石油天然气建设项目主管部门审批流程1.项目申请人向主管部门提交石油天然气建设项目申请材料。
The project applicant submits the application materials for the oil and gas construction project to the supervising department.2.主管部门负责对申请材料进行初步审查。
The supervising department is responsible for conductinga preliminary review of the application materials.3.若初步审查合格,主管部门将召集相关部门进行项目论证和评审。
If the preliminary review is satisfactory, the supervising department will convene relevant departments to conduct project demonstration and review.4.相关部门进行项目论证和评审,就项目的技术、经济等方面展开讨论。
Relevant departments conduct project demonstration and review, discussing technical, economic, and other aspects of the project.5.论证和评审结果将作为审批决策的重要依据。
The results of the demonstration and review will serve as important basis for approval decision-making.6.主管部门根据论证和评审结果,对项目进行综合评估。
The supervising department conducts a comprehensive assessment of the project based on the results of the demonstration and review.7.若综合评估通过,主管部门将批准项目立项。
燃气天然气竣工验收资料要求一、通常情况下应附资料:1、验收审批表5份,并加盖施工单位公章确认。
2、完工确认单2份。
3、整改项目表4份。
4、工程签证一览表1份。
5、工程移交清单3份。
6、工程结算数据单、居民工程类清单2份(商住楼或其它需要配套建设工商公用管道的工程,需将工商公用管及附属设施单独列出)。
7、竣工资料1套(含竣工图)。
二、特殊情况下应附基本资料:1、验收审批表5份,并加盖施工单位公章确认。
2、完工确认单2份。
3、整改项目表4份。
4、工程签证一览表1份。
5、工程移交清单3份。
6、工程结算数据单、居民工程类清单2份(商住楼或其它需要配套建设工商公用管道的工程,需将工商公用管及附属设施单独列出)。
7、竣工图一套、强度气密试验表(需有监理单位和现场管理员确认)、无损检测结果通知单(如有钢管)。
竣工图的编制要求1、凡按施工图进行施工没有变更的工程,由施工单位负责在原设计施工图上加盖“竣工图”标志章,即作为竣工图,(竣工图标志章的规格尺寸统一为80mm*50mm)。
2、凡在施工中的一般性变更,能够在原设计施工图上加以修改补充的,可不重新绘制竣工图,由施工单位在修改部位上杠改,用黑色签字笔注明修改内容并在修改部位附近空白处引线指示,盖上修改标志章(修改标志章统一规定尺寸为30mm*10mm),注明修改单日期、字、号、条,盖上竣工图章后即作为竣工图。
由于修改较大而使在原图上杠改后图面不清、辨认困难的应将修改部位框出在本张图的空白处或增页绘制,修改完成后,由施工单位加盖竣工图章。
3、凡项目修改、结构改变、工艺改变、平面布置改变以及发生其它重大改变而不宜在原施工设计图上进行修改补充的,应局部或全部重新绘制竣工图。
重新绘制的(包括电脑绘制的)竣工图,图签栏中的图号应清楚带有“建竣、结竣、工艺……”“或竣工版”等字样,制图人、审核人、负责人签名俱全。
并注明修改出图日期及版数后由施工单位加盖竣工图章。
加气站审批流程第一部分:加气站建设一般流程天然气加气站建设必须按照国家相关建设规定及程序进行报建审批。
加气站前期手续的办理,是加气站建设顺利实施的前提和必要条件,也是加气站后期投运手续办理的基础和保障。
加气站不同于一般的普通建筑,其建设过程要经过严格的审查,施工完成初验验合格后,经过政府方方面面的验收并取得相关部门意见及出具的证明。
加气站建设的前期手续:项目可行性研究报告(或项目建议书)、立项批文(发改委)、建设用地批准书、国有土地使用证(国土资源局)、地形测量图(附带矢量化光盘,测绘单位)、规划红线(规划局)、地质勘察报告(勘察单位)、施工图设计(设计单位)、规划许可证(规划局)、施工图审核意见书(市建委审图办)、建筑工程施工许可证(市建委)、建筑工程消防设计审核意见书(消防局)、安全评价报告批复(安全生产监督管理局)、环境评价报告批复(环境保护局)、压力管道安装安全质量监督检验申报表(甲方申报技术监督单位)、特种设备安装改造维修告知书(施工单位申报技术监督单位后,提交一份给甲方留存)。
加气站建设后期手续:建筑工程消防验收意见书(消防局)、危险化学品经营许可证(安全生产监督管理局)、压力容器产品质量监督检验报告(自治区锅炉压力容器质量安全检验研究所)、营业执照(工商局)、企业组织机构代码证(自治区质量技术监督局)、防雷防静电设施检验报告(自治区产品质量监督检验所)、压力容器使用证、气瓶充装证(自治区质量技术监督局)、房产证等。
一、选址(1)建设单位熟悉建站政策和标准规范,在城区或交通主干道上,按靠近水、电、气源,靠近车源,加气方便,基本符合城市规划和标准规范中消防、环保、安全要求,初选建站地址;(2)主管部门、建设、规划、安监、消防、环保、设计到现场定点。
(3)在国土部门办理土地征用手续和国土证:(4)在规划部门办理规划用地许可证、施工用地许可证。
二、立项(1)建设单位向当地产业产管部门(发改委)提出建站申请;(2)提供相应资料:立项报告(项目建议书)、可研报告、选址定点报告;(3)产业主管部门或发改委批准立项。
燃气新建工程办理各项手续清单、步骤及手续内容1 立项县、地区发改委A、投资协议、特许经营授权协议书B、立项申请书C项目建议书(可研报告)D调查资料及项目评估研究材料E可行性研究报告审批意见A、《关于项目建议书的批复》B、《关于同意XX燃气有限公司的批复》2 企业名称批复县、地区工商局A、《关于项目建议书/可研报告的批复》B、《关于XX燃气有限公司的批复》《关于同意XX燃气有限公司名称的批复》3 办理机构代码所在地域地区技术监督局A、《关于项目建议书/可研报告的批复》B、《关于XX燃气有限公司的批复》《关于同意XX燃气有限公司名称的批复》《机构代码证书》4 验资当地会计事务所A、开户行、验资款B、公章《验资报告》5 营业执照工商局A、《关于同意XX燃气有限公司名称的批复》B、《机构代码证书》C、《验资报告》营业执照(筹建期)6 可研报告评审发改委A、《可研报告》B、《可研报告评审的申请报告》发改委的评审意见(红头文件)7 确定站址A、规划管理局(建设局规划科)选址意见书。
选址申请及选址规划意见书、用地申请报告及县级以上人民政府城乡建设用地批准书国土局建委、规划、消防、环保、设计现场定点B 、用地红线图》A、《建设用地规划许可证》B、《消防审批意见》8 初步设计评审(环评)《初步设计方案》A、《环评报告》B、《初步设计方案》9 安监评审地区安监局A、《站区设计图》B、《安监评审报告》《安评批复或意见》10 建设用地建委规划科A、《立项批复》B、设计院《站区规划平面图》勘探设计院《地勘探报告》建设用地钉桩通知单(书)地形测量和拨地测量成果报告《建设工程规划许可证》11 征地国土资源局A《营业执照》B、《建设用地许可证》A、《土地出让合同》B、《国有土地使用证》12 银行开户XX银行A、《营业执照》B《组织机构代码证》C、《验资报告》D、公章《基本账户开户许可证》13 统计登记统计局A、《组织机构代码证》B、《营业执照》《统计证》14 建设工程规划许可证规划管理局(建设局规划科)A、《用地红线图》B、施工图及施工图规划评审意见C、《建设工程规划审批单》《建设工程规划许可证》15 燃气项目建设前审批燃气办A、《营业执照》.B、《特许经营授权书》或《特许协议》《燃气项目建设批准书》16 消防设计审批公安消防局A、计委立项批复B、工程报批图C、《国有土地使用证》《消防设计审批意见书》17 开工审批A、施工图审查(审图中心);B、在建委(局)办理合同鉴证;C、地区燃气办或技术监督局特种设备科办理《建设工程施工许可证》和安装告知书;D、在燃气质检站办理质检委托书E、在规划局办理《燃气管道路由规划》A、《建设工程规划许可证》B、《设计合同、资质》C、《施工合同、资质》D、《监理合同、资质》18物价批复发改委物价局A、物价批复申请报告B、相关文件《物价批复文件》19 临时占道市政、城管A、《建设工程规划许可证》B、《建设工程施工许可证》《临时占道许可证》《道路挖掘许可证》20、压力容器地区技术监督局相关图纸资料《压力目容器使用证》(要办理压力容器登记)、充装注册登记证;21办理化学危险品经营许可证安监部门(加气站及带小瓶装及运输)21 消防验收公安消防局竣工资料《消防验收合格证》22 消防安全公安消防局《消防验收合格证》《易燃易爆危险品消防安全许可证》23 竣工验收建委、技监局、燃气办《竣工资料》《验收报告》《建设合格意见书》24 防雷安全气象局施工图审查防雷检测验收合格证25 燃气经营建委、地区燃气办、省燃气办《设计施工监理资料资质》竣工材料及验收合格意见书等材料《燃气经营许可证》或者《管道天然气特许经营许可证》26更换营业执照工商局A、《燃气经营许可证》B、筹建期营业执照等营业执照27税务登记国税地税局相关材料税务登记证以上工作流程,需根据当地的实际情况及当地的政府相关部门的政策、要求等灵活掌握办事程序。
燃气工程项目的一般建设程序文件编号:TG/ENG/A013/08版本: 1日期:2008年4月港华集团工程部燃气工程项目建设程序概述一、 工程项目建设程序工程项目建设程序是指工程项目从设想、选择、评估、决策、设计、施工到竣工验收、投入生产或交付使用的整个建设过程中,各项工作必须遵循的先后工作次序。
它一般要经过投资决策和建设实施两个发展时期.这两个发展时期又可分为若干个阶段,它们之间存在着严格的先后次序,可以进行合理的交叉,但不能任意颠倒次序。
燃气工程项目的建设程序包括:特别说明:1、主要燃气场站和高压管线等重大建设项目,法规还要求前期请专业单位做好《安全评估报告》、《环境评估报告》、《消防审核意见》、场站土地还要取得土地管理部门《土地规划选址意见书》;以及工程竣工后相关安评、环评、消防、建设选址、及建设用地规划许可证等项目需进行后评估,核查和核实各项工作。
2、中小型燃气工程项目,包括市政中压管网和小区庭院管网等,一般前期工程可简化,各司应了解清楚当地政府主管部门要求及有关法规,做好前期申报工作,通常要求应执行框图中涂色的程序。
3、应严格执行招标程序,做好资格预选工作,保证公平竞争。
设计单位和承建商应根据工程规模,选择符合资质的队伍,其资质除应符合建设部的要求外,尚应具有质量技术监督局颁发的资格证书(详见附件1、2)。
4、压力管道和压力容器要报当地质量技术监督局参与监检。
5、外部有资质单位审计重大项目决算:一般指除主材费之外的工程费用达到一定金额的重大项目,根据集团指引和董事会决定安排外部审计。
6、应做好设计会审工作,严格控制设计变更;认真编制招标文件,明确施工合同责任和控制条款;严格执行施工签证控制制度,做好工程成本控制工作。
二、工程项目竣工资料1、工程项目竣工资料应按项目汇编好集中归档,《项目竣工资料汇编》应包括:以上流程所有报建审批证明文件;会议记录或纪要;设计和施工监理合同、主材和设备供应合同、型号材质清单;设计变更签证、施工签证、材质证明、试验报告、监检报告、监理报告、验收报告、与实际相符的竣工图纸、验收报告,以及经审核的材料清单、工程量清单和决算书等.其中,招标和中标文件作为公司商业机密文件,应注明机密性,严格做好收发、登记及单独归档.2、燃气工程项目建设各阶段资料内容及审批:附件1 压力管道适用范围一、具备下列条件之一的管道及其附属设施属监检范围:1、输送GB5044《职业性接触毒物危害程度分级》中规定的毒性程度为极度危害介质的管道;2、输送GB50160《石油化工企业设计防火规范》及GBJ16《建筑设计防火规范》中规定的火灾危险性为甲、乙类介质的管道;3、最高工作压力大于等于0。
加气站审批流程第一部分:加气站建设一般流程天然气加气站建设必须按照国家相关建设规定及程序进行报建审批。
加气站前期手续的办理,是加气站建设顺利实施的前提和必要条件,也是加气站后期投运手续办理的基础和保障。
加气站不同于一般的普通建筑,其建设过程要经过严格的审查,施工完成初验验合格后,经过政府方方面面的验收并取得相关部门意见及出具的证明.加气站建设的前期手续:项目可行性研究报告(或项目建议书)、立项批文(发改委)、建设用地批准书、国有土地使用证(国土资源局)、地形测量图(附带矢量化光盘,测绘单位)、规划红线(规划局)、地质勘察报告(勘察单位)、施工图设计(设计单位)、规划许可证(规划局)、施工图审核意见书(市建委审图办)、建筑工程施工许可证(市建委)、建筑工程消防设计审核意见书(消防局)、安全评价报告批复(安全生产监督管理局)、环境评价报告批复(环境保护局)、压力管道安装安全质量监督检验申报表(甲方申报技术监督单位)、特种设备安装改造维修告知书(施工单位申报技术监督单位后,提交一份给甲方留存)。
加气站建设后期手续:建筑工程消防验收意见书(消防局)、危险化学品经营许可证(安全生产监督管理局)、压力容器产品质量监督检验报告(自治区锅炉压力容器质量安全检验研究所)、营业执照(工商局)、企业组织机构代码证(自治区质量技术监督局)、防雷防静电设施检验报告(自治区产品质量监督检验所)、压力容器使用证、气瓶充装证(自治区质量技术监督局)、房产证等.一、选址(1)建设单位熟悉建站政策和标准规范,在城区或交通主干道上,按靠近水、电、气源,靠近车源,加气方便,基本符合城市规划和标准规范中消防、环保、安全要求,初选建站地址;(2)主管部门、建设、规划、安监、消防、环保、设计到现场定点.(3)在国土部门办理土地征用手续和国土证:(4)在规划部门办理规划用地许可证、施工用地许可证。
二、立项(1)建设单位向当地产业产管部门(发改委)提出建站申请;(2)提供相应资料:立项报告(项目建议书)、可研报告、选址定点报告;(3)产业主管部门或发改委批准立项。
石油天然气建设项目主管部门审批流程1.项目申请人需要向相关主管部门提交项目建设申请。
The applicant for the project needs to submit a construction application to the relevant competent department.2.主管部门收到申请后,将对项目进行初步审查。
After receiving the application, the competent department will conduct a preliminary review of the project.3.初步审查合格的项目将被要求提交详细的项目规划和设计方案。
Projects that pass the preliminary review will berequired to submit detailed project plans and design proposals.4.详细规划和设计方案将被送交专家组进行评估。
The detailed plans and design proposals will be sent toan expert group for evaluation.5.专家组将对项目的可行性、安全性和环保性进行评估。
The expert group will evaluate the feasibility, safety, and environmental impact of the project.6.评估结果将被提交给主管部门,主管部门将进行综合评估和审批。
The evaluation results will be submitted to the competent department, which will conduct a comprehensive assessment and approval.7.审批通过的项目将被要求进行环境影响评估,并提交相应报告。
燃气设施改动方案审批一、项目概述1.项目名称:燃气设施改动方案审批2.审查类型:承诺件3.受理机构:崇州市经济和信息化局4.办理窗口:市政务中心行政审批服务大厅6号窗口5.法定时限:20个工作日6.承诺时限:5个工作日7.收费标准及收费依据:不收费8.窗口电话:823132129.投诉电话:8231320210.办公地址及时间:崇州市世纪大道1000号;工作日:9:00-17:0011.网上预审:是12.网上审批:是二、法定依据1.《城镇燃气管理条例》(国务院令第583号)第38条;三、办理程序1. 申请人持相关材料向崇州市政务服务中心市经信局窗口提出申请资料,资料齐全,符合法定形式的,予以受理;申请材料存在可以当场更正错误的,允许申请人当场更正;申请材料不全或者不符合法定形式的,应当一次性告知申请人需要补正的全部料。
2.经审查符合法定条件、标准的,在承诺时限内核准。
四、申请材料申请表格燃气设施改动申请表原件4份(可从成都工业网下载);申请附件1.《燃气设施改动方案审批表》3份;2.燃气设施的改动方案设计、施工方案和总平面图(复印件);3. 影响用气的区域、民用户数和主要燃气用户名单;4.安全施工的组织、设计和实施方案,安全防护措施;5.不影响燃气用户安全正常用气的措施;6.设施改动施工现场平面位置图;7.施工单位资质证明材料。
注:以上申请资料除第2项提供复印件外,其余资料均提供原件;第3、5项仅限管道天然气供应企业提供。
五、使用范围暂无。
六、申请条件此事项无前置条件。
七、注意事项只受理崇州市内企业申请。
八、数量限制无九、审批结果十、事项类型行政许可十一、编码十二、审批不见面/仅跑一次/复杂事项仅跑一次十三、省市县联审否十四、服务分类十五、本利层级及审查类型本级办结/实质审查。
编号:天科燃气有限公司
天然气工程竣工资料
工程名称:
建设单位:
监理单位:
施工单位:
编制单位:
2016年7月
竣工验收技术资料目录工程名称:
天然气管道工程开工报告
图纸会审记录
天然气工程技术交底记录
焊工登记表
工程名称:工程编号:
附:电焊工压力管道焊工证
定位放线记录
室外安装质量记录
室内燃气工程质量鉴定书
工程材料报审表
管道涂漆质量记录表
沟槽开挖记录工程名称:
隐蔽工程安装记录
沟槽回填记录
工程名称:回填管段:全线回填
管道系统吹扫记录
天然气工程管道强度试验记录
压力管道气密性试验原始记录
天然气工程竣工报告
工程材料使用清单。
石油天然气审批流程1.申请单位向能源管理部门提交石油天然气项目审批申请。
The applicant submits the petroleum and natural gas project approval application to the energy management department.2.能源管理部门对申请材料进行审查,并进行初步评估。
The energy management department reviews the application materials and conducts a preliminary assessment.3.如果申请材料符合要求,能源管理部门将组织相关专家进行现场考察。
If the application materials meet the requirements, the energy management department will organize relevant experts to conduct on-site inspections.4.现场考察主要包括资源勘探情况、环境影响评估等内容。
On-site inspections mainly include the exploration of resources, environmental impact assessments, and other content.5.能源管理部门将根据现场考察结果,进行进一步的评估和论证。
The energy management department will conduct further evaluation and demonstration based on the results of on-site inspections.6.如果项目符合相关法规标准,能源管理部门将批准项目立项。
If the project meets the relevant legal and regulatory standards, the energy management department will approve the project establishment.7.项目立项后,申请单位需提交详细的开发方案和环保措施。
《燃气工程项目建设备案事项申请办事指南》1. 审批事项基本信息办件类型说明:●承诺件是承诺在一定的期限内完成的审批事项;●即办件是只要材料齐全,窗口就可以办理的事项;●联办就是多个单位共同审批的事项,也就是我们所说的联审;●上报件是本局没有最终审批权限,必须上报给更高一级政府审批的事项;2. 审批事项办事指南2.1. 法律法规(请在此填写该审批事项相关的法律法规)第六条燃气建设以及经营网点的布局要符合市燃气发展规划,执行国家有关法律、法规以及技术标准、规范和规程。
各镇(区)应当将燃气建设纳入本镇(区)国民经济和社会发展计划,实行就统一规划和管理。
第七条凡新建、改建、扩建燃气工程项目,应当经市政局及有关部门按规定的权限审查同意。
第八条燃气工程的设计和施工,应当由具有相应资质等级的燃气工程设计和施工单位承担;燃气工程的设计方案,必须经有关部门审查批准后方可实施。
禁止无资质证书或超越资质等级范围从事燃气工程设计、施工活动。
第九条燃气工程施工实行工程质量监督和建设监理制度。
第十条燃气工程项目竣工后,须经市政局组织有关单位验收合格,方可交付使用。
第十一条高层民用建筑必须安装燃气管道配套设施,与主体工程同时设计,同时施工,同时交付使用。
第十二条城市新区开发和旧区改造,应当根据燃气专项规划,配套建设燃气设施。
第十三条任何单位或个人无正当理由不得阻扰经批准的公共管道燃气工程的施工安装。
第十九条自建燃气设施供本单位使用的自供气单位(含工业、商业用户和住宅小区等),应当具备下列条件,并向市政局申领《广东省燃气使用许可证》后,方可运行:(一)有符合国家规范要求的储存、输配、充装设施;(二)有相应资格的专业管理人员和技术人员;(三)有健全的安全管理制度和企业内部管理制度;(四)有与供气规模相适应得抢修人员、设备和交通工具,或者已委托具备抢修条件的单位负责抢险抢修;(五)法律、法规和企业资质标准规定的其他条件。
《广东省燃气使用许可证》实行年审制度,未经年审或者年审不合格的,其燃气设施不得运行。
天然气项目开发流程下载温馨提示:该文档是我店铺精心编制而成,希望大家下载以后,能够帮助大家解决实际的问题。
文档下载后可定制随意修改,请根据实际需要进行相应的调整和使用,谢谢!并且,本店铺为大家提供各种各样类型的实用资料,如教育随笔、日记赏析、句子摘抄、古诗大全、经典美文、话题作文、工作总结、词语解析、文案摘录、其他资料等等,如想了解不同资料格式和写法,敬请关注!Download tips: This document is carefully compiled by theeditor. I hope that after you download them,they can help yousolve practical problems. The document can be customized andmodified after downloading,please adjust and use it according toactual needs, thank you!In addition, our shop provides you with various types ofpractical materials,such as educational essays, diaryappreciation,sentence excerpts,ancient poems,classic articles,topic composition,work summary,word parsing,copy excerpts,other materials and so on,want to know different data formats andwriting methods,please pay attention!天然气项目开发流程。
1. 勘探,确定潜在的天然气储层,并通过钻探和地质调查来评估储量。
管道天然气施工申报审批表(精)一、项目概述管道天然气施工申报审批表是为了申请管道天然气的施工、安装、改扩建等相关工程而填写的申报审批表,是管道天然气项目立项的重要文件。
二、申报审批表内容管道天然气施工申报审批表包含以下内容:1. 项目概况包括项目名称、建设地点、建设单位、建设性质、工程规模、工程概算等项目基本信息。
2. 工程建设内容包括工程建设内容、工程建设技术方案、主要施工工艺、施工时间等内容。
3. 安全与环保措施包括安全与环保措施、环保影响分析报告、安全生产管理方案等内容。
其中,安全与环保措施是管道天然气施工中非常重要的环节,需要仔细考虑并填写详细的措施。
4. 其他相关资料包括与工程建设有关的其他材料。
三、申请流程在填写完整的管道天然气施工申报审批表后,应按照以下流程进行申请:1. 申请人提交申请材料由申请人向相关部门提交申请材料,包括申报表和相关资料。
2. 受理部门审核受理部门对申报材料进行审查,并对申报材料进行审核。
3. 行政许可决定审核通过后,行政许可决定机关应当对审查结果作出行政许可决定,并向申请人告知。
四、申报审批表填写注意事项在填写管道天然气施工申报审批表时,需要注意以下事项:1. 清晰、准确地填写项目基本信息在填写“项目概况”部分时,要求对项目名称、建设地点、建设单位、建设性质、工程规模、工程概算等项目基本信息进行清晰、准确的填写。
2. 详细、规范地填写工程建设内容在填写“工程建设内容”部分时,要求详细、规范地填写工程建设内容、工程建设技术方案、主要施工工艺、施工时间等内容。
3. 重视安全与环保措施安全与环保措施是管道天然气施工中非常重要的环节,需要仔细考虑并填写详细的措施。
4. 提供完整的其他相关资料填写“其他相关资料”时,需要对与工程建设有关的其他材料进行完整的提供。
五、总结管道天然气施工申报审批表是为了申请管道天然气的施工、安装、改扩建等相关工程而填写的申报审批表,是管道天然气项目立项的重要文件。
第一阶段:公司注册登记成立一、公司注册登记成立基本程序1、名称预先核准(县工商局/市工商局)2、银行开户(临时帐户,一般选择工行或者建行)3、验资(有资质的会计师事务所)4、工商所或工商局登记科预核5、工商局登记6、公安局刻制印章(公章、财务章、法人章、合同专用章)7、质监局办理机构代码证8、国税登记9、地税登记10、办理公司基本帐户二、公司注册登记需要提供的材料1、股东为自然人的需要提供所有股东的身份证复印件2、股东为企业的需要提供该企业的营业执照复印件、法人代表证明件、法人身份证件、公司介绍(全部为复印件上加盖公章)3、拟成立公司会计人员的会计证和身份证复印件4、拟成立公司的名称(一般准备两个及以上)5、拟成立公司的股东组成、投资比例6、拟成立公司的股东会成员任命书7、拟成立公司的公司章程8、拟成立公司的公司董事会决议9、拟成立公司的公司住所使用证明(租赁房屋的提供租赁协议、房产证复印件,经营场所使用证明)10、以燃气项目注册登记时提供特许经营协议第二阶段:项目的立项项目的立项阶段包括项目申请报告(可研报告)的评审、立项申请等。
项目申请报告要经过评审(由当地建设局组织召开专家评审会,对项目申请报告(可研报告)的可行性进行评审即按照国家有关规定,可研报告的可行性要通过项目实施地的地方政府论证),在通过论证后方可报地方政府和发改委进行立项。
在项目立项前,要提供经评审后的环评报告。
一、规划选址《建设项目选址意见(书)》由规划局办理。
所需资料:1、《建设项目选址意见(书)》申请表(所在镇、建管所签意见并加盖公章);2、意向选址位置的1:500或1:1000地形图两份(标出用地范围);3、在已有土地上翻、扩建项目,需提供土地使用证复印件;4、规划要求提供的其它相关资料。
涉及产业政策的要符合城市规划和标准规范中消防、环保、安全要求,同时主管部门、专家、建委、规划、消防、环保、设计到现场定点并提出审核意见。
天然气类项目审批资料1.可行性研究报告、项目备案确认书(市发改委);2.控规平面设计图与施工设计图、建设项目选址意见书(市规划局);3.建设用地规划许可证(市规划局);4.建设用地审批(市国土局)、土地征用文件;5.建筑工程规划许可证(市规划局);6.建筑设计防火审核、消防审核意见书(公安消防分局防火处建审科);7.设计图纸审核意见书(省质监局、市建委审图公司);8.环境影响评价(含预评价)(专家委员会、市环保局开发处);9.安全评价(含预评价)(专家委员会、市安全生产监督局);10.特种设备使用登记证、计量合格证(市质量技术监督局锅特处、计量处);11.消防验收意见书(消防支队稽查大队);12.气瓶充装许可证(省质量技术监督局锅特处);13.燃气安全经营许可证(市政委燃气热力管理处);14.危险化学品经营许可证(市安全生产监督局危险化学品办公室);15.工商营业执照(省或市工商局);16.危险化学品道路运输许可证。
电、气工艺初设;说明是否符合国家标准、城市规划;加气站的消防、环保、安全等是否符合标准要求。
(3)初设审查:主管部门、发改委、建设、规划、消防、环保、安监、设计、业主参加,对初设进行评审;(4)主管部门或建设出具初设评审意见;(5)施工图设计:设计单位据此作加气站工艺、总图、建筑、结构、电器、给排水、暖通设计,并出施工蓝图。
四、报建(1)初设报消防、环保审查,出据审批意见,安监办理安全三同时证书;(2)初设总平图(含消防、环保、安监审批意见)报规划审查,进行勘测,划红线;(3)规划办理工程规划许可证;(4)建设办理工程施工许可证;五、建设(1)办理设备、土建、安装、水、电、气工程、监理招标,签订合同;(2)在质检站办理质检委托书;(3)在建设办理合同鉴证;(4)组织施工。
六、验收(1)进行工程质检,出据质检报告;(2)进行消防、安全、环保、压力容器等单项验收,并出据单项验收报告、危险化学品安全评价报告、防雷防静电检测报告、环保评价检测报告书;(3)在安监部门办理化学危险品经营许可证、在质监局办理压力容器使用许可证、充装注册登记证;(4)质检部门对加气机进行校验标定,出据计量使用许可证;(5)员工到有关部门进行技术培训,取得上岗证;(6)试运行、验收整改、完善;(7)综合验收前:建设单位准备申请竣工验收报告、相关批准文件、设计资料、施工资料、竣工资料、质检资料、监理资料、材料试验资料、财务决算资料、管理制度、事故处理应急预案等相关资料。
(8)主管部门主持,建委、规划、消防、环保、安办、质监、专家及设计、建设单位参加进行竣工验收报告;(9)在行业管理部门办理燃气经营许可证、公商行政管理局办理营业执照、燃气管理部门办理燃所资质证;(10)投产经营。
第二部分:加气站审批流程清单步骤手续内容审批机构审批需要相关材料批复文件或者证书名称1立项市(县)发改委 A、立项申请书B、项目建议书(可研报告)A、《关于项目建议书的批复》B、《关于同意XX燃气有限公司的批复》2企业名称批复地区工商局 A、《关于项目建议书/可研报告的批复》B、《关于XX燃气有限公司的批复》《关于同意XX燃气有限公司名称的批复》3办理机构代码所在地域地区技术监督局 A、《关于项目建议书/可研报告的批复》B、《关于XX燃气有限公司的批复》C、《关于同意XX燃气有限公司名称的批复》《机构代码证书》4验资当地会计事务所 A、开户行、验资款B、公章《验资报告》5营业执照工商局 A、《关于同意XX燃气有限公司名称的批复》B、《机构代码证书》C、《验资报告》营业执照(筹建期)6可研报告评审审计委 A、《可研报告》B、《单位对可研报告评审的申请报告》当地、地区发改委的评审意见(红头文件)7确定站址 A、规划管理局(建设局规划科)B、公安消防局 A、《用地红线图》B、《站区设计图》 A、《建设用地划许可证》B、《消防审批意见》8 站区初步设计的评审(环评)本地有资质的环境评审单位《初步设计方案》 A、《环评报告》B、《初步设计方案审批单》9安监评审本地或地区安监局 A、《站区设计图》B、《安监评审报告》《安评批复或意见》10建设用地当地建委规划科 A、《立项批复》B、规划设计院《站区规划平面图》C、勘探设计院《地址勘探报告》《建设工程规划许可证》11征地国土资源局 A、《营业执照》B、《建设用地许可证》 A、《土地出让合同》B、《国有土地使用证》12银行开户XX银行 A、《营业执照》B、《组织机构代码证》C、《验资报告》D、公章E、预留印章《基本账户开户许可证》13统计登记统计局 A、《组织机构代码证》B、《营业执照》《统计证》14建设工程规划许可证规划管理局(建设局规划科) A、《用地红线图》B、站区施工图及施工图规划评审意见C、《建设工程规划审批单》《建设工程规划许可证》15燃气项目建设审批建委燃气办 A、《营业执照》B、要求的其它文件《燃气项目建设批准书》16消防设计审批公安消防局 A、发改委立项批复文件B、工程报批图C、《国有土地使用证》《消防设计审批意见书》17开工审批地区燃气办或技术监督局特种设备科 A、《建设工程规划许可证》B、《设计合同、资质》C、《施工合同、资质》D、《监理合同、资质》 A、《燃气管道路由规划》B、《建设工程施工许可证》18物价批复所在地物价局 A、物价批复申请报告B、相关文件C、周边标准资料《物价批复文件》19 临时占道市政、城管 A、《建设工程规划许可证》B、《建设工程施工许可证》《临时占道许可证》20 压力容器当地、地区技术监督局相关图纸资料《压力容器使用证》(要办理压力容器登记)21 消防验收公安消防局相关竣工资料《消防验收合格证》22 消防安全公安消防局《消防验收合格证》《易燃易爆危险品消防安全许可证》23 站区竣工验收建委、技监局、燃气办《竣工资料》《验收报告》《气站建设合格意见书》24 燃气经营建委、地区燃气办、省燃气办《设计施工监理资料资质》竣工材料及验收合格意见书等材料《燃气经营许可证》或者《汽车加气特许经营许可证》25 更换营业执照工商局 A、《燃气经营许可证》B、筹建期营业执照等营业执照26 税务登记国税地税局相关材料税务登记证第三部分:关于实施北京市车用燃气加气站建设审批管理暂行办法的通知各区、县、局、总公司,各有关单位:为治理大气污染,加快发展燃气汽车,保证安全有序地建设车用燃气加气站,现对我市车用燃气加气站的建设审批管理作如下通知,请遵照执行。
一、在我市行政区域内新建、改建、扩建车用燃气加气站,应当根据本市车用燃气加气站总体建设规划的要求,遵循安全第一、布局合理、保证供气、方便加气的原则。
二、所有新建、改建、扩建的车用燃气加气站,不论其规模大小,一律按基本建设称许由建设单位主管部门向市计委申报立项。
市计委根据申报材料,会同市市政管委、规划局、环保局、消防局等有关部门共同审批。
三、车用燃气加气站的建设应符合交通、环保、技术监督、劳动、消防、公用等部门的技术规范和政策法规要求。
建设完成的车用燃气加气站需经消防、劳动、技术监督、公用等有关部门验收后方可投入运营。
四、经营单位办理工商注册手续之前,应取得燃气行业管理部门的资质认可,办理《燃气加气站运营许可证》。
五、车用燃气加气站的建设管理应执行国务院有关部门联合颁布的《城市燃气安全管理规定》、《城市燃气管理办法》及《城市燃气企业资质管理规定》,同时应参照汽油加油站有关建设管理规定。
六、本通知自发布之日起实施。
北京市计划委员会北京市市政管理委员会一九九九年七月一日附件一申报立项单位应提交的材料1.向市计委申请立项的报告;2.向市市政管委申请建设的报告;3.《汽车用燃气加气站建设的报表》;4.工程所需用地的建设用地规划许可证或国有土地使用证、或以前曾经批准建房的建设工程规划许可证;5.拟建工程项目的说明方案;6.加气站平面布置图;7.1/2000或1/500地形图2份(其中一份用铅笔划出用地范围);8.非土地所有方建设加气站的单位,需提供建设方与土地所有方签订的有关协议;9.建设单位与北京市液化石油气公司签订的供气协议;附件二审批程序1.社会建站由建设单位将申报材料报送市公安局。
由公安局汇总报市市政管委初审。
市政管委系统局、总公司的专用站由各局、总公司汇总报市政管委初审。
2.经初审,由市计委、市政管委、规划局、环保局、消防局等有关部门联合办公共同审批。
第四部分:北京市汽车用燃气加气站企业运行资质标准(试行)1、为加强本市汽车用燃气加气站的经营管理,确保车用燃气的安全使用,促进车用燃气加气站的健康有序发展,根据北京市人民政府《北京市清洁燃料车辆加气站管理规定》(1999年第31号令),结合本市实际情况,制定本标准。
2、本标准适用于北京市行政区域内从事汽车用燃气加气站经营活动的各类企业。
3、本标准所称汽车用燃气加气站是指专门为机动车辆(含船舶)提供天然气、液化石油气等车用燃气的充气经营服务单位。
4、凡从事燃气加气站经营活动的各类企业应当具备下列条件:4.1 与经营规模相适应的固定场所、通讯工具;4.2 4名以上有燃气、设备、经济等专业初级以上技术职称的管理人员,其中工程系列职称的人员不少于2人;4.3 与经营规模相适应的操作人员、设备维修人员,并取得北京市市政管理委员会颁发的岗位证书;4.4 有必备的维修设备、工具、消防器材和检测仪器,配置与经营规模相适应的抢修、维修服务专用车辆;4.5有按照国家及本市有关技术标准和法律、法规制定的安全操作规程、燃气加气站管理制度和应急预案;4.6有完善的安全和质量方面的管理制度及保证体系,有健全的岗位责任制;4.7 有完整的营业章程和规范化服务标准。
5、从事燃气加气站的企业,应当建立车用液化气销售档案,定期向市市政管委报送相关报表。
6、本市燃气加气站企业运行资质实行年度检验制度。
附件:北京市汽车用燃气加气站企业运行资质申报审批及年检程序一、申报审批程序1. 申报人持书面申请到北京市市政管理委员会燃气管理办公室(以下简称市市政管委燃气办)办理申报手续。
市市政管委燃气办接到申报人申请后,当进行登记,并发给申报人《北京市汽车用燃气加气站运行许可证申报表》。
2. 申报人将填写完毕的《北京市汽车用燃气加气站运行许可证申报表》及其它材料,报市市政管委燃气办。
3. 由市市政管委组织有关专家,在14个工作日内对其经营场所、经营人员、经营章程及服务标准、管理制度等进行全面评审,出据书面评审意见。
4. 符合资质标准的企业,由市市政管委批准核发《北京市汽车用燃气加气站运行许可证》(以下简称"许可证")。
二、年检程序1. 办理年检的时间为每年第4季度到翌年1季度(如有特殊情况,可延迟到第2季度),逾期不再办理;凡未办理年检的企业,取消其资质,并抄送市工商、行政管理部门。