Contents

Install FacilitySight 3 Install iFIX 4 Configure ENODE in FacilitySight 7 Configure iFIX Picture 8 Create new locations or remove existing locations for current project 8 Edit Script of picture 12 Configure iFIX OPC Powertool 14 Configure iFIX Database Manager (PDB) 20 Export the Database 20 Edit the CSV file to match this projects requirements 20 Import Database into the Database Manager 25 Configure PharmNet OPC 26 Items left in FacilitySight to complete the installation 29 Create Batch Set’s29 Create Automation to Enable and Disable the Sensors 29 Create Automation for each microbial location 29 Add security to FacilitySight and iFIX 29

Page 2 of 29

Install FacilitySight

https://www.doczj.com/doc/3d4345359.html,e FacilitySight CD or run Setup.bat from CD

a. Note: verify that purple USB key is not in computer

b.Select Yes, to register

c.Select ok, when HASP licensing is complete

d.Select Next to start FacilitySight Wizard and complete Wizard

2.Wait for Installation to complete

https://www.doczj.com/doc/3d4345359.html,unch FaciitySight with purple USB installed to verify the application opens properly

4.Close FacilitySight, remove Purple USB key

Page 3 of 29

Page 4 of 29

Install iFIX

Items needed: iFIX CD (with version 5.0), Service Pack 1, Service Pack 2, and SIM for workspace.

1.

Insert iFIX CD and start iFIX installation

2.

When prompted select typical installation

3.Select the default location to start install and select to begin the installation

4.Wait several minutes for installation

5.During the iFIX 5.0 installation enter the following details in the iFIX configure wizard.

a.Node Name: PMS

b.Node Type:SCADA

Connectivity: Networked

c.

6.

When prompted, Skip the Remote SCADA Node Configuration

7.When prompted, Do not install the iHistorian

Page 5 of 29

8.Finish the Installation and if you wish view the release note when prompted. Some customers

may want a print out of the release note for their documentation.

9.Install Service Pack 1 from USB drive or included CD

a.When prompted reset FactoryDefault.IFD select Yes

.

10.Install Service pack 2 from USB drive or included CD

a.If prompted reset FactoryDfault.IFD select Yes

.

11.Install workspace SIM iFIX50_1668890121.exe from USB driver or included CD

12.Copy initial files from USB Drive or CD into the iFIX install. You should copy the files into

C:Program files\ GE Fanuc\Proficy iFIX\ for each subdirectoy below. Replace the files if there are any existing versions.

13.These files should include the following

a.From the PDB directory: Database CSV file and the OPC file

b.From the Local directory: FixUSerPreferences.ini, PMS.SCU, and workspace.ini

c.From the PIC directory: the Picture and User.fxg

Page 6 of 29

Page 7 of 29

Configure ENODE in FacilitySight

Note: If you are preconfiguring the installation in an office or preparing for FAT, make sure the ENODE has the same modules in the same order that will be installed at the customer facility.

1. Install Purple USB Key to computer

2. Connect ENODE to network

3. Program IP Address

4. Launch FacilitySight

5. Open Instrument Configuration and program flow meter and solenoid valve for each microbial

location

6. The names used will be displayed on the screen in FacilitySight so use the ones specified by the

customer in the design documentation.

7.

Below are examples of the Analog Input and Relay Output screens for six Microbial Locations:

Configure iFIX Picture

https://www.doczj.com/doc/3d4345359.html,unch iFIX and make sure the workspace opens. If the application opens in run mode select

the workspace. If you are launching iFIX for the first time, select the “Don’t show this box” in

the lower left hand corner, then select the open PMS SCADA. Also, since we copied files into

the setup you might need to cancel errors about tags that iFIX can not find.

2.In the workspace rename the picture for this project by using the save as functionality Create new locations or remove existing locations for current project

Note: Use the picture above as a key for making the following changes.

3.Select entire group, or all the objects for a location. Copy and paste new locations until you

have the number of microbial locations needed for the installation.

4.Select the location name of the first position. If the items are grouped use the shift key to select

item in the group.

a.Once the item is selected edit the text by right clicking on the item and select Edit Text,

then delete and type in the desired text

5.Select the Sample Status, if the item is grouped use the shift key to select the item inside the

group.

a.Once the Sample Status is selected right click on the item and select Animation…

b.Select the Configure… button in the Additional Animations on the lower right hand

corner of the Basic Animations Dialog

Page 8 of 29

Page 9 of 29

c.

Select the text tab on the animation dialog that appears.

d. For the data source field change the item to represent the correct item in the PDB. See

image below for details. The item selected should be the Status tag for the location you

are editing.

Note: if you are creating or making changes to the pictures before you have changed

the PDB you might get an error regarding the tag, make sure you select “Use Anyway”

so that the formulas do not change.

e. Select OK, and then Select OK again.

6. Select the Combo box, if the item is grouped use the shift key to select the item inside the group.

a. Once the Sample Status is selected right click on the item and select Animation…

b. Select the Configure… button in the Additional Animations on the lower r ight hand

corner of the Basic Animations Dialog

c.

Select the Behavior tab

Page 10 of 29

d. Select OK, and then Select OK again.

7. Select the Sample Time, if the item is grouped use the shift key to select the item inside the

group.

a. Once the Sample Status is selected right cl ick on the item and select Animation…

b. Select the Configure… button in the Additional Animations on the lower right hand

corner of the Basic Animations Dialog

c.

Select the Color tab

d. For the data source field change the item to represent the correct item in the PDB. See

image below for details. The item selected should be the Timer tag for the location you

are editing.

e.

Select the Text tab

f. For the data source field change the item to represent the correct item in the PDB. See

image below for details. The item selected should be the Timer tag for the location you

are editing.

g. Select OK, and then Select OK again.

8.Select the Totalized Flow, if the item is grouped use the shift key to select the item inside the

group.

a.Once the Totalized Flow is selected right click on the item and select Animation…

b.Select the Configure… button in the Additional Animations on the lower right hand

corner of the Basic Animations Dialog

c.

Select the Text tab

d.For the data source field change the item to represent the correct item in the PDB. See

image below for details. The item selected should be the Total Flow tag for the location

you are editing.

e.Select OK, and then Select OK again.

9.Repeat Steps 2 – 6 for each location you added to the screen.

10.For the All Control Combo Box, you need to edit the Animation to control all the new Combo

boxes you have added, or deleted.

a.Select the ComboBox in the All Control section

b.Right click on the ComboBox and select Animation…

c.In the Data Source text box make sure that the OR statement correctly represents all the

locations that have been created for this installation. This list might be too long or you

Page 11 of 29

Page 12 of 29

might need to add additional locations to this formula

Edit Script of picture

11. Right click on the picture and select Edit Script…

12. The VBA editor will appear. For each location that you added a sub routines for the combobox,

start, pause and stop buttons were added to the code. The titles of the sub routines are correct; however the formulas in the sub routine are not correct. Each sub routine needs to be edited to reference the correct tags. Be very careful to change all the sub routines correctly.

a.

Example of the Stop sub routine

13. The All controls ComboBox, Start, Pause and Stop buttons need to be edited to include all the

microbial locations.

a.

Example of Start sub routine

14.The initialize combo box sub routine needs to be edited to add additional entries for each

combo box, you can also take the time to edit the correct numbers that your customer wants to see in the drop down box.

a.Example of initialize combo sub

routine

Page 13 of 29

Configure iFIX OPC Powertool

1.From the Database manager, select a tag that uses the OPC driver

2.Double click on the tab

3.Open the OPC P owertool by selecting the I/O Address… button next to the driver line

4.The OPC powertool will open and each flow tags from the ENODE needs to be added as a tag so

iFIX can totalize the flow and send it back to FacilitySight.

5.IF you are starting from a new configuration select the server button in the

lower left hand corner.

Page 14 of 29

6.When prompted for the OPC Server, Select the ParticleMeasuringSystems.facilityMonitoring.1

server.

Page 15 of 29

Page 16 of 29

7.

Once the server selected give the server the name of “S”

8. Select the Enable check box.

9. Select the Group Button in the lower left hand corner.

10.Enter a group name of “G”

11.Select the enable check box

Add each flow meter as an item by selecting the item Button on the bottom toolbar.

12.

Enter the item name that was used in the address of the *_Enable_Disable tag of the Database Manager.

Page 17 of 29

Page 18 of 29

13. Use the Browse Server…

Button to find the correct data fields on the server.

14. Repeat step 12 & 13 until all Flow meter values are added to the OPC Powertool.

15. Save the File to the PDB folder and note the name of the file

16. From the Options menu select Setup

17. Select the Default Path

tab on the setup dialog

18.Enter the filename you just created in the Default configuration file name: text box.

19.Add PDB\ to the end of the Default path for configuration file: in the middle of the dialog.

Select the Advanced tab and make sure it looks like the screen shot below:

20.

21.Select OK.

22.Select the start button (green arrow)

23.Select Save

24.Close the OPC Powertool

Page 19 of 29

Configure iFIX Database Manager (PDB)

Export the Database

You can start for the existing database or use a project CSV file from a previous project that is similar

1.Open the Database Manager by selecting the icon on the toolbar.

2.Open the “Local Node”

3.Export the Database to CSV file by selecting the Export button or Database menu then select the

Export… option.

4.When prompted give it a filename

Edit the CSV file to match this projects requirements

1.Open the file in Excel

2.For each AI tag duplicate two rows to represent the Value of the flow meter and the Status, in

this example FC1 and FC1_status:

3.Copy these two lines for each additional microbial location you are adding

4.Edit the following parameters for these two lines to represent each location

a.Tag Name

b.Next Block (heading Next BLK)

c.Edit the description if appropriate

d.Edit each address (heading I/O ADDRESS)

e.For status the Addresses should increment by 20

f.For the flow meter, this should be the same address used in the OPC power tool,

S;G;[name entered].value

g.A new line should look like this:

Page 20 of 29