PMP考试全真模拟试题(第三辑)

(版权所有,翻版必究)

1、Project management methodology is used internationally, project will achieve aimness best when it is agreed upon or accept by ?

A.Project manager

B.Project team

C.functional manager

D.Project sponsor

1、项目管理方法论在国际范围内被广泛应用,当谁认同和接受这些方法时,最有利于实现项目目标?

A.项目经理

B. 项目团队

C. 职能经理

D. 项目发起人

2. During the development of the project charter, the project manager identifies many highly probable risks and believes the project will fall. What is an appropriate next step?

A:Stop working on the project as the risk is too high

B:Stop working on the project charter and start work on the risk management plan C: Continue working on the project charter and start work on the risk management plan

D:Continue working on the project charter then review it when it with the stakeholders

2. 在制定项目章程的过程中,项目经理确认了许多可能性很高的风险,并认为项目将会失败。适当的下一步措施是什么?

A:停止为项目工作,因为风险太高

B:停止制定项目章程,开始制定风险管理计划

C:继续制定项目章程,并开始制定风险管理计划

D:继续制定项目章程,然后与项目干系人一起审查项目章程

3、Which of the following should be determined before developing project management plan?

A.Project plan updates

B.Stakeholder skills and knowledge

C.Work authorization system

D.Constraints and assumptions

3、在制定项目管理计划之前,应该确定下述哪项内容?

A. 项目计划更新

B. 干系人技能和知识

C. 工作授权系统

D. 制约因素和假设条件

4、You are assigned project manager in executing project, the project is in control on baseline, if customers are not satisfied with the performance, then what you should do firstly?

A.Discussing with project team

B.Baseline revised

C.Contract Renegotiation

D.Meeting with customers

4、在项目执行过程中,你被任命为项目经理。项目各项指标都在基线的允许范围内,如果客户对项目绩效不满意,你首先应该做什么?

A. 与项目团队一起讨论

B. 重新计算基线

C. 重新商谈合同

D. 与客户见面

5. In the course of managing a project for a client you find a way to save $10,000 in reducing the work investment based on a simpler development approach. This will not reduce the scope or operating capabilities for the end product in any way. However, it will reduce the billing for your company. What should you do?

A. Say nothing and continue on the prior course of action, saving the project billings for your company.

B. Inform the customer of the cost savings and the benefits and recommend changing the project plan to reflect the savings.

C. Approach your management and request direction.

D. Approach the customer with the change, but do not mention the $10,000 savings, keeping that as abudget contingency.

5. 在一次项目管理过程中,你发现通过使用一种简化开发的方法可以降低操作投资并为客户节省$10,000。这种方法不会对最终产品的范围和运行性能产生任何影响。然而,如果采用了这种方法将减少你们公司的营业额。你应该怎么做?

A. 什么也不说并且继续先前的行动计划,以保持你们公司的营业额

B. 通知客户这种节约成本的方法和收益,并且推荐更改项目计划以达到其的效果

C. 报告你的管理层并请求指示

D. 报告客户这种变更,但不提及可以节省$10,000,保持原有的项目预算

6. When are key project constraints documented?

A:During definition activity

B:During planning

C: During initiation

D:At the kick-off meeting

6.什么时候开始识别项目关键制约因素?

A:在定义活动阶段

B:在计划编制阶段

C:在项目启动阶段

D:在项目启动会议上

7. When the project relies on external vendors and contractors, what document describes how the project management system will be used?

A Statement of work

B Memorandum of understanding.

C. letter of intent

D. Project management plan.

7.在项目依赖外部供应商和承包商时,下列哪份文件描述了如何使用项目管理系统?

A 工作说明书

B 谅解备忘录

C 意向书

D 项目管理计划

8. A project manager was been assigned to a large enterprise located in another country. The project manager has planned the project properly and conducted all the phases of the project with success. Currently, the project manager is collecting the lessons learned during the project.

In what stage is the project manager?

A:Initiating

B:Planning

C: Executing

D:Closing

8. 项目经理被分配到位于另一个国家的一个大型企业。项目经理已经制定了合适的项目计划,并成功实施了项目各个阶段。目前,项目经理正在收集项目过程中的经验教训.

项目经理目前处于哪个阶段?

A:启动阶段

B:规划阶段

C:执行阶段

D:收尾阶段

9. A project manager takes over a large project supported by culturally diverse workforce. Within a week, it becomes clear that there is a significant conflict among two of the groups because the former project manager favored one group with special perks and accommodations.

What should the new project manager do?

A:Immediately begin facilitating a satisfactory resolution to the conflict using a collaborative approach resolution.

B:Find out why the project manager favored one group.

C:Post a new set of rules and regulations in s public location for all groups to see.

D:Report the problem to human resources.

9. 项目经理接手一个大型项目,该项目由不同文化的人员支持。不到一周时间,项目经理就发现其中有两组人员存在明显冲突, 因为前任项目经理更偏爱其中一组人员,为他们提供特殊的补贴和住宿条件。新项目经理应该怎么做?

A:使用协作的方法, 立即开始一个满意的解决方案来减轻冲突

B:找出前任项目经理偏爱其中一组的原因

C:在公共地点张贴所有成员都能看到的新规则和制度

D:向人力资源部报告此事

10. What is the main goal of regular risk monitoring?

A:To avoid all risks that could arise during the project

B:To communicate all potential risks to the stakeholders

C: To reanalyze existing risks and identify new risk exposure

D:To identify risks before starting the project

10. 定期监控风险的主要目标是什么?

A:避免在项目过程中可能发生的所有风险

B:向项目干系人沟通所有潜在风险

C:重新分析存在的风险并识别新暴露的风险

D:开始项目之前先识别风险

11. When closing a project, when will formal acceptance be obtained?

A:Upon receipt of a formal statement that the terms of the contract

B:Upon receipt of a formal upper management authority

C: Upon delivery of the final product to the customer

D:Upon delivery of all project-related document

11. 在项目收尾时,什么时候将通过正式验收?

A:收到符合合同条款的正式声明时

B:收到上级管理层正式授权时

C:将最终产品交付给客户

D:交付所有与项目相关的文件

12. Your project needs to have a major change in the equipment used on it. You know of a product that meets your needs, but you are worried that your brother owns the company that produces the product. What should you do?

A. Negotiate a good deal for the project with your brother

B. Let the customer know of the issue

C. Submit the bid and allow your brother to negotiate withe the contracting office

D. Eliminate your brother from bidding

12. 你的项目需要对项目所用的设备进行一项重大变更。你知道有一种产品可以满足你的需求,但你担心的是你的兄弟是生产这种产品那家公司的老板。你应该怎么做?

A. 就此项目与你的兄弟协商一个好价钱

B. 让客户知道这件事

C. 发出招标书并让你的兄弟与合同部门谈判

D. 不让你的兄弟参与投标

13. Why could the project manager interview the customer after all deliverables have been accepted?

A:To ensure that the acceptation criteria has been met

B:To measure customer satisfaction

C: To close out the project

D:To transfer knowledge from project team to the customer

13. 在所有可交付成果都已经验收之后,为什么项目经理还要与客户会面?

A:确保符合验收标准

B:衡量客户满意度

C:结束项目

D:将项目团队的知识移交给客户

14. A project manager is assigned to lead a development team with members located in different geographic locations. The team will be working on a project that will be lunched globally.

What should the project manager do FIRST?

A:Create a communication management plan

B:Schedule a video conference to introduce team members

C: Communicate the risk analysis to the project sponsor

D:Send an email to all team members

14. 项目经理被任命领导一支成员位于不同地理位置的开发团队。该团队会在全球不同区域内协同合作,以完成项目。项目经理首先应该做什么?

A:创建沟通管理计划

B:安排一次视频会议介绍团队成员

C:向项目发起人沟通风险分析

D:给所有团队成员电子邮件

15. In an implementation project, the development phase has been outsourced to an off-shore team. During the execution of the project, the off-shore team states that vital information to proceed in the development is missing. However, the on-shore design team has stated that all design documents have been provided.

What could most likely be the cause of this situation?

A:The communications management plan has not been created properly

B:The two teams do not get along well with each other

C: Project managers lack communication skills

D:The risk management plan has not been created properly

15. 在一个实施项目中,开发阶段的工作已经外包给一支海外团队。在执行项目期间,海外团队通知说有重要信息遗漏,但是国内设计团队说已经提供所有设计文档。造成这这种情况最有可能的原因是什么?

A:未正确创建沟通管理计划

B:两支团队相处的不好

C:项目经理缺乏沟通技巧

D:未正确创建风险管理计划

16、Which process is integration management performed ?

A.Project planning

B.Project executing

C.At key interface points

D.At the end of each project management phase

16、项目整合管理应该发生在哪个阶段?

A.项目规划阶段

B.项目执行阶段

C.在关键接口点

D.在项目管理的每个阶段结束

17、You have just been assigned as project manager in execution phase and you have to determine how you should control the project ,the best way is to:

A. Use a combination of communication methods

B. Hold schedule meetings

C. Refer to Gantt chart weekly

D. Meet with management regularly

17、你刚刚被分配到一个处于实施阶段中期的项目任项目经理,你正在确定你将如何控制这个项目,控制这个项目的最佳方法是:

A.使用综合的沟通方法

B.召开项目进度会议

C.每周参照甘特图

D.定期与管理层开会

18. Which strategy can be used to deal with negative risks?

A:Exploit

B:Share

C:Enhance

D:Transfer

18. 以下哪一种战略可被用来处理负面风险?

A:开拓

B:分享

C:增强

D:转移

19. A new produce development project is in its closing phrase. During production, unplanned redesigning and retesting was necessary. The project manager realizes that this happened because manufacturing engineers were not included in the planning and design process.

What’s the next action the project manager should take?

A:Enhance individual competence

B:Document a new lesson learned

C:Perform a quality audit

D:Update risk register

19. 目前一个新产品开发项目处于项目收尾阶段。在生产过程中,需要计划之外的重新设计和重新测试。项目经理认识到由于制造工程师没有参与设计和计划过程才会导致这种情况。项目经理下一步应采取什么措施?

A:增加个人能力

B:纪录一项新的经验教训

C:执行质量审计

D:更新风险登记册

20. A PMO manager is providing the company’s project manager with training on project management. The trainer states that for every project, project managers need to identify relevant quality standards for every project and determine how to satisfy them.

To which document is the PMO manager referring?

A:Quality audit checklist

B:Quality management plan

C:Quality policy

D:Quality assurance plan

20. PMO 经理正在为公司的项目经理提供有关的管理方面的培训,他说对于每个项目,项目经理都需要制定相关的质量标准并确定如何满足这些标准。PMO经理所指的是下列哪一份文件?

A:质量审计清单

B:质量管理计划

C:质量政策

D:质量保证计划

21. Which at the following techniques is an application of the theory of constraints and is useful when scheduling constrained resources?

A .Crashing

B. Resource levelling

C. Resource loading

D. Critical chain scheduling

21.下列哪一项技术属于制约因素理论的应用,并在对制约资源制定进度时起到作用?

A 赶进度

B 资源平衡

C 资源负荷

D 关键链进度安排

22. A risk has emerged that has not been anticipated in the risk register. Which risk monitoring tool should the project manager use to handle the situation? A:Risk reassessment

B:Risk audit technique

C:Risk register update process

D:Risk transfer tool

22. 一个在风险登记册中未预计到的风险出现了,若要解决这种情况,项目经理应使用下列哪一项监控工具?

A:风险重新评估

B:风险审计技术

C:风险登记册更新过程

D:风险转移工具

23. Which of the following is a cost estimate on tool?

A:Parametric estimation

B:Variance analysis

C:Performance measurement

D:Process analysis

23.下列哪一项属于估算成本的工具?

A:参数估算

B:偏差分析

C:绩效测量

D:过程分析

24. What is the process necessary for producing a preliminary high level definition that will be used by the project owner and project participants for planning and project success?

A:Developing project statement of work

B:Developing project charter

C:Developing WBS

D:Gathering requirement

24. 若要产生项目的初步概要定义,供项目业主和参与者规划和衡量项目是否成功,下列哪一项是其中必要过程?

A:制定项目工作说明书

B:制定项目章程

C:制定WBS

D:收集需求

25.During the planning phase of a project, the project manager realized that there are differences on the understanding of the project deliverables with a project stakeholders, That results in a strained relationship with that stakeholders. What should the project manager do to address this issue?

A. Ignore the stakeholder.

B Arrange a session with the stakeholder to understand the reasons behind the differences and address them

C. Escalate it to the sponsor so that they can sort it out for the project manager.

D. Ask the other team members to convince the stakeholder to back down.

25.在项目规划阶段,项目经理认识到与其中一名项目干系人在项目可交付成果方面的理解存在差异,从而造成与该项目干系人的关系紧张。

要解决这个问题,项目经理应该怎么做?

A.忽视该项目干系人

B.安排一次与该项目干系人的会议,了解造成理解差异的原因,并予以解决。

C 将该问题报给项目发起人,让他们为项目经理解决这个问题。

D 让其他团队成员说服项目的干系人妥协。

26. The project team is collecting all the requirements and scope from the customer and stakeholders. The project manager in charge of the project is trying t complete the chart.

What tool and technique should the project manager use?

A:Scope decomposition

B:Expert judgment

C:Activity sequencing

D:Project scheduling

26.项目团队正从客户和项目干系人那里收集所有需求和项目范围。负责该项目的项目经理正在尝试完成项目章程。项目经理应该使用下列哪一项工具和技术?

A:范围分析

B:专家判断

C:排列活动顺序

D:项目进度安排

27. The project sponsor calls the project manager and provides them with information about a new project. The project manager asks the project sponsor to provide a project charter. However, due to their busy schedule, the project sponsor is unable to provide a project charter. Which of the following paths should the project manager pursue?

A:Proceed with the project scope statement preparation, ignoring the absence of a project.

B:Prepare a first draft of the project charter and interactively work on it until it is signed off by the project sponsor.

C:Assemble a project team and begin work on the project

D:Draft detailed project requirements.

27. 项目发起人联系项目经理,向项目经理提供一个新项目的信息。项目经理要求项目发起人提供项目章程。然而,由于项目发起人很忙,无法提供项目章程。项目经理应执行下列哪一个路线?

A:开始制定项目范围说明,忽视无项目章程这个问题

B:制定项目章程的初稿,并且不断修订,直到获得项目发起人的签署同意

C:组建项目团队,并开始项目工作

D:起草详细的项目要求

28. A project manager has faced serious disagreements between two team members and has decided to gain better understanding of the situation before taking an action. Which of the conflict management modes is the project used.

A:Withdrawing

B:Smoothing

C:Compromising

D:Collaborating

28. 项目经理面临两名团队成员之间的严重分歧,它决定在采取行动之前了解更多的情况。项目使用的哪一种冲突管理模式?

A:撤退

B:缓解

C:妥协

D:协作

29、The result of creating WBS process is:

A.Project schedule

B.Team's meeting of minds

C.Project finish date

D.Risk lists

29、创建工作分解结构过程的结果是

A.项目进度计划

B.团队意见统一

C.项目完成日期

D.风险清单

30、During an informal meeting with your project client you are offered a substantial monetary incentive to alter the configuration of the product to meet the client's personal need. This change may result in additional project costs and schedule delays. The appropriate action to take would be

A. Refrain from accepting the offer and advise the customer to submit a request to the change control board.

B. Accept the offer and issue an internal configuration change request to the design group

C. Obtain additional information about the request and the customer's personal need before accepting the offer

D. Delay acceptance of the offer until you can ensure that you can protect yourself from any legal liabilities

30.在与你的客户的一次非正式会议上,客户为了达到自己个人的某种需要,送给你一笔可观的现金,同时要求你更改产品的配置。这样做将导致项目进度拖延和成本超支,你应该采取的适当做法是:

A. 拒绝接受现金,建议客户向变更控制委员会提出变更请求

B. 接受现金,并向设计小组颁发一份内部配置变更请求

C. 在接受客户的送礼之前,获得有关变更请求和客户需要的其他信息

D. 推迟接受送礼,直到你能确保自己免于法律责任

31. Two members of a team work side-by-side. Both are productive but their problems approaches are very different. This leads to frequent arguments and distrust. What development stage is the team probably in?

A:Formation

B:Storming

C:Conforming

D:Performing

31. 团队中的两个成员并肩合作,这两个成员工作能力都很强,但是他们各自的问题解决方

法极为不同,导致频繁发生争论和互相不信任。该团队可能处于下列哪个开发阶段?

A:组建阶段

B:震荡阶段

C:规范阶段

D:成熟阶段

32、Due to a lack of an employee training and proper production control, defects in a production run caused rework which cost the company $250,000. How much of this cost is directly attributable to the employees on the production line?

A. $75,000

B. $37,500

C. $212,500

D. $145,000

32、由于员工缺乏培训和适当的生产控制,生产过程中发现了错误需要返工解决。返工成本为$250,000。其中员工负有责任的成本为

A. $75,000

B. $37,500

C. $212,500

D. $145,000

33、An organization receives proposals from five pre-qualified sellers for provision of services for a project. Selection of a seller will be based upon evaluation of several qualitative criteria. It is now required to shortlist two sellers based upon the proposals submitted . What tool or technique should the project manager use to establish the shortlist?

A.Seller rating system

B.Weighting system

C.Contract negotiation

D. Independent estimates

33、一家组织收到五家资格预审合格的项目服务供应商的建议书,供应商的选择将以多项指定标准的评估为基础,现在要求根据提交的建议书缩减到二名供应商若要获得缩减名单,项目经理应该使用下列哪项工具或技术?

A. 供应商分级系统

B. 加权系统

C. 合同谈判

D. 独立估算

34、A project manager finds a seller is not meeting its contractual obligations even after several meetings and warnings. What should the project manager do?

A. Ignore the findings and continue with the seller.

B. Document the findings and continue with the seller.

C. Terminate the contract with the seller according the clauses of contract

D. Continue to have meetings with the seller and give warnings

34、项目经理发现,经多次开会并提出警告之后,某供应商仍不能完全完成合同义务,项目

经理应该怎么办?

A.忽视该问题,继续与该供应商合作

B.记录该问题,继续与该供应商合作

C.根据合同的提前终止条款终止与该供应商的合同

D.继续与该供应商开会并给与警告

35、All of the following assist in determining the impact of a scope change EXCEPT:

A. Project charter.

B. Baseline.

C. Performance measurement.

D. Milestones.

35、下列因素有助于决定范围变更的影响,但不包括:

A. 项目章程

B. 基准

C. 绩效测量

D. 里程碑

36、Two months into a designed project,the customer requested a modification to the

project.The change was made without notify the project manager.During the final

testing phase,result were different from what was planned for,This scenario is an

example of which of following?

A. Poor definition of the test plan

B. Poor development of quality management

C. Poor use of scope change control

D. Poor adherence to the communication plan

36在一个设计项目开始两个月后,客户要求对产品作修改。在没有通知项目经理的前提下

就做了这项变更。在最终测试阶段,测试结果与当初计划的不同。这种情况是下列哪项例子?

A.测试计划定义不完善

B.质量管理计划编制不完善

C.使用范围变更控制的技能差

D.不坚持沟通计划

37、Scope change control MUST be integrated with all of the following control

processes EXCEPT:

A. Schedule

B. Cost

C. Procurement

D. Quality

37、范围变更控制必须与下列控制过程整合起来,但不包括:

A. 进度

B. 成本

C. 采购

D. 质量

38、During the execution of the project, the customer reviews the project status with project manager. The customer realizes that expected work was not included in the statement of work.

What is the next step the project management should take?

A. Submit the change request to the change control board for approval.

B. Review the project schedule to accommodate the new request.

C. Invoke the change request process.

D. Perform fast tracking to exceed customer’s expectations.

38、在项目执行期间,客户与项目经理一起评审项目状态,客户意识到预期工作未包含在工作说明书中。项目经理下一步应该采取什么措施?

A、将变更请求提交给变更控制委员会批准。

B、评审项目进度表适应新的请求。

C、调用变更请求过程。

D、实施快速跟进,以超出客户期望。

39、The team’s project manager has little technical knowledge about the project or the organization.On which type of power is the project manager MOST LIKELY to rely?

A. Coercive

B. Legitimate

C. Referent

D. Delegated

39、团队项目经理对项目或组织有关的技术知识知之甚少。项目经理最有可能依赖于哪一类型的权力?

A、强制型

B、合法型

C、潜示型

D、授权型

40. You decided to ask the team to work overtime to meet a deadline. This resulted in labor costs that exceeded your planned budget by $9,250. When questioned by your supervisor about exceeding the budget, you should:

A. Advise her that you didn't authorized the overtime, they must have just been behind on their work

B. Advise her that you asked the team to work overtime to meet the deadline which resulted in the overrun

C. Advise her that the team wasn't performing at their optimal level and you had it take corrective measures to meet the deadline

D. Advise her that you were unaware of the overrun and you will find out what happened and get back to her

40. 为了能够在最终期限前完成项目,你要求项目团队加班。这造成人力成本超过原有预算$9,250。当上级向你询问超支问题时,你应该:

A. 告诉她,你没有要求加班,加班是由于团队成员工作落后造成的

B. 告诉她,为了能够在最终期限前完成项目,你要求项目团队加班,所以引起超支

C. 告诉她,团队没有表现出最佳状态,因此为了能够保证项目最终期限,你不得不进行纠正

D. 告诉她,你不知道超支,你会找出原因再回答她

41. During construction of a new manufacturing facility in another country, one of your team members complains to you that the wage paid to the workers is below the acceptable wage in your home country. In this situation it is BEST to:

A. Pay the workers at the new facility the same wage as your country

B. Pay the workers at the new facility a little less than the same wage as your country

C. Pay the workers as appropriate wage for the country within which they work

D. Ignore the issue as you have not heard the workers complain

41. 在位于另一个国家的新设备制造项目中,你的一个团队成员向你抱怨,付给该国工人的工资水平低于你本国的最低工资水平。在这种情况下,你最好:

A. 按你本国的工资水平支付给制造新设备的工人

B. 按稍低于你本国工资水平的标准支付给制造新设备的工人

C. 按工人所在国的适当工资水平支付工人工资

D. 不理睬这件事,就好像你没有听到抱怨

42、who is responsible for creating the quality plan?

A. Senior management

B. Quality manager

C. Quality team members

D. Project manager and project team members

42、谁应该负责创建质量计划?

A、高级管理层

B、质量经理

C、质量团队成员

D、项目经理和项目团队成员

43、In the early stage of establishing the project plan, the leadership of the project manager should be :

A.coaching

B. supporting

C.authorization

D.directing

43、在制定项目计划的早期阶段,项目经理的领导方式是:

A. 教练

B. 支持

C. 授权

D. 指挥

44、A new project manager has been assigned to work on a complex global project. The previous project manager has been reassigned to another project. During the handover, the new project manager discovers that the project charter has been

developed and approved.

To establish project deliverables, what should the new project manager do next?

A. Review the charter with customers and stakeholders to obtain their feedback.

B. File the charter with the PMO.

C. Gather the stakeholders’ needs, wants and expectations.

D.Define scope.

44、一名新项目经理被任命管理一个复杂的全球项目。前任项目经理被任命管理另一个项目。在交接期间,新项目经理发现项目章程已经制定并获得批准。若要确定项目可交付成果,新项目经理下一步应该做什么?

A、与客户和项目干系人评审项目章程,获得他们的反馈意见。

B、将项目章程提交给PMO。

C、收集项目干系人者的需求、需要和期望。

D、进行定义范围。

45.A team member makes a serious error that is left uncorrected on a project To hide their error, the team member intentionally misleads the rest of the team on the work they had done.

After discovering the error, what conflict resolution technique should the project manager use with the team member?

A Forcing

B Smoothing

C Compromising

D. Withdrawing

45.团队某成员在项目中犯了一个严重的错误,未得到纠正。为了掩盖错误,针对他们已完成的工作,该成员故意误导其他团队成员。在发现这个错误后,项目经理应该对该团队成员采取哪一种冲突解决技巧?

A 强制

B 缓解

C 妥协

D 撤退

46、The shortcoming of democratic management style is:

A.difficult to achieve decisions quickly

B. the majority rule doesn't always produce appropriate solution

C. when vote for wrong memebers in the project team, wrong decision-making will follow

D.all of the above

46、民主管理方式的缺点是:

A. 难以快速决策

B. 多数原则不一定产生合适的解决方案

C. 如果在项目团队对有错误的成员进行投票,则产生错误决策

D. 以上都是

47、Understanding the Halo effect is very important, because there is such kind of

tendency:

A. the interior promotion

B. hires the best

C. promotes those who excel at respective area of technology to be project managers D. promotes those who have had project management training experience to be project managers

47、了解光环效应非常重要,因为有这样一种趋势:

A.内部提拔

B.聘用最优秀的

C.提拔那些在某技术领域优秀的人做为项目经理

D.提拔那些受过项目管理培训的人做为项目经理

48、A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.

A. 1, 9

B. 9, 1

C. 1, 1

D. 9, 9

48、项目经理相信, 管理的最佳方式是在团队中形成良好的、和谐的工作关系, 高效团队将随后而来。从而带来高绩效。项目经理可被定义为一个_____ 经理。

A.1, 9

B.9, 1

C.1, 1

D.9, 9

49. The project manager must complete the project in the shortest time possible. To do so, the Project manager decides to schedule non-dependent tasks so they occur simultaneously. Which technique is the manager employing?

A. Crashing the project timeline.

B. Allowing team members to work overtime.

C. Fast tracking the project.

D. Scheduling a phased implementation.

49.项目经理必须在尽可能短的时间内完成项目。为做到这一点,项目经理决定安排相互独立的任务,以便可以同时执行。项目经理使用的是什么技巧?

A.压缩项目时间(赶工)。

B.允许团队成员加班工作。

C.项目快速跟进。

D.安排分阶段实施。

50. Which of the following inputs are included in integrated change control?

A. project management plan, change requests and work performance information

B. lesson learned, project plan updates and performance report

C. additional planning and corrective measure

D.change control system

50.下列哪一项包含在整体变更控制之内?

A.项目管理计划、变更请求和工作绩效信息

B.经验教训、项目计划更新和绩效报告

C.额外的规划和纠正措施

D.变更控制系统

51. A functional manager of a project team has refused a request to release a resource to a project The project manager decides to meet with the functional manager to find a solution. Which skill is the project manager using?

A. Compromise

B. Conflict management

C. Exercising authority

D. Negotiation

51.一个职能经理拒绝安排某个员工到项目上去。项目经理决定与职能经理当面讨论,寻求解决方案。项目经理使用的是什么技巧?

A.妥协

B.冲突管理

C.行使职权

D.谈判

52、Which of the following is a recognized risk identification technique?

A. Ranking

B. Watch List

C. Brainstorming

D. Monte Carlo analysis

52、下列哪一项属于公认的风险识别技术?

A. 排序

B.监视清单

C.头脑风暴

D.蒙特卡洛分析

53、Situations calling for a matrix organization include outside pressure for dual focus, _____ and pressure for high information processing capability.A.Pressure for clear accountability

B.Pressure for reduced duplication of effort

C.Pressure for shared resources

D.Pressure for formalized communication

53、矩阵型组织需要应对双重焦点的外部压力, _____ 和具备高信息处理能力的压力。A.职责明确的压力

B.减少重复工作的压力

C.资源共享的压力

D.形式化沟通的压力

54. A consulting firm was awarded a mega credit card processing system revamping project. Having failed to deliver the expected product within budget the last two mega projects, what approach should the consulting firm take in the initial stages of the project to avoid past failures?

A. Allow employees to work overtime.

B. Move its best employee from smaller projects to this mega one

C. Divide the project into multi-phases project

D. Hire additional technical employees from oversea market

54.一家咨询公司获得一个大型信用卡处理系统改进项目。在过去已经有两个大型项目未能按预算交付预期产品的情况,为避免再次发生这种失败,该咨询公司应该在项目初始阶段采取哪种方法?

A.允许雇员加班工作

B.将其最好员工从较小的项目调进大型项目中。

C.将项目分成一个多阶段项目。

D.在海外市场雇用额外技术工人。

55. The project manager is mandated to provide a cost estimate for a project. The estimate is accepted by the sponsor as being of a rough order of magnitude (ROM) level, yet the sponsor is expecting an accuracy range of -5 to+10% .Which range is more appropriate given that the project manager has just completed the project charter?

A. –25 to +25%

B. –50 to +100%

C. –25 to +175%

D. –50 to +50%

55.项目经理按要求提供的项目成本估算。发起人认可该估算可以作为一份粗略的量级(ROM)估算,但是发起人希望准确性范围为-5至+10%。假设项目经理已经完成了项目章程,下列哪个范围更为适当?

A.–25to +25%

B.–50to +100%

C.–25to +175%

D.–50to +50%

56、A project manager recently rewarded an individual with a promotion that carried with it a very small salary increase but substantially more responsibility. The project manager appears to be appealing to the employee's _____ need.A.Monetary

B.Physiological

C.Esteem

D.Self-actualization

56、一个项目经理最近奖励并晋升了一个雇员,只有非常小的工资增加量,但是充分地赋予了更多责任。项目经理看上去喜欢满足雇员的_____ 需要。

A.金钱

B.生理

C.尊重

D.自我实现

57. Which of the following conflict management techniques would be the most effective for long-term resolution of conflicts?

A Smoothing

B Confronting

C Withdrawal

D Compromising

57. 下面哪一项技术对于解决长期冲突是最有效的?

A. 缓解

B. 面对

C. 撤退

D. 妥协

58、The project manager review the project chanter with the stakeholders. What is the step of the process?

A. Gain project change approval.

B. Develop the work breakdown structure.

C. Form the project term.

D. Develop the preliminary scope statement.

58.项目经理在与项目干系人一起评审项目章程。该过程的下一步是什么?

A.获得项目章程批准

B.制定工作分解结构。

C.组建项目团队

D.制定项目初级说明书.

59、A project management decides to lock into risks and issues faced by the project. The project manager uses an Ishikawa diagram.

This technique is an example of which of the following?

A. Delphi technique

B. Root cause analysis

C. SWOT analysis

D. Pareto charting

59. 项目经理决定调查项目所面临的风险和问题.项目经理使用了石川图。这项技术属于下列哪一项的实例?

A.德尔斐技术

B.根本原因分析

C.SWOT分析

D.帕累托图

60、when does project manager most likely face personnel problem?

A.submitting project report

B.customer visiting

C.the project stage point

D.designing project review meetings

60、项目经理最有可能面临的人员问题发生在什么时候?

A.提交项目报告时

B.客户来访期间

C.项目交界点上

D.设计审核会议期间

61. Why is the project acceptance criteria an important component of the project scope document?

A. It forces the stakeholder to accept the product.

B. It signifies a sign-off on the requirements.

C. it defines the conditions of satisfaction for the product.

D. it definer a formal method to confirm stakeholder needs.

61.为什么项目验收标准是项目范围文件的重要组成部分?

A. 能让项目干系人接受产品。

B.它表示对需求的签署验收。

C.它确定产品的满足条件。

D.它定义了确认项目干系人需求的正式方式。

62、There are hard causes of conflict (e.g. conflicting schedules) and soft causes. Soft causes are as important as hard causes. Soft causes include diversity of disciplinary expertise, _____, and the project manager's power of reward and punishment.

A.Performance tradeoffs

B.Ambiguity of roles

C.Administrative procedures

D.Determining earned value

62、冲突有硬的起因(如:矛盾的进度表) 和软起因。软起因和硬起因一样重要。软起因包括专业技术的多样性, _____, 以及项目经理进行奖励和处罚的权利。

A.性能的权衡

B.角色二义性

C.管理程序

D.确定收益价值

63. There is a schedule delay on a prototype of commercial product for six months. The project sponsor asked a consultant to evaluate the impact of the delay. The consultant confirmed six-week delay was caused by a problem that project manager and team found two months before and were working to resolve. Which of the following reports has been reviewed by the sponsor can avoid the miscommunication between the sponsor and the project manager?

A. special analysis

初三英语一模模拟题1

初三英语一模模拟题 一、完形填空 It was a cold windy winter day and I was walking home from work. My head pointed down against the 1 when I noticed an old lady. She was 2 on the sidewalk in her house slippers (拖鞋). As I 3 her, I saw that she was well into her 80s, and she was holding some 4 in her hands. I walked on and arrived at the traffic light. Waiting there, I saw the mailbox 5 the street. The light turned green, but I pretended (假装) to check my phone and waited for her to catch up with me. In this neighborhood, even crossing with the green light was 6 . Drivers often drove 7 through red lights and stop signs. I stayed there until she 8 me. I turned to her and touched her gently on the arm. She smiled and took my hand in hers and 9 it. Her small hand was soft and warm. Hand-in-hand, we were waiting for the10 to change. When the light turned green, we walked together slowly across the street,11 the letters in the mailbox. Then I took her12 across the street. As I walked the rest of the way home, I could still feel the13 of her hand in my own. People say the first language of all humans is14 . A caring touch helps to make a bad situation15 . And even now, every time I think of the old lady, I can still feel the power of touch. 1. A. crowd B. snow C. wind D. rain 2. A. begging B. walking C. running D. riding 3. A. knew B. expected C. missed D. passed 4. A. letters B. pictures C. books D. flowers 5. A. across B. over C. through D. behind 6. A. strange B. crazy C. dangerous D. safe 7. A. carefully B. quietly C. wildly D. calmly 8. A. called B. reached C. found D. caught 9. A. pushed B. pulled C. hit D. held 10. A. way B. light C. ride D. traffic 11. A. took B. sent C. dropped D. locked 12. A. forward B. back C. away D. ahead 13. A. warmth B. trust C. care D. love 14. A. help B. kindness C. touch D. action 15. A. interesting B. necessary C. popular D. Hopeful 二、阅读理解 (A)

葫芦岛市2019年中考历史模拟试题及答案

葫芦岛市2019年中考历史模拟试题及答案 注意事项 1.本试卷满分100分,考试时间60分钟。闭卷考试,请注意分配答题时间。 2.答案全部写在答题卡上,写在试卷或草稿纸上无效。 一、单项选择题(本大题共15小题,每小题3分,共45分) 1. 北宋初,四川地区使用铁钱,但携带很不方便。宋真宗时,成都16家富商联合发行一种纸币,叫做 “交子”,用来代替铁钱在市场上流通。南宋时,纸币的需要量更大,政府就大量印行纸币。这表明交子 A. 具有市场流通交易凭证的功能 B. 促进了宋代经济重心的南移 C. 是宋政府敛聚财富的主要手段 D. 提高了四川富商的社会地位 2. 西安事变结束时,美国记者史沫特莱说:“西安事变……是一次全国性的胜利。一个一的中国…… 终于在渐渐诞生。”她所说的“统一”是指 A. 西安事变最终获得和平解决 B. 抗日民族统一战线正式建立 C. 国共两党停止内战走向合作 D. 抗战胜利台湾回到祖国怀抱 3.每个时代都有自己的流行语,如现在的网络流行语“蓝瘦香菇”“萌萌哒” “尬聊”等。新文化运动是中国近代史上一次空前的思想大解放运动,与它紧密相关的流行语是 A.民主共和 B.实业救国 C.民主科学 D.维新变法 4. 1949~1956年,我国农村生产关系变化的趋势是 A.封建土地所有制→社会主义公有制→家庭联产承包责任制 B.封建土地所有制→农民土地所有制→社会主义集体所有制 C.封建剥削制度→个体小农经济→社会主义合作经济 D.互助组→初级农业生产合作社→高级农业生产合作社 5. 历史和现实都告诉我们,只有社会主义才能救中国,只有中国特色社会主义才能发展中国,这是 人民的选择、历史的结论。我国进入社会主义初级阶段的标志是 A.三大改造的基本完成 B.土地改革完成 C.“一五”计划完成 D.中华人民共和国成立 6. 20 世纪50 年代中期,“红色资本家”荣毅仁说:“对于我,失去的是我个人的一些剥削所得…… 得到的却是一个富裕、繁荣、强盛的社会主义国家。”与荣毅仁说这番话密切相关的历史事件是 A. 土地改革运动完成 B. 对资本主义工商业的社会主义改造 1

模拟试题三有答案教学教材

模拟试题三 1、在人寿保险经营过程中,与均衡保费定期保险相比,保费递增定期保险的退保率所表现出来的规律(C) A、均衡保费定期保险的退保率高于保费递增定期保险的退保率 B、均衡保费定期保险的退保率等于保费递增定期保险的退保率 C、均衡保费定期保险的退保率低于保费递增定期保险的退保率 D、均衡保费定期保险的退保率高于或等于保费递增定期保险的退保率 2、被保险人从事剧烈体育活动,一般应经过特别约定才能承保,原因是(A) A、遭受意外伤害的概率太大 B、风险过大 C、伤害后果不能确定 D、保费负担有失公平 3、在医疗保险中,规定超过免赔额以上部分的医疗费用采用由保险人和被保险人共同分摊方式的条款称为(C)A、重复保险条款B、顺序给付条款C、比例给付条款D、给付限额条款 4、在客户服务中,财产保险公司应客户要求,收集中长期气象,灾害预报及实时的天气预报信息,协助客户做好灾害防御工作服务内容属于(B) A、定损服务 B、特殊服务 C、售前服务 D、售中服务 5、保险合同对当事人双方诚信的要求远远高于其他合同,其主要原因是(D) A、保险标的的不确定性 B、保险合同双方地位的不平等 C、保险合同的复杂性 D、保险双方信息的不对称性 6、在年金保险中,以两个或两个以上的被保险人中至少尚有一个人生存作为年金给付条件,但给付金额随着被保险人的人数减少而进行调整的年金保险是(D) A、个人年金 B、联合年金 C、最后生存者年金 D、联合及生存者年金 7、在医疗保险中,主要承保被保险人治疗疾病的一般性医疗费用的保险属于(C) A、综合医疗保险 B、费用保障保险 C、普通医疗保险 D、长期护理保险 8、不违反《保险销售从业人员监管办法》有关规定的事项(B) A、因保险销售人员的销售误导,保险公司扣留当事人资格证书 B、因保险销售人员的销售误导,保险公司扣留当事人执业证书 C、因保险销售人员的销售误导,保险代理机构扣留当事人资格证书 D、因保险销售人员的销售误导,投保人扣留当事人资格证书 9、我国反不正当竞争法规定,经营者不得采用不正当手段从事市场交易,损害竞争对手,该法所列举的不正当竞争手段之一是(B) A、以次充好 B、假冒他人注册商标 C、生产淘汰产品 D、伪造检疫结果 10、保险代理人进行代理活动的名义是(B) A、以投保人的名义 B、以保险人的名义 C、以被保险人的名义 D、以保险代理人的名义 11、在保险事故中,同时发生多种原因导致损失,且各原因的发生无先后顺序之分,对损失都起决定性作用,若这些原因都属于被保风险,则保险人对该损失的正确处理方式是(C) A、不予赔偿 B、部分赔偿 C、全部赔偿 D、比例赔偿 12、在人寿保险经营中,计算保单费用,每张保单开支,单位保费费用和每次保单终止费用等项目时的主要依据是(D)。 A以往病史B文化水平C保单类型D平均保额 13、在年金保险中,为了防止年金受领人过早死亡,丧失领取年金权利而产生的一种年金保险称为(A) A、最低保证年金 B、最高保证年金 C、远期保证年金 D、近期保证年金 14、王某,男,35岁,现投保5年期定期寿险一份,假设死亡给付发生在期末,利率为2%,35岁那年的死亡率为0.0010.王某35岁那年的自然保费是98元,则王某投保的保险金额是(A) A、100000元 B、150000元 C、200000元 D、300000元 15、一般,合同保证保险主要针对的合同是(C) A、用于机械制造的制造合同 B、用于产品销售的买卖合同 C、用于建筑工程的承保合同 D、用于技术转让的转让合同 16、保险销售从业人员在执业之前取得的《保险销售从业人员资格证书》意味着取得了(D)

山东省潍坊市2020届高三高考模拟(5月三模)考试文综历史试题

试卷类型:A 潍坊市高考模拟考试 文科综合能力测试历史部分2019.5 一、选择题:本题共35小题,每小题4分,共140分。在每小题给出的四个选项中,只有 一项是最符合题目要求的。 24.据《史记》记载,帝桀之时,自孔甲以来而诸侯多畔夏,桀不务德而武伤百姓,百姓弗堪。 汤修德,诸侯皆归汤。汤遂率兵以伐夏桀。桀走鸣条,遂放而死。汤乃践天子位,代夏朝天下。据此可知 A.分封制度下诸侯拥有较大的自主权 B.商汤的成功缘于他修德务民 C.司马迁修史旨在维护封建统治秩序 D.夏商更替实现了社会的转型 25.历史学家蒙文通指出:“非入汉而墨翟之学失其传,殆墨学之精神入于儒,而儒遂尊于后世 也。”该学者认为 A.儒学因吸收墨学而独尊 B.墨学已经融入主流思想 C.儒学开放包容空前统一 D.汉代儒墨两派融合并存 26.宋代真宗年间,商税收入达450万贯,到仁宗嘉佑三年增加到2200万贯,50年间增加了近 四倍,以后平均每年在1000万贯左右。这一现象表明,宋代 A-城市经济的繁荣发展B.海外贸易发达促进商税增长 C.货币税已取代实物税 D.商税成为财政收入重要来源 27.明代巡抚辖三司,但《会典》明载:巡抚“不许辄差都、布、按三司及军卫、府州县正官、 掌印官”;巡抚对有错误或不称职的三司官不能自行处理,只能奏罢:巡抚违法,三司官可以直接向中央参奏。这表明,明代地方管理制度 A.官员之间关系复杂隶属不明 B.以权力制约加强中央集权 C.利于维护地方的相对独立性 D.因分权方式而降低了效率 28.19世纪晚期,中国出现了第一批股份制企业。

A.逐步探索企业经营模式的近代化 B.近代工业开始在东部沿海地区起步 C.出现了最早的民族资本主义企业 D.结束了外国资本对证券市场的垄断 29.有学者指出,新文化运动前的宪政努力,把注意力完全放在了“国家富强”的根本目的之上, 而像自由、控权、保障人权这样的价值理念,终究要湮灭于国家利益的追求之中。这一观点基于当时 A.救亡图存成为时代追求 B.宪政努力背离民主方向 C.实业救国思想深入人心 D.民主观念缺乏社会基础 30.1941年,在粉碎蒋介石发动的第二次反共高潮的严酷斗争中,为了尽可能多地争取和团结 朋友,周恩来明确提出:“干革命,人越多越好,为了团结更多的人,思想上可以‘求同存异’。” 这表明 A.日本侵略重心转移 B.中共努力维护抗战大局 C.国共合作基础丧失 D.国民党消极抗日失去民心 31.图4是我国某时期的一幅农村宣传画。这反映了当时 A.土地公有制基本确立 B.小农经济形态不复存在 C.农业合作化调动了农民的积极性 D.土地自主经营解放了农村生产力 32.古代雅典一直没有成文法,贵族利用手中的权力任意解释传统习惯法。公元前621年,雅典 制定了第一部成文法典,规定:“凡能自备武装的人有公民权,而不能自备武装的人则无公民权;官吏由贵族会议选拔制改为公民抽签选举制;公民通过选举.组成一个四百零一人的议事会。”该法典 A.标志着雅典民主政治的确立 B.保证了民众的民主权利 C.一定程度上扩大了统治基础 D.使贵族失去了最高权力 33.卢梭认为:正是现代科学启蒙所导致的科学对政治社会的大规模“入侵”造成了公民德性的消 失,“随着科学与艺术的光芒在我们的地平线上升起,(公民)德性也就消失了。”这表明卢梭 A.对启蒙运动深刻反思 B.已经走向科学理性对立面 C.成为宗教神学卫道士 D.对近代民主政治感到失望

2020年湖南省中考《历史》模拟试题(三模)(含答案)

湖南省2020年中考模拟考试试卷 (历史) 温馨提示: (1)本学科考试形式为开卷考试; (2)本学科试卷分试题卷和答题卡两部分,考试时间为90分钟,满分为100分; (3)请你将姓名、准考证号等相关信息按要求填涂在答题卡上; (4)请你在答题卡 ...上作答,答在本试题卷上无效。 一.选择题(每小题4个选项中,只有一项最符合题意。本大题共20道小题,每小题2分,共40分) 1. 邵阳某中学开展远古时期人类的研究,列出的关键词有长江流域、干栏式房屋、 水稻,请你判断他们研究的是哪一远古居民 A.元谋人 B.河姆渡人 C.半坡人 D.山顶洞人 2. 在商鞅变法之中的秦国,哪些人能受到政府的奖励? ①勤奋苦读的人②耕田和织布多的人③军功卓著的人④经商致富的人 A.①② B.①②③ C.②③ D.②③④3. “光盘行动”是邵阳县某餐馆提倡顾客就餐时不剩饭菜的口号,这与下列哪一人物的主张一致? A.老子 B.孔子 C.韩非子 D. 墨子 4. “连接亚欧风物,融汇东西文明”——“一带一路”勾画了开放包容、和平发展、 互利共赢的新蓝图。在古代,丝绸之路是 A.沟通中西交通的陆上要道 B.唐代商人出海贸易的交通要道

C.连接中国南北的交通大动脉 D.清朝对外文化交流的桥梁 5. 2016年4月,教育部发函同意邵阳医专并入邵阳学院,同意首批增设临床医学、 护理学、药学、医学检验技术4个本科专业。该举措有利于医学教育的发展。在中医学发展史上作出突出贡献的有 A.张衡 B.王羲之 C.张仲景D.贾思勰 6. 学完秦汉时期的历史后,有几位同学对这一时期的基本特征进行了概括,你认为 准确的是 A.中华民族的起源 B.国家的产生与社会的变革 C.统一国家的建立 D.政权分立与民族融合 7.拟从2017级高中生起高考不分文理科,并告别一考定终身。追溯历史发展轨迹, 最早通过考试选拔人才开始于 A.隋朝 B.唐朝 C.明朝D.清朝 8. 新版第五套人民币100元纸币已经进入人们的生活。纸币给人们的生活带来了极大的便利,假如你是一位收藏家,你要收藏世界上最早的纸币应该是 A.交子 B.会子C.美元D.欧元 9. 黎淼同学准备写一篇历史小论文,为此他借来了《贞观实录》、《谈武周风云》、《论开元执政得失》等书籍作参考。请你据此判断,下列最可能的论文标题是 A.浅议繁荣与开族的社会 B.试论经济重心的南 移 C.简论民族融合的发展 D.略谈大变革的时代 10. 左图为2016年初水下打捞出的清代沉船“致远舰”舷窗 图片。提到此舰,我们会联想起120多年前那场激烈的海战,

2019合肥三模文综历史

合肥市2019年高三第三次教学质量检测 文科综合试题·历史 24.商周时期,国家遇到重大问题时,君主要征求“国人”的意见,“国人”也可以通过舆论来干预朝政。西周 王室重臣召公曾以“防民之口,甚于防川”的比喻,劝谏周厉王不要限制民众的舆论。这说明当时 A.君主专制政体不够完善 B.原始民主遗存尚有影响 C.公众舆论决定国家事务 D.统治阶级内部矛盾尖锐 25.传统观点认为,秦二世而亡缘于暴政。后来有研究者认为秦朝社会变革力度远超人们的心理承受能力,导致 帝王、群卿乃至庶人都处于恐惧之中而又没有合理的消解渠道是压倒秦朝的最后一根稻草;又有学者提出,秦朝制度抑制了多元文化的发展,没有得到中原以及关东人士的认同,遭反抗以至亡国。据此可知,关于秦二世而亡的认识 A.后期学者研究比传统观点可信 B.只能有一种正确合理的解释 C.随着研究视角拓展而趋于全面 D.缺少对古代其他王朝的观察 26.唐朝把《孝经》作为学校的必修课。《唐律疏议》中涉及孝的有58条,约占全部条款的11%,从不孝罪的论定、 定刑、惩罚措施以及为官的丁亲原则、家族中的尊卑等级等,皆有细致的规定。这充分表明唐朝时期 A.四书五经逐渐被冷落 B.传统孝道受到重视 C.儒家思想开始法制化 D.统治政策开明开放 27.商业类书籍是明清时期书市中的大端。徽商刊刻了如《天下水陆路程》、《宝货辨疑》、《商贾便览》等著 作,举凡算帐、交税、用银、用秤、出行气候、商业通信、求神保佑发财等一切知识和经验都包括在内。这反映了 A.文化进步推动政府政策调整 B.贾而好儒成为商人共同追求 C.印刷技术变革促进商业繁荣 D.商业发展助推知识结构更新 28.民国初期的政党、社团有300多个,如统一党、共和党、统一共和党、共和建设讨论会、中国社会党等等。这 些党派大体为原有的革命派、立宪派、旧官僚三派势力的分合。这一现象的出现 A.得益于清朝统治的土崩瓦解 B.标志政党政治的正式确立 C.导致了资产阶级的软弱妥协 D.说明民主革命的基础广泛 29.梁启超在《欧游心影录》中说:“泰西思想界,现在依然是浑沌过渡时代,他们正在那里横冲直撞寻觅曙光。 许多先觉之士正想把中国、印度文明输入,图个东西调和。这种大业只怕要靠我们才得完成哩。”梁启超的这一认识 A.反映了对民族文化的自信 B.缘于戊戌变法的失败 C.表现出对西方文化的绝望 D.导致五四运动的爆发 30.下图是1945年8月一1947年底国民政府发行法币数额图(据杨荫溥《民国财政史》)。图中数据的变化主要是 因为

模拟试题三及答案

模拟试题三及答案 考场号______ 座位号______ 班级_________ 姓名_________ 学号______________ 、(共25分,每小题5分)基本计算题 1.试应用冲激函数的性质,求表示式2^; (t)dt的值 -□0 2 . 一个线性时不变系统,在激励e (t)作用下的响应为A(t),激励e2(t)作用下的响应为r2(t),试求在激励Dc(t) ? D2€2(t)下系统的响应(假定起始时刻系统无储能)< 3?有一LTI系统,当激励捲⑴二u(t)时,响应y i(t) =3e2u(t),试求当激励X2(t)八⑴时,响应y2(t)的表示式(假定起始时刻系统无储能)。 4.试绘出时间函数t[u(t) -u(t -1)]的波形图

5?试求函数(1 -e^)u(t)的单边拉氏变换 二、(15分,每问5分)已知某系统的系统函数为H (s)二-,试求(1)该s +7s + 10 系统函数的零极点;(2)判断该系统的稳定性;(3)该系统是否为无失真传输系统,请写出判断过程。 、(10分)已知周期信号f(t)的波形如下图所示,求f(t)的傅里叶变换F(3)

四、(10分)信号f(t)频谱图F(「)如图所示,请粗略画出: (1)f(t)cos「'0t)的频谱图;(2)f(t)e j0t的频谱图(注明频谱的边界频率)

五、(25 分)已知■d T f(t) 3- f (t) 2f(tH2-e(t) 6e(t),且e(t) = 2u(t), dt2dt dt f(0_) =2 , f'(0J=3。试求:(1)系统的零输入响应、零状态响应;(2)写出系统函数,并作系统函数的零极点分布图;(3)判断该系统是否为全通系统。

中考化学一模模拟卷(含答案)

2019年中考化学一模模拟卷(含答案) 为了能帮助广大学生朋友们提高成绩和思维能力,下文特地为大家整理了2019年中考化学一模模拟卷,希望能够切实的帮到大家,同时祝大家学业进步! 一、选择题 1.某校兴趣小组同学将课本“测定空气中氧气的含量”实验装置(如甲图)改进为新的实验装置(如乙图),以下评价不恰当的是 A.甲、乙两装置实验前都要检查装置的气密性 B.乙装置实验中胶塞先向右移动,后向左移动 C.乙装置简洁,减少了甲图装置中导管引起的误差 D.甲装置实验中没夹紧弹簧夹,会使测定结果偏小 2.下列实验,不能成功的是 A.收集一瓶氧气,观察颜色 B.观察颜色来区分高锰酸钾和氯酸钾 C.闻气味来区分白酒和白醋 D.用10毫升量筒量取5.56mL 的水 3.下列说法正确的是( ) A.工业上常采用分离液态空气法制氧气,该原理是利用氮气和氧气的密度不同进行分离 B.实验是制取气体的原料必须是纯净物 C.氧气的化学性质比较活泼,属于可燃物

D.空气质量报告中所列的空气质量级别越小,空气质量越好 4.为鉴别空气、氧气、二氧化碳三瓶气体,可选用的方法是 A.将水倒入三瓶气体中 B.将澄清的石灰水倒入三瓶气体中 C.闻三瓶气体的气味 D.将燃着的木条分别伸入三瓶气体中 5.除去下列物质中的少量杂质,所选用的试剂及操作方法均正确的是( ) 选项物质(括号内为杂质) 试剂操作方法 A HCl( CO2) 适量NaOH溶液洗气 B NaCl (NaOH) 过量稀盐酸蒸发结晶 C CO2(CO) 足量O2 点燃 D 稀盐酸(稀硫酸) 适量硝酸钡溶液过滤 6.下列物质的鉴别方法错误的是( ) 待鉴别的物质鉴别方法 A 腈纶和羊毛纤维燃烧,闻燃烧产生的气味 B 食盐溶液和盐酸滴加无色酚酞试液,观察溶液颜色的变化 C 氯化铵和尿素[CO(NH2)2] 与熟石灰混合后一起研磨,闻气味 D CO2和CO 通入澄清石灰水中,观察溶液是否变浑浊 7.现有空气、氧气、二氧化碳的三瓶气体,最简单的区别方法是( ) A.测量三种气体的密度 B.将燃着的木条分别伸入三瓶气体

2020届吉林省吉林市三模历史试题

吉林市普通中学2020届高中毕业班第三次调研测试 文综历史试题 24.西周在吸取商代灭亡教训的基础上,将刑法体制进行调整,相比于前朝减轻许多;但是对于“不孝不友”等违背基本伦理规范的行为,还是主张要“刑兹无赦”。这表明西周的刑法体制 A.贯彻“明德慎罚”的司法原则B.推动法律由野蛮走向文明 C.服务于巩固统治的现实需要D.确保宗法原则得以贯彻落实 25.西汉前期,社会活跃着许多大盐铁商,他们资金雄厚,生产规模庞大,有的冶铁商同时役使上千人的劳动力。西汉中期以后,这些商人转而把资金投入农业,扩大地产。这一变化 A.体现国家经济政策的影响B.反映了政府宽松的商业政策 C.强化了自耕农的存在基础D.有助于提高商人的政治地位 26.唐代,儒学家韩愈激烈地批判佛学,提出对于佛教应该“人其人,火其书,庐其居”。到了北宋,以程颐程颢为代表的学者,却基本上都“出入于老释者数十年”,对佛学进行了长期、深入的研究。这一变化 A.体现了政府对外来文化的开明政策B.反映了大一统时代的恢弘气度 C.有助于儒学在这一时期的新发展D.表明弃儒从佛的现象已相当普遍 27.以下是根据相关著作整理清代江南地区部分生产资料和生活必需品的物价变化: 这表明清代这一时期 A.物价的变化受世界市场影响颇多B.传统的经济增长方式业已难以为继 C.精耕细作的农业模式进一步完善D.新的生产关系的发展导致物价波动28.1861年,清政府建立了总揽外交事务的总理衙门。当其时,君臣朝野之间往往视之为不祥之物,“士大夫顾清议者多耻预其选”。同时,当时对于这一机构的说法是“俟军务肃清,外国事务较简,仍归军机处办理,以符旧制”。上述材料突出反映了 A.理衙门在当时被视为临时性机构B.传统外交观念仍有极大的历史惯性

2019年山东省青岛市中考历史模拟试卷(三)(解析版)

2019年山东省青岛市中考历史模拟试卷(三) 一、选择题(本大题共40小题,共40.0分) 1.有学者认为,甲骨卜辞的记载反映了早期人类身处的社会历史状况和思维特征。这种自然崇拜反映的 自然与人的关系以及人对社会的认识,影响了中华民族几千年的天人思想的发端与雏形。甲骨卜辞() A. 反映了我国早期社会的真实状况 B. 促进了自然与人的和谐 C. 影响了秦汉以后政治文明的走向 D. 推动了中华文化的成长 2.中国的古典文化在日本获得了传承性发展,甚至日本人起名字通常要参考四书五经,皇室尤为如此, 如明治天皇名睦仁,大正天皇名嘉仁,昭和天皇名裕仁,平成天皇名明仁。日本天皇名字在多缀“仁”,说明他们对哪一著作的推崇() A. B. C. D. 3.读图:秦朝建立中央集权制度属于秦朝巩固国家统一的措施() A. 政治方面 B. 经济方面 C. 文化方面 D. 思想方面 4.学习历史,首先要注意时间概念,懂得计算年代,现在世界上通用的是公元纪年,公元纪年把每100 年叫做一个“世纪”。习惯上每个世纪头20年叫某世纪初,最后10年又叫某世纪末。据此刘邦于公元前202年建立汉朝,时间上应该表述为() A. 公元前3世纪初 B. 公元前3世纪末 C. 公元前2世纪初 D. 公元前2世纪末 5.法国学者谢和耐在《中国社会史》中写道:“张骞上表指出了域和位于阿姆河南北地区的屠民对中国 的丝绸的强烈兴趣,正是这种原因才决定了汉朝向塔里木盆地和帕米尔开拓的重大袂定。”这说明张賽出使西域获得的情报() A. 加强了汉朝对西域的管辖 B. 扩大了汉朝的统治区域 C. 摧动了汉朝开拓西部疆主 D. 促进了汉朝丝织业发展 6.如图反映的是我国数学领域的一项重大成果,取得这一成果的数学家是() A.刘徽 B.祖冲之 C.锺繇 D. 顾恺之 7.大运河对于中国来说远比长城对于中国更重要。大运河连接黄河流域长江 流域,连接了两个文明。使黄河流域长江流域逐渐成为一体。“鸿恩大德,前古未比。”那么,隋朝修建大运河所起的最重大的影响是() A. 满足隋炀帝游江都的愿望 B. 加强北部边防 C. 加强南北经济的交流 D. 巩固隋朝的统一 8.在历史上某个时期的黄河流域曾发生了严重的蝗灾,引起了皇帝的重视,“尔食朕百姓五谷,如食朕 之肺腑。”在宰相姚崇的辅佐下,蝗灾没有继续蔓延,很快被制止住了。上述事件发生于() A. 唐太宗时期 B. 唐玄宗时期 C. 武则天时期 D. 宋太祖时期 9.北宋统一后,首都汴京是南北钦食技术的交流中心,南宋时汴京的饮食业涌入杭州等地。宋朝人普遍 喜欢饮酒和饮茶,城市中还有许多凉饮店,出售甘豆汤、漉梨浆、木瓜汁、沉香水、荔枝膏水等饮料。 由此推知,宋代() A. 商品经济发展助推社会生活变化 B. 经济重心完成转移 C. 城市经济结构发生了革命性变革 D. 商业市镇经济繁荣 10.海上丝路盛于宋元,使中外经济文化和科技交流进一步发展。从科技角度看,宋元时期海外贸易兴盛 的原因有哪些? ①指南针应用②造船业发达③交子在市场上流通④政府的鼓励政策⑤国家统一,经济发展() A. ③④ B. ①③ C. ②③ D. ①② 11.统一多民族国家的巩固和发展,啊中华民族生生不息、绵延不断、屹立于世界民族之林的根本。下列 各项均体现上述观点,其中发生于明清时期的史实是() ①忽必烈在中央设中书省,在地方设行中书省,进一步加强了对全国的统治 ②戚继光消灭倭寇、郑成功收复台湾、雅克萨之战的胜利,捍卫了国家主权与民族利益 ③清政府设置驻藏大臣,进一步密切了西藏与内地的联系,加强了中央对西藏的管辖 ④乾隆帝时期平定大小和卓叛乱,巩固了祖国西北边疆 A. ①②③ B. ①②④ C. ②③④ D. ①③④ 12.中国古代文化科技灿烂辉煌,下列按时间先后排列正确的是() A. ①②③④ B. ③④②① C. ①③④② D. ③④①② 13.有专家指出:“太平天国运动的进步性在于试图从土地所有制方面解决占中国绝大多数人口的农民的 土地问题。”下列各项能够论证这一观点的是() A. 金田起义 B. 《天朝田亩制度》 C. 定都天京 D. 《资政新篇》 14.史学家胡绳认为,中国近代史在半殖民地半封建社会形成过程中从时间上能够衔接起来的三个环节是: 1840-1864年;1864-1901年;1901-1919年。贯穿这三个历史环节的主题应该是() A. 追求平均主义,建立天朝上国 B. 借鉴苏俄经验,践行马克思主义 C. 发展资本主义,建立民主共和 D. 抵抗西方侵略,推进中国近代化 15.汪林茂在《层次的晚清三次新政》中说:“洋务新政的主要目的是强兵……但活动内容的实效和递进 意义已远远超出了洋务派的主观目的范围。”下列最能体现上述材料含义的是() A. 轮船招商局 B. 江南制造总局 C. 安庆内军械所 D. 福州船政局 16.胡适认为:“民国六七年北京大学所提倡的新文化运动,无论形式上如何五花八门,意义上只是思想 解放与个人解放。”郁达夫也说过:“五四(新文化)运动的最大的成功,第一要算个人的发现。” 由此可见新文化运动()

2018年临沂三模文综历史试题

山东省临沂市2018年普通高考模拟考试(三模)文综历史试题2018.5 一、选择题 24.西周至春秋时期朝聘礼的程序贯穿着礼物互赠,西周的礼赠具有“重礼轻财”与敬让之意,春秋时期礼赠发生了轻礼仪、重献物的转变。这反映了 A.宗族宗法的礼乐文化消亡B.等级尊卑分明的社会秩序崩溃 C.王道体系取代了霸政体系D.以国力为标准的等级制度形成 25.东汉时期,人们尊儒尚儒,高门世族累世习经学,士人讲求儒家学问更是靡然成风,然而魏晋时却是“公卿士大夫罕通经业”,甚至连一国之君的曹髦也对儒家经义发出毫不客气的质疑。该变化反映出A.时代变迁影响价值观念选择B.正统思想随王朝兴替而变化 C.佛道思想强烈冲击儒学地位D.门阀世族喜好决定世风转移 26.2003年1月,国家文物局专家组、故宫博物院等单位20多名考古专家和陶瓷专家,一致认为:安徽繁昌窑是长江下游唯一专烧青白瓷的大型古瓷窑遗址,现在能确定是北宋早期的瓷窑,其出土文物与?韩熙载夜宴图?所绘温壶、托盏等典型器物特征吻合。繁昌窑年代的确定主要使用了 A.专家论证法B.地层确定法C.史料印证法D.年代确定法 27.18世纪到20世纪初,在广州等地有许多表现中国自然景观、风土人情以及日常生活的外销画,这些外销画融进了西洋绘画的技巧,但风格又和西洋画有明显的区别。这反映了广州 A.传统艺术已逐渐没落B.是中西文化融汇之地 C.受到工业文明的冲击D.对外贸易居全国首位 28. 表1 表1是近代中国工业统计资料,表中数据变化的主要因素是 A.洋务运动的持续发展B.列强侵略程度减轻 C.政府调整了经济政策D.产业结构发生变化 29.表2 表2 A.比较客观地反映当时国共两党实情B.受制于艰苦战争环境未做实地调查 C.和以后相关研究相比较可信度更高D.体现了国民党必被历史潮流所抛弃 30.

员工培训测试题模拟试题3答案

一、单选题 (共20题) 1、霍兰德职业测试强调人格与工作的匹配,社会型人格适合的工作为()。 (1分) 教师 2、下列排序符合员工援助计划演进过程是()。①职业戒酒计划(OAP)②员工援助计划(EAP) ③员工提升计划(EEP)。 (1分) B ①②③ 3、 EAP的方案实施过程中以预防为重点,下列选项中属于初级预防内容的是()。 (1分) 改变人事管理制度,减少或消除导致职业心理问题的隐身 4、非全日制用工,是以小时计酬为主,劳动者在同一用人单位一般平均每日工作不超过()。(1分) 4小时 5、下列对劳务派遣合同与一般劳动合同的区别描述不正确的是()。 (1分) 劳务派遣合同规定被派遣劳动者的试用期时间和试用期薪酬 6、下列进行员工满意度调查要达到的目的中最为重要的一个是()。 (1分) 找出本阶段出现的主要问题及其原因 7、在员工满意度调查的后期HR及管理人员要根据调查结果与员工进行沟通,下列()不属于必须沟通的内容。 (1分) 企业问题对公司产生的影响 8、《劳动合同法》对劳务派遣单位的设立有明确规定,下列说法不正确的是()。 (1分) D劳务派遣单位可以向本劳务派遣单位的单位股东所属单位派遣劳动者 9、心理契约与组织承诺的区别在于心理契约()特点。 (1分) 双向性 10、柯达公司不仅善于生产留下人们美好形象的胶卷,而且也建造了平抑员工情绪的“幽默房”,这属于员工情绪管理中的()。 (1分) 为员工提供情绪疏导的渠道 11、对于解释在组织中不同成员对同一种需要的不同态度和行为,期望理论认为主要取决于()。 (1分) 期望值×效价 12、()年,以产业关系作为教学和研究对象的独立学科最早在美国威斯康星大学建立。(1分) 1920 13、员工关系管理贯穿于人力资源管理的四类基本管理方面,()属于人力资源开发中的员工关系管理。 (1分) 员工的职业生涯规划 14、无过失性解除合同时,用人单位须提前()天以书面形式通知劳动者本人或者支付劳动者()月工资后,可以解除劳动合同。 (1分) 30天,一个月 15、员工关系管理环境中的外部环境不包括()。 (1分) 生产经营环境 16、()不能够降低员工对单一重复性工作的反感。 (1分) 改善工作环境 17、选项()不属于来自员工个体的压力。 (1分) 面对自己很忙,同事很闲的状况感到压力大没有成就感 18、()不是员工安全立法的意义。 (1分)

中考数学一模模拟试题及答案(练习)

2019年中考数学一模模拟试题及答案(练 习) 我们经常听见这样的问题:你的数学怎么那么好啊?教教我诀窍吧?其实学习这门课没有什么窍门。只要你多练习总会有收获的,希望这篇中考数学一模模拟试题,能够帮助到您! A级基础题 1.用下列一种多边形不能铺满地面的是() A.正方形 B.正十边形 C.正六边形 D.等边三角形 2.(2019年湖南长沙)下列多边形中,内角和与外角和相等的是() A.四边形 B.五边形 C.六边形 D.八边形 3.在?ABCD中,AC与BD相交于点O,则下列结论不一定成立的是() A.BO=DO B.CD=AB C.∠BAD=∠BCD D.AC=BD 图4-3-9 图4-3-10 图4-3-11 图4-3-12 图4-3-13 4.如图4-3-10,在?ABCD中,AD=2AB,CE平分∠BCD,并交AD边于点E,且AE=3,则AB的长为() A.4 B.3 C.52 D.2 5.若以A(-0.5,0),B(2,0),C(0,1)三点为顶点画平行四边形,则第四个顶点不可能在() A.第一象限 B.第二象限 C.第三象限 D.第四象限 6.?ABCD的周长为36,对角线AC,BD相交于点O,点E

是CD的中点,BD=12,则△DOE的周长为____________. 7.?ABCD与?DCFE的周长相等,且∠BAD=60°,∠F=110°,则∠DAE的度数为__________. 8.如图4-3-13,顺次连接四边形ABCD四边的中点E,F,G,H,则四边形EFGH 的形状一定是__________. 9.已知一个多边形的内角和是外角和的32,则这个多边形的边数是________. 10.在平行四边形ABCD中,对角线AC,BD交于点O,经过点O的直线交AB于E,交CD于F.求证:OE=OF. 11.在?ABCD中,E,F是对角线BD上两点,且BE=DF. (1)图中共有______对全等三角形; (2)请写出其中一对全等三角形:________≌__________,并加以证明. B级中等题 12.如图4-3-16,已知四边形ABCD是平行四边形,把△ABD 沿对角线BD翻折180°得到△A′BD. (1)利用尺规作出△A′BD(要求保留作图痕迹,不写作法); (2)设DA′与BC交于点E,求证:△BA′E≌△DCE. 13.在?ABCD中,延长DA到点E,延长BC到点F,使得AE=CF,连接EF,分别交AB,CD于点M,N,连接DM,BN. (1)求证:△AEM≌△CFN;

人教版2019版中考历史模拟试卷(3月份)D卷(模拟)

人教版2019版中考历史模拟试卷(3月份)D卷 姓名:________ 班级:________ 成绩:________ 考试须知: 1、请首先按要求在本卷的指定位置填写您的姓名、班级等信息。 2、请仔细阅读各种题目的回答要求,在指定区域内答题,否则不予评分。 一、选择题 1 . 1935年10月,毛泽东怀着无比兴奋的心情赋诗一首《七律·长征》,其中“更喜岷山千里雪,三军过后尽开颜”是广为传诵的名句。这首诗创作于哪一历史事件结束之后? A.井冈山会师B.遵义会议 C.吴起镇会师D.会宁会师 2 . 某学生在历史课堂笔记中整理出如下知识提纲: 这表明该学生学习的历史内容是 A.俄国废除农奴制改革B.北魏孝文帝改革 C.赫鲁晓夫改革D.日本明治维新 3 . 据统计,20世纪最后三十年,世界最富裕的5个国家的人均收入增长了75%,最穷困的5个国家增加了206%,世界人口增加了15亿,而绝对贫困总数减少了2亿。这说明经济全球化 A.加大国际经济投资风险 B.拉大各国之间的发展差距 C.促进国家间的国际合作 D.对经济发展具有促进作用 4 . 如下图所示,二战后美日欧经济实力对比发生了重大变化。对此变化,下列表述错误的是()

A.从美国一枝独秀到美日欧三足鼎立B.美国丧失了世界一流经济强国地位 C.欧共体的建立促进了欧洲的崛起D.日本上升为世界第二大经济强国 5 . 我国社会主义初级阶段的基本路线的“一个中心”是指() A.改革开放B.经济建设C.四项基本原则D.民主与法制建设 6 . 在古代,中华民族创造了璀璨的文化。下列搭配正确的是 A.贾思勰——《齐民要术)B.钟繇——《诗经》 C.胡昭——《离骚》D.范缜——《黄帝内经》 7 . 近代中国向西方学习,经历了学习技术—学习制度—学习思想的三个阶段,作为这三个阶段的标志性事件是 A.太平天国、洋务运动、辛亥革命 B.太平天国、洋务运动、五四运动 C.太平天国、洋务运动、新文化运动 D.洋务运动、辛亥革命、新文化运动 8 . 古人这样评价大运河:“北通涿郡之渔商,南运江都之转输,其为利也博哉。”从中可以看出大运河直接作用是 A.实现了南水北调 B.加强了民族融合 C.促进了南北经济交流 D.有利于中外文化交流 9 . 中共十一届三中全会就体现党的指导思想及决定党和国家重大方针政策的实际作用来看,已经成为中共中央领导集体的核心是

天津市河西区2019年高考三模历史试卷

绝密★启用前 天津市河西区2019年高考三模历史试卷 试卷副标题 xxx 注意事项: 1.答题前填写好自己的姓名、班级、考号等信息 2.请将答案正确填写在答题卡上 第I 卷(选择题) 请点击修改第I 卷的文字说明 一、单选题 1.考古资料表明,西周甚至春秋早期,各诸侯国甚至是一些相距遥远的诸侯国与周王朝之间的青铜等器物,在形制、纹饰和工艺上都表现出很强的一致性。对此现象解释合理的是 A .青铜器物实现了标准化生产 B .分封制促进了文化的同质化 C .诸侯国的青铜器皆周王所赐 D .是血缘同宗在文化上的体现 2.1983年湖北张家山汉墓中出土的大量竹简,包括《二年律令》,内称:“有任人以为吏,其所任不廉、不胜任以免,亦免任者。”这一规定 A .旨在增强中央权威维护统一 B .促进了国家政务的有序运行 C .有利于强化各级官员责任意识 D .目的是厉行法治突显皇权至上 3.明朝时期,监察御史和六科给事中被称为“言官”,专职弹劾百司。朱元璋要求由“贤良方正”之人来充任言官,明成祖朱棣则进一步强调言官要“有学识、通达治”。明朝对言官的选任实行任职回避,且规定不能选用胥吏出身和曾犯“奸贪罪名”的人为言官。明朝实行上述举措的本质意图是 A .加强监察队伍的建设 B .为实现吏治清明创造条件 C .培养优秀的监察人才 D .为监察工作提供制度保障

4.罗马法被近代社会广泛借鉴采用,其中的私法精神和内容尤其被重视,它包括所有权、债权、婚姻家庭与继承等方面的规范。由此看出,罗马法与近代社会相契合的是A.古罗马的民主与法治精神 B.自然法中的人人平等原则 C.对私人权利的规范与保护 D.近代资产阶级法学的渊源 5.1948~1949年夏,英、法、美等国通过各自渠道同中国共产党接触,试探与将要成立的新政府建立某种形式的外交关系的可能性。中共中央考虑:不接受足以束缚手脚的条件;可以采用积极办法争取这些国家承认;也可以等一等,不急于争取这些国家的承认。这反映出 A.中国共产党奉行独立自主的外交政策 B.西方国家放弃了对国民党政权的支持 C.中国突破了美国的外交孤立 D.新政府不急于获取国际支持 6.1943年1月,晋察冀根据地进行新一届边区行政委员会选举。新当选的委员中,共产党员占三分之一,左派进步人士、中间分子和其他分子(不含国民党顽固势力)占三分之二。这一现象 A.充分体现了统一战线策略 B.推动了国共两党再次合作 C.扩大了反封建的群众基础 D.反映了阶级矛盾日益缓和 7.1953年至1957年,我国生产资料在进口中所占比重年均达到92.36%,高于经济恢复时期年均84.7%的水平;消费资料所占比重仅为7.64%,较经济恢复时期的15.3%有较大下降。这一变化反映了 A.经济发展加大消费资料供给 B.经济建设深受外来模式影响 C.生产关系变革减少进口需求 D.西方国家经济封锁已经打破 8.据江苏省统计局权威数据统计:江苏对外贸易从1974年出口0.77亿美元起步,到1996年出口超100亿美元,用了近23年;从出口超100亿美元,到2000年出口超200 亿美元,用了4年时间。江苏外贸出口4年就达到第二个百亿美元的主要原因是

经济学基础模拟试卷三附答案

经济学基础模拟试卷三 1. 当两种商品中一种商品的价格发生变化时,这两种商品的需求量都同时增加或减少,则这两种商品的需求的交叉价格弹性为( ) A .正 B .负 C .0 D .1 2. 所有下列因素中除哪一种以外都会使需求曲线移动( ) A. 购买者(消费者)收入变化 B. 商品价格下降 C. 其它有关商品价格下降 D. 消费者偏好变化 3. 某消费者需求曲线上的各点( ) A .表示该消费者的效用最大点 B .不表示效用最大点 C .有可能表示效用最大点 D .以上说法都不对 4. 同一条无差异曲线上的不同点表示( ) A .效用水平不同,但所消费的两种商品组合比例相同 B .效用水平相同,但所消费的两种商品组合比例不同 C . 效用水平不同,两种商品组合比例也不相同 D .效用水平相同,两种商品组合比例也相同 5. 恩格尔曲线是从下列哪条曲线中导出的( ) A. 价格—消费曲线 B. 收入—消费曲线 C. 无差异曲线 D. 需求曲线 6. 完全垄断厂商达到长期均衡的条件是( ) A . MR=SMC=LMC B .MR=M C C .MR=SMC=LMC=SAC D .MR=SMC=LMC=SAC=LAC 7. 边际收益递减规律发生作用的前提条件是( ) A .连续等量地投入某种生产要素而保持其他生产要素不变 B .生产技术既定不变 C .按比例同时增加各种生产要素 D .A 和B 8. 正常商品的价格上升,则( ) A .替代效应使需求量增加,收入效应使需求量减少 B .替代效应使需求量减少,收入效应使需求量增加 C .替代效应使需求量增加,收入效应使需求量增加 D .替代效应使需求量减少,收入效应使需求量减少 9. 由企业购买或雇佣任何生产要素所发生的成本是指( ) A .显成本 B .隐成本 C .固定成本 D .可变成本 10. 下列说法中错误的一种说法是( ) A. 只要总产量减少,边际产量一定是负数 B. 只要边际产量减少,总产量一定也减少 C. 随着某种生产要素投入量的增加,边际产量和平均产量增加到一定程度将趋于下降,其中边际产量的下降一定先于平均产量 D. 边际产量曲线一定在平均产量曲线的最高点与之相交 11. 消费者剩余是消费者的( ) 一、单项选择题(请在备选答案中选出一个正确答案,并把正确答案的标 号写在题干后的括号内。每小题1分,共30分)

相关主题
文本预览
相关文档 最新文档