Aktogay Copper Project Sulphide Plant

Method Statement

For Railway Crossing Construction and Cable Protective Pipe Installation

11250-ZB-NFC-0000-MS-G-0056Rev.D

D 26-Feb-2016

Issued for

comment

Xia Chunyu Liu Baoguo Guan Chengming

C18-Feb-2016Issued for

comment

Xia Chunyu Liu Baoguo Guan Chengming

B01-Nev-2015Issued for

comment

Gou Xing Ge Wang Jia Guan Chengming

A 16-April-2015Issued for

Approval

Xia Chunyu Liu Baoguo Sun Yuanpeng

Rev#Date Reason for Issue Prepared by Reviewed by Approved by

Contents

1.Start of work (3)

2.Work completion phase (3)

3.Environmental protection measures (4)

4.Health,Safety and Environment(HSE)Management System (4)

5.Risk analysis (6)

Attachments: (8)

1.Start of work

The Contractor starts to work after KAZ Minerals representative approves and confirms the drawings and the other contractors permit the Contractor’s access to the construction site.

Obtain necessary permits to work on railway and get coordination with local aktogay train KTZ company.Isolation of rail to prevent trains on track while working on track

2.Work completion phase

All work must fully comply with the current applicable editions of the documents issued by the Customer,including,without limitation to,drawings, technical services,manufacturers'recommendations,and standards and norms.

The construction will be carried out according to the following stages:

2.1Removal of the existing upper structure of the railway

Dismantling of the various parts composed of railway sleepers.

Manual digging of the gravel layer.

Provide sketch drawing for road rerouting,road traffic requirement signs

2.2Foundation pit excavation

Building of a crane platform to facilitate the crane’s operation.

Excavation of the cable trench to the design elevation of the casing foundation, and leveling and tamping of the foundations.

2.3Installation of hot dip galvanized(HDG)steel pipes

Laying of sands at the bottom.

Installation of hot dip galvanized steel pipes.

Laying of sands on the upper layer.

Placing of cable protective covers.

Backfilling of cable trench.

Setting up of plastic signs.

2.4Construction of the roadbed

(a)When the soil layer's thickness is more than0.5m,carry out both soil tamping layer by layer and backfilling of the trench.

(b)When the soil layer's thickness is not more than0.5m,carry out construction of the railway’s roadbed.

2.5Installation of the upper structure of the railway

When the number of sleepers per1km is1600(1440),use R65-type rails whose length https://www.doczj.com/doc/5113955910.html,y rails and concrete sleepers on the roadbed.

Laying of gravels on the roadbed.

Levelling of the roadbed.

3.Environmental protection measures

1)Environment protection should be carried out on the construction site.If,due to the construction,we have to excavate the road and stop the supply of water and electricity,we must make application and get approval in advance.We will repair the excavated roads and ditches timely,remove the site waste materials and rubbish as soon as possible,level the site,make good drainage for the site.When the construction is finished,the site shall be clean without any waster materials.

2)The soil from trench excavation will not be piled up on the road and shall be transported out of the site.During transportation,the soil shall be prevented from coming off the trucks,so as to keep the roads clean.

3)Remove all isolations and close the permits when the work finished.

4.Health,Safety and Environment(HSE) Management System

An HSE administration system shall be set up.HSE management manuals and procedure work documents should be prepared,and records should be taken.

4.1HSE management goal

No construction accidents,no injuries,no environmental pollution accidents.

Put an end to production death accidents,huge fire hazard accidents and traffic accidents.

Construction sites are standard and clean,and environmental protection meets the requirements of Kazakhstan standards.

All the people engaged in special work have the related certificates and be authorised to work on railways.

The designed safety and technical measures are all taken.

4.2HSE management measures.

Necessary permits obtained to work on rail,positive isolation of track eg.lock on track noise(expossive)devices to warn of approaching train

For the selection of the construction temporary camp,fire-proof,anti-explosion, and windproof conditions should be considered,so as to choose a good place.

The rubbish and waste water produced in the temporary camp should be

concentrated and then discharged,and they should not pollute the environment and water resources.

The health and safety of the personnel on the construction site should be fully considered.

The construction site should be cleaned in advance so that it will be neat.The roads should be unblocked to facilitate the transportation and installation.

People should set up warning boards,warning tapes,alarm lamps,guardrails, and banners when there is cutting or excavation on the main roads.In order that the roads will not be blocked,the construction should be carried out only on half part of each road.Red lights must be set up at night.

During the cable trench excavation,pay attention to the protection of the underground fiber optical cables,water supply and drainage pipes,and cables and other facilities.

The workers entering the construction site must wear the uniform personnel protection equipment(PPE),and the people engaged in special work should use the PPE according to the relevant regulations.

Necessary permits obtained to work on rail,positive isolation of track eg.lock on track noise devices to warn of approaching train

5.Risk analysis

NO.Hazards Consequenc

e

Hazard Analysis Control Measures

Remaining

hazard

analysis Conclusion Likelihood Consequence Risk Rating Control Measures Action BY Action When Likelihood Consequence Risk Rating

1

No safety

measures,no

training,no

work permit

Cause fatality

or injury

358

Prepare well for

safety,no training,

no working

Supervisors,

riggers and

operators

Before

activity

112

2Inadequate

supervision

Accident

goes worse

due to

delayed

actions

268

Assign dedicated

supervisors to

monitor all the time

Supervisors,

riggers and

operators

During

activity

123

3Defects of

equipment

Equipment

damage and

personnel

injury

347

Do inspection before

lifting to make sure

lifting equipment is

safe in condition

Supervisors,

riggers and

operators

During

activity

213

4Cutting injury Personnel

injury

246

Distance between

rebar tool handle and

cutting machine cut

should be more than

200mm

Supervisors,

riggers and

operators

During

activity

213

5"No smoking"

and"no fire"

signs not

available in

activity area

Fire257

Smoking not

allowed,erect

smoking area

Supervisors,

riggers and

operators

During

activity

112

6Random cable

extending and

attaching to

rebar

Electrical

hurt

246

Electricians check

site regularly,

intensify training

Supervisors,

riggers and

operators

During

activity

213

7Unsafe voltage

of lighting in

damp area

Electrical

hurt

257

Apply safe voltage in

damp area,such as

36V,24V,12V

Supervisors,

riggers and

operators

During

activity

112

8

No protection

for working at

height,no body

harness used

Falling358

Must wear body

harness when

working at height

Supervisors,

riggers and

operators

During

activity

213

9Scaffolding is

not proper,not

certified

Other injuries448

Scaffolding must be

erected by certified

scaffolding workers,

before use,must be

inspected by HSE

department and tag

out

Supervisors,

riggers and

operators

During

activity

112

10No proprietary

switch cabinet,

not following

regulations

Electrical

hurt

246

Stationary type

equipment use

proprietary switch

cabinet,and follow

regulations

Supervisors,

riggers and

operators

During

activity

112

11The sling is not

attached to over

the center of

gravity of the

load;no

protection when

sling has to be

tied to under the

center of gravity

of the load

Lifting

accident

268

The sling attaches to

over the center of

gravity of the load;

provide protection

when sling has to be

tied to under the

center of gravity of

the load,arrange

qualified and

certified riggers

Supervisors,

riggers and

operators

During

activity

123

12

Riggers and

operators not

understand

lifting

procedures,

crane

function,signals

and safety rules

Lifting

accident

369

Riggers and

operators understand

lifting procedure,

equipment functions,

signals and safety

regulations.

Supervisors,

riggers and

operators

During

activity

213

Attachments:

1、Cable trench location diagram

2、The conduit layout for cable trench across the rail

SIZE SCALE

PROJECT No 11250

LLP NFC Kazakhstan

TITLE

AKTOGAY COPPER PROJECT DRAWING CHECKED DESIGNED

01-04-15

Yuan Jianfu Xiao Peng

01-04-15

100100100100

100450

100

150

100

2300

100

2170

PLASTIC MARKER TAPE RED EMBOSSED

WITH(DANGER-ELECTRICAL CABLES)

CABLE PROTECTION STRIP HI-IMPACT PVC,ORANGE

THE CONDUIT LAYOUT FOR CABLE TRENCH

ACROSS THE RAIL

150 HDG CONDUITS

RAIL

RAILWAY BASE

BEDDING SAND

SELECTED FINE

COMPACTED BCAK FILL

SIZE

SCALE PROJECT No 11250

LLP NFC Kazakhstan

TITLE

AKTOGAY COPPER PROJECT DRAWING CHECKED DESIGNED

01-04-15

Yuan Jianfu

Xiao Peng

01-04-15