当前位置:文档之家› 典型车间变电所及低压配电系统设计—

典型车间变电所及低压配电系统设计—

典型车间变电所及低压配电系统设计—
典型车间变电所及低压配电系统设计—

摘要

变电所是电力系统的重要组成部分,它担负着从电力系统中受电、经过变压,然后分配电能的任务,因此变电所的设计工作是整个电网设计和运行的重要部分。

本次设计对10kV车间配电所及低压配电系统进行了详细设计,根据各个车间的负荷数量和性质,生产工艺对负荷的要求,以及负荷布局,本着安全、可靠、优质、经济,结合实际情况,解决对各个部门的安全可靠,经济技术的分配电能问题。

设计时,首先进行各个车间负荷计算及确定无功补偿方案,提出2个可行的主变压器配置方案,然后通过对技术经济指标,确定主变压器的选择,进而确定主接线方案。接着进行短路电流计算,并根据短路电流计算结果选择变电所所需的一次设备、确定二次回路和继电保护整定以及车间照明设计,最后进行防雷接地设计。

关键字:车间变电所主变选择一次设备继电保护

ABSTRACT

Substation is an important part of power system, it assumes by electricity from the power system, through the transformer, and then assigned the task of power, so the designof substation design and operation of the entire power grid an important part.

The design of the 10kV distribution plant clinics and low voltage distribution system designed in detail,according to the various workshops the number and nature of the load, the production process on the load requirements as well as load distribution, in a safe, reliable, high-quality, economy, combined with the actual situation to address the various departments of the safe, reliable, economic and technological problem of the distribution of power.

First of all, for each plant load calculation and determine the reactive power compensation scheme, proposed two possible configuration of the main transformer, and then on the technical and economic indicators to determine the choice of the main transformer, and then determine the main connection of the program.Followed by short-circuit current calculation and choice according to short-circuit current calculations in a

substation equipment needed to determine the secondary circuit and relay setting and lighting design workshop, the final design for lightning protection and grounding.

Keywords: workshopsubstation;Select the main transformer;Primary Equipment;relay protection

目录

1.1 供配电的现状 (2)

1.2 本设计的目的及意义 (3)

1.3 本设计的主要工作 (4)

1.4 车间原始资料 (5)

2.2 负荷计算 (5)

2.3 无功功率补偿 (13)

3.1 变压器的台数和容量选择 (13)

3.2主接线设计方案 (16)

4.1 短路电流计算条件 (19)

4.2 高压电网短路电流计算 (19)

4.3 低压电网短路电流计算 (22)

5.1 一次设备选择与校验的条件与项目 (27)

5.2 高压电器的选择与校验 (31)

5.3 低压电器的选择与校验 (39)

5.4 高低压母线选择 (46)

5.6 变电所进出线及与临近单位联络线的选择 (47)

7.1 二次回路设计 (48)

7.2 继电保护整定 (48)

9.1 变电所的防雷保护 (54)

9.2.变电所公共接地装置的设计 (55)

1 绪论

1.1 工厂供配电的现状

改革开放十几年来,国民经济飞速发展,人民的物质文化水平日益提高。但从全局来看,发展水平不尽相同,在国内各地区,变电所自动化水平也参差不齐。总的看来,沿海经济开放地区发展速度较快。以能代表自动化发展水平的无人二次变为例,深圳地区已有相当部分达到无人值守,在自动化方面,具备了遥信、遥测、遥控、遥调功能,并具有微机保护设备。遥控的实现,可避免运行人员的误操作,计算机根据当前的运行状态,做出正确的判断,供运行人员参考,避免系统事故的发生,减少人身伤亡及财产损失,提高经济效益。此外,山东、河北、江苏等地也投产了一部分无人值守二次变,而且根据发展情况,他们制定了一条原则,就是新投产的二次变一定达到无人值守程度,旧的变电所通过改造也要逐步实现无人值守。他们所采用的设备大部分为国外进口,但自动化设备也不乏国内产品,如南京自动化设备厂的微机保护及RTU 等均有应用。内陆地区虽比不上沿海经济区的发展速度,但在自动化方面也取得了很大进展,在东北的多数城市如哈尔滨、大庆等电业部门已投入了多套微机保护系统,而在微机远动、绝缘在线监测方面也取得了一定的成绩。为了进一步提高电力自动化水平,各省局目前也在逐步扩大无人值守二次变和220kV 变电所综合自动化试点范围,这些都将推

动各省变电所自动化的迅猛发展。

从有关变电所自动化产品方面看,国内目前已有众多厂家能生产微机远动、微机保护等设备,绝缘在线监测及微机故障处理设备也不断涌现,大部分都已达到能投入实际运行的水平,有些产品如微机保护已跻身国际先进行列。

综上所述,目前国内变电所自动化工作正处于飞速发展、蒸蒸日上的阶段。

1.2 本设计的目的及意义

在工厂里,电能虽然是工业生产的主要能源和动力,但是它在产品成本中所占的比重一般很小(除电化工业外)。电能在工业生产中的重要性,并不在于它在产品成本中或投资总额中所占的比重多少,而在于工业生产实现电气化以后可以大大增加产量,提高产品质量,提高劳动生产率,降低生产成本,减轻工人的劳动强度,改善工人的劳动条件,有利于实现生产过程自动化。从另一方面来说,如果工厂的电能供应突然中断,则对工业生产可能造成严重的后果[1]。

因此,做好工厂供电工作对于工业生产,实现工业现代化,具有十分重要的意义。由于能源节约是工厂供电工作的一个重要方面,而能源节约对于国家经济建设具有十分重要的战略意义,因此做好工厂供电工作,对于节约能源、支援国家经济建设,也具有重大的作用。

1.3 本设计的主要工作

①选用需用系数法确定计算负荷,将车间内多台设备按其工作特点分组,把负荷曲线大致相近的分为一组,即用电设备组,然后一组为单位进行负荷计算。在充分发挥设备潜力、改善设备运行性能、提高其自然功率因数的情况下,达不到规定的工厂功率因数要求时,则需要考虑增设无功功率补偿装置;

②按设计要求来选择选择一台S9低损耗配电变压器,联结组别采用Yyn0;

③根据主变压器的选择以及负荷对供电可靠性的要求初步确定2个比较合理的主接线方案,并根据技术经济指标选择合适的;

④按照正常运行条件(即电气设备正常运行的工作电压及工作电流)选择电气设备,按短路电流所产生的电动力效应及热效应进行校验,并考虑设备装设地点的环境条件对设备的影响;

⑤通过比较经济指标和技术技术指标确定主接线方案;

⑥在高压侧装设专用计量柜、三项有功电度表、无功电度表和电压互感器-避雷器柜等。在低压侧的动力出线上装设有功电度表和无功电度表,照明线路上装有三相四线有功电度表。低压并联电容器组线路上安装无功电度表。每一回路均装设电流表。低压母线装有电压表。在主变压器上装设瓦斯保护、过电流保护和过负荷保护等继电保护装置并对继电保护装置进行整定,检验其是否符合要求。

⑦根据相关技术要求进行车间电气照明设计,使得生产车间拥有

足够的照度。

⑧进行接地与防雷设计。

1.4 车间原始资料

本厂为三班工作制,年最大负荷利用小时数为4000小时,属三级负荷。

①电源从35/10KV 工厂总降压变电所采用架空线路受电,线路长为400m ,已知与本厂高压侧有电气联系的架空线路总长度为80km ,电缆线路总长度为25km ;如下图所示:

10KV A MV S k .200)

3(

架空线路

400m0.4Ω/km

10KV 车间变电所(待设计)

工厂总降压变电所

图1.1 引入车间变电所的线路图

②工厂总降压变电所10KV母线上的短路容量为250MVA。

③工厂总降压变电所10KV配电出线路定时限过流保护装置的整定时间为2S;

④要求车间变电所最大负荷时功率因数在0.9以上;

⑤在车间变电所10KV侧进行计量。

机加工一车间用电设备及其他车间用电情况

表1.1机加工一车间设备明细表

表1.2其它车间负荷计算表

2 负荷计算和无功功率补偿

2.2 负荷计算

2.2.1 单组用电设备计算负荷的计算公式

①有功计算负荷(单位为KW ):e d P K P =30,d K 为系数

②无功计算负荷(单位为kvar ): ?tan 3030P Q =

③视在计算负荷(单位为kva ): ?cos /3030P S =

④计算电流(单位为A ):N U S I 3/3030=,式中N U 为用电设备额定电压

(单位为KV )

2.2.2 多组用电设备计算负荷的计算公式

①有功计算负荷(单位为KW ):i p P K P .3030∑=∑

式中30P ∑是所有设备组有功计算负荷30P 之和,p K ∑是有功负荷同时系

数,可取0.85~0.95。

②无功计算负荷(单位为kvar ):i p Q K Q .3030∑=∑

式中30Q ∑是所有设备无功30Q 之和, q K ∑是无功同时系数,可取

0.9~0.97。

③视在计算负荷(单位为kva ): 23023030Q P S +=

④计算电流(单位为A ):N U S I 3/3030=

2.2.3 机加工一车间电力负荷计算

依照车间平面图中设备配置情况,将车间配电线路分为三条回路。

回路一包含设备代号为: 1到13,32到35;回路二包含设备代号为:14到31;回路三为照明回路。

① 回路一计算负荷:

查表知,d K =0.2,?cos =0.5,?tan =1.73

=e P (10.5+2.075+8.6533+5.625+4.62537+31.9+35.7+10+70)Kw =224.125Kw

e d P K P =)1(30=0.23224.125Kw = 44.825Kw

?tan )1(30)1(30P Q ==44.825Kw 31.73=77.547var k

kVA P S 65.895.0/825.44cos /)1(30)1(30===?

A V kVA U S I N 209.136)3803/(65.893/)1(30)1(30=?==

② 回路二计算负荷:

电热设备组,查表知,d K =0.7,?cos =1,?tan =0,=e P 89Kw 热30P =0.73 (20+24+45)Kw =62.3Kw

热30Q =62.3Kw 30=0

金属切削机床组,查表知,d K =0.2,?cos =0.5,?tan =1.73,=e P 83.975Kw

金30P =83.975Kw 30.2=16.795Kw

金30Q =16.795Kw 31.73=29.055var k

回路二计算负荷总计:

=e P 89Kw +83.975Kw =172.975Kw

)2(30P =热30P +金30P =79.095Kw

某电机修造厂全厂总降压变电所及配电系统设计

某电机修造厂全厂总降压变电所及配电系统设计 一、生产任务及车间组成 1.本厂产品及生产规模 本厂主要承担全国冶金工业系统矿山、冶炼和轧钢设备的配件生产,即以生产铸造、锻造、铆焊、毛坯件为主体,生产规模为:铸钢件1万吨、铸铁件3千吨、锻件1千吨、铆焊件2千5百吨。 2.本厂车间组成 (1)铸钢车间;(2)铸铁车间;(3)锻造车间;(4)铆焊车间;(5)木型圈车间及木型库;(6)机修车间;(7)砂库;(8)制材场;(9)空压站;(10)锅炉房;(11)综合楼;(12)水塔;(13)水泵房及污水提升站等。 二、设计依据 1.厂区平面布置图(略) 2.全厂各车间负荷计算表如下:各车间380伏负荷

3.供用电协议 工厂与电业部门所签订的供用电协议主要内容如下: (1)工厂电源从电业部门某220/35千伏变电所,用35千伏双回架空线路引入本厂,其中一个为工作电源,一个作为备用电源,该变电所距离工厂东侧4.5km处,单位长度电抗值为0.4Ω/km。 (2)供电系统短路技术数据如下: 区域变电所35kV母线短路数据如下: 系统最大运行方式:S dmax=200MVA;系统最小运行方式:S dmin=175MVA (3)电部门对本厂提出的技术要求 ①区域变电所35kV配出线路定时限过电流保护装置的整定时间为2秒,工厂总降不应大于1.5秒。 ②该厂的总平均功率因数值应在0.9以上。 ③在企业总降压变电所高压侧进行计量。

三、设计范围与任务 1.负荷计算 全厂总降变电所负荷计算,是在车间负荷计算基础上进行的,考虑车间变电所变压器的功率损耗,从而求出全厂总降变电所高压侧计算负荷及总功率因数。列出负荷计算表,表达设计成果。 2.总降变电所位置和各个变压器台数以及容量的选择 考虑电源进线方向,综合考虑设置各个变电所的有关因素,结合全厂计算负荷以及扩建备用的需要,确定主变台数容量。 3.厂总降压变电所主接结线设计 根据变电所配电回路数,负荷要求可靠性级别的计算负荷值,确定高低压侧的接线形式。 4.厂区高压配电系统设计 根据厂内负荷情况,从技术、经济合理性确定厂区配电电压。择优选择配电网布置方案,按选定配电系统作线路结构与敷设方式设计。 5.工厂供配电系统短路电流计算 工厂用电,通常为电网末端负荷,其容量远远小于电网容量,均按无限容量系统供电进行短路电流计算。 6.改善功率因数装置设计 COS,通过查表和计算求出达到供电部门要根据负荷计算要求本厂的高压配电所的 求的数值所需补偿的无功功率。由产品样本选出需补偿电容器的规格和数量,并选用合适的电容器柜。 7.变电所高低压侧设备选择 参照短路电流计算数据和各回路计算负荷以及相应的额定制,选择各种电器设备、开关柜等。用主结线图、设备材料表等表达设计成果。 8.继电保护及二次结线设计 内容包括继电保护装置、监视及测量仪表、控制和信号装置及备自投,用二次回路原理图或展开图及元件材料表来表达设计成果。 9.变电所防雷、接地装置设计 参考本地气象、地质资料设计防雷装置,并进行接地装置设计计算。 10.总降变电所变、配电装置总体布置设计 综合前述设计计算成果,参照有关规程,进行室内、室外变配电装置的总体布置和施工设计。 11.车间(机加车间)变电所及低压配电系统设计 根据生产工艺要求,车间环境,用电设备容量、分布情况等进行设计,确定车间变电所所用变台数、容量。 四、本厂的负荷性质 本厂为三班工作制,年最大有功负荷利用小时数为6000小时。属于二级负荷。 五、工厂的自然条件 1.气象条件 (1)最热月平均最高温度为30℃; (2)土壤中0.7~1米深处一年中最热月平均温度为20℃; (3)土壤冻结深度为1.10米; (4)夏季主导风向为南风; (5)年雷暴日数为31天。

供配电工程课程设计-10KV变电所电气设计

供配电工程课程设计任务书 1.题目 能动学院10kV变电所电气设计 2.原始资料 2.1 课题原始资料 工程概况地下室为自行车库,地上五层,集实验室、办公室、研究室等综合性建筑。框架结构,现浇楼板,共有南北两栋楼。根据工程的总体规划,学院楼拟用两台变压器,一用一备,两路10kV电源进线引自校内10kV总配电所,变压器设在北楼一层的室内。现已建一台10/0.38kV变压器,另一台为二期工程,二级负荷的备用电源引自校内10kV总配电所。在南楼设置总配电间,电源引自北楼变电所。本工程消防负荷(如排烟风机、消防电源、应急照明、防火卷帘等)、弱电电源、客梯电力等为二级负荷,其余照明、空调、实验用电等均为三级负荷。二级负荷采用双回路(分别引自两段低压母线)供电,消防负荷采用双回路供电,两路电源末端配电箱自动切换;三级负荷采用单回路供电。 电力负荷:

2.2 供电条件 (1)供电部门110/10kV变电所位于工程附近1.5km处,10kV母线短路电流为20kA,根据需要可提供给用户1路或2路10kV专线供电。 (2)采用高供高计,要求月平均功率因数不少于0.95。不同电价负荷,计量分开。如学校用电统一执行居民电价,公共建筑执行商业照明电价、非工业动力电价,工业企业生产用电统一执行大工业电价、职工生活用电执行居民电价。 (3)供电部门要求用户变电所高压计量柜在进线主开关柜之前,且第一柜为隔离柜。 2.3 其他资料 当地最热月的日最高气温平均值为38℃,年最热月地下0.8m处最高温度平均值为25℃。当地年雷暴日数为35天。当地地质平坦,海拔高度为100m,土壤为普通粘土。 3.具体任务及技术要求 本次课程设计共1.5周时间,具体任务与日程安排如下: 第1周周一:熟悉资料及设计任务,负荷计算与无功补偿、变压器选择。 周二:供配电系统一次接线设计,设计绘制变电所高压侧主接线图。 周三:设计绘制变电所低压侧主接线图。 周四:设计绘制变电所低压侧主接线图。

工厂总配变电所及配电系统设计

工厂总配变电所及配电 系统设计 文档编制序号:[KKIDT-LLE0828-LLETD298-POI08]

重庆大学网络教育学院毕业设计(论文) 题目某工厂总配变电所及配电系统设计 学生所在校外学习中心四川遂宁校外学习中心 批次层次专业201601、专科起点本科、电气工程及其自动化 学号W1420345 学生杨敏 指导教师董光德 起止日期

在国民经济高速发展的今天,电能的应用越来越广泛,生产、科学、研究、日常生活都对电能的供应提出更高的要求,因此确保良好的供电质量十分必要。论文注重理论联系实际,理论知识力求全面、深入浅出和通俗易懂,实践技能注重实用性,可操作性和有针对性。 本设计选择进行了一个模拟的中小型工厂10/、容量为的降压变电所,区域变电站经10KV双回进线对该厂供电。该厂多数车间为三班制。本厂绝大部分用电设备属长期连续负荷,要求不间断供电。全年为306个工作日,年最大负荷利用小时为6000小时。属于二级负荷。 论文论述了供配系统的整体功能和相关的技术知识,重点介绍了工厂供配电系统的组成和部分。系统的设计和计算相关系统的运行,并根据工厂所能取得的电源及工厂用电负荷的实际情况,并适当考虑到工厂的发展,按照安全可靠、技术先进、经济合理的要求,确定了变电所的位置与形式及变电所至变压的台数与容量、类型及选择变电所主接线方案及高低设备与进出线。 本论文共分部分包括:负荷计算和无功功率补偿、变电所位置和形式选择、变电所主变压器的台数、类型容量及主接线方案的选择、短路电流的计算、变电所一次设备的选择与校验、变电所电气主结线图、工厂二次回路方案的选择继电保护的设计与整定以及防雷、接地设计:包括直击雷保护、行波保护和接地网设计。 关键词:负荷计算短路计算主接线无功补偿设备选择

工厂供配电系统设计设计

湖南理工职业技术学院 工厂供配电技术课程设计题目:某工厂供配电系统的电气设计 年级专业:风能工程系机电1132班 学生姓名:龙博 指导老师:卢永辉 2015年06月15日

摘要 工厂供电,是指工厂所需的电能的供应与分配,也称工厂配电。 众所周知,电能是现代工业生产的主要能源和动力。电能既能易于由其他形式的能量转换而来,而易于转换为其他形式的能量以供应用。电能的输送和分配既简单经济,又便于控制、调节和测量,有利于实现生产过程自动化,而且现代社会的信息技术和其他高新技术无疑不是建立在电能应用的基础之上的。因此电能在现代工业生产及整个国民经济生活中应用极为广泛。 本论文设计首先计算电力负荷和变压器的台数、容量;利用所学的知识确定变电所的位置。计算出短路电流的大小,选出不同型号的变压器,进而确定变压器的连接组别,画出必要的变电所主接线图。 关键词:主接线图、短路电流、电力负荷、变压器 目录 第1章前言 (4) 第2章设计任务 (5) 2.1 原始资料 (5) 2.2 工厂平面图 (5) 2.3 工厂供电电源 (5)

2.4 工厂负荷情况 (6) 2.5 设计要求 (7) 第3章全厂负荷计算和无功功率补偿 (8) 3.1 负荷计算 (8) 3.2 无功功率补偿 (11) 第4章变电所高压电器设备选型 (12) 4.1 主变压器的选择 (12) 4.2 各个车间变压器的选择 (12) 4.3 10KV架空线的选择 (13) 第5章短路电流的计算 (14) 5.1 短路的基本概念 (14) 5.2 短路的原 (14) 5.3 短路的后果 (14) 5.4 短路的形成 (15) 5.5 三相短路电流计算的目的 (15)

[某工厂变电所设计]某工厂车间变电所供配电设计

[某工厂变电所设计]某工厂车间变电所供配电设计 第一章绪论 1.1.1机械工厂供电的意义和特点 工厂是工业生产的主要动力能源。工厂供电设计的任务是从电力系统取得电源,经过合理的传输,变换,分配到工厂车间中的每一个用电设备上。随着工业电气自动化技术的发展,工厂用电量的迅速增长,对电能的质量,供电的可靠行以及技术经济指标等的要求也日益提高。供电设计是否完善,不仅影响工厂的基本建设投资,运行费用和有色金属的消耗量,而且也反映到工厂供电的可靠性和工厂的安全生产上,他与企业的经济效益,设备和人身安全等是密切相关的。 供电设计的任务是从厂区以外的电网取得电源,并通过厂内的变配电中心分配到下厂的各个供电点。它是工程建设施下的依抓,也是日后进行验收及运行维修的依据。供电设计首先要确定供电系统并进行用电负荷计算,然后将设计的供电系统图及用电容量向供电部门申请。申请用电容量的大小应满足生产需要,也要考虑到节省投资和节约能源,这就要求设计者对对工艺专业和公用专业用电负荷系数有足够的把握。在设计计算中除了查找外,还必须借助于设计者在中长期积累的经验数据。由于机械工厂车间组成类型多,产品、工艺日新月异,对供电要求各不相同,非专业设计院或个体设计者一不了解机械

生产工艺和生产规律,要作出好的设计,相对来说要困难些。比如机加工车间,从设备明细表中看出用电电量颇大,大小设备用电量相差较大,用电特点是短时下作制的设备多,机加工设备辅助传动电机一般仅工作几秒钟,而停歇时间却达几分钟、甚至几小时。在作负荷计算时对设备下作时间要了解, 并把不同的用电设备按组划分确定其 计算功率。 工厂供电工作要很好地为工业生产服务,切实保证工厂生产和生活用电的需要,并做好节能工作,就必须达到下列基本要求: ①安全在电能的供应,分配和使用中,不应发生人身事故和设备事故②可靠应满足电能用户对供电可靠性即连续供电的要求③优质应满足电能用户对电压和频率等质量的要求 ④经济供电系统的投资要省,运行费用要低,并尽可能节约电能和减少有色金属的消耗量 此外,在供电工作中,应合理的处理局部和全局,当前和长远等关系,既要照顾全局和当前的利益,又要有全局观点,能顾全大局,适当发展。

供配电系统设计毕业设计

届毕业生毕业设计说明书 题目:某机械厂供配电系统设计 院系名称:电气工程学院专业班级: 学生姓名:学号: 指导教师:教师职称:讲师 20年6月6日

目次 1 2 3 4 5 6 7结概述 (1) 1.1 国内外发展现状 (1) 1.2 供配电系统的研究意义 (1) 1.3 研究的内容 (2) 负荷计算及无功补偿 (3) 2.1 电力负荷的类型 (3) 2.2 负荷计算 (3) 2.3 无功功率补偿 (8) 变电所主变压器选择和主接线方案选择 (10) 3.1 变电所主变压器的选择 (10) 3.2 主接线方案设计 (10) 3.3 厂区规划图 (12) 短路电流的计算 (14) 4.1 短路电流计算的基本公式 (14) 4.2 电抗标幺值的计算公式 (14) 4.3 确定基准值、计算电抗标幺值 (15) 高、低压电气设备的选择与校验 (18) 5.1 高压设备的选择与校验 (18) 5.2 低压设备的选择与校验 (20) 5.3 母线的选择 (20) 5.4 导线的选择 (21) 继电保护的整定与计算 (22) 6.1 高压线路的继电保护 (22) 6.2 电力变压器的继电保护 (23) 防雷和接地装置 (24) 7.1 防雷 (24) 7.2 接地装置 (24) 7.3 防雷措施 (25) 论 (26) 致谢 (27) 参考文献 (28) 附录A 电气主接线图 (30)

1 1.1概述 国内外发展现状 现代大中型工厂供配电系统的电气主接线和运行方式都比较复杂,各种电 气设备的数量和种类也比较多,随着经济和现代工业建设的迅速发展,供电系统的设计越来越全面、系统,工厂用电量迅速增长,对电能质量、技术经济状况、供电的可靠性指标也日益提高,因此对供电设计也有了更高、更完善的要求。 供配电系统是电力系统的电能用户,也是电力系统的重要组成环节。它由总降压变电所、高压配电所、车间变电所、配电线路以及用电设备组成。在小型工厂中,电能先经过高压配电所,然后经过变压器降压,低压配电线路将车间变电所的电能送到各低压用电设备。 在我国,供配电的建设未能得到重视,资金短缺,技术性能落后,另外供配电技术环节形成电力需求与供配电设施不协调的局面。随着人们生产活动的日渐增多,工厂对电能的需求也在日益增加,作为评估电能质量的相关指标,例如电能的可靠性、电能的经济状况、电能的质量等指标也随之有待提高。 1.2供配电系统的研究意义 现如今,电能已经成为人们生活中不可或缺的能源和生活工具,其在工业 生产,生活的各个领域中获得了广泛应用,为人们提供更加舒适便捷的工作环境和生活环境创造了条件。电力是现代事业发展的主要能源和动力,没有电力可以说就没有国有经济的现代化。现代的生活都离不开电力,都是建立在电气的基础上。因此,电力供应如果中断,将会给现代的发展带来严重的影响。譬如那些对可靠性有有很高要求的企业,即使工厂中设备停电的时间极短,也能引起工厂中严重的事故发生,轻则把电气设备烧坏,重则威胁到人身安全,故而,必须认真做好达到系统供电要求,切实保证电力系统的正常运行,更好地发展生产,实现过程的全部自动化。 要切实保障生产和日常社会生活的需求,就必须做好工厂供电系统的工作,在确保可靠供电的前提下,考虑并努力做好节能减排工作,实现高效,优质供电供电部门必须做到以下几点:

典型车间变电所及低压配电系统设计—

摘要 变电所是电力系统的重要组成部分,它担负着从电力系统中受电、经过变压,然后分配电能的任务,因此变电所的设计工作是整个电网设计和运行的重要部分。 本次设计对10kV车间配电所及低压配电系统进行了详细设计,根据各个车间的负荷数量和性质,生产工艺对负荷的要求,以及负荷布局,本着安全、可靠、优质、经济,结合实际情况,解决对各个部门的安全可靠,经济技术的分配电能问题。 设计时,首先进行各个车间负荷计算及确定无功补偿方案,提出2个可行的主变压器配置方案,然后通过对技术经济指标,确定主变压器的选择,进而确定主接线方案。接着进行短路电流计算,并根据短路电流计算结果选择变电所所需的一次设备、确定二次回路和继电保护整定以及车间照明设计,最后进行防雷接地设计。 关键字:车间变电所主变选择一次设备继电保护

ABSTRACT Substation is an important part of power system, it assumes by electricity from the power system, through the transformer, and then assigned the task of power, so the designof substation design and operation of the entire power grid an important part. The design of the 10kV distribution plant clinics and low voltage distribution system designed in detail,according to the various workshops the number and nature of the load, the production process on the load requirements as well as load distribution, in a safe, reliable, high-quality, economy, combined with the actual situation to address the various departments of the safe, reliable, economic and technological problem of the distribution of power. First of all, for each plant load calculation and determine the reactive power compensation scheme, proposed two possible configuration of the main transformer, and then on the technical and economic indicators to determine the choice of the main transformer, and then determine the main connection of the program.Followed by short-circuit current calculation and choice according to short-circuit current calculations in a

10~0.4kV变电所供配电系统初步设计

10~0.4kV变电所供配电系统初步设计 摘要:从负荷计算、无功补偿、站址选择、主接线选用、短路电流、设备选型、继保配置、防雷接地、照明、配网自动 化等方面论述了10kV变电站设计的主要内容和设计程序. 关键词: 10kV变电站; 设计; 负荷计算; 无功补偿 10kV配电网属中压配电网,它延伸至用电负荷的中心或居民小区内,直接面对工矿企业和居民等广 大用户的供电需要,起着承上启下确保用户供电的作用,因此10kV配电网所处的地位十分重要. 在配电 工程中,能否保证系统安全、经济、可靠地运行,工程的设计质量是一个重要条件. 本文就10kV变电站的 设计思路进行探讨. 1 负荷计算及负荷分级 计算负荷是确定供电系统,选择主变容量、电气设备、导线截面和仪表量程的依据,也是整定继电保护 的重要数据. 因此,正确进行负荷计算及负荷分类是设计的前题,也是实现供电系统安全、经济运行的必要 手段. 此阶段需要的原始资料有: ①供电区域的总平面图; ②供电区域逐年及最终规模的最大负荷、年耗电 量、功率因数值及项目投产日期; ③每回出线的名称、负荷值、各负荷的性质及对供电可靠性或其它方面的 特殊要求; ④供电部门对电源电压、供电方式、电源路数及继电保护、自动装置等方面的相关意见; ⑤用户 对变电站设置方面的数量、容量、位置等的设想及资金准备情况等. 计算负荷的方法多种多样,如需用系数法、二项式法、利用系数法等. 目前多数采用需用系数法与二项 式法相结合的方法,部分采用利用系数法. 但是由于利用系数法其理论依据是概率论和数理统计,计算结

果比较接近实际,因此也适用于各类的负荷,在以后的负荷计算工作中将占主导地位. 负荷根据其对供电可靠性的要求可划分为一、二、三级负荷. 对于一级负荷,如医院的手术室等必须有 两个独立的电源供电,如同时具备两个条件的发电厂或变电所的不同母线段等,且当两个独立电源中任一 电源失去后,另一电源能保证对全部一级负荷的不间断供电. 对于一级负荷中的特别重要负荷,也称保安 负荷. 如用于银行主要业务的电子计算机及其外部设备、防盗信号等必须备有应急电源,应由两个独立的 电源点供电. 如两个发电厂、一个发电厂和一个地区电网或一个电力系统中的两个区域性变电所等. 独立 于正常电源的发电机同样可作为应急电源,实行先断后通. 对于二级负荷一般需有两个独立电源供电,且 当任一电源失去后,另一电源能保证对全部或部分的二级负荷供电. 对于三级负荷,通常只需一个电源供 电. 在各类负荷中,除了保安负荷外,都不应按一个电源系统检修或故障的同时另一电源又发生故障进行 设计. 2 无功补偿的确定 在电力系统中,存在着广泛的、大量的感性负荷,在系统运行中消耗大量的无功功率,降低了系统的功率因数,增大了线路的电压损失,电能损耗也增高. 因此,国家供用电规则规定:无功电力应就地平衡,用户 应在提高用电自然功率的基础上设计和装置无功补偿设备,并做到随其负荷和电压变动及时投入或切除, 防止无功倒送. 目前广泛采用并联电容器作为无功补偿装置,分集中补偿和分散补偿两种. 在确定无功补 偿方案时应注意如下问题: 2. 1 补偿方式问题

某塑料制品厂全厂总配变电所及配电系统设计

摘要 某塑料制品厂全厂总配变电所及配电系统设计是对工厂供电的设计。本设计对工厂供电方式、主要设备的选择、保护装置的配置及防雷接地系统进行了相应的叙述,其中还包括全厂的负荷计算、高压侧和低压侧的短路计算、设备选择及校验、主要设备继电保护设计、配电装置设计、防雷和接地设计等。本设计通过计算出的有功、无功和视在功率选择变压器的大小和相应主要设备的主要参数,再根据用户对电压的要求,计算补偿功率,从而得出所需补偿电容的大小与个数。 根据国家供电部门的相关规定,画出总配变电所及配电系统的主接线图。电气主接线对电气设备的选择,配电所的布置,运行的安全性、可靠性和灵活性,对电力工程建设和运行的经济节约等,都有很大的影响。,,, 关键词:变电所,负荷计算,设备选型,继电保护 ABSTRACT

The whole plant distribution substation andpower distribution system designof a plastic products factory is for powerplant design. The design makes thenarrative about thefactory power supply, main equipment selection,protection device configuration and groun dingsystem for lightning protection, whichalso includesthe load calculation of the factory,theshort circuit current calculation of the highpressure side and low pressure side, equipment selection andvalidation, the main equipment relay protection design, power distribution equipment design, lightning protection andgroundingdesign. This design is based on thecalculation of the active p ower, reactivepower and apparent power transformer andthe size of the corresponding main equipment main parameter, then worksout the compensation computing power according touserrequirements to v oltage .Thus it can obtain the desirable size and numberof compensat ion capacitor. According to the relevantprovisions of the nationalelectricity sector, the design draws the main connection diagram about the total distributionsubstation andpowerdistributionsystem. Main el ectricalconnection havegreat influence on the electrical equipmentselection,the layout of the distribution,operation safety, r eliability and flexibility,also power engineering construction and economy ofthe operationand so on. Keywords: substations, load calculation,equipment selection,re lay protection

标准件厂冷镦车间低压配电系统及车间变电所设计超详细

标准件厂冷镦车间低压配电系统及车间变电所 设计超详细 Standardization of sany group #QS8QHH-HHGX8Q8-GNHHJ8-HHMHGN#

某标准件厂冷镦车间低压配电系统及车间变电所设计 1 10kv变电所设计任务书及分析 工程设计任务书内容包括:工程设计目的,建设规模和系统供电的连接,用电单位负荷容量,工程建设期限等,工程设计人员接到任务书后,应对设计任务书作初步分析,并收集有关设计资料. 10kv变电所设计任务书 1.1.1 变电所位置 本变电所设在冷镦车间东北角。车间内最热月平均气温为30℃;地中最热月平均气温为25℃;土壤冻结深度为1.10m;车间属正常干燥环境;车间原址为耕地,地势平坦。地层以砂粘土为主,地下水位-5.3m。 1.1.2 变电所基本设计资料 1.变电所电压等级:10/ 2.本变电所10kv经0.2km电缆线路与本厂总降压变电所相连。 3.工厂总降压变电所10kv母线上的短路容量按300Mkv计。工厂降压变电所 10kv配电出现定时限过电流保护整定时间top=。 4.要求车间变电所最大负荷时功率因数不低于,车间变电所10kv侧进行电能计量。 5.本变电所除给冷镦车间供电外,还需给工具、机修车间供电。 6.负荷情况: (1)工具车间要求车间变电所低压侧提供四路电源。 (2)机修车间要求车间变电所低压侧提供一路电源。 (3)工具,机修车间负荷计算表如表1-1所示。 表1-1 工具、机修车间的负荷统计表 ,属于三级负荷。 (5)冷镦车间生产任务急产品规格:本车间主要承担我国机械和电器制造工业的标准螺钉配件生产。标准螺钉元件规格范围为M3-M18,车间明细表1-2如图所示

10KV变电所配电系统设计

10KV变电所及其配电系统的设计 摘要:变电所是电力系统的一个重要组成部分,由电器设备及配电网络按一定的接线方式所构成,他从电力系统取得电能,通过其变换、分配、输送与保护等功能,然后将电能安全、可靠、经济的输送到每一个用电设备的转设场所。变电所涉及方面很多,需要考虑的问题多,分析变电所担负的任务及用户负荷等情况,选择所址,利用用户数据进行负荷计算,确定用户无功功率补偿装置。同时进行各种变压器的选择,从而确定变电站的接线方式,再进行短路电流计算,选择送配电网络及导线,进行短路电流计算。选择变电所高低压电气设备,为变电所平面及剖面图提供依据。本变电所的初步设计包括了:(1)总体方案的确定(2)负荷分析(3)短路电流的计算(4)配电系统设计与系统接线方案选择(5)继电保护的选择与整定(6)防雷与接地保护等内容。 关键词:变电所;负荷;输电系统;配电系统

第1章绪论 1.1工厂变配电所的设计 1.1.1用户供电系统 电力用户供电系统由外部电源进线、用户变配电所、高低压配电线路和用电设备组成。按供电容量的不同,电力用户可分为大型(10000kV·A以上)、中型(1000-10000kV·A)、小型(1000kV·A及以下) 1.大型电力用户供电系统 大型电力用户的用户供电系统,采用的外部电源进线供电电压等级为35kV 及以上,一般需要经用户总降压变电所和车间变电所两级变压。总降压变电所将进线电压降为6-10kV的内部高压配电电压,然后经高压配电线路引至各个车间变电所,车间变电所再将电压变为220/380V的低电压供用电设备使用。 某些厂区环境和设备条件许可的大型电力用户也有采用所谓“高压深入负荷中心”的供电方式,即35kV的进线电压直接一次降为220/380V的低压配电电压。 2.中型电力用户一般采用10kV的外部电源进线供电电压,经高压配电所和10kV用户内部高压配电线路馈电给各车间变电所,车间变电所再将电压变换成220/380V的低电压供用电设备使用。高压配电所通常与某个车间变电所合建。 3.小型电力用户供电系统 一般小型电力用户也用10kV外部电源进线电压,通常只设有一个相当于车间变电所的降压变电所,容量特别小的小型电力用户可不设变电所,采用低压220/380V直接进线。 1.1.2工厂变配电所的设计原则 1.必须遵守国家的有关规程和标准,执行国家的有关方针政策,包括节约能源、节 约有色金属等技术经济政策。 2.应做到保障人身和设备安全、供电可靠、电能质量合格、技术先进和经济合理,应采用效率高、能耗低、性能较先进的电气产品。 3.应根据工程特点、规模和发展规划,正确处理近期建设与远期发展的关系,做到远、近期结合,以近期为主,适当考虑扩建的可能性。 4.必须从全局出发,统筹兼顾,按照负荷性质、用电容量、工程特点和地区

供配电系统设计毕业设计

届毕业生 毕业设计说明书题目:某机械厂供配电系统设计 院系名称:电气工程学院专业班级: 学生姓名:学号: 指导教师:教师职称:讲师 20年 6月 6日

目次 1 概述 0 1.1 国内外发展现状 0 1.2 供配电系统的研究意义 0 1.3 研究的内容 (1) 2 负荷计算及无功补偿 (1) 2.1 电力负荷的类型 (1) 2.2 负荷计算 (1) 2.3 无功功率补偿 (4) 3 变电所主变压器选择和主接线方案选择 (5) 3.1 变电所主变压器的选择 (5) 3.2 主接线方案设计 (6) 3.3 厂区规划图 (7) 4 短路电流的计算 (7) 4.1 短路电流计算的基本公式 (7) 4.2 电抗标幺值的计算公式 (7) 4.3 确定基准值、计算电抗标幺值 (8) 5 高、低压电气设备的选择与校验 (9) 5.1 高压设备的选择与校验 (10) 5.2 低压设备的选择与校验 (11) 5.3 母线的选择 (12) 5.4 导线的选择 (12) 6 继电保护的整定与计算 (13) 6.1 高压线路的继电保护 (13) 6.2 电力变压器的继电保护 (14) 7 防雷和接地装置 (14) 7.1 防雷 (14) 7.2 接地装置 (14) 7.3 防雷措施 (16) 结论 (16) 致谢 (17) 参考文献 (17) 附录A 电气主接线图 (19)

1 概述 1.1 国内外发展现状 现代大中型工厂供配电系统的电气主接线和运行方式都比较复杂,各种电气设备的数量和种类也比较多,随着经济和现代工业建设的迅速发展,供电系统的设计越来越全面、系统,工厂用电量迅速增长,对电能质量、技术经济状况、供电的可靠性指标也日益提高,因此对供电设计也有了更高、更完善的要求。 供配电系统是电力系统的电能用户,也是电力系统的重要组成环节。它由总降压变电所、高压配电所、车间变电所、配电线路以及用电设备组成。在小型工厂中,电能先经过高压配电所,然后经过变压器降压,低压配电线路将车间变电所的电能送到各低压用电设备。 在我国,供配电的建设未能得到重视,资金短缺,技术性能落后,另外供配电技术环节形成电力需求与供配电设施不协调的局面。随着人们生产活动的日渐增多,工厂对电能的需求也在日益增加,作为评估电能质量的相关指标,例如电能的可靠性、电能的经济状况、电能的质量等指标也随之有待提高。 1.2 供配电系统的研究意义 现如今,电能已经成为人们生活中不可或缺的能源和生活工具,其在工业生产,生活的各个领域中获得了广泛应用,为人们提供更加舒适便捷的工作环境和生活环境创造了条件。电力是现代事业发展的主要能源和动力,没有电力可以说就没有国有经济的现代化。现代的生活都离不开电力,都是建立在电气的基础上。因此,电力供应如果中断,将会给现代的发展带来严重的影响。譬如那些对可靠性有有很高要求的企业,即使工厂中设备停电的时间极短,也能引起工厂中严重的事故发生,轻则把电气设备烧坏,重则威胁到人身安全,故而,必须认真做好达到系统供电要求,切实保证电力系统的正常运行,更好地发展生产,实现过程的全部自动化。 要切实保障生产和日常社会生活的需求,就必须做好工厂供电系统的工作,在确保可靠供电的前提下,考虑并努力做好节能减排工作,实现高效,优质供电供电部门必须做到以下几点:

车间变电所及其低压配电系统的设计

车间变电所及其低压配电系统的设计 姓 名 张勋 学 号 20097353 院、系、部 电气工程系 班 号 方0953-3 完成时间 2012年6月20日 ※※※※※※※※※ ※※ ※※ ※ ※ ※※※※※ ※※※※ 2009级 工厂供电课程设计

第1章设计任务1.1 设计要求

(1)由总降压变电所的配出电压和用电设备的电压要求,参考国际规定的标准电压等级确定车间变电所的电压级别。 (2)计算负荷采用需用的系数法,计算出单台设备支线、用电设备组干线和车间变电所低压母线和进线的计算负荷。 (3)由计算负荷结果,确定补偿方式,计算出补偿容量,选择电容器个数和电容柜个数。 (4)按对负荷可靠性要求,确定车间变电所电气主接线。 (5)按车间变电所低压母线的计算负荷,确定变电器的容量和台数。 (6)导线截面积的选择,支线和干线按发热条件选择,进线电缆按经济电缆密度选择,按允许发热,电压损耗进行校验。 (7)短路电流计算,绘制计算电路和等值电路图,确定短路点,计算出各短路点短路电流值及短路容量。 (8)车间变电所低压母线按发热条件选择,按短路的热合力校验。 (9)按国家规定的标准符号和图符,用CAD画出车间变电所的电气主接线图、车间配电系统和配电平面图。 1.2. 设计条件 1、负荷全部为三级负荷,对供电可靠性要求不高。 2、车间平面布置图如图1所示,车间电气设备明细表如表1所示,外车间低压母线转供负荷如表2所示。 图1 某车间平面布置图 表1 机加车间电气设备明细表如下表所示

表2 车转供负荷名细表如下表所示

; d 低压母线有功功率同时系数为0.90,无功功率同时系数为0.95。 3.车间采用三班制。年最大有功负荷利用小时数为5500H。 4.供电电源条件: 从本厂35/10KV总降变电所用架空线引进10KV电源,该变电所距本车间南0.3KM。 供电部门提出的技术要求如下: 工厂总降压变电所10KV配电出线定时限过电流保护装置的整定时间tp=1.3s。 车间最大负荷时功率因数不得低于0.9。 在车间变电所10KV侧进行计量。 5.工厂自然条件。 气象条件。年最高气温38度,年平均气温35度,年最低气温8度,年最热月平均最高温30度,年最热月地下0.7米-1米处平均温度20度,常年主导风向为南风;年雷暴日180天;土壤冻结深度1.1米。 地质水文资料。平均海拔200米,地层以沙质黏土为主,地下水位3米-5米,地耐压力位20吨每平方米。 第2章车间变电所的电压级别 根据已知车间变电所负荷均为三级负荷,对供电可靠性要求不高,因此可采用线路-变压器接线方式。它的优点是接线简单、使用设备少和建设投资省;其

工厂供配电系统设计设计完整版

工厂供配电系统设计设 计 HUA system office room 【HUA16H-TTMS2A-HUAS8Q8-HUAH1688】

湖南理工职业技术学院 工厂供配电技术课程设计题目:某工厂供配电系统的电气设计 年级专业:风能工程系机电1132班 学生姓名:龙博 指导老师:卢永辉 2015年06月15日

摘要 工厂供电,是指工厂所需的电能的供应与分配,也称工厂配电。 众所周知,电能是现代工业生产的主要能源和动力。电能既能易于由其他形式的能量转换而来,而易于转换为其他形式的能量以供应用。电能的输送和分配既简单经济,又便于控制、调节和测量,有利于实现生产过程自动化,而且现代社会的信息技术和其他高新技术无疑不是建立在电能应用的基础之上的。因此电能在现代工业生产及整个国民经济生活中应用极为广泛。 本论文设计首先计算电力负荷和变压器的台数、容量;利用所学的知识确定变电所的位置。计算出短路电流的大小,选出不同型号的变压器,进而确定变压器的连接组别,画出必要的变电所主接线图。 关键词:主接线图、短路电流、电力负荷、变压器 目录 第1章前言 (4) 第2章设计任务 (5) 2.1 原始资料 (5) 2.2 工厂平面图 (5) 2.3 工厂供电电源 (5)

2.4 工厂负荷情况 (6) 2.5 设计要求 (7) 第3章全厂负荷计算和无功功率补偿 (8) 3.1 负荷计算 (8) 3.2 无功功率补偿 (11) 第4章变电所高压电器设备选型 (12) 4.1 主变压器的选择 (12) 4.2 各个车间变压器的选择 (12) 4.3 10KV架空线的选择 (13) 第5章短路电流的计算 (14) 5.1 短路的基本概念 (14) 5.2 短路的原 (14) 5.3 短路的后果 (14) 5.4 短路的形成 (15) 5.5 三相短路电流计算的目的 (15)

车间变电所设计

四川大学网络教育学院 课程设计说明书 课程设计题目:车间变电所设计 校外学习中心: 学生姓名: 专业: 电气工程及其自动化 层次: 年级: 11秋 学号:

一、前言 本设计是根据创越机械厂的供电电源情况及本厂用电容量和负荷性质,同时考虑到工厂的发展规划,按照保障人身和设备的安全、供电可靠、技术先进和经济合理的要求,采用符合国家现行有关标准的效率高、低能耗、性能先进的电气产品等原则进行变电所的电气设计。 本设计共分八章,首先根据创越机械厂的负荷情况进行有关计算,确定出变电所的位置在电镀车间的东侧紧靠厂房而建,型式为附设式,而后对变电所主接线方案进行选择。采用单母线接线,考虑到厂里有二级负荷,故除由附近一条10KV的公共电源干线取得工作电源外,可采用高压联络线由邻近单位取得备用电源,再通过对两种方案(方案1:装设一台主变压器,型号为S9-1600/10;方案2:装设两台主变压器,型号为S9-1250/10)的技术经济比较得出两种方案均能满足技术指标要求,但方案1比方案2节省397.405万元,经济指标远优于方案2,最终选择方案1,接着通过短路电流计算选择和校验变电所的一次设备,确定出高压断路器采用S N10-10I/630,隔离开关采用GN86-10/200型,户外采用GW4-15G/200型等设备的型号规格及变电所高低压进出线的型号。为了保证供电的安全可靠性,最后两章论述了本所采用的二次回路方案、继电保护方式及变电所的防雷规划与接地装置的设计。 本设计在各位老师的指导下已完成,在此对各位老师表示衷心的感谢,如有不恰之处,请多多指教。

二、目录 第一章负荷计算和无功功率补偿 (1) 第二章变电所位置和型式的选择 (3) 第三章变电所主变压器和主接线方案选择 (4) 第四章短路电流的计算 (7) 第五章变电所一次设备的选择校验 (10) 第六章变电所进出线和与邻近单位联络线的选择 (12) 第七章变电所二次回路方案的选择与继电保护整定 (23) 第八章变电所的防雷保护与接地装置的设计 (27) 主要参考文献 (29)

住宅建筑变电房及供配电设计要点教学文案

住宅建筑变电所及供配电设计要点总结 变电所及供配电设计是住宅设计的重要内容之一,由于各地供电局对变电所及供配电设计又有一些特殊的规定,这些特殊规定反过来又会影响着设计院对建筑、电气、结构、暖通等专业的设计;为避免当地供电局对变电所及供配电设计与设计院的设计不一致,而造成后期各专业的返工,结合融科海阔天空和融科橡树澜湾变电所及供配电设计,总结了一些设计要点。 一、供电局对供配电系统总的要求 1、住宅建筑供配电实行公用和专用配电的方式,居民住宅生活用电属于公用用电,该部分资产无偿划拨给当地供电局,并由其管理、维护,专用配电的资产属于建设单位,由建设单位或委托其他单位管理、维护。 2、在一个规划小区建筑(或单体建筑)内,若专用配电用电负荷小于50KW,其负荷电源可在公用变压器搭接,可不设专用变压器。 3、计量方式:公用配电采用住宅分表计量到户(又称“一户一表”),专用供配电采用高压侧设总计量方式,低压侧设分表计量。 二、变电所设计要点 1、变电所位置选择要点 1)、要求变电所相对位于负荷中心,且低压供电半径不宜超过200 m; 2)、要求变电所正上方或侧上方不能是如厨房、卫生间、浴室、泳池等经常积水的场所; 3)、要求变电所不得设在有爆炸危险环境或火灾危险环境的正上方或正下方; 4)、要求变电所周围(包括正上方和正下方)不得紧邻住宅的卧室、书房、起居室等要求安静的场所,若紧邻上述场所,则要求变电所做隔音处理,变电所内壁采用防火隔音棉等复合材料,要求噪音衰减30分贝以上;

5)、要求变电所的位置方便设备运输及搬运;不宜采用吊装口作为搬运通道; 6)、要求变电所的位置方便高压电缆进线和低压电缆出线。 2、变电所对建筑专业设计要点 1)、变电所面积要求:单台变压器变电所面积为60-80 m 2,两台变压器变电所面积为120-150 m 2;当变电所的形状不规则或变电所内有结构柱时,要求适当加大变电所的面积; 2)、层高要求:变电所室内净高(室内地坪至梁下口)不小于3 m; 3)、门窗要求:变电所长度大于7米,要求设置不少于2个独立向外开启的钢质甲级或乙级防火门,门要求设置在两端;长度大于60米时,要求增设1个独立向外开启的钢质甲级或乙级防火门(变电所位于地下室时,其门要求为甲级防火门,变电所位于地上时,通向相邻房间的门为甲级防火门,通向过道或室外,要求为乙级防火门),门宽要求1 . 8 m,高度为2 . 4 m; 4)、室内墙面、天棚装饰要求:白色内墙涂料要求 5)、室内地面装饰要求:地坪要求做防潮防水处理,室内地面铺设300×600浅灰色仿古地砖; 6)、室内电缆沟要求:要求做防潮防水处理,电缆沟尺寸600×600—800 m m (宽×深,单排支架为600 m m深,两排支架为800 m m深);沟盖板荷载不小于2KN/ m 2) 7)、室外通道要求:要求室外运输通道宽度不小于3 . 5 m,净空高度不小于3 . 5 m,搬运通道宽度不小于2 . 0 m,净空高度不宜小于2 . 5 m;当变电所室内外存在高差时,不能利用台阶的形式进行处理,应采用小于12°的斜坡处理,并满足搬运通道要求。 3、变电所对结构专业设计要点

相关主题
文本预览
相关文档 最新文档