隧道 工程项目英语

  • 格式:docx
  • 大小:202.46 KB
  • 文档页数:18

下载文档原格式

  / 18
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

Table of Contents

8.1.5 tunnel (2)

8.1.5.1 type of tunnel (2)

8.1.5.1.1 classified by construction method (2)

8.1.5.1.2 classified by shape of cross-section (2)

8.1.5.2 construction method (3)

8.1.5.2.1 construction procedure (3)

8.1.5.2.2 TBM method (4)

8.1.5.2.3 dill and blast (5)

8.1.5.2.4 cut and cover (7)

8.1.5.2.5 ventatilation (8)

8.1.5.2.6 lighting system (9)

8.1.5.2.7 tunnel finishes (9)

8.1.5.3 glossary (10)

8.1.5 tunnel

8.1.5.1 type of tunnel

8.1.5.1.1 classified by construction method

8.1.5.1.2 classified by shape of cross-section

8.1.5.2 construction method 8.1.5.2.1 constructionprocedure

8.1.5.2.2 TBM method

What tmbis:

What parts included in TMB

Modern TBMs typically consist of the rotating cutting wheel, called a cutter head, followed by a main bearing, a thrust system and trailing support mechanisms.

What soil conditions applied in

In hard rock, either shielded or open-type TBMs can be used. All types of hard rock TBMs excavate rock using disc cutters mounted in the cutter head.

In fractured rock, shielded hard rock TBMs can be used, which erect concrete segments to support unstable tunnel walls behind the machine.

In soft ground, there are three main types of TBMs: Earth Pressure Balance Machines (EPB), Slurry Shield (SS) and open-face type. Both types of closed machines operate like Single Shield TBMs, using thrust cylinders to advance forward by pushing off against concrete segments.

Merit and weakness

TBMs have the advantages of limiting the disturbance to the surrounding ground and producing a smooth tunnel wall. This significantly reduces the cost of lining the tunnel, and makes them suitable to use in heavily urbanized areas. The major disadvantage is the upfront cost. TBMs are expensive to construct, and can be difficult to transport. TBMs is much more efficient and results in shortened completion times (when they operate successfully).

TBM procedure

8.1.5.2.3 dill and blast

What dill and blast method is

Drilling and Blasting is the controlled use of explosives and other methods such as gas pressure blasting pyrotechnics, to break rock for excavation. It is practiced most often

in mining, quarrying and civil engineering such as dam or road construction.

Type of drill and blast

TYPE 1 :Twin sidewall drift face excavation

TYPE 2 :Single sidewall drift face excavation

TYPE 3 :Crown, bench and invert face excavation procedureof drill and blast method