design changes, construction quality control, confirmation of stop points and so on, to ensure that QA system is functioning normally and successfully. 本工程的质量管理工作准则是预防为主,抓好各职能部门负责人的工作质量和检测质量,质保体系各级责任人员必须到岗到位,深入施工现场和检测班组,履行本专业职责,从检测方案、工艺卡编审,技术交底,检测质量过程控制等入手,严格把关,保证质量体系运转正常。

b) Strictly adhere to national standards and specifications as promulgated on project quality, and adopt proper testing technologies and ways to guarantee testing quality; regularly inspect the testing quality to eliminate the potential quality perils; in addition, keep close cooperation with the supervision party, and focus jointly on testing quality to make testing quality meet client’s requirements.

严格遵守国家有关工程质量规范、标准。采用正确的检测技术和方法以保证检测质量。定期检查检测质量以排除质量隐患。与总包方、监理方、监督方紧密配合,共同抓好施工质量,满足业主要求。

c) Project manager takes complete charge of testing quality of the project, and quality

Project manager 项 目 经 理

NDT operators 作业人员

Assessor 审核员 Document Controller 资料员

Inspector 检测员

Technical & quality director 技术质量负责人

Construction supervisor 施工负责人

HSE director HSE 负责人

supervisor is mainly responsible for general quality management, including project testing quality management at the site; construction directors at every departments shall also be responsible for quality supervision, they shall clarify quality requirements and obligations when they are allocating and adjusting works, to make QA system and testing mechanism integrate reliably and function effectively in a synchronous manner all the time.

项目经理是工程检测质量的总负责人,技术质量负责人是日常质量管理工作的主要负责人,负责现场的工程检测质量管理。在布置岗位、调整分工的同时还要下达工作质量要求,明确质量责任,做到质保体系和工作机构一体化,保证质保体系与检测活动有效地同步运转。

d) As the core of the overall testing quality management, the technical director controls technical data of the project department and all full-time responsible personnel, at the same time, he instructs and supervises distributing and recycling of testing operation codes in each testing phases to ensure QA system coordinate completely all the time.

技术质量负责人作为整个工程检测质量管理的核心,管理着各专职责任人以及项目部的技术数据中心,指导并督促各检测施工阶段工艺卡的下发和回收,保证质量管理上下协调一致。

e) Strengthen quality supervision, and establish project testing quality inspection and acceptance system according to the program documents of company’s QA system, inspect and accept the testing materials, key parts and procedures strictly, at the same time issue the testimony documents; intensify quality veto system, rectify and modify the unacceptable parts within a limited time period.

加强质量检查职能,按照公司质量保证体系程序文件的要求,建立工程施工检测质量检查验收制度。对检测材料进行验收,对底片、原始记录、报告等关键部位进行检查验收,并有见证资料。加强质量否决制度,对有质量问题的部位限期整改。

f) Project department shall assign specially testing operators and film evaluating and verifying personnel, they should check and guarantee the quality which they should control, and solve any quality problems being found without delay; they shall collect the quality materials at every work phases, and make good quality control so as to nip perils in the bud; 项目经理部设有评片员、审核员、作业人员等,所有以上质量控制人员在现场各把自己的质量关,出现质量问题及时处理,搜集各阶段的质量资料,做好过程管理工作,质量管理阶段以防患于未然为原则;

g) Before testing implementation, clarify and explain thoroughly the technical plan and concrete requirements concerned, and constantly improve testing level of testing personnel;

检测前对检测工艺卡及有关具体规定进行技术交底及答疑,不断提高操作者的检测技术水平;

h) We will intensify education to all employees on quality consciousness, sense of ownership, occupational ethics, enterprise reputation, good management experiences, work styles and actual achievements collecting and absorbing from ourselves and other fraternal units, and strengthen their conception of quality first;

抓好质量意识的教育,我公司将从对职工的主人翁责任感、职业道德、企业信誉、本单位、兄弟单位在质量管理方面的好经验、好作风、实际成果等多方面的内容进行教育,使全体人员不断加强质量第一的观念;

i) In order to implement and realize related management stipulations on testing quality, the project department shall formulate corresponding incentive regulations, to make proper rewards and punishment upon related testing behaviors.

为了保证施工检测质量管理有关规定的落实,项目部应制定出相应的奖惩条例,对各项目组的检测质量进行考核、奖惩。

4.3.3 NDE QA/QC system running 无损检测质量管理体系运行

a) Project manager shall organize project management, execution, confirmation and to carry on testing works with accordance to quality system.

项目经理按照质量体系的要求,组织项目管理、执行、验证、开展相应工作。

b) During construction preparation period, project manager shall organize to formulate reasonable project quality policy and target on the basis of project features, expectation and requirements as set forth by the client, and which could not be issued for implementation until they are approved by the project manager, it is guaranteed that all personnel in the project department shall understand and follow them well all the time.

项目经理在组织进行检测准备时,要针对工程特点、甲方的期望和要求,制定出项目质量方针和质量目标,项目质量方针和目标由项目经理批准发布实施,并确保项目部各级人员都理解,贯彻执行。

c) Project department shall organize to establish “nondestructive testing project planning” and “QA/QC plan”, which shall be consistent with the project and quality req uirements and of strong operability, to direct the testing implementation and meet the design drawings, standards, specifications and client’s requirements.

项目部应组织编制与工程项目和质量要求相一致的、操作性强的《无损检测项目计划书》和《质量计划》来指导工程项目检测施工,满足设计图纸、标准规范和业主的要求。d) Testing quality supervision is realized by self-check, common check and supervision by the project department and exterior supervision and monitoring departments.

检测作业的质量监督由作业层的自检、互检,项目部的质量监督和外部监控组成。

e) Testing quality shall be evaluated strictly according to related NDT standards and

specification as specified in the design documents, especially for the repair parts.

检测过程质量控制严格按设计要求的无损检测标准和有关规范进行评定,尤其对返修复位的检测则严加控制。

4.3.4 Examination and evaluation of QA/QC system 无损检测质量管理体系的考核

a) Our project quality system will receive examination and evaluation of local petrochemical project quality supervision station and project construction supervision department at any time, for the unacceptable items being found, we shall analyze the reasons and work out reasonable correction measures and plan, and complete the correction as soon as possible.

项目质量体系接受当地石化工程质量监督站及工程建设监理公司质量体系审核,对审核出的不合格项,要及时分析不合格的原因,制定纠正措施及实施计划,按时完成整改。

b) Project manager shall organize an internal inspection on QA/QC system of the project every three months to ensure that QA/QC system is acceptable and valid and could satisfy the requirements to realize the quality policy and target as formulated for the project; for the unacceptable item being found, “unacceptable reports” shall be prepared, and correct them on time, related records shall be stored and filed properly; “four rates” shall be taken to check and judge the implementation conditions of NDT QA/QC system and testing procedures, reasonable correction and prevention measures shall be adopted to realize excellent testing performance.

项目经理每三个月要对项目工程组织一次质量体系的内部检查,确保检测项目质量体系的适宜性和有效性,以满足项目质量方针和质量目标的落实,对发现的不合格项要填写“不合格报告”,并进行整改落实,记录应予以保存。并通过“四个率”检查无损检测质量体系管理及检测工艺执行情况,及时纠正和采取预防措施来指导检测实施,达到保证检测质量创优的目的。

c) QA/QC system of the project shall not only adhere to the project documents as issued by the client, it also shall satisfy other related specifications and standards and receive examination and evaluation of local petrochemical project quality supervision station and project construction supervision department at any time.

项目质量体系除执行项目文件外,还应接受当地石化工程质量监督站及工程建设监理公司主管、相关部门的监督、考核和执行项目文件以外的系统要求执行的其它文件。

4.3.5 QA measures 质量保证措施

a) Strictly accept materials to avoid unqualified material inflow into testing procedures.

严把材料验收关,不合格的材料严禁流入作业程序。

b) Make the technical personnel know clearly about the construction drawings, technical requirements, structural features, testing standards and specifications to be applicable, special testing technical requirements and QA measures.

由项目部组织技术人员熟悉图纸,掌握工艺要求,结构特点及所采用的规范、验收标准以及特殊检测技术要求和质量保证措施。

c) Technical director shall organize related engineers to hold a design explanation and clarification activity, optimize testing plan and enhance its rationality and practicability, to ensure that the quality target could be achieved successfully.

由项目技术负责人组织专业工程师参加设计交底,优化检测方案,提高其科学性和实用性为保证质量奠定基础。

d) Special testing personnel shall pass qualification check and confirmation ahead of time and submit the copies of qualifications to the client for filing.

提前做好特殊检测人员资质审查工作,并将合格证复印件交甲方代表备案。

e) Testing shall be carried on strictly according to the specifications concerned, all procedures shall conform to the specifications, standards, design drawings and testing plan.

检测过程应严格按规范要求进行,过程控制应符合规范、标准、图纸和检测方案的要求。

4.4Control of documents and records 文件记录控制

4.4.1 Control procedure文件记录管理

a) Valid versions of NDT technical documents and testing standards shall be controlled and managed by the document controller of the project as assigned by the technical director;

无损检测技术文件和无损检测标准的有效版本管理由技术负责人委派项目资料管理员

控制;

b) Technical & quality supervisor shall be responsible for controlling of NDT quality records, testing plan and operation codes;

项目检测方案和工艺卡及现场无损检测质量记录由技术质量负责人实施管理。

4.4.2 Filling of quality records 质量记录的填写

a) Original testing records shall be completed and confirmed by signature by the testing operators themselves;

检测原始记录应由检测操作人员亲自填写,并签字;

b) Testing commission registration, testing result notice sheets, repair registration and records for processing in the darkroom shall be filled out carefully, neatly and legibly as requested;

检测委托台帐、检测结果通知书、返修登记台帐、暗室工作记录应书写工整,并按格式认真填写;

c) Testing reports shall be printed and impressed with the company seal, the auditing column must be signed by the person issuing the reports.

检测报告应由电脑打印,并加盖公章,评审一栏必须由本人签字。

4.4.3 Filing/archiving of testing documents 检测资料归档

a) Testing commission registration, repair registration, records for processing in darkroom, testing distribution layout, original testing records and reports for testing works which have not been completed at the site, shall all be controlled and managed by the document controller of the project;

现场未竣工的检测委托台帐、返修登记台帐、暗室工作记录、检测布置图、检测原始记录、检测报告等均由项目资料管理员负责管理;

b) After testing work is completed, testing commission registration, repair registration, records for processing in darkroom, testing distribution layout, original testing records and reports and NDT statistics, shall all be submitted to the comprehensive management department for filing/archiving.

项目工程结束后,检测委托台帐、返修登记台帐、暗室工作记录、检测布置图、检测原始记录、检测报告、单项工程无损检测统计表等一同上缴公司综合管理部,由资料管理员统一登记存档管理。

4.5Testing equipment quality control 检测设备质量控制

4.5.1 Control scope 控制范围

NDT equipments include ray machines, ultrasonic crack detectors, magenetic detection devices and so on.

包括射线机、超声波探伤仪、磁粉探伤仪等无损检测仪器;

4.5.2 Control contents 控制内容

a) Periodic calibration: all testing equipments shall be calibrated periodically as stipulated and be supplied with inspection records and reports;

定期检定:所有检测设备要按规定进行检定,且有检定记录及报告;

b) Confirmation marks: testing equipments having been calibrated shall have a confirmation mark indicating its status;

确认标识:检测设备经检定后,应带有表明其状态的确认标记;

c) Operation environment: proper working conditions shall be created for testing equipments to guarantee the safety of the testing equipments and smooth testing performance.

使用环境:在使用检测设备时,应为检测工作创造适宜的工作环境,保证检测设备的安全和检测工作的顺利进行。

4.5.3 Operation instructions 使用操作

a) Suitable testing equipments shall be chosen before testing performance;

检测设备使用前,应选用适用本工程的检测设备;

b) Personnel operating the equipments shall have certain qualifications and operate the equipments according to operation instructions and related specifications;

使用设备的人员应具备一定的资格,操作设备一定要按设备操作规程或使用说明书要求进行;

c) Once equipment accident/incident happens, report it to the departments concerned as stipulated, and deal with the accident/incident in strict accordance with equipment management program.

发生设备事故要按规定上报有关部门,严格按公司设备管理办法中有关设备事故处理的规定执行。

4.6Testing material control 采购检测材料的质量控制

4.6.1 General 总则

a) The principle of material controlling is to guarantee the quality and progress of the project, accelerate the capital turnover, reduce the consumption, save the expense and to be propitious to enhance economic efficiency;

物资控制应本着保证工程质量和进度,加速周转,降低消耗,节省费用有利于提高经济效益的原则进行控制;

b) NDT consumable materials shall be procured based on the principle of quality first and price low and quality good.

无损检测消耗材料的采购应本着质量第一、货比三家的原则。

4.6.2 Obligations 职责

a) Unified procurement, acceptance and allocation of all NDT materials shall be carried on by the company.

公司负责无损检测材料的统一采购、验收、分配。

b) Project construction supervisor is responsible to work out the testing material budget and plan, and make a revision accordingly based on the project progress and quality status; at the same time, after being approved by project manager, the company shall adjust materials supply based on actual requirements in time;

项目施工负责人组织编制检测材料的使用计划,同时根据项目进度、质量状况及时修订检测材料需求计划,并经项目经理审核,公司根据需求及时调整材料的供给;

c) Project construction supervisor is responsible for receipt and sending of testing materials; 项目施工负责人负责现场检测材料的入库管理、使用发放;

d) Testing personnel shall use the testing materials reasonably and effectively.

检测操作人员应有效合理地使用检测材料。

4.7Testing identification marks and traceability 检测标识和可追溯性

4.7.1 Identification marks of tested work pieces受检工件的检测标识

4.7.1.1 Radiographic testing identification marks 射线检测标识

a) Butt welds of pipeline 管道对接焊缝

b) For butt welds of pipeline of ≤Ф100, if they are radiated for two times as specified by the related standards, the radiated position shall be marked with“1 , 2 ”; but for pipeline of >Ф100, they should be marked as per radiation times and sections;

≤Ф100的管道对接焊缝按标准透照2次,在透照位置上标明“1 、2 ”;>Ф100的管道按透照次数的区段进行标识;

c) Marks shall be made specially in testing distribution layout if required by the client;

如用户需要,还应在检测布置图中进行标识;

d) Marks shall be made on the negatives according to related standards and testing operation codes, besides identification codes of the testing operators.

射线底片上的标识除标准和检测工艺卡的要求外,还应有透照该片检测操作人员的代码标识。

4.7.1.2 Identification marks for ultrasonic testing 超声波检测标识

a) Marks shall be made as per testing operation codes according to actual conditions.

按检测工艺卡根据具体情况进行标识。

b) Testing marks are distributed in the work-piece sketch.

在工件示意图中进行检测布置标识。

4.7.1.3 Identification marks for surface testing 表面检测标识:

Marks shall be made as per testing operation codes according to actual conditions.

按检测工艺卡根据具体情况进行标识。

4.7.1.4 Testing report number is unique. 检测报告编号的唯一性

4.7.2 Control of traceability 可追溯性的控制

a) Traceability is applied to following procedures:

检测实施过程应具有可追溯性的过程:

——radiographic testing; 射线检测的过程;

——ultrasonic testing; 超声波检测的过程;

——liquid penetration testing 渗透检测的过程。

b) The films for testing procedures of traceability and testing sketches concerned shall be properly stored for later confirmation and testimony of correct testing implementation.

对具有可追溯性的射线底片、相关检测示意图等必须妥善管理,保证验收复位的准确性。

4.8Quality control of unacceptable items 不合格品的质量控制

4.8.1 General 总则

It is formulated for proper identification and control of those unacceptable items being detected during testing performance according to related standards, and with the purpose to prevent potential quality risks or misjudging as caused by human factors or by taking unacceptable testing manner.

为了确保对检测实施中出现的不符合标准要求的检测结果得到识别和控制,以防止因本身检测质量不合格而误判及导致其产品存在质量隐患。

4.8.2 Obligations and responsibilities 职责

a) Technical supervisor is responsible to formulate the measures and plan to correct the unacceptable items appeared in the course of testing.

技术负责人负责检测过程中出现的不符合标准质量要求的检测结果纠正措施的制定。b) Project manager is responsible to examine and approve the above-mentioned correction measures and plan.

项目经理负责检测实施中出现的不符合标准质量要求的检测结果纠正措施的审批。

c) Quality supervisor is responsible to supervise the implementation of above-mentioned correction measures and plan.

质量负责人负责检测过程中不符合标准质量要求的检测结果纠正措施的实施。

4.8.3 Operation procedures 工作程序

4.8.3.1 Identification of unacceptable items 不合格品的识别

a) The items which are deemed to be in violation of NDT work guide book or related testing standards by evaluating and auditing shall be judged to be unacceptable.

检测实施过程中,由项目检测评审时认定违反无损检测作业指导书或检测标准质量要求的,判定为不合格品。

b) The items which are identified to be unacceptable by WISON Company, owner’s project management team or national technical and quality supervision department shall also be included.

检测实现过程中,惠生公司、业主项目管理组或政府技术质量监督部门等检查发现提出

的不合格品。

4.8.3.2 Correcting of unacceptable items 不合格品纠正措施的实施

For the unacceptable item which self is not in accordance with the related standards, technical supervisor shall organize the testing operators to analyze and find out the reasons and obligation, and the quality supervisor shall work out reasonable and practicable correction measures and plan based on the reason analysis as obtained by technical group and then implement it after being approved.

因本身检测质量不符合标准要求造成的不合格品,由项目技术负责人负责组织现场检测人员分析其产生的原因和责任,由项目质量负责人根据原因分析结果制定相应纠正措施,并按经审批的纠正措施进行实施。

4.8.3.3 Recheck after correction of the unacceptable items 不合格品纠正后的再验证

After being corrected, the unacceptable items shall be rechecked and evaluated by the quality supervisor according to NDT work guide book and testing standards; only after being approved by WISON Company, owner’s project management team or national technical and quality supervision departments, all materials concerned could be archived, besides testing reports.

不合格品纠正后,由项目质量负责人根据无损检测作业指导书或检测标准质量要求重新评审进行再验证,经惠生公司、业主项目管理组或政府技术质量监督部门等认可后进行归档,并出具检测结果报告。

4.8.3.4 Unacceptable information management 不合格品的信息管理

Technical & quality supervisor of the project shall collect and register all information on unacceptable items, then classify, reorganize and issue them to owner’s project management team periodically.

项目技术质量负责人负责不合格品的有关信息进行汇总登记,并分类统计整理,并定期上报业主项目管理组。

4.9Data analysis 数据分析

4.9.1 Obligations and responsibilities 职责

Technical & quality supervisor of the project shall collect, analyze and process all information related to testing results, and issue these information to WISON Company periodically.

项目技术质量负责人负责对项目与检测结果有关的数据信息进行收集、分析和处理,并

将分析结果定期上报惠生公司。

4.9.2 Operation procedures 工作程序

4.9.2.1 Data classification 数据的分类

a) Data and information on testing quality: it includes quality records, data on unacceptable items and inspection information issued by WISON Company, owner’s project management team or national technical and quality supervision department, etc.

检测质量信息数据:包括质量记录、不合格品的信息、惠生公司、业主项目管理组或政府技术质量监督部门等检查结果信息等;

b) Data and information on the client: it includes commission, complaint and advice as issued by the client and return visit information and so on.

顾客信息数据:包括委托投诉、施工单位建议、用户回访情况等;

4.9.2.2 Data collection 数据的收集

a) Data and information on testing quality

检测质量信息数据

Data and information on testing quality shall be collected and recorded according to NDT work guide book and testing standards.

检测质量信息数据按无损检测作业指导书或检测标准的要求进行记录。

b) Data and information on the client: 顾客信息数据

Technical & quality supervisor of the project shall collect, record and classify such data and information as commission, complaint and advice being issued by the client and return visit information and so on.

项目技术质量负责人负责对委托投诉、施工单位建议、用户回访情况等进行分类记录。

c) Data analyzing methods 数据的分析方法

Technical supervisor shall make a statistical analysis of the above-mentioned data and information as per their sources and influence, besides specifications of equipment and tool and methods.

项目技术负责人对收集的数据按数据的来源、影响因素、方法、机具材料等数据特征指标进行统计分析。

4.10Prevention measures 预防措施

4.10.1 Obligations and responsibilities 职责

Based on a series of analysis of the data and information on unacceptable items, technical & quality supervisor of the project shall organize to formulate the testing quality control plan

and prevention measures accordingly to avoid them happening again as much as possible.

项目技术质量负责人根据发生的不符合项数据分析结果,为防止不符合项的再次发生,应组织制定检测质量控制预防措施。

4.10.2 Operation procedures 工作程序

4.10.2.1 Application of prevention measures 制定预防措施的范围

——Prevention measures during project system running;

项目体系运行过程中的预防措施;

——Prevention measures during testing implementation;

检测实施过程中的预防措施;

——Prevention measures for film processing in the darkroom;

暗室处理过程中的预防措施;

——Prevention measures for evaluating and verifying of testing results

检测结果评审过程中的预防措施

4.10.2.2 Defining potential unacceptable items and the cause

潜在不合格及其原因的确定

Technical & quality supervisor of the project shall generally define the potential unacceptable and its reason according to NDT QA/QC system running conditions and by analysis of testing implementation procedure before testing performance.

项目技术质量负责人根据无损检测质量管理体系运行情况、检测过程实施前对检测实现过程的分析等,确定潜在不合格及其原因。

4.10.2.3 Formulating of prevention measures 预防措施的制定

Technical & quality supervisor of the project shall organize to formulate corresponding prevention measures according to NDT QA/QC system running conditions and the possibilities appearing in the course of testing performance as described above.

项目技术质量负责人在无损检测质量管理体系运行或检测过程实施中可能出现的上述

情况,组织制定相应的预防措施。

4.10.2.4 Requirements for formulating of prevention measures 预防措施的内容制订要求

a) The prevention measures shall be formulated according to NDT QA/QC system documents, testing operation codes, work guide book and related testing standards;

预防措施的制定依据,根据无损检测质量体系文件、检测工艺卡、无损检测作业指导书或检测标准的要求进行编制;

无损检测施工方案

青岛东方影都万达茂幕墙外装修工程无损检测专项施工方案 编制: 审核: 审批: 编制单位:苏州柯利达装饰股份有限公司 日期: 2016年9月20日

目录 第一章编制依据 (2) 第二章工程概况 (2) 工程建设概况 (2) 工程施工条件 (2) 第三章施工安排 (3) 管理人员配置及职责 (3) 探伤流水段的划分 (4) 工程施工重点和难点分析及应对措施 (4) 施工进度安排 (5) 第四章施工准备计划 (5) 劳动力配置计划 (5) 探伤仪器配置计划 (5) 施工机具配置计划 (5) 技术复核和隐蔽验收计划 (6) 第五章施工方法 (7) 工艺流程 (7) 施工要点 (8) 施工方法详细 (8) 第六章各项管理措施 (10) 质量管理措施 (10) 工期管理措施 (11) 安全管理措施 (11) 成品保护管理措施 (11) 环境管理措施 (11)

第一章编制依据 依据标准 (1)GB/T11345-1989《钢焊缝手工超声波探伤方法和探伤结果分级》。 (2)GB/T50621-2010《钢结构现场检测技术标准》。 (3)JG/T203-2007《钢结构超声波探伤及质量分级法》。 (4)GB 50205-2001《钢结构工程施工质量验收规范》。 (5)设计说明 (6)施工组织设计 (7)地方及行业规范 第二章工程概况 工程施工条件 1、本工程工地连接的节点焊接量大,弯弧方管-直线方管、折线龙骨-水平横杆连接均为全熔透焊接,现场焊缝均为二级。 a.采用钢龙骨的地方主要受力骨架均采用国产Q235-B或Q345-B碳素结构钢, 表面氟碳喷涂处理。焊缝金属应与主体金属相适应。当不同强度的钢材连接时,可采用与低强度钢材相适应的焊接材料。 b.焊缝宽度满足设计要求,不得任意加大焊缝,避免焊缝立体交叉和在一处集

道路硬化施工方案设计

施工组织设计 目录

1.工程概况 2.主要工程指标承诺 2.1质量承诺 2.2工期承诺 2.3安全承诺 2.4技术档案资料承诺 2.5现场管理 3.施工部署 3.1项目部组织机构的建立 3.2施工组织与协作 3.2.1施工组织 3.2.2施工原则 3.3施工部署 3.3.1工程特点分析 3.3.2现场布置 3.3.3施工进度计划 3.4施工准备 3.4.1技术准备 3.4.2生产要素准备 3.4.3现场准备 4.主要施工方案 4.1街道硬化施工 4.1.1路面拆除 4.1.2基层压实 4.1.3砌筑路牙石 4.1.4混凝土路面铺设 4.1.5路面混凝土养护 4.1.6切缝 4.2玉皇观庙施工 4.2.1模板 4.2.2钢筋 4.2.3混凝土 4.2.4砌体工程 5.工程质量保证措施 6.防治质量通病措施 7.成品保护措施

8.工期保证措施 8.1保证工期主要措施 8.1.1组织保证 8.1.2资金保证 8.1.3施工要素保证 8.1.4安全保证 8.1.5质量保证 8.1.6技术保证 8.1.7管理保证 9.安全、文明施工保证措施 9.1安全管理制度 9.1.1安全生产责任制 9.1.2安全教育、培训制度 9.1.3安全防措施制 9.1.4安全交底制 9.1.5安全检查制 9.1.6班组“三上岗”、“一讲评”活动制 9.1.7安全标志 9.2本现场重点安全防护措施 9.3文明施工措施 10.环保、消防施工措施 10.1环保施工措施 10.2消防安全防护措施 11.采用的新技术、新工艺、新材料、新设备 12.提高质量、降低造价、保证工期合理化建议 13.拟投入本项目的主要施工设备表(附表一) 14.劳动力计划表(附表二) 15.施工进度计划表(附图一) 16.施工现场平面布置图(附图二) 施工组织设计1.工程概况

无损检测施工组织设计方案

xxx市劳务移民安置 供排水及天然气配套工程无损检测施工组织设计 编制: 审核: 批准: 郑州石油天然气华龙无损检测有限公司

目录 目录 (1) 一.编制依据 (2) 二.工程概况 (2) 三.检测部署 (2) 1.项目经理部主要人员情况 (2) 2.检测机组人员配置 (2) 3.设备配置 (3) 4.施工时间 (3) 四.质量管理和HSE管理及措施 (3) 1.质量管理及措施 (3) 1.1质量管理 (3) 1.1.1质量方针 (3) 1.1.2质量目标 (3) 1.1.3质量承诺 (3) 1.2质量管理的具体措施 (3) 1.2.1检测人员的控制 (3) 1.2.2检测设备的控制 (4) 1.2.3检测材料的控制 (4) 2. HSE管理及措施 (4) 2.1HSE管理总则 (4) 2.2HSE方针 (4) 2.3HSE目标 (4) 2.4HSE承诺 (4) 2.5HSE管理措施 (4) 五、工期保证措施 (5) 1 保证工程检测进度 (5) 2对人员、设备、材料的要求 (5) 六、主要检测设备一览表 (6) 七、拟交工的无损检测竣工资料 (6)

xxx市劳务移民安置供排水及天然气配套工程 施工组织设计方案 根据xxx市劳务移民安置供排水及天然气配套工程的具体特点,为确保管道环焊缝的检测质量,特制定本方案。 一、编制依据 1.《工业金属管道工程施工及验收规范》GB50235-97 2.《金属熔化焊焊接接头射线照相》GB/T 3323—2005 3.《压力容器无损检测》JB4730-2005 4.《放射卫生防护基本标准》GB4792—84 二、工程概况 本工程地点位于xxxx。所有中压焊口进行100%射线检测,合格级别为Ⅱ级。不能进射线检测的焊口,可采用渗透检测。焊口总数以实际检测口数为准。 三、检测部署 1、项目经理部主要人员情况: 2、检测机组人员配置: 根据工程量及工期的要求设定检测机组,并设暗室一个。无损检测人员暂行分配如下(可根据现场施工实际情况再临时调整,保证施工正常进行)。 3、设备配置

道路施工组织设计方案()

改造工程施工组织设计方案 一、工程概况 本工程为八圩港(横港—环城南路)改造工程,该路段计划施工工期为90日历天。 1.1、施工内容: 1.1.1、东岸新建挡墙桩号E0+168.4~E0+507,新建挡墙长338.6m,其中挡墙结构断面(一)长度为129.11m,挡墙结构断面(二)长度为209.49m。根据业主要求:本工程河道东岸桩号E0+168.4~E0+240.76区段列为二期工程建设,挡墙结构断面详见施工图; 1.1.2、西岸新建挡墙桩号W0+168.4~W0+504.07,新建挡墙长335.67m,其中挡墙结构断面(一)长度为43.2m,挡墙结构断面(二)长度为28.96m,挡墙结构断面(三)长度为158.99m,挡墙结构断面(四)长度为104.52m,挡墙结构断面详见施工图。 1.1.3、三江路桥为1跨16m、宽15m钢筋砼板式桥,河道蓝线宽度为14m,与道路中心线呈3度斜桥;桥台采用轻型桥台,下部基础均采用桩基础,上部结构为C50预应力空心板梁。 二、施工总体部署 2.1、施工准备 与甲方协议签订之后,本公司根据现场工程实际情况,调动一切积极因素,利用熟悉本地施工条件的优势,就近调集施工人员做好上场准备。 由项目经理带领施工技术部、安全质量部、物资设备部、计划部、等在本地的人员10人进驻现场,进行前期准备,其余人员在10天内调集完毕,在最短时间内进驻现场。并组织精测人员根据施工图纸及业主提供的原始测量基准点、测量标志、基准线或水准点或其他书面资料,按国家测绘标准和本工程精度要求,对本工程测设施工加密控制网,并及时提交监理单位,直至获得认可,在此同时,施工单位将陆续组织工程所需的各种施工机械、各项设备进场,联系各种材料厂家准备供料计划,并做好开工前的其他工作。

无损检测的概述

无损检测的概述(总12页) -CAL-FENGHAI.-(YICAI)-Company One1 -CAL-本页仅作为文档封面,使用请直接删除

第一章无损检测概述 1.1无损检测目的 1.2无损检测范围 1.3常用的无损检测办法 ) ) ET) 第一章无损检测概述 无损检测是指在不损伤和破坏材料、机器和结构物的情况下,对它们的物理性质、机械性能以及内部结构等进行检测的一种方法,是探测其内部或外表的缺陷(伤痕)的现代检验技术。所以,无损检测技术是提高产品质量,促进技术进步不可缺少的手段。 1.1无损检测的目的: (1)确保工件或设备质量,保证设备安全运行 用无损检测来保证产品质量,使之在规定的使用条件下,在预期的使用寿命内,产品的部分或整体都不会发生破损,从而防止设备和人身事故。这就是无损检测最重要的目的之一。 (2)改进制造工艺.

无损检测不仅要把工件中的缺陷检测出来,而且应该帮助其改进制造工艺。例如,焊接某种压力容器,为了确定焊接规范,可以根据预定的焊接规范制成试样,然后用射线照相检查试样焊缝,随后根据检测结果,修正焊接规范,最后确定能够达到质量要求的焊接规范。 (3)降低制造成本 通过无损检测可以达到降低制造成本的目的。例如,焊接某容器,不是把整个容器焊完后才无损检测,而是在焊接完工前的中间工序先进行无损检测,提前发现不合格的缺陷,及时进行修补。这样就可以避免在容器焊完后,由于出现缺陷而整个容器不合格,从而节约了原材料和工时费,达到降低制造成本的目的。 1.2无损检测的范围 (1)组合件的内部结构或内部组成情况的检查 (2)材料、铸锻件和焊中缺陷缝的检查 a、质量评定 b、寿命评定 (3)材料和机器的计量检测

无损检测方案

广西天然气支线管网项目隆安-武鸣天然气支线施 工无损检测服务 无损检测方案 新疆鑫泰材料设备检测有限公司 法定代表人或其委托代理人:(签字) 2018年7月5日

目录 无损检测方案摘要 (1) 1.0 编制依据 (2) 1.1招标文件提供的资料 (2) 1.2国家现行的法令、法规,地区颁发的安全、消防、环保、文物等管理规定 (2) 1.3无损检测技术标准及验收规范 (2) 2.0 工程概况 (3) 2.1工程名称、建设规模、建设地点、开竣工时间 (3) 2.2自然条件、社会依托 (3) 2.3主要工程量 (3) 3.0 检测部署 (4) 3.1检测资源准备 (4) 3.2现场检测部署 (4) 4.0 主要工作程序 (5) 4.1概述 (5) 4.2射线检测质量控制管理工作程序(框图) (7) 4.3超声波检测质量控制管理工作程序(框图) (8)

4.5射线底片的保管、储存和查阅管理程序 (11) (1)射线底片的保管 (11) (2)底片的储存 (12) (3)底片的查阅 (13) 4.7射线检测工艺规程、工艺卡(现场准备执行的X射线检测工艺卡)射线检测质量保证措施 (13) (1)射线检测工艺规程及工艺卡 (13) (2)超声波检测工艺规程及工艺卡 (26) (3)射线检测质量保证措施 (45)

无损检测方案摘要: 本无损检测方案根据招标文件的要求及工程概况,结合新疆鑫泰材料设备检测有限公司以往参与建设的同类型工程检测经验,罗列了无损检测方案编制依据、工程概况,详细叙述了该工程中标后将要采取的检测部署、主要工作程序、资源进场计划、检测质量保证措施、保证焊接进度措施和信息及文件管理。对业主特别关注的 问题进行了详细的说明。 我公司将以科学、公正、优质、及时的检测服务为宗旨,以求真务实,严格诚实为指导,本着优化工艺、优选人员、优化设备、材料的原则,并制定详细的质量保证措施,规范检测行为,加强过程管理,保证检测科学、及时、准确、公正。1.0 编制依据 1.1招标文件提供的资料 1)《广西天然气支线管网项目隆安-武鸣支线施工无损检测招标文件》。 1.2国家现行的法令、法规,地区颁发的安全、消防、环保、文物等管理规定 《建设工程质量管理条例》 《质量管理体系》GB/T19001-2008 《中华人民共和国安全生产法》 《建筑施工现场环境与卫生标准》JGJ146-2004 《职业健康安全管理体系》GB/T28001-2009 《健康、安全与环境管理体系》Q/SY1002.1-2007 《放射性同位素与射线装置放射防护条例》国务院第449号令 《电离辐射防护与辐射源安全防护标准》GB18871-2002 《工业X射线探伤放射卫生防护标准》GB16357-1996 《石油天然气工业健康、安全与环境管理体系》(SY/T6276-1997) 1.3无损检测技术标准及验收规范 《钢制管道焊接及验收》SY/T4103-2006 《天然气管道工程设计规范》GB50251-2003 《油气长输管道工程施工及验收规范》GB50369-2006 《石油天然气钢质管道无损检测》SY/T4109-2013 上述要求及标准具体以施工图纸及总说明为准。

道路工程施工组织设计方案

目录 一、施工组织设计 (1) (一)编制说明及编制原则 (2) (二)工程概况 (3) (三)施工准备 (4) (四)主要施工工艺及方法 (6) (五)质量目标及保证措施 (10) (六)安全生产目标及保证措施 (13) (七)进度计划保证措施 (14) (八)雨季施工安排及施工技术措施 (15) (九)文明施工及环境保护 (16) (十)工程进度形象表 (18)

(一)编制说明及编制原则 一、编制说明: 1、依据山东力克碳素股份有限公司150kt焙烧项目(二期)路面施工工程招标文件。 2、现场考察的实际情况。 3、《市政工程施工规范》。 4、《市政工程质量检验评定标准》。 5、《市政工程施工及验收规范》。 6、本工程的特点、工期要求及本单位的技术水平和设备配套等情况。 二、编制原则 根据招标文件要求及工程特点,确定编制原则为:精心组织、科学管理、合理安排、突出重点、重点环保、文明规范。 1、确保实现业主所要求的安全、质量目标 在充分理解业主意图的基础上,以施工设计图纸为主导,采用先进、合理、经济、可行的施工方案,并满足施工规范和设计要求,确保施工安全和质量优良。 2、确保实现业主要求的工期目标 依据我单位现有技术水平、施工管理经验和设备配套能力,施工进度安排合理、高效,施工区段划分协调、统一,资源配置合理、有

效,做到均衡生产,以确保工程施工总工期。 3、优化方案,减少投入 充分考虑本标段工程施工环境和工程特点,充分比选、优化,从工期、投入和施工干扰方面综合考虑,做到方案合理,切实提高工作效率,降低工程造价。 4、注重环保和文明施工,创文明、绿色工地 严格执行相关法律、法规,保护环境、保护文物,争创文明工地;合理规划施工用地,力求施工全过程对环境破坏最小,制定较周密的环境保护措施。 5、充分考虑各种施工界面的协调,处理好各种关系 注意搞好与设计、监理工程师及相关各承包商间的协调关系;为工程的顺利实施创造好的条件;注意搞好与工程所处政府及居民之间的协调关系,避免扰民和民扰事件的发生。 (二)工程概况 1、工程概况: 山东力克碳素股份有限公司150kt焙烧项目(二期)路面施工工程,工程起点为东三路与新建项目连接线交叉口,向东约400米的中心路面、部分环路及过路涵管。路幅为16.1*380米中心路面。道路结构为:素土夯实,压实度≥93%,300厚3:7灰土分两步夯实,300

常用无损检测技术分析

158 第三篇 常用无损检测技术 第15章 射线照相检测技术 15.1射线照相检测技术概述(Ⅱ级人员仅要求本节内容) 射线是具有可穿透不透明物体能力的辐射,包括电磁辐射(X 射线和γ射线)和粒子辐射。在射线穿过物体的过程中,射线将与物质相互作用,部分射线被吸收,部分射线发生散射。不同物质对射线的吸收和散射不同,导致透射射线强度的降低也不同。检测透射射线强度的分布情况,可实现对工件中存在缺陷的检验。这就是射线检测技术的基本原理。射线照相检测技术,利用射线对胶片可以产生感光作用的原理,采用胶片记录透射射线强度,在底片上形成不同黑度的图像,完成检验。图15—1显示了射线照相检测技术的基本原理。 射线照相检测的基本过程为准备、透照、暗室处理、评片,从底片上给出的图像,判断缺陷性质、分布、尺寸,完成对工件的检验。 图15-1 射线照相检测技术基本原理 图15-2 光电效应示意图 射线照相检验技术可应用于各种材料(金属材料、非金属材料和复合材料)、各种产品缺陷的检验。检验技术对被检工件的表面和结构没有特殊要求。检验原理决定了,这种技术最适宜检验体积性缺陷,对延伸方向垂直于射线束透照方向(或成较大角度)的薄面状缺陷难于发现。射线照相检验技术特别适合于铸造缺陷和熔化焊缺陷的检验,不适合锻造、轧制等工艺缺陷检验。现在它广泛应用于航空、航天、船舶、电子、兵器、核能等工业领域。 射线照相检测技术直接获得检测图像,给出缺陷形貌和分布直观显示,容易判定缺陷性质和尺寸。检测图像还可同时评定检测技术质量,自我监控工作质量。这些为评定检测结果可靠性提供了客观依据。 射线照相检测技术应用中必须考虑的一个特殊问题是辐射安全防护问题。必须按照国家、地方、行业的有关法规、条例作好辐射安全防护工作,防止发生辐射事故。 15.2射线照相检测技术基础 15.2.1 射线与物质的相互作用 射线按其特点分为二类:电磁辐射和粒子辐射,以下仅讨论X射线与γ射线(电磁辐射)。 X射线、γ射线与物质的相互作用是光量子和物质的相互作用。包括光量子与原子、原子核、原子的电子及自由电子的相互作用。主要的作用是:光电效应、康普顿效应、电子对效应和瑞利散射。图15—2、图15—3、图15—4是光电效应、康普顿效应、电子对效应作用示意图。

施工供水管道焊缝无损检测施工方案

目录 一、编制依据 0 二、工程概述 0 三主要设备、人员配置 0 3.1主要设备 0 钢尺、测厚仪、硬度计、放大镜、超声波探声仪、渗透剂、显像剂。 0 3.2主要人员配置 0 四、焊缝的无损检测 0 4.1无损检测前应具备的条件 0 4.2无损检测的工艺 (1) 五、确保检测质量的措施 (2) 六、安全、环保、文明施工要求 (3) 6.1安全施工要求 (3) 6.2环保施工要求 (3) 6.3文明施工要求 (4)

供水管道焊缝无损检验施工方案 一、编制依据 1、施工供水系统设计施工图纸。 2、GB50235-2010《工业金属管道工程施工规范》。 二、工程概述 本工程施工供水管道主要供应主体工程施工用水、业主及承包商营地等生活用水。施工供水系统设计总供水能力为440m3/h,其中上库区施工供水能力为180m3/h,下库区施工供水能力为200m3/h,营地生活供水能力约60m3/h。丰水季节一般从赤石坑水池中直接取水。赤石坑取水泵站设有两组水泵,一组水泵供水至业主营地及承包商营地作生活水源;另一组水泵供水至1号水池。电站建成后该取水泵站改建成业主营地生活用水的永久取水泵房。1号水池为施工供水工程的中心水池,水池容量1000t,供工程所有施工用水取用。上库区施工用水由三级加压泵站逐级加压提供,一级加压泵站从1号水池中取水,并经新建的部分输水管道(DN200无缝钢管)和利用原有小水电引水钢管(DN350)联合输送至原小水电水库中储存;再经二级加压泵站输送至2号水池、三级加压泵站输送至3号水池。3号水池容量500t,设置高程为1030m,可自流供给上库区绝大部分施工用水。当枯水季节来临时,赤石坑沟来水及储水量不能满足工程用水要求,此时则利用登源河取水点进行补充,与赤石坑取水点联合供水,以满足工程施工用水之需。 三主要设备、人员配置 3.1 主要设备 钢尺、测厚仪、硬度计、放大镜、超声波探声仪、渗透剂、显像剂。 3.2 主要人员配置 1、我项目部现场安排检验负责人1名、检验记录员1名、领工员1名、技术主管1名、安全员1名; 2、外委检验机构安排经过技术监督部门授权的机构培训,取得相应项目的无损检测合格证,并持证上岗的焊缝检测人员。 四、焊缝的无损检测 4.1无损检测前应具备的条件 1、检测范围内的管道安装工程已按设计图纸全部完成,安装质量符合有关规定; 2、焊接管道安装单线图按现场实际情况绘制完毕,焊接方法、焊工钢号标示完

道路工程施工组织设计方案

A4 施工组织设计(方案)报审表 工程名称:安康今东物流园区室外工程 陕西省建设监理协会印刷

安康今东物流区室外道路工程 施 工 组 织 设 计 编制人: 审核人: 审批人: 安康市康泰建筑工程有限公司

2017年2月12日 (一)编制说明及编制原则 一、编制说明: 1、陕西安康今东物流园项目道路工程施工合同; 2、陕西安康今东物流园项目道路工程施工图纸; 3、《城市道路路基工程施工及验收规范》(CJJ44-91) 4、《公路路面基层施工技术规范》(JTJ034-2000) 5、《公路路基施工技术规范》(JTJ033-95) 6、《公路工程质量检验评定标准》(JTGF80/1-2004) 7、《全国通用给水排水标准图集》(04S516) 8、《市政排水管道工程及附属设施》(06MS201) 9、《混凝土结构工程施工质量验收规范》(GB50204-2002) 10、《市政排水管渠工程质量检验评定标准》(CJJ3-90) 二、编制原则 根据工程特点,确定编制原则为:精心组织、科学管理、合理安排、突出重点、重点环保、文明规范。 1、确保实现业主所要求的安全、质量目标 在充分理解业主意图的基础上,以施工设计图纸为主导,采用先进、合理、经济、可行的施工方案,并满足施工规范和设计要求,确保施工安全和质量优良。

2、确保实现业主要求的工期目标 依据我单位现有技术水平、施工管理经验和设备配套能力,施工进度安排合理、高效,施工区段划分协调、统一,资源配置合理、有效,做到均衡生产,以确保工程施工总工期。 3、优化方案,减少投入 充分考虑本标段工程施工环境和工程特点,充分比选、优化,从工期、投入和施工干扰方面综合考虑,做到方案合理,切实提高工作效率,降低工程造价。 4、注重环保和文明施工,创文明、绿色工地 严格执行相关法律、法规,保护环境、保护文物,争创文明工地;合理规划施工用地,力求施工全过程对环境破坏最小,制定较周密的环境保护措施。 5、充分考虑各种施工界面的协调,处理好各种关系 注意搞好与设计、监理工程师及相关各承包商间的协调关系;为工程的顺利实施创造好的条件;注意搞好与工程所处政府及居民之间的协调关系,避免扰民和民扰事件的发生。 (二)工程概况 1、工程概况: 设计道路位于陕西安康今东物流园内,道路全长为368.251米,

无损检测技术综述

无损检测技术原理与应用 安全工程1401班 2014074201 1无损检测技术的定义及发展概况 随着中国科学和工业技术的发展,高温、高压、高速度和高负荷已成为现代化工业的重要标志。但它的实现是建立在材料高质量的基础之上的。必须采用不破坏产品原来的形状,不改变使用性能的检测方法,以确保产品的安全可靠性,这种技术就是无损检测技术。无损检测技术不损害被检测对象的使用性能,应用多种物理原理和化学现象,对各种工程材料,零部件,结构进行有效地检验和测试,借以评价它们的连续性、完整性、安全可靠性及某些物理信息。目的是为了评价构件的允许负荷、寿命或剩余寿命,检测设备在制造和使用过程中产生的结构不完整性及缺陷情况,以便及时发现问题,保障设备安全[1]。 无损检测技术是机械工业的重要支柱,也是一项典型的具有低投入、高产出的工程应用技术。可能很难找到其他任何一个应用学科分支,其涵盖的技术知识之渊博、覆盖的基本研究领域之众多、所涉及的应用领域之广泛能与无损检测相比。美国前总统里根在发给美国无损检测学会成立20周年的贺电中曾说过,(无损检测)能给飞机和空间飞行器、发电厂、船舶、汽车和建筑物等带来更高的可靠性,没有无损检测(美国)就不可能享有目前在飞机、船舶和汽车等众多领域和其他领域的领先地位。作为一门应用性极强的技术,只有与国家大型工程项目结合,解决国家大型和重点工程项目中急需解决的安全保障问题,无损检测技术才能有用武之地和广阔的发展空间[2]。 我国无损检测技术的快速发展得益于经济的快速发展和国家综合实力的快速增强。近十年来,我国经济一直处于快速发展期,无损检测事业也处于蒸蒸日上的局面,其总体形势和水平已是十年前无法比拟。在我国各工业部门和国防单位,我国无损检测工作者取得了令世人瞩目的成绩[2]。 2无损检测技术的基本类型及其原理 目前常用的无损检测类型主要有超声检测技术、射线检测技术、磁粉检测技术、渗透检测和红外检测技术五种,本文选取其中3种检测技术对其基本原理和应用进行简单的讲述,选取超声波检测技术和红外检测技术这两种检测技术进行

管道无损检测方案

管道无损检测方案 1.概述 本工程各种管道约15000米,分不锈钢SS304、SS316、碳钢、合金钢、PP/GRP、CS+PTFE等多种材质。根据工艺、技术的不同要求,现场需拍片约40000张,硬度试验900点。 本方案编制参考了招标文件中技术说明S-00-1540-002以及美国ASME标准(1986)。 2.检验项目 2.1射线探伤 ⑴射线探伤的检查比例,按照JGC在“技术说明”中的要求执行。 ⑵射线探伤的检查比例应符合设计要求及有关技术条件的规定。 ⑶要求100%检查的管道应逐个焊口整圈100%检查,确保不漏检。 ⑷要求10%抽检的管道应按相应焊工的相应焊缝按10%比例整圈检查。 ⑸管径≤3″厚度δ≤7.62mm采用双壁双影椭圆透照,每个焊口间隔 90°各拍一张,共两张。 ⑹管径=2″厚度≥8.74mm;管径=2-1/2″厚度≥9.53mm;管径=3″厚度≥11—13mm时应采用双壁单影分段透照,拍摄四张。 ⑺管径≥4″采用双壁单影或单壁单影透照,每个管口至少拍摄四张,T各种规格管道焊缝的拍摄数量应与现场测试检查程序中的要求一致。 ⑻胶片选用FUJI“100”型。采用的铅箔增感屏,当采用X射线探伤时,前屏厚0.03mm,后屏厚0.1mm;当采用γ射线探伤时,前后屏厚均为0.1mm。 ⑼10″以下包括10″的管道探伤时,胶片规格为10″×4″;12″-72″的管道探伤时,胶片规格为12″×3-1/3″。有特殊要求的按要求执行。

⑽ 所摄底片应无划伤,水迹,伪缺陷,当采用X 射线时AB 级的底片黑度D=1.8-3.5,当采用γ射线时底片黑度D=2.0-3.5,底片象质指数均应满足不同厚度的要求。底片上标识应齐全(包括管段号,焊口号,焊工号,拍摄日期,返修次数)。 ⑾ 用Ir192γ射线探伤时,应加装准直器,以减少散射线对底片像质的影响。 ⑿ 大口径管预制时,对接焊缝可采用环焊缝内透法或环缝外透法。现场组对焊缝,可采用双壁双影或双壁单影法,具体方法见图示。 探伤设备的选用:当穿透厚度<20mm 时用X 光机探伤,其穿透力应能满足透照工件的要求;当穿透厚度≥20mm 时用Ir192γ探伤机,其影像应与X 光底片相同。探伤机的操作机构应安全可靠,源强应能满足探伤工艺要求。 ⒀ 环焊缝透照的最小焦距: L AB 级=10d ×L 22/3 k=T ′/ T ≯1.1 小口径管环焊缝椭圆透照的最小焦距 Lmin=d ×δ/ug+δ 射线源射线源 胶片 胶片 胶片 射线源 双壁单影 单壁单影 胶片射线源 胶片 胶片 射线源 射线源 双壁双影 (椭圆

无损检测施工方案

无损检测施工方案 施工组织设计(方案)报审表A,2工程名称:云南昆钢师宗98万吨/年焦化项目编号: 致:昆钢xx工程建设监理公司项目监理部 我方已根据施工合同的有关规定完成了空分系统安装工程无损检测施工组织设计(方案)的编制,并经我单位上级技术负责人审查批准,请予审查。 附:施工组织设计(说明、图表)份 施工方案(说明、图表)份 总承包单位(章): (总包)项目经理: 日期: 承包单位(章):项目经理: 日期: 项目监理机构审查意见:项目监理机构审查意见: 总监: 心、jin? (专业)监理工程师: 项目监理机构(章) 日期: 日期: 建设单位审查意见: 建设单位(章) :业主代表: 日期:

昆钢xx98 万吨/年焦化项目 36000Nm/h 型空分安装工程 批准: 审核: 编制: 检测单位:xx 开元安装工程有限公司 二?一?年九月 录目 1、工程概况,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, 2 、编制依据 ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, 3 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5、施工方法、技术措施 ,,,,,,,,,,,,,,,,,,,,,,,,,,,,, 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 、施工进度计划 ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5、质量保证措施及控制点设置 ,,,,,,,,,,,,,,,,,,,,,,,,,, 6 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5、劳动力需用计划及技能要求、施工机具、计量器具 ,,,,,,,,,,,,,,,,,,,,,,,,,,,,, 7 8、安全技术措施及环境管理,,,,,,,,,,,,,,,,,,,,,,,,,,, 、文明施工措施,,,,,,,,,,,,,,,,,,,,,,,, 9 J 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 w 1 工程概况 3 工程名称:6000Nm/h 型空分设备安装工程无损检测施工 建设单位:昆钢xx 焦化 施工单位:xx 开元安装工程有限公司 监理单位:昆钢xx 工程建设监理公司

市政道路工程施工方案设计

目录 第一章工程概况 一、概况 二、工程结构 第二章编制依据及质量目标 一、编制依据 二、组织措施 三、质量目标 第三章施工准备 一、劳动准备 二、技术准备 三、材料准备 四、现场准备 五、管线施工准备 六、施工进度计划 七、施工现场平面布置 第四章主要分部施工方案及技术措施 一、道路 二、排水 三、桥梁 四、板涵 第五章质量目标和保证措施 一、质量目标 二、管理网络 三、保证措施

第六章工程工期保证措施和雨季施工措施 一、工期保证措施 二、缩短工期措施 三、雨季施工措施 第七章施工现场文明管理措施 一、文明施工措施 二、安全生产措施 三、管线综合穿插施工措施 四、社会矛盾方面影响施工的措施 五、成品保护措施 第八章工程成本降低措施 第九章加强多边合作与协调 附表1:项目部具体人员配置 附表2:劳动力组合表 附表3:拟投入本工程的主要施工机具表 附表4:本项目材料试验仪器和质检设备配备表附表5:施工进度计划表 附图1:施工组织机构网络图 附图2:施工现场平面布置图 附图3:石灰土施工工艺流程图 附图4:二灰碎石施工工艺流程图 附图5:沥青下封层工艺流程图 附图6:沥青路面工艺流程图 附图7:排水管道工艺流程图 附图8:质量保证体系图 附图9:文明施工网络图 附图10:安全管理网络图

第一章工程概况一、工程概况 * * * * * * * * * * * * * 二、工程结构 1、道路部分结构 (1)机动车道结构 3cm 细沥青砼面层 4cm 中沥青砼面层 5cm 粗沥青砼面层 沥青封层 20cm(5.5:12.5:82)二灰结石基层 35cm12%石灰土基层+压实路床处理(2)非机动车道结构 3cm 细沥青砼面层5cm 中沥青砼面层 沥青封层 15cm(5.5:12.5:82)二灰结石基层 30cm12%石灰土基层 压路床处理 (3)人行道结构 25*25*5cm彩色道板铺设 3cm1:2.5号水泥砂浆度座浆

无损检测施工技术方案

广州南沙泰山石化仓储项目 外管及码头管道工程 无损检测施工技术措施 中国石油天然气第一建设公司 广州项目经理部 二00六年四月十六日 1工程概况及施工特点 (1)

1.1工程概况 (1) 2编制依据 (1) 3无损检测方案 (2) 3.1检测对象和方法 (2) 3.2无损检测施工总体要求 (2) 3.3检测标准 (2) 3.4无损检测委托程序 (3) 3.5无损检测程序 (3) 3.6射线检测(RT)工艺要求 (3) 3.7检测报告及不合格焊缝的处理 (5) 3.8质量保证措施 (5) 3.9无损检测作业安全管理 (6) 4人力机具动员计戈U (8) 4.1人力动员计划 (8) 4.2人力机具动员计划 (8) 5附件 (8)

1工程概况及施工特点1.1工程概况 工程名称:广州南沙泰山石化仓储项目外管及码头管道工程; 建设地点:广州南沙小虎岛石化工业区; 设计单位:广东省石油化工设计院(外管廊管道) 中交第四航务工程勘察设计院(码头管道) 监理单位:广州宏达工程顾问有限公司 施工单位:中国石油天然气第一建设公司 建设规模: 广州南沙泰山石化仓储项目外管及码头管道工程,主要工程范围有:(1)燃料油库区至码头各相关泊位的DN6OO/10 L290燃料油保温伴热输油管线3根,DN300/8.5、20#燃料油保温伴热输油管线4根;(2)成品油库区至码头各相关泊位的DN500/10 L290汽油输油管线2根,DN300/8.5、20#汽油输油管线3根;(3)成品油库区至码头 各相关泊位的DN500/10 20#柴油输油管线2根,DN300/8.5、20#柴油输油管线3根;(4)码头各相关泊位至码头根部紧急切断阀(含紧急切断阀)之间的DN250/6 20# 化工品输油管线10根,DN200/6 20#化工输油管线14根,DN200的不锈钢输油管线6根;(5)各油品主管道(燃料油、汽油、柴油、化工品)至各泊位的分支管道闸阀之间的分支管道(不含分支管道闸阀的安装);(6)配套的蒸汽(含保温)、氮气、压缩空气、含油污水等公用工程管道;(7)码头蒸汽冷凝水(含保温)回收系统。 2编制依据 2.1广州南沙泰山石化仓储项目外管及码头管道工程施工图纸 2.2《工业金属管道工程施工及验收规范》GB50235-97 2.3《现场设备、工业管道焊接工程施工及验收规范》GB50236-98 2.4《石油化工有毒、可燃介质管道工程施工及验收规范》SH3501-2002 2.5《工业金属管道工程质量检验评定标准》GB50184-93 2.6 JB/T4730-2005《压力容器无损检测》

道路工程施工设计方案与技术措施方案

第五章施工方案与技术措施 第一节工程总体施工方案 一、工程总体施工方案 施工准备:2017年5月19日—2017年5月25日 雨、污水管线施工:2017年5月19日—2017年7月15日 沥青混凝土路面工程:2017年7月20日—2017年8月20日 各工序开工前准备工作: 1、技术准备 组织所有管理及施工技术人员,认真熟悉图纸,学习有关施工技术规范、检验评定标准及工艺操作规程,了解本工程设计意图、施工特点和特殊工序要求,要全员充分了解现场情况。 测量人员做接桩工作,技术、试验及其他管理人员及时到位完成各项准备工作,根据计划安排提出工程用料计划,施工机具计划,明确各类物资进场时间,做好材料试验、报验及厂家资质审查,通过后及时进行加工订货工作。 2、测量准备工作: 2.1对所交点的中心桩和水准点进行复核,认真填写测量复核记录,上报驻地监理工程师进行验收。 2.2验收合格后进行中心桩的拴点和临时水准点引测工作。中心桩的拴点应设置保护措施,临时水准点设置在固定可靠的柱桩上,桩点设明显标志并妥善保护。 2.3测量人员应认真学习复核图纸,掌握有关数据并做好内业工作。 2.4施工完成后应配合有关部门进行竣工测量。 第二节施工方案与技术措施 一、排水工程施工方案 1、道路挖探 通过对设计图纸的认真研究和现场实际勘察,施工前,根据业主提供的现况管线分布图及综合管线规划图,对管线走向进行全面调查,找出与规划位置相矛盾的管线,全部进行挖探,挖探深度与排水管道沟底设计标高相同,摸清各管线的埋深和走向,绘制实际的地下管线分布图,与各相对应管线单位达成施工保护共识后,对其进行填埋。并在现场做出明显标记,派专人保护巡查,防止施工中受到损失。积极与业主、监理及管线管理单位协商,编制每条管线详细的改移及保护措施,若在单位挖探过程中发现的管线高程不能满足正常施工

无损检测技术的方案

射线检测技术方案 一、射线检测设备和原材料现场验收程序 1)无损检测所用设备、材料的生产厂家、品牌必须由业主和监理工程师认可。 2)材料和设备到场后应由专人负责接货、验收。审查随货配备材料合格证,材质证明书、说明书是否齐全,并根据装箱单对材料、设备进行外观检查,抽查、测试和鉴别标记,做好检查验收记录。 3)材料和设备到达现场经检查验收合格,并再经业主或监理认可方可使用。 4)不合格的材料和设备要坚决退货,合格的材料和设备按规定入库存放。 5)材料、设备的搬运和运输由设备材料负责人负责。并做好材料、设备的运输、搬运、储存、防护和管理。由技术质量负责人对此过程控制的执行情况进行监督和检查。材料、设备的搬运和运输要做到轻拿轻放,防止剧烈颠簸,避免仪器、设备在搬运过程中因碰撞而出现故障,以防止胶片出现折痕,药粉泄漏等情况发生。 6)材料、设备的管理要设立专用库房。库房内配备温度计,湿度计、灭火器具等,库房内保持通风、干燥。库房内材料摆放要整齐,并按要求做好状态标识。避免阳光直射。材料和设备要专人、专岗进行保管,保证其从入库到发放期间储存得当,防止因保管不当造成材料和设备损坏、受潮、腐蚀和丢失。 7)对材料的入库和发放要认真检查并做好记录。帐、卡、物相符。保管期间,要定期进行抽检,防止失效、变质,保证材料的质量。不合格的材料不能发放使用,杜绝不合格材料用到工程上。对设备要定期维护保养,保证设备始终处于良好状态。对有故障的设备要及时进行维修,保证生产需要。 二、射线检测质量控制管理工作程序 1) 在接到监理检测指令后,随即依照指令对焊缝进行射线检测,应并在监理要求的时间内,将检测结果报送监理。 2) 检测责任人员在接到监理检测指令后,应对工件的结构、坡口形式、焊接方法及管壁厚度等进行了解,并核对监理指令与所透照工件是否相符,核对内容包括:项目名称、焊缝编号、管壁厚度等。在对焊缝进行射线检测前,应对焊缝外观进行检查,外观不合格有权拒绝检查并通知监理工程师,待施工单位整改合格后重新进行检测。 3) 每张底片必须有初评、复评工序。对底片评定质量,探伤技术负责人应进行抽查审核。对因片质不和格或曝光不足等原因造成底片需重拍或补拍的,应通知监理单位并及时组织

无损检测的概述

第一章无损检测概述无损检测目的无损检测范围常用的无损检测办法射线检测(RT)渗透检测(PT)磁粉检测(MT)超声检测(UT)涡流检测(ET) 第一章无损检测概述 无损检测是指在不损伤和破坏材料、机器和结构物的情况下,对它们的物理性质、机械性能以及内部结构等进行检测的一种方法,是探测其内部或外表的缺陷(伤痕)的现代检验技术。所以,无损检测技术是提高产品质量,促进技术进步不可缺少的手段。无损检测的目的: (1)确保工件或设备质量,保证设备安全运行 用无损检测来保证产品质量,使之在规定的使用条件下,在预期的使用寿命内,产品的部分或整体都不会发生破损,从而防止设备和人身事故。这就是无损检测最重要的目的之一。 (2)改进制造工艺. 无损检测不仅要把工件中的缺陷检测出来,而且应该帮助其改进制造工艺。例如,焊接某种压力容器,为了确定焊接规范,可以根据预定的焊接规范制成试样,然后用射线照相检查试样焊缝,随后根据检测结果,修正焊接规范,最后确定能够达到质量要求的焊接规范。(3)降低制造成本 通过无损检测可以达到降低制造成本的目的。例如,焊接某容器,不是把整个容器焊完后才无损检测,而是在焊接完工前的中间工序先进行无损检测,提前发现不合格的缺陷,及时进行修补。这样就可以避免在容器焊完后,由于出现缺陷而整个容器不合格,从而节约了原材料和工时费,达到降低制造成本

的目的。 无损检测的范围 (1)组合件的内部结构或内部组成情况的检查 (2)材料、铸锻件和焊中缺陷缝的检查 a 、质量评定 b 、寿命评定 (3)材料和机器的计量检测通过定量的测定材料和机器的变形量或腐蚀量来确定能不能继续使用。例如,用超声波测厚仪来测定容器的腐蚀量,通过射线照相来测定原子反应堆用过的燃料棒的变形量、喷气发动机叶片的变形量等。(4)材质的无损检测 无损检测可以用来验证材料品种是否正确,是否按规定进行处 理,例如,可采用电磁感应法来进行材质混料的分选和材料热处理状态的判别。(5)表面处理层的厚度测定 确定各种表面层的深度和厚度。例如,用电磁感应检测法可以测定渗碳淬火层的深度和镀层的厚度。 (6)应变测试常用的无损检测办法射线检测(RT) 射线检测(探伤)有X射线、丫射线和中子射线等检测方法。它是利用各种射线源对材料的透射性能及不同材料的射线的衰减程度的不同,使底片感光成黑度不同的图像来观察的。射线检测用来检测产品的气孔、夹渣、铸造孔洞等立体缺陷。当裂纹方向与射线平行时就能被检查出来。 1、基本原理 利用射线通过物质时的衰减规律,即当射线通过物质时,由于射线与物

装置检修无损检测施工方案

文件编号:DQLH-ARGG-JSCS-10-2010 xx公司180万吨/年ARGG装置检修工程 无损检测技术方案 xx公司 xx项目经理部 2010年7月14日 版次:第A1版

目录 1.无损检测技术要求 (3) 2.主要检测方案 (3) 3. 检测部位表面质量要求 (3) 4.检测时机 (3) 5.检测工艺流程 (4) 6.射线检测(RT)工艺 (6) 7.渗透检测(PT)工艺 (12) 8.磁粉检测(MT)工艺 (13) 9.无损检测人员资格要求 (15) 10、质量保证措施 (16) 11风险识别及预防措施 (16) 12、安全措施 (17)

1.无损检测技术要求 (1)检测比例要求: A、本工程无损检测主要是工艺管线焊缝的检测、再生斜管固定口的探伤、进口烟道焊缝的探伤等,检测比例要符合设计或规范规定。 B、抽检时以每一种管线号为基准对每名焊工所施焊的不同材质,不同规格的焊接接头按设计要求进行抽检。 C、对管道焊缝返工扩检应执行GB50235-97中的下列规定: 当抽样检验未发现需要返修的焊缝缺陷时,则该次抽样所代表的一批焊缝应认为全部合格;当抽样检验发现需要返修的焊缝缺陷时,除返修该焊缝外,还应采用原规定方法按下列规定进一步检验: a每出现一道不合格焊缝应再检验两道该焊工所焊的同一批焊缝。 b当这两道焊缝均合格时,应认为检验所代表的这一批焊缝合格。 c当这两道焊缝又出现不合格时,每道不合格焊缝应再检验两道该焊工的同一批焊缝。 2.主要检测方案 (1)对于本装置中工艺管道对接焊缝射线检测一般采用常规χ射线检测为主的检测方法。 (2)工艺管道检测有困难的固定焊口、容器类焊缝等可采用γ射线进行双壁单影或双壁双影透照。 (3)对于大壁厚(单壁≥25mm)工艺管道对接焊缝可采用下列检测方法: A、周向χ射线或γ射线周向一次曝光。 B、γ射线双壁单影透照。 3. 检测部位表面质量要求 (1)进行检测作业前,必须对被检焊缝的表面质量进行确认,符合标准要求后方可进行检验。 (2)射线检测部位表面的不规则状态以不掩盖或不影响内部缺陷显示作为是否修磨处理的限度。 4.检测时机 (1)检测对象应经形状尺寸和外观质量检查合格后,方可进行检测。