对板式无砟轨道轨道中维修问题的相关探讨摘要:板式无砟轨道在我国的铁路工程中应用比较广泛,随着我国铁路建设的不断发展,各种高新技术不断出现,轨道工程中各种问题也不断出现。如何更好的发现解决问题,及时做好维修工作,是保证铁路工作顺利开展的一个重要工作,也是对人民生命财产负责的一个重要表现。本文就我国板式无砟轨道轨道板与砂浆层出现的离缝问题得维修,展开了全面的探讨。

关键词:板式无砟轨道;轨道板;砂浆层;离缝;异丁烯树脂;维修技术

abstract: the plate ballasted track was widely used in china’s railway project, with the continuous development of china’s railway construction, a variety of high-tech emerging track project issues continue to emerge. how to better solve the problem, do maintenance work in a timely manner is an important work to ensure the smooth development of railway work, it is also responsible for an important manifestation of people’s lives and property. this paper discussed maintenance of the problem in plate without ballasted track board and mortar layer appears.

key words: plate ballasted track; orbital plate; mortar layer; away from the seam; isobutylene resin; maintenance 中图分类号:u216.9文献标识码: a 文章编号:2095-2104

CRTSI型板式无砟轨道结构

CRTS I型板式无砟轨道结构 西南交通大学王其昌 (2009.05) 1、结构组成 CRTS I型板式无砟轨道结构由钢轨、弹性扣件、轨道板、水泥乳化沥青砂 浆充填层、混凝土底座、凸型挡台及其周围填充树脂等组成。图 1.1 (a)、(b) 为平板式、框架式板式无砟轨道,图 1.2和图1.3分别为其横纵断面图。 (a) (b) 图1.1 CRTS I型板式无砟轨道 图「2 CR T型板式板式无砟轨道横断面图 图1.3 CRTS I型板式无砟轨道纵断面图 时速200?250公里及时速300?350公里客运专线CRTS I型板式无砟轨道通用参考图[图号:通线(2008) 2201及通线(2008) 2301],已经铁道部经济规

划设计院2008年7月发布。 2、路基地段CRTS I 型板式无砟轨道 图2.1为路基地段CRTS I 型板式无砟轨道,设计应符合下列规定: L 」 L 」 图2.1路基地段CRTS I 型板式无砟轨道 (1) 底座在路基基床表层上设置。 (2) 底座每隔一定长度,对应凸形挡台中心位置,设置横向伸缩缝。 (3) 线间排水应结合线路纵坡、桥涵等线路条件具体设计。当采用集水井 方式时,集水井设置间隔应根据汇水面积和当地气象条件计算确定。 严寒地区线 间排水设计应考虑防冻措施。 (4) 线路两侧及线间路基表面以沥青混凝土防水材料封闭,路基面防水材 料的性能应符合相关规定。 3、桥梁地段CRTS I 型板式无砟轨道 图3.1为桥梁地段CRTS I 型板式无砟轨道,设计应符合下列规定: (1) 底座在梁面上构筑,底座通过梁体预埋套筒植筋与桥梁连接。在底座 一定宽度范围内,梁面应进行拉毛或凿毛处理设计。 (2) 底座对应每块轨道板长度,在凸形挡台中心位置,设置横向伸缩缝。 (3) 底座范围内,梁面不设防水层和保护层;底座范围以外,根据桥梁设 计的相关规定设置防水层和保护层。 (4) 桥上扣件纵向阻力及梁端扣件结构型式应根据计算确定。 ____ A 廉中心应

高速铁路有砟、无砟轨道结构及精调.

第二章高速铁路有砟、无砟轨道结构及精调 第一节概述 无砟轨道是以混凝土或沥青混合料等取代散粒道碴道床而组成的轨道结构形式。由于无碴轨道具有轨道平顺性高、刚度均匀性好、轨道几何形位能持久保持、维修工作量显著减少等特点,在各国铁路得到了迅速发展。特别是高速铁路,一些国家已把无碴轨道作为轨道的主要结构形式进行全面推广,并取得了显著的经济效益和社会效益。以下是无砟轨道的主要优势和缺点。 一、无砟轨道的优势主要有: 1、轨道结构稳定、质量均衡、变形量小,利于高速行车; 2、变形积累慢,养护维修工作量小; 3、使用寿命长—设计使用寿命60年; 二、无砟轨道的缺点主要有: 1、轨道造价高:有砟180万/km,双块式350万,1型板式450万,2型 板式500万。 2、对基础要求高因而显著提高修建成本:有砟轨道可允许15cm工后沉 降,无砟轨道允许3cm,由此引起的以桥代路及路基加固投资巨大。 3、振动噪声大:减振降噪型无砟轨道目前尚不成功,减振无砟轨道选型 存在较大困难。 4、一旦损坏整治困难:尤其是连续式无砟轨道。 第二节无砟轨道结构 一、国外铁路无碴轨道结构型式 国外铁路无碴轨道的发展,数量上经历了由少到多、技术上经历了由浅到深、品种上经历了由单一到多样、铺设范围上经历了由桥梁、隧道到路基、道岔的过程。无碴轨道已成为高速铁路的发展趋势。 1.日本 日本是发展无碴轨道最早的国家之一。早在20世纪60年代中期,日本就开始了无碴轨道的研究与试验并逐步推广应用,无碴轨道比例愈来愈大,成为高速铁路轨道结构的主要形式。据统计,日本高速铁路无碴轨道比例,在20世纪70年代达到60%以上,而90年代则达到80%以上。

CRTSII型板式无砟轨道施工

AUTOCAD2012 安装序列号666-69696969 产品秘钥001D1.txt C RTSⅡ型板式无砟轨道施工 内容摘要:CRTSⅡ型板式无砟轨道是通过水泥乳化沥青砂浆调整层将预制轨道板铺设在现场摊铺的混凝土支承层或现浇柱的钢筋混凝土底座上,并适应ZPW-2000轨道电路要求的纵连板式无砟轨道结构形式。京津城际轨道交通工程首次在国内采用CRTSⅡ型板式无碴轨道技术,本文结合施工经验和CRTSⅡ板式无碴轨道的特点,简要的总结了CRTSⅡ板式无碴轨道施工工艺。 关键词:CRTSⅡ型板式无碴轨道施工工艺 一、概况 京津城际轨道交通工程是我国首次采用CRTSⅡ板式无碴轨道技术的客运专线,该技术从德国博格公司引进,轨道板又称博格板,因板式无碴轨道系统的特点和工程的实际特点,轨道板的生产及运输、存放、底座砼施工、CA砂浆灌注和轨道板精调则是施工中需要特别重视的重难点工程,也是施工工艺上需要突破的难点工程。 CRTSⅡ板式无碴轨道板系统主要有四部分组成:两布一膜滑动层、钢筋混凝土底板座、CA砂浆垫层和轨道板 京津城际轨道交通工程桥梁占有很大的比例,桥上底座为连续钢筋砼板带结构,为适应中国长桥施工需要,针对这一特点,博格公司提出了新型施工工艺:临时端刺方案,通过增设后浇带连接器来解决砼温度应力及变形应力放散问题。该方案对施工工序有严格的要求,同时还有复杂的温度及长度变化计算,对施工各工序间的衔接组织提出了很高的要求。 二、无碴轨道总体施工安排 根据CRTSⅡ型版式无碴轨道施工工艺的特点,必须做到合理安排、精心设计、科学管理以期达到工序衔接合理,形成追赶式、流水线式的施工场面 CRTSⅡ型板式无下面就CRTSⅡ型板式无碴轨道施工现场所涉及到的施工工艺和施工方法进行简要的描述,结合德国博格公司的技术文件和我们现场施工中所涉及到的问题我们将会详细的进行阐述。 3.1 滑动层施工工艺 滑动层铺设前首先检查桥面,核对梁面高程、平整度,检查梁面防水层质量等,

CRTSⅡ型板式无砟轨道施工工法

CRTSⅡ型板式无砟轨道施工工法 1 前言 沪杭客运专线设计采用Ⅱ型板式无砟轨道,设计时速350km/h。通过学习、研究德国博格公司原始技术资料,借签京津城际积累下来的经验教训,外出实地参观学习同时在建的京沪高铁,积极与设计、业主、监理、兄弟单位以及这方面的专家沟通、咨询,充分利用各方面的资源,立足现场实际,提早着手准备,探索、总结、现场观摩、培训学习,在仅一个多月的无砟轨道紧张施工中大胆实施、积极创新,形成了自己一套相对成熟、完善的CRTSⅡ型无砟轨道施工工法。 2 特点 2.1 施工工艺成熟、可靠,质量保证。 2.2 工艺简单,操作方便,可形成流水作业。 2.3 施工效率高,尤其适合快速施工。 3 适用范围 该工法适用于CRTSⅡ型板式无砟轨道结构的高速铁路、客运专线、城际轨道交通等工程的路基、桥上无砟轨道施工。 4 工艺原理 CRTSⅡ型轨道板铺设工艺分两种工况:铺装路基上CRTSⅡ型板和铺装长桥上CRTSⅡ型板。 4.1 桥上无砟轨道结构设计 桥上CRTSⅡ无砟轨道结构由两布一膜滑动层/高强挤塑板、混凝土底座板、水泥乳化沥青砂浆调整层和轨道板四部分组成。自上而下分为:20cm 厚混凝土轨道板,2cm~4cm 沥青砂浆垫层,19cm 厚(直线段)混凝土底座板,“土工布+塑料膜+土工布”滑动层(简称两布一膜)。梁缝处1.5m 范围内为消除梁端转角对底座板的内力,加装5cm 厚高强挤塑板。 Ⅱ型轨道板标准长度6.45m,板缝5cm,板间用张拉锁纵向连接。轨道板铺设于桥面上经精调和灌浆后进行纵向张拉连接成为整体。为了适应连续底座板连续结构,在桥梁两端路基上设置摩擦板及端刺(桥上设临时端刺),以限制底座板中的应力及温度变形,两端刺间底座板纵向跨梁缝连续,在桥梁固定支座上方通过梁体设置的预

(整理)CRTSⅠ型板式无砟轨道施工技术.

CRTSⅠ型板式无砟轨道施工技术 一、概述 CRTSⅠ型板式无砟轨道由钢轨、弹性分开式扣件(本项目为WJ-7A 型扣件)、充填式垫板、轨道板、水泥乳化沥青砂浆调整层、钢筋混凝土底座、凸形挡台及其周围填充树脂等组成。结构分路基、桥梁和隧道地段,结构高度分别为787mm、687mm。轨道板均为预制,标准板长度为4962mm、3685mm和4856mm,一标范围内用到异型板长度有两种分别为4652mm和3345mm。 二、轨道结构设计 (一)总体设计 1.桥梁地段 桥梁地段轨道结构高度为687mm(钢轨176+扣件39+轨道板220+砂浆50+底座202),底座板宽度为2.8m。底座在梁面分段设置,每块轨道板长度底座设置20mm伸缩缝,伸缩缝对应凸形挡台中心并绕过凸形挡台。底座范围内梁面不设防水层和保护层,轨道中线2.6m范围内的梁面在梁场预制时应进行拉毛处理,梁体采用预埋套筒植筋与底座连接。

注意:1.底座施工之前检查梁面是否按要求拉毛。 2.轨道施工完成后再进行桥梁防水层的施工。 3.严格控制梁缝处扣件间距,一般不应大于700mm,困难条件下最大不超过725mm,不满足要求时底座进行悬出,悬出量最大不超过50mm。采取底座悬出措施后扣件间距也不能满足困难条件下要求时应对梁缝进行处理。 4.严格控制梁面高程,保证底座厚度在允许范围内。 2.路基地段 路基地段轨道结构高度为787mm(钢轨176+扣件39+轨道板220+砂浆50+底座302),底座板宽度为3.0m。底座在基床表层上分段设置,普通路基地段每3~4块轨道板长对应的底座长度设置一处伸缩缝。伸缩缝宽20mm。两块底座板之间伸缩缝处设置10根传力杆,传力杆为直径38mm的光圆钢筋。设置标准按《公路水泥混凝土路面施工技术规范》(JTG F30-2003)中表9.1执行。混凝土整体浇筑路基上每块轨道板对应一处伸缩缝,伸缩缝宽20mm。同时,在混凝土路基沉降缝上方底

CRTSⅢ型板式无砟轨道结构组成及施工工艺

CRTSⅢ型板式无砟轨道结构及施工工艺 CRTSⅢ型板式无砟轨道结构组成 1.桥梁地段无砟轨道结构 桥梁地段CRTSⅢ型板式无砟轨道由钢轨、弹性扣件、轨道板、自 密实混凝土层、隔离层、底座等部分组成。轨道结构高度为762mm。轨道板宽2500mm,厚210mm;自密实混凝土层厚100mm,宽度2500mm, 采用C40混凝土;底座C40钢筋混凝土结构,宽度2900mm,直线地段厚 度200m。轨道板与自密实层间设门型钢筋。自密实层设凸台,与底座 凹槽对应设置,凹槽尺寸为1000×700mm,凹槽周围设橡胶垫板。 2.路基地段无砟轨道结构 路基地段CRTSⅢ型板式无砟轨道由钢轨、弹性扣件、轨道板、自 密实混凝土层、隔离层、底座等部分组成。轨道结构高度为862mm。轨道板宽2500mm,厚210mm;自密实混凝土层宽度2500mm,厚100mm,

采用C40混凝土;底座C40钢筋混凝土结构,宽度3100mm,直线地段厚 度300m,每3块板下底座为一块,相连底座间设传力杆结构。轨道板 与自密实层间设门型钢筋。自密实层设凸台,与底座凹槽对应设置,凹槽尺寸为1000×700mm,凹槽周围设橡胶垫板。 CRTSⅢ型板式无砟轨道施工工艺 1.2 工程特点 CRTSⅢ型板式无砟轨道工程施工工序繁多,技术复杂,质量标准高,须专业化队伍精心施做。底座板施工、自密实混凝土配制及灌注、铺装与精调等技术含量高,施工难度大,需认真研究并借鉴在建同类工程经验。施工便道条件较差,轨道板运输困难且存在较大风险。桥上、隧道内作业面狭窄,物流组织困难。 2 主要施工方案 无砟轨道系统由钢筋混凝土底座板、中间隔离层、自密实混凝土填充层和轨道板组成(见图1)。轨道板采用工厂预制。根据工期和线路铺设长度配备无碴轨道施工设备,每套设备负责2个作业单元交

板式无砟轨道混凝土轨道板暂行技术条件

客运专线铁路CRTSI型 板式无砟轨道 混凝土轨道板暂行技术条件 科技基[2008]74号 中国铁道出版社

客运专线铁路CRTSI型板式无砟轨道 混凝土轨道板暂行技术条件 1 适用范围 本暂行技术条件适用于客运专线铁路CRTSI型板式无砟轨道用混凝土轨道板(含预应力混凝土轨道板、预应力混凝土框架板及普通钢筋混凝土框架板,以下简称轨道板)。 本暂行技术条件规定了轨道板用原材料及成品的技术要求、试验方法、检验规则、标识、存放、运输、装卸和质保期。 2 规范性引用文件 下列文件中的条款通过本暂行技术条件的引用而成为本暂行技术条件的条款。凡是注明日期的引用文件,其随后所有的修改单(不包括勘误的内容)或修订版均不适用于本暂行技术条件,然而,鼓励根据本技术条件达成协议的各方研究是否可使用这些文件的最新版本。凡是不注明日期的引用文件,其最新版本适用于本暂行技术条件。 GB1596 用于水泥和混凝土中的粉煤灰 GB/T18046 用于水泥和混凝土中的粒化高炉矿渣粉 GB8076 混凝土外加剂 GB/T8077 混凝土外加剂匀质性试验方法 GB/T176 水泥化学分析方法 JC/T420 水泥原料中氯的化学分析方法 TB10210 铁路混凝土与砌体工程施工规范 TB/T2922 铁路混凝土用骨料碱活性试验方法 TB/T3054 铁路混凝土工程预防碱骨料反应技术条件 GB/T50080 普通混凝土拌合物性能试验方法 GB/T50081 普通混凝土力学性能试验方法标准 TB10425 铁路混凝土强度检验评定标准 GBJ82 普通混凝土长期性能和耐久性能试验方法 GB/T5223.3 预应力混凝土用钢棒

板式无砟轨道工程轨道板施工方案

板式无砟轨道工程轨道板施工方案

新建铁路沈丹客运专线TJ-3标工程 CRTSⅢ板式无砟轨道工程 专项施工方案 编制: 复核: 审核: 批准: 中建股份沈丹客运专线TJ-3标项目部三工区 二〇一四年四月

目录 一、编制依据 ......................................................................................................... - 1 - 二、工程概况 ......................................................................................................... - 2 - 2.1 工程概况 ............................................................................................ - 2 - 2.2底座板布置及结构尺寸 ..................................................................... - 2 - 2.3曲线地段超高设置............................................................................. - 5 - 2.4施工条件............................................................................................. - 7 - 2.4.1自然气候条件................................................................................. - 7 - 2.4.2交通运输条件................................................................................. - 7 - 2.4.3工区沿线可用材料资源................................................................. - 8 - 2.4.4水、电、燃料可用资源情况......................................................... - 8 - 2.4.5通信................................................................................................. - 8 - 三、施工计划安排 ................................................................................................. - 8 - 3.1工期安排............................................................................................. - 8 - 3.1.1单元评估计划................................................................................. - 8 - 3.1.2施工计划......................................................................................... - 8 - 四、施工前期准备 ................................................................................................. - 9 - 4.1技术准备............................................................................................. - 9 - 4.1.1技术培训......................................................................................... - 9 - 4.1.2线下工程验收及交接..................................................................... - 9 - 五、轨道板施工 ................................................................................................... - 12 - 5.5钢筋焊网安装及钢筋加工、绑扎 ................................................... - 18 - 5.6立模 ................................................................................................... - 20 - 5.7底座混凝土施工 ............................................................................... - 21 - 5.8混凝土拆模及养护 ........................................................................... - 23 - 5.9隔离层和弹性垫层施工 ................................................................... - 24 - 5.10自密实混凝土钢筋焊接网安装..................................................... - 25 - 5.11轨道板存放..................................................................................... - 26 - 5.12轨道板铺设..................................................................................... - 29 - 5.13轨道板防上浮和偏移设备安装..................................................... - 31 - 5.14自密实混凝土层施工..................................................................... - 31 - 六、劳动力计划 ................................................................................................... - 33 - 七、各项保障措施 ............................................................................................. - 33 - 7.1工期保证措施 ................................................................................... - 33 - 7.2 质量保证措施 .................................................................................. - 34 - 7.3安全保证措施 ................................................................................... - 37 - 八、环境保护和文明施工目标及措施 ............................................................... - 38 - 8.1环境保护目标 ................................................................................... - 38 - 8.2环境保护措施 ................................................................................... - 38 - 8.3文明施工目标 ................................................................................... - 38 - 8.4文明施工措施 ................................................................................... - 39 -

客运专线铁路CRTSI型板式无砟轨道混凝土轨道板预制施工工法

客运专线铁路CRTS I型板式无砟轨道工程施工工法

1、前言 我公司承担某铁路客运专线TJ-3标第二松花江特大桥DK784+805.42~DK834+518.9段无砟轨道工程的施工任务,其中DK784+805.42~DK832+748.59段为桥梁段,DK832+748.59~DK834+518.9为路基段。整段线路平面位置包括3条平曲线,从小里程至大里程方向平曲线半径分别为R=8000m(超高h=155mm)、R=7000 m(h=155mm)、R=10000 m(h=115mm);纵断面方向有12条竖曲线,线路最大纵坡为12‰。 正线主要采用CRTS I型板式无砟轨道结构。轨道结构由混凝土底座、凸形挡台及周围填充树脂、乳化沥青砂浆调整层、轨道板、WJ-7B扣件和60kg/m钢轨组成。桥梁段轨道结构高度为687mm,路基段为787mm。 混凝土底座及凸形挡台采用C40钢筋混凝土结构。桥梁段混凝土底座宽2800mm,高度为200mm,凸形挡台半径260mm,高出底座板260mm,每隔1块单元板长度设置一道横向伸缩缝;路基段混凝土底座宽为3000mm,高300mm,凸形挡台尺寸与桥梁段相同,每隔2块标准板长设置一道横向伸缩缝,路基与桥台相接处设置1道伸缩缝;缩缝对应凸形挡台位置,并按行车方向绕过凸台。伸缩缝宽20mm,采用聚乙烯泡沫塑料板填充,竣工前缝上部50mm高围用沥青软膏密封。 全线主要采用P4962、P3685、P4856和P4856A四种标准轨道板,并根据地段类型、桥梁类型、长度进行布置,如32m梁上采用P3685+5块P4962+P3685,24m梁上采用P4856A+3块P4856+P4856A,5.5m桥台采用P5500型轨道板。轨道板和底座板中间设置CA砂浆充填层,轨道板与凸形挡台之间采用凸台树脂进行定位。 CRTS I型板式无砟轨道结构是我国在东北严寒地区首次应用的轨道结构,一航局

无砟轨道与有砟轨道的对比

湖南高速铁路职业技术学院毕业论文 (2012届) 论文题目:无砟轨道与有砟轨道的对比 姓名:卿景明 系(院):湖南高速铁路职业技术学院 专业名称:铁道工程 指导老师:*** 2012 年 5 月20 日 中文摘要

随着高速铁路的大规模建设、既有线提速改造及重载铁路的快速发展,作为铁路重要基础设施的轨道结构需要不断更新、技术不断完善。高速铁路的技术核心是高速度,它对轨道结构就有了高平顺性和高稳定性的要求。传统的轨道结构已不适应目前铁路发展的需要,结构形式和设计方法必须相应改变。 在高速发展的今天,轨道交通已经成为了主流的交通工具,特别是城市轨道交通,而轨道交通现在基本都采用无砟轨道的技术进行施工,它相比于有砟轨道确实有一定的优势但也不可避免有各方面的劣势。 随着我国铁路建设水平的不断发展和提高,铁路的建设模式正逐步从客货共线形式向客货分离形式转变,通过对客运专线无砟轨道与有砟轨道的技术、经济比较,无砟轨道已成为客运专线的发展趋势。由于国内铁路建设和运输条件与国外存在差异,没有一种成熟的结构形式能够完全用“拿来主义”坐在国内运用。因此我国铁路轨道技术的发展应当总结国外铁路无砟轨道与有砟轨道的结构特点,充分分析国内的铁路结构和运用条件,选择技术先进、经济合理的轨道结构形式,对比分析无砟轨道与有砟轨道的各种技术,从而优化轨道结构。 关键词:高速铁路无砟轨道有砟轨道 Abstract

With the high speed railway, large-scale construction of existing railway-speed-increasing transformation and overloaded railway of rapid development, as an important railway infrastructure of track structure need to constantly updated, technology improvement. High-speed rail technology core is high speed, it to track structure is the GaoPingShun sex and the high reliability requirements. The traditional rail structure can meet the needs of the development of the current railway, structure form and design method must change accordingly. In the current rapid development of rail transit has become the mainstream of transportation, especially on urban rail transit, and rail traffic now are the basic technology to track a frantic jumble no construction, it is compared to the frantic jumble of a certain track advantage but also hard to avoid the disadvantages. With China's level of railway construction development and improve, railway construction mode gradually from the passenger and freight line forms to passenger separation form change, through to the special passenger line frantic jumble no tracks with a frantic jumble of technology, economy comparison orbit, frantic jumble no track has become the development trend of the passenger special line. Because domestic railway construction and transportation conditions and foreign different, not a kind of mature structure form can completely with "copycat" sat in the domestic use. So China's railway track technology development should be summarized foreign railway tracks with a frantic jumble no frantic jumble the structure characteristics of the track, the full analysis of the domestic railway structure and applying condition, select the advanced technology, reasonable economy of track structure form, comparison and analysis of the frantic jumble no tracks with a frantic jumble of orbit technology, so as to optimize the rail structure. Keywords

CRTSII型板式无砟轨道精调施工工法

CRTSII型板式无砟轨道精调施工工法 京沪项目翟春辉 一.前言: CRTSⅡ型板式无砟轨道技术是我国引进德国博格板式无砟轨道系统技术后,经过消化、吸收、再创新,形成中国特色的板式无砟轨道技术。 轨道板精调是将预制好的CRTSII型轨道板,通过测量安放在指定承轨槽上精调标架棱镜的三维坐标,计算出轨道板实测坐标与设计计算坐标之间的偏差值,调整安装在轨道板下的精调千斤顶,使轨道板位置达到设计要求的过程。 二.工法特点. II型轨道板精调系统要求高标准、高精度、高质量、工序控制严格。精度高体现在位置、几何尺寸、时间、温度等方面,譬如:现浇梁的顶面平整度控制4m/8mm;底座板高程精度±5mm,轨道板粗定位≤10mm,轨道板精确定位控制在≤0.2mm;CA 砂浆从搅拌成品到提升上桥,最终到灌注入板缝控制在30 分钟内;底座混凝土基本浇筑段必须在一天内完成等。因此,板式无砟轨道精调是II型板施工控制中的重要环节。 三.CRTSⅡ型板精调施工工艺 1、CRTSⅡ型板精调采用技术标准及主要技术要求 1.1 采用标准 ⑴、《客运专线无砟轨道铁路工程施工质量验收暂行标准》(铁建设 [2007]85号); ⑵、《高速铁路CRTSⅡ型板式无砟轨道施工质量验收暂行标准》(铁建设【2009】218 号文); ⑶、《客运专线铁路无碴轨道铺设条件评估技术指南》(铁建设[2006]158 号); ⑷、《高速铁路工程测量规范》(TB 10601-2009); ⑸、《高速铁路无砟轨道工程施工精调作业指南》铁建设函【2009】674号 2.2主要技术要求 CRTSⅡ型板(博格板)精调的基础是:每块CRTSⅡ型板结构上具有10对在工厂经过精确打磨过的承轨槽;CRTSⅡ型板调板时控制点为相对精度能够达到平面0.2mm、高

CRTSI型板式无砟轨道结构

CRTSⅠ型板式无砟轨道结构 西南交通大学王其昌 (2009.05) 1、结构组成 CRTSⅠ型板式无砟轨道结构由钢轨、弹性扣件、轨道板、水泥乳化沥青砂浆充填层、混凝土底座、凸型挡台及其周围填充树脂等组成。图1.1(a)、(b)为平板式、框架式板式无砟轨道,图1.2和图1.3分别为其横纵断面图。 (a)(b) 图1.1 CRTSⅠ型板式无砟轨道 41 50 300(路) 200(桥隧仰) I型板式无碴 轨道横断面图 358(隧无仰) 图1.2 CRTSⅠ型板式无砟轨道横断面图 图1.3 CRTSⅠ型板式无砟轨道纵断面图 时速200~250公里及时速300~350公里客运专线CRTSⅠ型板式无砟轨道通用参考图[图号:通线(2008)2201及通线(2008)2301],已经铁道部经济规

划设计院2008年7月发布。 2、路基地段CRTSⅠ型板式无砟轨道 图2.1为路基地段CRTSⅠ型板式无砟轨道,设计应符合下列规定: 图2.1 路基地段CRTSⅠ型板式无砟轨道 (1)底座在路基基床表层上设置。 (2)底座每隔一定长度,对应凸形挡台中心位置,设置横向伸缩缝。 (3)线间排水应结合线路纵坡、桥涵等线路条件具体设计。当采用集水井方式时,集水井设置间隔应根据汇水面积和当地气象条件计算确定。严寒地区线间排水设计应考虑防冻措施。 (4)线路两侧及线间路基表面以沥青混凝土防水材料封闭,路基面防水材料的性能应符合相关规定。 3、桥梁地段CRTSⅠ型板式无砟轨道 图3.1为桥梁地段CRTSⅠ型板式无砟轨道,设计应符合下列规定: (1)底座在梁面上构筑,底座通过梁体预埋套筒植筋与桥梁连接。在底座一定宽度范围内,梁面应进行拉毛或凿毛处理设计。 (2)底座对应每块轨道板长度,在凸形挡台中心位置,设置横向伸缩缝。 (3)底座范围内,梁面不设防水层和保护层;底座范围以外,根据桥梁设计的相关规定设置防水层和保护层。 (4)桥上扣件纵向阻力及梁端扣件结构型式应根据计算确定。 (5)桥面采用三列排水方式。

CRTSI型板式无砟轨道铺设场外揭板试验方案

新建哈尔滨至齐齐哈尔铁路客运专线工程 CRTSI型板式无砟轨道铺设场外揭板试验方案 (HQTJ-3) 编制: 复核: 批准: 中铁十六局集团有限公司哈齐客专项目部 二〇一二年十二月

目录 1工程概况 (1) 2 线外试验段概况 (1) 3 试验段目的 (1) 4 试验内容 (1) 5 线外试验段施工工期计划 (2) 5.1 实验室建设 (2) 5.2 底座板及挡台施工 (2) 5.3 干粉库房和乳化沥青库房建设及材料进场 (2) 5.4 机械及机具设备进场 (2) 5.5 轨道道板铺设及揭板总结 (2) 6 线外试验准备工作 (2) 6.1 组织机构 (2) 6.2 人员配置 (3) 6.3 物资材料 (3) 6.4 机具设备 (3) 7 施工方案 (4) 7.1 底座板及凸形挡台施工工艺 (4) 7.2 轨道板吊装 (4) 7.3 轨道板粗铺 (5) 7.4 轨道板精调 (6) 7.5 CA砂浆灌注工艺 (9) 7.6 CA砂浆的灌注施工质量控制要点 (15) 7.7 凸台树脂灌注工艺 (15) 7.8 揭板检查 (17) 8 施工现场安全技术措施 (18) 1

1工程概况 哈齐客专HQTJ-3标位于黑龙江省大庆市境内,起迄里程:DK109+000~DK173+600(其中DK169+780~DK172+460段大庆站改范围由其它单位施工),全线正线按无砟轨道CRTS Ⅰ型轨道板设计,CRTSI型板铺板双线总长度为61.920Km。 为掌握CRTSⅠ型板式无砟轨道的施工技术,形成一套熟练的无砟轨道底座板施工,轨道板铺设、精调,水泥乳化沥青砂浆拌制及灌注施工工艺。我标段自2013年4月15日对安达跨牵出线特大桥直线段及曲线段(圆曲线最大超高)段进行模拟现场实际进行试验。 2 线外试验段概况 我标段计划试验段设在安达跨牵出线特大桥右侧线路外,二分部3号钢筋厂内,试验场地长50m,宽5m。浇筑桥梁底座板模型30.072米(单线),包括直线段和曲线段工况,其中直线段曲线段各15.036米(单线,直线板3块,曲线板3块),底座板、轨道板及其安装与实际工程完全一致。CPⅢ共设臵6对,间距30米,均匀分布。 3 试验段目的 线外试验段主要目的是熟练掌握各工序施工工艺,形成一套适合当地气候特点的无砟轨道铺设、精调,水泥乳化沥青配臵及灌注施工工艺,并进行人员实作培训。具体目的如下: 3.1 进行底座板的施工工艺试验,并熟悉和掌握工艺; 3.2 进行GRP点测设,并熟悉和掌握平差方法; 3.3 进行轨道板铺设、精调工艺试验,并熟悉和掌握工艺; 3.4 进行轨道板压紧施工工艺试验,并熟悉和掌握工艺; 3.5 进行水泥乳化沥青砂浆现场配合比调试及砂浆拌制、灌注工艺试验,并熟悉和掌握工艺。 4 试验内容 4.1 曲线和直线段GRP点测设及平差试验和方法验证; 4.2 轨道板精调工艺试验; 4.3 压紧工艺试验; 4.4 水泥乳化沥青灌注工艺试验; 1

无砟轨道施工方案

2.3.8无砟轨道施工方案 2.3.8.1 总体施工方案 本标段无砟轨道采用CRTS Ⅲ型板式无砟轨道。其由钢轨、扣件、预制轨道板、配筋的自密实混凝土、限位凹槽、中间隔离层(土工布)和钢筋混凝土底座等部分组成。CRTS Ⅲ型板式无砟轨道结构见“图2-3-8 CRTS Ⅲ型板式无砟轨道横断面图”。轨道板采用单元分块式结构,在路基和桥梁地段轨道板间采用不连接的分块式结构。 轨道中心线 轨道板中间隔离层 自密实混凝土 钢筋混凝土底座 图2-3-8 CRTS Ⅲ型板式无砟轨道横断面图 扣件:采用WJ-8B型弹性扣件。 轨道板:采用先张法预应力轨道板,标准轨道板型号为P5600、P4925和P4856三种,板厚均为200mm,承轨台高度为38mm,混凝土强度等级为C60。 自密实混凝土及限位凹槽:轨道板下铺设自密实混凝土,强度等级为C40,设计厚度为90mm,长度和宽度与轨道板对齐,中间设置单层钢筋焊网。自密实混凝土与混凝土底座采用限位凹槽的方式进行限位和纵横向力的传递,每块轨道板下设置两个限位凹槽,凹槽尺寸为700mm×1000mm,限位凹槽处加设配筋,限位凹槽周围(侧面)设置弹性垫层,弹性垫层应满足结构受力、变形和材料耐久性要求。 中间隔离层:采用厚度为4mm的土工布。 底座:采用钢筋混凝土结构,双层CRB550级冷轧带肋钢筋焊网,直径为φ12mm。底座伸缩缝宽度为20mm,采用聚苯乙烯泡沫塑料板填缝;路基地段底座混凝土强度等级为C35,底座宽度3100mm,底座板厚度为300mm。每3块~4块轨道板对应长度设置宽度为20mm伸缩缝,在伸缩缝位置设置传力杆;桥梁地段底座混凝土强度等级为C40,长度为对应每块轨道板长度,底座宽度为2900mm,底座板厚度为200mm。

CRTSⅡ型板式无砟轨道施工工法

CRTS II型板式无玮轨道施工工法 1前言 沪杭客运专线设计采用11型板式无碎轨道,设计时速350km/ho通过学习、研究德国博格公司原始技术资料,借签京津城际积累下来的经验教训,外出实地参观学习同时在建的京沪高铁,积极与设计、业主、监理、兄弟单位以及这方而的专家沟通、咨魂,充分利用各方面的资源,立足现场实际,提早?着手准备,探索、总结、现场观摩、培训学习,在仅一个多月的无砰轨道紧张施工中大胆实施、积极创新,形成了自己一套相对成熟、完善的CRTS II型无碎轨道施工工法。 2特点 2. 1施工工艺成熟、可靠,质量保证。 2.2工艺简单,操作方便,可形成流水作业。 2.3施工效率高,尤其适合快速施工。 3适用范围 该工法适用于CRTS II型板式无炸轨道结构的高速铁路、客运专线、城际轨道交通等工程的路基、桥上无硅轨道施工。 4工艺原理 CRTS II型轨道板铺设工艺分两种工况:铺装路基上CRTS 11型板和铺装长桥上CRTS n型板。I■ vy vy i ■ ■ 4.1桥上无酢轨道结构设计 桥上CRTS II无炸轨道结构由两布一膜滑动层/高强挤梨板、混凝土底座板、水泥乳化沥青砂浆调整层利轨道板四部分组成。自上而下分为:20cm厚混凝土轨道板,2cm? 4cm沥青砂浆垫层,19cm厚(直线段)混凝土底座板,“土工布+塑料膜+ 土工布”滑动层(简称两布一膜)。梁缝处L 5m范围内为消除梁端转角对底座板的内力,加装5cm 厚高强挤塑板。 II型轨道板标准长度6.45m,板缝5cm,板间用张拉锁纵向连接。轨道板铺设于桥面上经精调和灌浆后进行纵向张拉连接成为整体。为了适应连续质座板连续结构,在桥梁两端路基上设置摩擦板及端刺(桥上设临时端刺),以限制底座板中的应力及温度变形,两端刺间底座板纵向跨梁缝连续,在桥梁固定支座上方通过梁体设置的预埋螺纹钢筋和抗剪齿槽与梁体固结,形成底座板纵向传力结构。底座板两侧设置侧向扫块,限制底座板

客运专线铁路CRTSI型板式无砟轨道制造施工工法

精品资料推荐 客运专线铁路 CRTS I型板式无砟轨道制造施工工法

目录 1适用范围 (1) 2引用标准 (1) 3原材料的质量检验与控制 (3) 3.1原材料的质量检验 (3) 3.2原材料的质量控制(性能要求) (4) 3.3混凝土耐久性检验要求 (4) 4轨道板模型 (7) 5预应力混凝土轨道板的生产工艺流程 (8) 6钢筋加工 (9) 7骨架预制、吊装 (11) 7.1轨道板钢筋骨架预制 (11) 7.2钢筋定位 (11) 7.3钢筋绑扎 (12) 7.4钢筋骨架存放及运输 (13) 7.5轨道板钢筋骨架安装 (13) 8模板安装 (14) 8.1清模 (14) 8.2模板安装 (14) 8.3模型维护 (15) 9混凝土施工 (16) 9.1混凝土配料搅拌工艺流程 (16) 9.2混凝土配料搅拌工艺要求 (17)

9.3混凝土搅拌 (17) 9.4混凝土运输 (18) 9.4混凝土灌注和振动 (19) 10混凝土蒸汽养护、试件制作和强度检验 (20) 10.1蒸汽养护 (20) 10.2试件制作和强度检验 (20) 11脱模 (22) 12半成品存放和水养护 (26) 13预应力施加 (27) 13.1 一般规定 (23) 13.2张拉设备要求 (23) 13.3张拉准备工作 (24) 13.4张拉作业 (24) 13.5预应力钢棒切割和封锚 (25) 14轨道板的储存和堆放 (27) 15减震型轨道板 (28) 16成品检验 (28) 17产品标记和产品合格证 (30) 18轨道板装卸和运输 (31) 19职业健康安全环境保护注意事项 (31)