QUEST Project management provides organizations with a methodology to:

A Become more efficient and effective in accomplishing goals that cannot be handled well by

the traditional structure

B Manage high risk repetitive work

C Provide clients with multiple points of contact

D Provide guidance in accomplishing repetitive activities

E All of the above

A

QUEST Configuration (baseline) control monitors performance against the

A scope baseline

B original schedule

C original budget

D All of the above.

E None of the above.

A

QUEST A summary WBS is usually developed in the

A Conceptual phase

B implementation phase

C planning phase

D close-out phase

E All of the above phases

A

QUEST A project may be defined as _____

A an integrated approach to managing projects

B a coordinated undertaking of interrelated activities.

C a group of activities directed by a project manger over a life cycle

D an undertaking with a defined starting point and defined objectives

E All of the above.

D

QUEST Approval to proceed is normally made at the end

of the _____ phase of a typical project.

A conceptual

B development

C implementation

D execution

E close-out

A

QUEST Lessons learned are most often based upon

project historical records. Lessons learned can

be used to:

A See what mistakes others have made

B See how others have solved problems

C Predict trends, highlight problems and identify alternatives

D All of the above

E A and B only

D

QUEST A program can best be described as:

A A grouping of related activities which last two years or more

B The first major subdivision of a project

C A grouping of projects, similar in nature, which support a product or product line and

have no definable end point

D A product line

E Another name for a project

C

QUEST Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:

A The project manager

B The functional manager

C The project sponsor

D The client

E All of the above

A

QUEST The project charter is a document designed to tell _____ exactly what the project

entails.

A The project manager

B The project office

C The project team

D The project sponsor

E Anyone associated with the project

E

QUEST Work authorization forms are needed in order to: A Authorize line organizations to charge against the project

B Establish an audit trail

C Develop a structured methodology for release of

funds

D All of the above

E A and C only

D

QUEST The scope baseline/project charter is prepared

by the:

A Project manager

B Project manager and project office

C Project manager, project office and functional team

D Project manager, project office, functional team and project sponsor

E Project manager, project sponsor and customer/user

E

QUEST Typical characteristics of a work package include:

A Representation of units of work at a level where work is performed

B Clearly distinguishes one work package from all others assigned to a single functional

group

C Limits the work to be performed to relatively short periods of time

D All of the above

E A and B only

E

QUEST Problems can occur in properly defining a project because:

A Project goals may not be agreeable to all parties

B The plan was "too loose," thus allowing priorities to change

C Low turnover of project personnel

D Too much communication between the client and project personnel

E The project objectives were quantified

A

QUEST In preparing a good project definition, experienced project managers will:

A Concentrate mainly on the end product rather than costs or benefits. These come later.

B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must

get beneath it.

C Understand that a project definition/plan is a dynamic rather than static tool, and thus

subject to change.

D Try to convert objectives into quantifiable terms.

E All of the above

E

QUEST Project life cycles provide a better means of measurement of progress and control. The

four phases of a project are conceptual development, _____, _____, and _____.

A Preliminary planning, detail planning, closeout

B Implementation, reporting, termination

C Development, implementation, termination

D Execution, reporting, finishing

E Implementation, termination, post-audit review

C

QUEST The contractual statement of work (CSOW)

A Must be the same as the proposal statement of work

B Does not identify reporting requirements

C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work

D Identifies the contractor’s organizational structure for the project

E All of the above

C

QUEST Which of the following can result in misinterpretation of the statement of work?

A Using imprecise language (i.e. nearly, approximately)

B Mixing tasks, specifications, special instructions

and approvals

C No pattern, structure or chronological order

D Wide variation in the size of tasks or details of

work

E All of the above

E

QUEST A project manager believes that modifying the scope of the project may provide added value

for the customer. The project manager should:

A Change the scope baseline

B Prepare a variance report

C Call a meeting of the configuration control board

D Change the project’s objectives

E Postpone the modification until a separate enhancement project is funded after this

project is completed according to the original

baseline

E

QUEST The document authorizing functional areas to charge against the project is the:

A Work authorization form

B Scope baseline

C Project charter

D Management plan

E Linear responsibility chart A