DIKGATLHONG DAM PROJECT

CONTRACT NO.1:

DAM AND ASSOCIATED WORKS AND ACCESS ROAD

大坝监测仪器施工方案

(振弦式渗压计)

批准:

审核:

编制:

SINOHYDRO CORPORATION LTD.

November 18th 2008

大坝监测仪器施工方案

(振弦式渗压计)

一、工程简介

迪克戈洪大坝工程的观测项目主要有:水位及地下水位观测、坝体表面观测渗流观测、空隙水压力观测。其主要观测仪器和设施如下:

各种仪器将跟随工程的进展而进行安装,其中渗压计分为振弦渗压计和竖管渗压计,振弦渗压计具体分布部位和工程量见下表:

二,供货商资料

该工程的监测仪器供货商为基康北京公司,该公司的详细资料如下:

Geokon INC. of USA has been the world leader in high-quality geotechnical instruments design and manufacturing since it was founded in 1979.Geoko Instruments(Beijing) co.,Ltd.was founded in 1998 as a wholly-owned enterprises of the Geokon Inc.,which specialized in desing, production and sale of security monitoring instruments and automatic monitoring and control systems, the integration projects and the technological consultation and services as well and “china Industrial production permit”

Geokon instruments are divided into two large series of vibrating wires (vw) and Fiber Bragg Gratings (FBG),widely used for monitoting security and stability of hydraulic structures,tunnels,brdges,highways and other projects,such as stress,strain,displacement,load,pressure,temperature,tilt,settlement and data acquisition,etc.

As a member of china dam security monitoring committee,Geokon Instruments (Beijing) Co.,Ltd. Is one of the most prestigious companies majored in hydropower project security monitoring and the largest supplier of water conservancy and hydropower security monitoring instruments in china.

Geokon Beijing Co. Jiang xiaoqang

Unit 1111 General Manager Tianchuang Science plaza Mr.G.J.Li

NO.8 Caihefang Road Sales Director

Haidian District Tel:+86-10-62698899 Beijing Fax:+86-10-62698866 100080 https://www.doczj.com/doc/e98052671.html,

China https://www.doczj.com/doc/e98052671.html,/en

三、施工计划

根据安全监测的特点,坝内观测仪器,设备及观测等随坝体填筑施工的项目同步进行。根据总体计划安排,CH3+650和CH3+450断面EL864.00以下的振弦渗压计在2009年9月29日

以前完成安装;CH3+850断面EL864.00以下的振弦渗压计在2009年7月15日以前完成安装;CH2+800断面的渗压计在2010年5月31日以前完成安装.

四、GK-4500振弦式渗压计安装方法

1、基础渗压计安装

现场安装前将率定合格的渗压计浸泡在净水中以排出感应端的空气,然后用纱布、细砂将渗压计感应端包裹并浸入水中达到饱和状态以备安装。

测量放点,进行钻孔,孔径为φ100,钻孔深度为渗压计预定位置以下15~30cm,并对钻孔进行清洗。孔底部用干净的细沙填充至渗压计端头以下15cm的位置,即可放入渗压计,在放入之前先将渗压计封装在一个沙袋里,保持干净,然后放入,并在电缆上做好标记,待仪器就位后环绕周围填充干净的砂子,填充高度在渗压计以上15cm。采集区砂子回填后对孔进行密封,具体做法是先填充500mm厚的膨胀土,然后在用水泥浆填至孔口位置。

孔密封后渗压计电缆周边回填粒径最大不超过5mm的1A料,并掺入10%的膨胀土(体积比),回填高度为300mm至电缆沟底部,渗压计电缆从电缆沟水平引出。

2、坝体渗压计安装

测量放点,开挖仪器坑(宽×高=800×900),在坑底回填一层30cm厚的过滤料,再回填一层10cm厚干净饱和的中粗砂,仪器安装就位后,回填20cm厚干净饱和的中粗砂,然后在回

填30cm的中粗纱至坑口,并人工夯实;并读取初始值。具体做法见下图。

3、电缆施工

电缆铺设程序

测量放线→电缆沟开挖→电缆铺设→回填该区域填料→人工夯实

电缆沟开挖:施工前在测量放线的开挖区边线处按仪器的位置,对观测电缆进行编号,根据设计图纸,根据回填区域的不同,共分为三种,具体见设计图纸58016-1602,在大坝每个仪器安装断面电缆沟固定位置设置Bentonite Cutoff,具体位置见设计图纸58016-1600和58016-1602,电缆沟开挖采用人工开挖。

电缆安装:电缆在电缆沟内水平引设时,应呈“S”型布设,处于自然松驰状态。电缆安装高程为沟底向上75mm位置。

电缆沟回填:电缆上下各75mm高度内回填该区域的粒径不大于100mm的回填料。电缆沟回填采用人工回填,回填人工逐层夯实至基础面。

五、施工期仪器监测

仪器安装前,应测读一次。安装埋设后,立即读取初始读数,15分钟读取一次,至少三次;安装后的14天内,每天测读一次。出现异常现象时,应按工程师的指示加密观测次数。

六、安装时间和土建施工进度的协调

由于仪器的埋设过程中经常出现与施工进度相冲突的情况,这样就必须在埋设过程中与施工方进行必要的协调。在保证埋设质量的前提下,应该尽量避免影响施工单位的施工,应该不因为埋设仪器而耽误工期。与施工方进行必要的沟通,避免因为施工不当而造成仪器、电缆的损坏。

七、仪器安装注意事项

(1)电缆敷设过程中,要保护好电缆头和编号标志,防止浸水或受潮;应经常检测电缆和仪

器的状态及绝缘情况,并进行记录和说明;

(2)电缆敷设时,应加注标识,注意保护,选好临时观测位置,观测电缆的保护要有切实可靠的措施;

(3)在电缆走线的线路上,应设置警告标志。尤其是暗埋线,应对暗埋线位置和范围设置明显标志。

(4)仪器在出厂时有厂家编号,使用者根据设计图纸上仪器的监测断面、控制坐标、仪器型号等统一编号,称为设计编号。在埋设前必须让设计编号与厂家编号相对应,这样就要求每支仪器设备都要建立自己的档案卡,以免发生混乱。施工期间,在所有仪器电缆上每隔20米加上一个耐久的标签,标签上应注有仪器的编号及类型。特别是在观测端要加两个这样的标签,以保证能根据标签来识别不同的仪器,以免给资料整理工作带来不必要的麻烦。

八、仪器安装埋设流程

迪克戈洪大坝安全监测仪器安装埋设工作流程

振弦式渗压计作业指导书

word文档整理分享 1、适用范围及依据 (1) 1.1适用范围 (1) 1.2标准及依据 (1) 2、测量原理及仪器结构 (1) 2.1测量原理: (1) 2.2仪器结构: (1) 2.3型号、规格及技术指标 (1) 3、安装埋设 (2) 3.1验收与保管 (2) 3.2仪器安装 (2) 3.2.1 渗压计的安装埋设 (3) 3.3 电缆安装 (9) 3.3.1 仪器电缆接长 (9) 3.3.2 电缆的接长 (9) 4、数据读取与计算 (10) 4.1 人工测量与计算 (10) 4.1.1 仪器与振弦式仪器检测仪的连接 (10) 4.1.2 数据读取与记录 (10) 4.2 自动测量 (12) 4.2.1 自动测量的计算 (12) 5、注意事项 (12) 6、安全与环保 (12) 6.1安全施工 (12) 6.2环境保护 (12) 7、附件 (13)

振弦式渗压计作业指导书 1、适用范围及依据 1.1适用范围 振弦式渗压计适用于长期埋设在水工建筑物(地基或基岩)内部和其它混凝土建筑物及土体内部,长期观测建筑物或土体内部的渗透(孔隙)水压力,亦可用于观测水库水位的变化,并可同时测量埋设点的温度。渗压计加安装配套附件可在测压管、管道、地基钻孔中使用。 1.2标准及依据 DL/T 5178-2003 《混凝土大坝安全监测技术规范》 SL 60-1994 《土石坝安全监测技术规范》 GB/T13606-92 《岩土工程用钢弦式压力传感器国家标准》 2、测量原理及仪器结构 2.1测量原理: 当被测水压荷载作用在渗压计上,将引起弹性膜片的变形,其变形带动振弦转变成振弦应力的变化,从而改变振弦的振动频率。电磁线圈激振振弦并测量其振动频率,频率信号经电缆传输至读数装置,即可测出水荷载的压力值,同时可同步测出埋设点的温度值。 2.2仪器结构: 振弦式渗压计由透水石、不锈钢 感应膜片、密封壳体,信号传输电 缆、振弦及激振电磁圈等组成。 2.3型号、规格及技术指标

大坝、溢洪道土石开挖施工方案

湖北兴山县毛家河水电站 边坡开挖及支护工程施工方案 1、概述 开挖及支护工程主要包括:大坝坝基覆盖层、趾板基础石方开挖,溢洪道土方明挖及石方开挖,大坝及溢洪道基础地质缺陷超挖处理;灌浆平洞洞内支护;大坝趾板边坡支护;溢洪道边坡支护。支护型式主要为:锚杆、喷射混凝土(包括挂网喷护)等。支护工程主要工程量根据现场实际情况确定。 开挖及支护工程主要工程量见表1-1。 表1-1 主要开挖及支护工程量表 25 L=4.0m 4@100 25 L=6.0m 孔内保护花管 (56 L=0.5m) 2、施工依据 ⑴监理工程师签发的施工图纸、设计文件及其它相关的文件。 ⑵现行规程、规范、合同文件和施工组织设计总体要求。 ⑶业主、监理现场施工要求。

3、施工布置 3.1施工道路 ⑴充分利用发包人提供的场内交通设施和工区现有道路,并辅以必要的养护和改建,新建施工道路按工程施工需要进行布置,在开挖范围内的临时道路可根据工程进展情况随时进行调整。 ⑵左岸:从左岸上坝公路可到达左坝肩,左岸574.0m高程上坝公路向上游可通往沙湾电站;在中线,拟在515.0m高程修建临时施工道路作为左岸岸坡开挖出渣道路,同时向上布置施工便道至岸坡开挖面。 ⑶右岸:利用现场已有的右岸低线公路作为大坝开挖的主要施工道路。 3.2风、水、电布置 大坝土石方开挖施工供风、水、电布置均从总布置接引。其中: ⑴施工供风:溢洪道开挖工作面布置两台20m3的移动式空压机,大坝开挖工作面布置一台20m3的移动式空压机;另配4台4 m3移动式空压机作为辅助供风设备。 ⑵施工供水:从大坝左岸▼595m高程的水池接引,采用¢32塑料管敷设致各个施工用水点。 ⑶施工供电:左岸由1#配电所供电,供电容量为400KVA,右岸由2#配电所供电,供电容量为200KVA。 3.3水流控制及防汛措施 开挖施工中,如遇雨季或汛期,将会有如下情况的水流对工程施工产生影响: ⑴雨水沿道路流向坡面,对已开挖的垂直壁面产生冲刷和浸蚀。 ⑵高边坡开挖后,断层顶部暴露,且与边坡形成不稳定的三角体、悬挂体,雨水及汇水对其进一步冲刷可能会引起滑坡或塌方,影响施工进展。 ⑶两岸边坡开挖及支护的施工废水、雨水、汇水及上下游渗水将会给基坑产生大量积水而影响坝基开挖施工。 为了防止产生上述不利影响,将对雨季施工中的水流和防汛采取相应措施: ⑴采取“高水高排、低水低排”的原则,首先施工高边坡顶部的拦水坎和截水沟,将水引向河床或冲沟,防止地表水大量流入施工作业面,减少对边坡的冲刷和浸蚀。 ⑵对断层及岩溶通道的地下水进行疏导,必要时采取喷混凝土防护,及时闭合裂隙,并采取挡水坎引水至截水沟,减少水流进入施工区。 ⑶做好施工道路排水系统,在内侧设排水沟,有效疏排地表水。 ⑷根据现场情况,设置临时集水井及各部位的截、排水沟。 ⑸设置临时及永久施工排水泵站将汇水及时排至围堰外。 施工期临时排水与永久排水相结合,天沟安排在开挖前实施;开挖区排水采取预留3%缓坡倾向外侧,以便渗水、雨水能自流至开挖区外,局部积水采用人

大坝填筑施工组织设计

填埋场A单元环场坝及分割坝填筑施工方案 1.概况 河北省危险废物处置工程填埋场A单元环场坝填筑方量4.202万m3、分割坝填筑方量3863m3,总填筑为:总计划填筑天,则坝体填筑日强度达 m3/天。 坝体填筑计划工期17个月,2010年8月开始填筑至2012年的6月底。2011年6月底全坝段填筑到1028m高程,满足1028m 高程的度汛要求。2012年6月底大坝填筑设计高程1054.0m后,预留预沉降高度0.4m,主河床坝段填筑至1054.4m高程,2012年底前修筑坝顶道路等工程。 坝体填筑按区、段、单元划分进行,坝面分三区,即:左岸坝肩填筑区、右岸坝肩填筑区、河床段区,每区分为三个独立工作面。先施工左、右坝肩段,再施工河床段。按照不同高程设上坝道路。 2.坝体填筑进度安排 2.1施工总体进度安排 按照设计要求,坝基开挖1006m高程,换填干净砂至1008m 高程,作为大坝填土建基面。根据总进度计划和现场相关条件,2010年8月开始填筑右岸坝0+475~坝0+720坝段。9月开始填筑左岸坝0+135~坝0+350坝段,达到1014m高程。上游起小断面挡水,下游为防渗墙施工提供工作面,10月底截流后,加快纵向围堰拆除及河床段坝基开挖,为2011年大坝全断面填筑创

造有利条件。 2.2主要节点工期 2010年10月底大坝截流,大坝左右坝段填筑高程达到1014m 高程。 2010年11月底坝体上游小断面填筑高程达到1021m高程。 2011年6月30日大坝全断面填筑高程达到1028m满足度汛水位高程 2012年6月30日大坝填筑完工。 3 坝体填筑施工方法 3.1坝体填筑施工道路布置 3.1.1上坝道路布置采用岸坡与坝坡相结合的布置方式,上坝道路按双车道设计,两岸上坝主干道路面宽7m,最大纵坡控制在10%左右;坝体下游坡面的临时上坝道路路面宽7m,最大纵坡控制在10%以下。 3.1.2上坝道路 根据大坝填筑不同高程在下游坡修筑三条“之”字型上坝路,分别在1008~1023m、1023~1038m、1038~1054m高程布设。 3.2坝体填筑坝料平衡计算 本工程开挖料主要为大坝清基开挖料和左坝肩削坡量,清基料和削坡料不能用于坝体填筑,大坝清基土方开挖运至大坝上、下游进行平整,左坝肩削坡料用于坝前平台填筑。 (1)平衡依据:根据招标文件提供的坝料工程量和各时段坝

大坝导流施工方案

大坝导流施工方案

CB01 施工技术方案申报表 (承包[ ]技案003号) 合同名称:普定县红坪水库工程建设项目一标段合同编号:PDSTGCSG- -07

说明:本表一式份,由承包人填写,监理机构签收后,发包人份、设代机构份、监理机构份、承包人份。 普定县红坪水库工程建设项目一标段 (合同编号:PDSTGCSG- -7) 大坝导流施工方案 批准: 核定: 审查: 编写: 二0一六年四月 贵州山川秀水利建设有限公司

目录 第一章概述 ............................................................................. 错误!未定义书签。 1.1工程概况 ..................................................................... 错误!未定义书签。 1.2导流标准 ..................................................................... 错误!未定义书签。 1.3导流方式 ..................................................................... 错误!未定义书签。第二章围堰设计 ..................................................................... 错误!未定义书签。 2.1水文资料 ..................................................................... 错误!未定义书签。 2.2进度文件的要求.......................................................... 错误!未定义书签。 2.3设计流量的选定.......................................................... 错误!未定义书签。 2.3.1截流设计流量的选定......................................... 错误!未定义书签。 2.3.2围堰设计标准确定 ............................................ 错误!未定义书签。 2.4导流建筑物设计.......................................................... 错误!未定义书签。 2.4.1围堰设计 ............................................................ 错误!未定义书签。 2.4.2导流明渠设计 .................................................... 错误!未定义书签。第三章围堰施工 ..................................................................... 错误!未定义书签。 3.1施工平面布置.............................................................. 错误!未定义书签。 3.1.1围堰及导流渠施工平面总布置图如下: ......... 错误!未定义书签。 3.1.2料场及施工道路 ................................................ 错误!未定义书签。 3.2施工方案 ..................................................................... 错误!未定义书签。 3.2拟投入的人员及机械设备 .......................................... 错误!未定义书签。 3.2.1拟投入人员表: ................................................ 错误!未定义书签。 3.2.2拟投入主要机械设备表:................................. 错误!未定义书签。

渗压计用户手册中文版

欧美大地 欧美大地 欧美大地 1 我们无所不能 用户指南 振弦式渗压计 PW 系列 本手册翻译由欧美大地仪器设备中国有限公司提供,欧美大地版权所有。

欧美大地 欧美大地 欧美大地 2 目录 1 产品............................................................................................................................................................3 1.1 仪器制造 .........................................................................................................................3 1.1.1 PWS and PWC ...........................................................................................................................4 1.1.2 PWP ..............................................................................................................................................4 1.1.3 PWF ..............................................................................................................................................4 1.2 振弦原理 ............................................................................................................5 1.3 率定 ..........................................................................................................................................5 1.4 技术规格. (6) 2 读数与分析 ..............................................................................................................7 2.1 验货读数............................................................................7 2.2 初始读数 ........................................................................................7 2.3 现场功能检测 ......................................................................................8 2.4 压力公式 (W I T H T H E M B-6T /6T L R EA D O U T ) .................................................9 2.5 压力公式(多项式)(W ITH THE MB-6T/6TLREADOUT)..................................... 11 3 安装......................................................................................................................................12 3.1 过滤器饱和 .......................................................................................................................... 12 3.1.1 低压烧结不锈钢过滤器s......................................................................................12 3.1.2 高压陶瓷过滤器s..............................................................................................................121 3.2在土体里安装....................................................................................................................... 12 3.2.1 紧密的粘土.....................................................................................................................................12 3.2.2 粒状材料...............................................................................................................................12 3.3在钻孔里安装 ...................................................................................................... 13 3.4安装在软基里................................................................................. 14 3.5 电缆标签.................................................................................................................. 15 3.6 电缆铺设................................................................................................................................. 15 3.6.1 从垂直孔到水平沟槽的过渡.................................................................15 3.6.2 水平电缆铺设...........................................................................................................................15 3.7 雷击保护.................................................................................................................. 15 4 综合........................................................................................................................................16 4.1 电缆路线安排..................................................................................................................................... 16 4.2 转换表 (温度 V S 电阻 )....................................................................... 18 4.3 转换因子 ..................................................................................................................... 20 4.4 参考.. (21)

渗压计及测压管施工方案

测压管及渗压计施工技术方案 根据首部挡水坝基础渗流监测布置图[图号:NJ54 SG-51-6(5)(6)(7)],在闸坝基础布置测压管(内设渗压计)7套,监测坝基扬压力;在防渗墙两头及下游侧布置测压管(内设渗压计)6套,监测两岸绕坝渗流情况。我部对测压管及渗压计安装埋设提出以下施工技术方案。 1.仪器布置和工程量 1.1坝基渗流监测 在监测剖面闸0+003.00m的坝基范围内顺坝轴向布设7套测压管(内设渗压计),钻孔埋设,深入坝基1米,渗压计及测压管设计位置和设计工程量如下: 坝基渗压计及测压管设计位置和设计工程量表 1.2绕坝渗流监测

在防渗墙两头及下游侧布置测压管(内设渗压计)6套,监测两岸绕坝渗流情况。两岸绕渗孔各测点的布置随水工防渗布置和地形地质情况做具体调整,渗压计电缆实际长度根据管线去向确定。设计位置和设计工程量如下: 绕坝渗流测压管设计位置和设计工程量表 2.仪器设备和材料性能参数 2.1测压管 2.1.1进水管、导管和沉淀管 进水管:φ50镀锌钢管,进水孔φ8mm,呈梅花型布置,水平方向沿管壁周长均匀布成6排;竖向孔距为50mm,每节钢管两端加工 外丝扣; 导管和沉淀管:φ50镀锌钢管、外箍接头、管顶盖和管底盖,每节钢管两 端加工外丝扣。 2.1.2无纺土工布 300g/m2,等效孔径095<0.12mm,垂直渗透系数10-2cm/s。 2.1.3孔内回填料 反滤料:干净砾石,粒径10~15mm。

沥青麻布:位于测压管建基面,用于封孔时隔离水泥浆。 水泥砂浆:C15水泥砂浆 2.1.4测压管顶保护盒 管帽:φ260mm带丝扣和止水垫圈管帽; 管盖:φ50镀锌管堵头,带电缆穿线孔; 2.2渗压计 生产厂家:南京达捷大坝安全技术发展公司; 传感器类型:振弦式; 型号规格:SXX-150; 测量范围:0.5MPa; 分辨率:0.2%F.S; 2.3读数仪表 生产厂家:基康仪器(北京)有限公司; 型号:BGK408; 测量范围:400~4500Hz; 温度测量范围:-30~70℃; 分辨率:频率0.1Hz,温度0.1℃; 示值误差:<0.002%。 2.4观测电缆及连接 生产厂家:南京南瑞集团公司大坝工程监测分公司 电缆型号:NDBT2×2×11/0.2通信电缆 热缩接头:φ3mm芯线绝缘热缩套管、φ10mm绝缘热缩套管、热熔胶保护管:φ70 PVC管 3.测压管钻孔和回填 在施工现场具备钻孔条件时将及时按照设计位置进行测量放点,钻孔施工过程中按照设计钻孔技术要求随时检控。因测压管钻孔回填材料的特殊要求,所有回填材料由我部按照设计图纸要求准备并回填。 本工程有闸坝测压管和绕坝渗流测压管钻孔,在具备钻孔条件时及时另行上报钻孔施工方案。 4.仪器设备埋设、安装和调试: 4.1测压管管路安装 测压管钻孔深度应比设计测压管管底稍低,以防止局部坍塌而影响测压管埋设高程,钻孔工作结束后,测压管埋设之前钻孔应冲洗干净; 测压管安装前使用水位计测量孔内地下水位并记录,两次测读误差应不大于2cm;

水库大坝基础开挖方案

广西隆林县三轮河水库工程 XXXXXXXX 三轮河水库工程总承包项目部 大坝基础开挖方案

年月

1.1工程概况 ............................................................... 1 1.2主要工程量 ............................................................. 2 1.3施工依据 2、施工总平面布置 ........................................ ..4 2.1 施 工 道 路 布 置 ..................................................... ..4 2.2风、水、电供应 ....................................................... ..4 3、施工方法 .......................................... .. (4) 3.1 场 内 交 通 道 路 布 置 ??… ........... .. (4) 3.2 各 部 位 开 挖 施 工 方 法??… .... .. (5) 3.3 开 挖 程 序 和 开 挖 方 法 ??… .... .. (6) 3.4 基 坑 开 挖 进 度计划 及 资源 配 置 ??… ?- (13) 1、工程概况 ............................................ .. 1 4.1 质 量 保 证 措 施 ....... . .. (15) 4.2 安 全 保 证 措 施 ....... ... . (17) 5、环保保护与文明施工 … ?… 17 (15) 4、质量、安全保证措施 ..............................

坝体土方填筑施工方案

三门峡市山口水库复建工程坝体土质防渗填筑 施工方案 批准: 审核: 编制: 河南省水利第二工程局 第五工程处 二O一O年十月十七日 三门峡市山口水库复建工程 页脚内容0

坝体土质防渗填筑施工方案 1.工程概况 工程枢纽由大坝、岸边溢洪道、输水建筑物等组成。溢洪道位于大坝左岸,输水建筑物位于大坝右岸。 大坝坝型为土质防渗体分区坝,分为土质防渗区和堆石区,两区间为反滤层和过渡层,最大坝高42.50m,坝顶高程662.50m,坝顶宽6m,坝顶长153m,上游坝坡自上而下为1:2.5、2.75,下游坝坡为1:2,土质防渗体下游坡为1:0.45,大坝上游护坡为现浇砼块护坡,下游坝坡626高程以下为干砌石护坡,以上为浆砌石条带内植草皮护坡,坝基及坝肩防渗为截水槽和帷幕灌浆。 溢洪道位于大坝左岸,为无闸控制正槽溢洪道,轴线水平投影总长327.3m,坝轴线对应位置架设跨溢洪道交通桥,桥面宽4.5m,桥长44m,共分3跨,单跨14m,上部结构为现浇砼板梁结构,下部结构为钢筋砼桥墩。 输水系统位于大坝右岸,设计输水流量为1m3/s, 由岸塔式进水口、无压输水涵洞等组成,均座落于右岸基岩上,进水塔进口底板高程637.5m。 机电设备及金属结构安装工程、附属工程、移民工程、水土保持工程等其它内容详见图纸。 工程移民道路分永久移民道路和施工期移民道路,永久移民道路通过跨溢洪道交通桥自坝顶穿过。施工导流采用非汛期围堰挡水,导流管导流,汛期坝体临时断面挡水,导流管导流,围堰最大高度约 8m,导流管为直径1400mm承插式钢筋砼管。 2土方填筑工程量 主要工程量:土方填筑约32万m3。 3施工机械配置 根据施工需要及碾压试验,本项工程主要施工机械配置如下:1.0m3~1.6m3反铲挖掘机2台、15t 自卸汽车10~15辆、SD16推土机1~2台、ZL50装载机1台、20T凸块振动碾1台、DH90振动打夯机 2台。 4土方填筑施工程序

水库大坝防渗面板砼专项施工方案

大坝防渗面板施工案 第一章概况 东塘水库位于义乌北部大镇东塘片,浦支流大江上游,坝址位于大镇新建村上游200m 峡谷中,距义乌市区约30km。坝型为浆砌重力坝,水库集雨面积F=19.37km2,主流长度10.96km,总库容293.31万m3,正常库容254.79万m3。正常水位168.20m(1985高程基准,下同),50年一遇设计洪水位169.83m,300年一遇校核洪水位170.25m。本水库是一座以供水、灌溉为主,结合防洪等综合利用的小(一)型水库。 大坝防渗面板位于大坝迎水面,处于“U”型河谷中,左岸坝0+000~坝0+.4段建基面高程为162.70~134.6m,河谷底坝0+.4~坝0+086段建基面高程为134.6m,右岸坝0+086~坝0+134.05段建基面高程为134.6m~169.42m;防渗面板顶高程为170.9m,顶部宽度0.50m,迎水面坡度为1:0.1,背水面与原大坝相连,采用C25W6F100砼。防渗面板每隔10~15m设伸缩缝一条,距面板表面200mm设铜片止水一道,并在表层设SR塑性填料及盖片,缝间用低发泡聚乙烯闭塑料填充。 底板下设固结灌浆2排,间间距3m,深在建基面以下8m;帷幕灌浆1排,间间距2m,布置在底板基础轴线上,帷幕灌浆伸入相对不透水层(q<5Lu)以下5m;砼底板与岩地基之间连接设Ф25锚筋,锚筋间距1.2m形布置伸入岩基础2.5m,共3排;主要布置在大坝两侧山体段嵌槽(围:坝0+000至坝0+,坝0+086至坝0+134.05)。遇断层及破碎带进行挖槽回填砼处理。 主要工程量:嵌槽开挖3280 m3,C25W6F100砼防渗面板6432m3,铜片止水265m,伸缩缝842 m2,迎水面锚筋2930根,趾板锚筋393根,迎水坡原高频振捣砂浆防渗面板凿除2945 m2。

大坝监测仪器施工方案(振弦渗压计)

DIKGATLHONG DAM PROJECT CONTRACT NO.1: DAM AND ASSOCIATED WORKS AND ACCESS ROAD 大坝监测仪器施工方案 (振弦式渗压计) 批准: 审核: 编制: SINOHYDRO CORPORATION LTD. November 18th 2008

大坝监测仪器施工方案 (振弦式渗压计) 一、工程简介 迪克戈洪大坝工程的观测项目主要有:水位及地下水位观测、坝体表面观测渗流观测、空隙水压力观测。其主要观测仪器和设施如下: 各种仪器将跟随工程的进展而进行安装,其中渗压计分为振弦渗压计和竖管渗压计,振弦渗压计具体分布部位和工程量见下表: 二,供货商资料

该工程的监测仪器供货商为基康北京公司,该公司的详细资料如下: Geokon INC. of USA has been the world leader in high-quality geotechnical instruments design and manufacturing since it was founded in 1979.Geoko Instruments(Beijing) co.,Ltd.was founded in 1998 as a wholly-owned enterprises of the Geokon Inc.,which specialized in desing, production and sale of security monitoring instruments and automatic monitoring and control systems, the integration projects and the technological consultation and services as well and “china Industrial production permit” Geokon instruments are divided into two large series of vibrating wires (vw) and Fiber Bragg Gratings (FBG),widely used for monitoting security and stability of hydraulic structures,tunnels,brdges,highways and other projects,such as stress,strain,displacement,load,pressure,temperature,tilt,settlement and data acquisition,etc. As a member of china dam security monitoring committee,Geokon Instruments (Beijing) Co.,Ltd. Is one of the most prestigious companies majored in hydropower project security monitoring and the largest supplier of water conservancy and hydropower security monitoring instruments in china. Geokon Beijing Co. Jiang xiaoqang Unit 1111 General Manager Tianchuang Science plaza Mr.G.J.Li NO.8 Caihefang Road Sales Director Haidian District Tel:+86-10-62698899 Beijing Fax:+86-10-62698866 100080 https://www.doczj.com/doc/e98052671.html, China https://www.doczj.com/doc/e98052671.html,/en 三、施工计划 根据安全监测的特点,坝内观测仪器,设备及观测等随坝体填筑施工的项目同步进行。根据总体计划安排,CH3+650和CH3+450断面EL864.00以下的振弦渗压计在2009年9月29日

水库大坝深基坑开挖专项方案

目录 1概述 (2) 1.1工程概况 (2) 1.2地形地质 (2) 1.3工程特点 (2) 2工程施工方案 (2) 2.1施工内容 (2) 2.2主要工程量 (3) 2.2主要施工方法 (3) 2.2.1施工准备 (4) 2.2.2基坑排水 (4) 2.3土方开挖 (6) 2.4石方开挖 (6) 3施工进度计划 (7) 4主要施工资源配置 (7) 4.1强度分析 (7) 4.2设备配置 (7) 5质量和安全保证措施 (9) 5.1质量保证措施 (9) 5.2安全保证 (9) 5.3安全防护 (10) 5.4土石方挖装作业安全措施 (11) 5.5汽车运输作业安全措施 (11) 5.6供电与电气设备安全措施 (11) 5.7防洪、防火、防盗及危爆物品管理措施 (12)

1 概述 1.1 工程概况 兴仁县响水水库大坝工程位于兴仁县潘家庄镇夏溪村夏溪河上游响水沟上。工程规模为小(1)型水库,工程等别为Ⅳ等,主要由挡水建筑物,泄洪建筑物、取水兼导流建筑物等组成。其中,挡水建筑物为面板堆石坝,坝顶高程1566.2m,最大坝高45.7m,坝顶长度124.27m。 1.2 地形地质 响水水库位于夏溪河上游响水沟1#跌坎与2#跌坎之间的槽谷内,两岸山体连绵,河谷呈对称“V”型。两岸岸坡坡度35~50°,谷底高程1526.0m,谷底宽度20~25m,河床纵坡比降1~1.5%。 大坝轴线附件及两岸坡地层岩性为三碟系下统飞仙关组(T1f)泥岩、砂岩细砂岩砂质泥岩等互层岩性。两岸强风化厚度7~7m,弱风化厚度8~10m;河沟谷底部为第四系砂卵砾石冲洪积层,覆盖层厚度2.5~3.5m,强风化厚度4~5m,弱风化厚度7~8m。库区内无较大构造节理裂隙发育。 1.3 工程特点 本工程由于前期上坝公路征地、林木砍伐、地形地质条件差等因素影响,导致主体工程(尤其是导流洞工程)施工滞后,工期紧张。为了加快施工进度,进入主体工程施工后,大坝、导流工程施工采取平行作业。 由于响水沟在枯期流量很小,5年一遇月平均流量0.019m3/s。在两岸坝肩边坡开挖完成,导流洞还不具备过流条件情况下,采取临时导流施工措施进行坝基开挖。 2 工程施工方案 2.1 施工内容 ⑴坝基开挖临时导流措施。 ⑵坝基土石方开挖与地质缺陷处理。 ⑶坝基开挖安全保证措施。

大坝填筑作业指导书

大坝填筑作业指导书 1.编制目的 为了使宜兴市油车水库工程大坝填筑过程中,施工人员(质检人员)及操作人员能够明确坝体填筑各工序的技术、质量要求,掌握基本的施工方法,满足坝体填筑的技术、质量及进度要求,编制本作业指导书。 2.适用范围 本作业指导书适用于宜兴市油车水库工程大坝填筑全过程。 3. 相关文件 3.1相关规程、规范 (1)《土工合成材料应用技术规范》GB50290—98; (2)《土工合成材料测试规程》SL/T235—1999; (3)《水利水电工程土工合成材料应用技术规范》SL/T225—98; (4)《碾压式土石坝施工技术规范》DL/T5129-2001; (5)《土工试验规程》SL237-1999。 3.2设计文件 3.3投标书 4.职责 在坝料填筑过程中,明确施工技术、质检及各部门之间的职责,做到分工明确,相互协调。 工程部:负责施工现场的技术交底、测量放线、试验取证、生产调度工作,合理组织人员、设备,满足现场施工需要。 质保部:负责组织验收,检查督促现场施工过程中的质量控制是否满足质量要求。安全部:检查施工过程中,包括挖运、坝体填筑的施工能否满足安全需要。 机物部:确保现场的物资保证,如水管、碾压机具配件、修理、洒水设备等满足施工需要。 经营部:负责施工协作队伍的落实,督促检查协作队伍进场后能否满足施工需要。 .大坝填筑的先决条件5. 在大坝填筑之前,坝基必须满足下列条件: (1)坝基经过计算的平面、剖面图复核检查完成。 (2)坝基清理及地质缺陷处理质量已经通过检查和验收。 (3)坝料开采区,用于填筑坝体各种级配料的物理力学性能指标已经抽样检验合格。 (4)现场生产性试验的各种碾压参数及各项试验成果通过检查和验收。 (5)人员设备按计划组织到场,且现场施工技术、生产人员及操作人员经过培训,掌握了坝体填筑各种级配料的施工技术要求。 (6)坝料开采区、填筑区的洒水能够满足施工强度要求。

大坝趾板和面板等砼与止水施工方案

.1 大坝趾板混凝土施工 .1.1主要工程量和施工分块 大坝趾板混凝土施工的主要项目包括锚筋、钢筋、止水和混凝土浇筑等,其中混凝土7241m3、钢筋约230t,混凝土属D1类,要求最小抗压强度20Mpa(28d),抗渗标号W12,抗冻F100级,最大骨料粒径40mm,平整度要求为U2。 大坝趾板按设计图要求共分35块,其中河床7块,左岸12块,右岸16块。 趾板共分5种类型,厚度0.6m~1.0m,宽度6m~12m。均为单层钢筋,要求与φ28锚筋钩牢,锚筋深入基岩4m,纵横间距均为1.5m。 .1.2混凝土入仓方式 河床部位趾板、跳仓浇筑,采用W200A履带吊机配2~3m3卧罐吊运入仓,6 m3搅拌车供料;两岸趾板混凝土根据不同高差,分别选用履带吊机提升入仓、混凝土泵泵送入仓或通过溜槽入仓。两岸趾板紧接河床段趾板自下而上按设计分段进行施工。 .1.3趾板锚筋与钢筋安装 锚筋施工在基础处理完毕后进行。 1.锚筋在厂内加工运至现场安插,安插前,先将孔内冲洗干净,灌入水泥砂浆,然后插入锚筋。锚筋安插后应将其嵌固,防止外力碰撞。 2.钢筋在厂内加工运往现场绑扎,趾板设计钢筋直径为φ22~φ28,可采用现场焊接或搭接连接,结构钢筋成型后应与锚筋钩牢,并预埋灌浆导管。 .1.4模板安装 趾板侧模一般采用标准钢模板,攘角用木模板;两岸斜坡模板采用翻模法施工,踏步用木模板拼装。

.1.5止水安装 见.5节。 .1.6混凝土浇筑 趾板混凝土按常规浇筑,表面平整度需满足设计要求,混凝土浇筑完毕后,需及时洒水养护,并做好复盖保护。特别要做好止水片的保护。根据标书要求,趾板浇筑后28d内,附近20m范围内不得进行放爆。对基础超挖过大部位,宜将超挖部分先用混凝土回填至设计高程,再浇筑趾板混凝土。 混凝土温度控制见溢洪道混凝土施工部分的14.6节。 .1.7施工进度 趾板混凝土应在相应区的垫层Ⅱ、过渡层ⅢA及主堆石区ⅢB填筑前完成。见.6节。 .1.8质量控制 见.7节。 .2大坝面板混凝土施工 .2.1面板主要工程量及浇筑分段 面板分项工程包括钢筋、止水和混凝土等。其中钢筋约2150t,混凝土62838m3,属C3类混凝土,要求最小抗压强度25Mpa,抗渗标号W12,抗冻F100级,最大骨料粒径40mm,平整度要求为F2。 面板混凝土分三段浇筑,分段工程量见附表.2-1。 面板混凝土分期工程量表 附表.2-1

振弦式计算数值参考

仪器名称: 振弦式土压力计 VWE型振弦式土压力计 产品使用说明书 仪器型号: VWE型振弦式土压力计,其中包括有VWE-1、VWE-2、VWE-4、VWE-6、 VWE-10、VWE-16、VWE-25等系列型号。 仪器用途: VWE型振弦式土压力计适用于长期测量土石坝、土堤、边坡、路基等结构物内部土体的压应力,是了解被测结构物内部土压力变化量的有效监测设备,并可同步测量埋设点的温度。 土压力计在工业、民用建筑工程中安装埋设,通常是为了测量建筑物与土体接触的界面土压力值,一般都埋设在界面上,因此称在这种情况下应用的土压力为界面式土压力计。 为了解土体对结构物的作用力,或结构物对地基土体的正压力,应在结构物或地基上选择几个断面进行测点的布设。断面应选择结构物与土体承受的压力最大处,同时也是最需要了解结构物与土体受力状态的地方。 产品特点: 土压力计主要用于测量结构物与土体交界面上的土压应力值,单只土压力计可测量与感应板相垂直的正应力,多只土压力计互成角度安装即可测量出埋设点受力的空间状态。 土压力计根据用途不同分为:用于测量不同介质接触面(界面)垂直压力的界面土压力计,和用于测量土体本身内部应力变化的土中土压力计。如测量混凝土建筑物基础与土基接触面的压应力;测量地下遂洞、隧道土体对混凝土护壁的压应力;测量各种场合的护坡、护壁、抗滑桩土体对其的压应力;测量土石坝、路基等内部土体的应力的变化值等等。 土压力计测量的是压应力值,在安装埋设当中如果方法不正确,土压力计容易发生脱空卸载现象,从而影响观测的准确性。因此,土压力计安装埋设的正确性显得尤其重要。 土压力计是否处于良好的运行状态,几乎完全取决于仪器受压面与土体间是否完全接触,因此埋设中必须注意土压力计受压面与土体之间是否会形成空隙,并尽量消除仪器下面由土壤析水引起的积水。 工作原理: 当被测结构物内土应力发生变化时,土压力计感应板同步感受应力的变化,感应板将会产生变形,变形传递给振弦转变成振弦应力的变化,从而改变振弦的振动频率。电磁线圈激振振弦并测量其振动频率,频率信号经电缆传输至读数装置,即可测出被测结构物的压应力值。同时可同步测出埋设点的温度值。 技术参数: 规格代号VWE-1 VWE-2 VWE-4 VWE-6 VWE-10 VWE-16 VWE-25 尺最大外径 D,156