当前位置:文档之家› LEAD-GNL3Z-CP-052 MS for Lube Oil Flushing at GTG 51-MJ01 ABCD Rev.2 - APPROVED

LEAD-GNL3Z-CP-052 MS for Lube Oil Flushing at GTG 51-MJ01 ABCD Rev.2 - APPROVED

LEAD-GNL3Z-CP-052 MS for Lube Oil Flushing at GTG 51-MJ01 ABCD Rev.2 - APPROVED
LEAD-GNL3Z-CP-052 MS for Lube Oil Flushing at GTG 51-MJ01 ABCD Rev.2 - APPROVED




C
EA D EAD
?
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 2 / 13 A 0 1 2 IFC
TABLE?OF?CONTENT?
1. 2. 3. 4. 5. 6. 7. 8. 9. PURPOSE SCOPE OBJECTIVES REFERENCES HSE ROLES & RESPONSIBILITY THREATS & MITGATIONS PROCEDURE ATTACHMENT SCHEMATIC DIGRAM BY GE FOR LUBE OIL FLUSHING ? JSA 3 3 3 4 56 7 8 91

?

C
EA D EAD
?
1. Purpose
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 3 / 13 A 0 1 2 IFC
The purpose of this procedure is to: ? Ensure that Lube Oil Flushing is carried out safely. ? Detail the necessary steps to carry out Lube Oil flushing in accordance with Vendor requirements RIC8990006 / 4 Rev.7. ? Outline all steps necessary to meet oil cleanliness standards in line with API 614 PARA 4.3.3.7.1 for test screen cleanliness and acceptability criteria for oil analysis in accordance with ISO 4406 class 15/12. Note: Class 15/12 means that there are more than 160 and up to and including 320 particles equal to or larger than 4 μm per millilitre and more than 20 and up to and including 40 particles equal to or larger than 6 μm per millilitre.
2. Scope
This procedure outlines the preparation, execution, acceptance criteria and reinstatement activities necessary to successfully complete lube oil flushing activities at Gas Turbine Generator 51-MJ01-A/B/C/D.
The following circuits were identified by Vendor for Lube Oil Flushing; 1. 2. 3. 4. Lube oil short circulation bypassing Lube Oil Cooler Lube oil short circulation including Lube Oil Cooler Lube oil long circulation on main circuit Hydraulic oil circuit.

C
EA D EAD
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 4 / 13 A 0 1 2 IFC
3. References
Title Document
GE OIL & GAS GENERAL NOTES FOR OIL SYSTEM FLUSHING GE OIL & GAS TURBOGENERATOR INSTALLATION & PRECOMMISSIONING SCHEMATIC DIAGRAM LUBE OIL AUXILIARY SYSTEM SCHEMATIC DIAGRAM OIL COOLER SYSTEM SCHEMATIC DIAGRAM STARTING MEANS SYSTEM
RIC8990006 / 4 Rev. 7
SECTION 7
GNL3Z-V-405073-0150 sh.1
GNL3Z-V-405073-0152
GNL3Z-V-405073-0154
SCHEMATIC DIAGRAM LUBE OIL TURBINE SYSTEM
GNL3Z-V-405073-0150 sh. 2
SCHEMATIC DIAGRAM GENERATOR SYSTEM
GNL3Z-V-405073-0150 sh. 3
SCHEMATIC DIAGRAM OIL VAPOUR SEPARATOR SYSTEM SCHEMATIC DIAGRAM HYDRAULIC RATCHET SYSTEM SCHEMATIC DIAGRAM HYDRAULIC OIL SYSTEM
GNL3Z-V-405073-0151
GNL3Z-V-405073-0149 sh. 3 GNL3Z-V-405073-0149 sh. 1

C
EA D EAD
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 5 / 13 A 0 1 2 IFC
SCHEMATIC DIAGRAM IGV SYSTEM SCHEMATIC DIAGRAM FUEL GAS SKID SYSTEM SCHEMATIC DIAGRAM FUEL GAS DLN SKID GENERAL SPECIFICATION LUBE OIL AND SEAL OIL FLUSHING
WASTE MANA WASTE MANAGEMENT PLAN GEMENT PLAN CONSTRUCTION HSE Plan
GNL3Z-V-405073-0149 sh. 2 GNL3Z-V-405073-0144 sh. 1 GNL3Z-V-405073-0144 sh. 2 318800-GNL3Z-ST-PR-00-79026
318800-GNL-3Z-AP-EV-00-85041
318800-GNL-3Z-AP-SE-85001 318800-GNL-3Z-AP-SE-85022
HSE REQUIREMENTS FOR SUBCONTRACTORS
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN POLLUTION CONTINGENCY PLAN FOR CIVIL WORKS
318800-GNL-3Z-AP-EV-00-85040
318800-GNL-3Z-AP-EV-00-85042
4. HSE
4.1. General
It is both Contractor and Client policy to integrate Health, Safety, Environment and Risk Management into every aspect of its business activities: to this end the Contractor (SAIPEM), Subcontractor (LEAD) and Vendor (GE Nuovo Pignone) will act positively to prevent injury to personnel and damage to facilities and the environment. At all times the Contractor, Subcontractor and Vendor will comply with all safety, fire and environmental laws and regulations without regard to the degree of enforcement. All Pre-Commissioning activities will be performed following general principles of effective HSE management and in accordance with the applicable site execution plan requirements for safety and working environment. HSE shall be built into the Pre-Commissioning work at procedure and Method statement level and will be reflected in all work activities.

C
EA D EAD
? ? ? ? ? ?
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 6 / 13 A 0 1 2 IFC
Contractor Pre-Commissioning Focal Point for these activities will ensure that: Subcontractor and Vendor understand and adhere to all Project Health, Safety and Environmental policies and standards. Relevant standards, good engineering practise and principles of risk management are applied at all times. Immediately rectify areas where deficiencies exist. The acceptance of responsibility at and from the top, exercised through a clear chain of command throughout the activities, including Subcontractor and Vendor. A conviction that high standards are achievable through proper management. Every member of Contractor, Subcontractor and Vendor has a duty to ensure that all Project policies and principles are adhered to, to take all necessary steps to reduce risk to personnel and facilities.
4.2 Specific issues
In addition to adherence to site execution and HSE plans the following specific safety issues are to be addressed prior to the commencement of each activity. PPE ? The use of PPE is mandatory for all Contractor, Vendor and Subcontractor members. Any additional safety equipment required for specific tasks will be made available prior to commencement of any activities by Subcontractor. Material?Safety?Data?Sheet?(MSDS) ? MSDS for all Oils and additional chemicals used during Lube Oil Flushing activities must be available at worksite in a visible location and a copy must also be attached to the Work Permit.
Tool Box?Meetings ? Prior to the commencement of activities the Contractor Pre-Commissioning Focal Point will ensure that Subcontractor, Vendor and Discipline Engineers involved in the tasks participate in joint Toolbox meeting to ensure that everyone taking part understands the activities that are taking place and what actions must be taken to ensure a safe work place. When a step is reached in the procedure which requires modification to the Lube Oil Flushing circuit then the Contractor Pre-Commissioning Focal Point will ensure that all personnel involved in these activities clearly understand the sequence of events that must be executed before proceeding.
?
Job?Safety?Analysis ? Prior to all activities the Contractor and Subcontractor Pre-Commissioning Focal Points will jointly prepare a JSA for the activities which must then be clearly communicated to all personnel involved in the activities.

C
EA D EAD
SIMOPS ?
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 7 / 13 A 0 1 2 IFC
The Contractor Pre-Commissioning Focal Point will jointly, with the Contractor PreCommissioning HSE Supervisor and Subcontractor Pre-Commissioning Focal Point, review on a daily basis SIMOPS issues that might affect the safety of personnel or facilities prior to the commencement of Lube Oil Flushing activities. Procedure P13 SIMOPS Management at Site will be utilized during these activities.
Permit?to?Work ? The Construction Permit to Work procedure will be used for these activities.
Electrical?Hazards ? As a temporary Generator Set will be utilised for these activities it is Contractor and Subcontractor responsibility to ensure that all equipment and temporary cabling is suitable for use prior to the commencement of energization.
5. Roles AND Responsibilities
5.1 Contractor Pre-Commissioning Focal Point (SAIPEM)
? Has overall responsibility for coordinating Pre-Commissioning activities in support of Lube Oil Flushing between Vendor, Subcontractor and Discipline Engineers. ? Has responsibility for organizing and executing testing to meet acceptance criteria as outlined by Vendor.
5.2. Subcontractor Pre-Commissioning Focal Point (LEAD)
? Has day to day responsibility for coordinating Pre-Commissioning activities in support of Lube Oil Flushing and will be responsible for ensuring; ? ? ? ? Correct Tools and equipment are available for executing Lube Oil Flushing. Ensure that suitably qualified personnel with Supervision are available to provide 24 hour coverage during Lube Oil Flushing. Confirm that shift handovers will be carried out at GTG. Ensure that an emergency plan is in place so that in the event of an emergency such as fire, loss of containment or injury that everyone involved in the activities are fully aware of contingencies. Communication plan is in place ensuring that contact numbers for key personnel are in place. Prepare a safety Plan. Ensure that adequate lighting is available at night.
? ? ?

C
EA D EAD
?
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 8 / 13 A 0 1 2 IFC
Ensure that all Subcontractor personnel understand scope of work and there responsibilities.
5.3. Contractor Pre-Commissioning HSE Supervisor (SAIPEM)
? Has responsibility for informing all adjacent work groups what activities are taking place and associated risks. ? Ensure that Tool box meetings are carried out correctly and that all personnel involved in Lube Oil Flushing activities are aware of any risks. ? Will also assist the Pre-Commissioning Focal point with the preparation of JSAS, barriers and other precautions as outlined in the safety plan.
5.4 Vendor Focal Point (GE Nuovo Pignone)
? Provide Technical support and carry out pre-determined checks prior to and during Lube Oil Flushing activities. ? Ensure that temporary Electrical connections are correctly implemented.
5.5 Rotating Equipment Specialist (SAIPEM)
? Verify checks made by Vendor and liaise with Contractor Pre-Commissioning Focal point to ensure that adequate spares such as gaskets, filters etc. are available.
Threats AND Mitigations
5.1. Threats and Mitigations during Lube Oil Flushing
Environmental?Impact ? The potential for Lube Oil leaks during Lube Oil Flushing is real so measures most be put in place to minimise spills and coordinate clean ups. Spill kits will be supplied by Subcontractor. ? Risk of fire is low however portable fire extinguishers will be on hand and available for use if required. Suggest that CO2 hand held extinguishers be used to minimise damage to equipment. Ensure that all personnel involved in this activity are aware of hazards associated with CO2 and have been trained to use extinguishers.
SIMOPS ? During Lube Oil Flushing no other activities except those being directed by Vendor will be allowed within the vicinity of the GTG. ? Loop Testing will be in progress during Lube Oil Flushing. Care must be taken to ensure that Lube Oil Flushing is not interrupted.

C
EA D EAD
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 9 / 13 A 0 1 2 IFC
Spare?Parts ? It is Rotating Equipment Specialist responsibility to ensure that adequate spare parts are available (obviously not every contingency can be planned for however Vendor will determine what is considered necessary for the task at hand).
6. PROCEDURE
6.1. Specific pre-start activities and considerations
1. Blowing with clean, dry and oil free air will be executed in the following systems as advised by Vendor; a. Lube Oil Flushing Circuit b. Oil Vapour Separator Circuit c. Hydraulic Oil Flushing Circuit
?
2. Lube Oil Tank must be inspected for Cleanliness prior Lube Oil Flushing. 3. Three random samples of Lube Oil must be taken from drums to be used as baseline reading for cleanliness prior to Lube Oil Filling. 4. All orifice plates required must be removed prior to air blowing and Lube Oil Flushing and stored in a safe location until final reinstatement after the completion of Lube Oil Flushing. 5. All instruments except those designated by Vendor must be removed and stored in a safe location. (Such as gauges, transmitters and switches). 6. All instrument root valves in Lube Oil Circuits must be tagged and closed prior to Air Blowing and Lube Oil Flushing. 7. Prefabricated temporary spools may be required at control valve locations (utilise hoses may not be practicable where space is an issue). 8. All removed valves must be taped to ensure that internals remain clean and stored in a safe location. 9. To avoid contamination of the on skid Lube Oil System, the off-skid Lube Oil Cooler will have a dedicated basket strainer installed prior to return of oil to the Lube Oil Tank. The 100 Mesh basket strainer must have isolation valve so that frequent cleaning can be carried with minimal loss of oil. 10. Control valve bypasses must be flushed during Lube Oil Flushing. 11. Install all designated temporary hoses, permanent filters and temporary mesh screens prior to leak testing. 12. Temporary mesh screens must be installed so that any debris will be easily removable during inspections. 13. All temporary restriction orifices should be Stainless Steel, while temporary blinds and spades can be carbon steel. 14. Leak testing with dry, clean and oil free air is the last activity prior to filling the circuit with Flushing Oil. 15. Ensure that Aux. Lube Oil Pump PL-2 and Lube Oil Heater 23QT-1/2/3/4 are available utilising temporary power prior to start the Lube Oil Flushing activities. Warning: Lube Oil Heaters 23QT-1/2/3/4 must be switched off when Aux. Lube Oil Pump PL-2 is not running. Note: All instrument tags indicated in this procedure are related to Gas Turbine Generator

C
EA D EAD
Step 4 5 7
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 10 / 13 A 0 1 2 IFC
51-MJ01-A. For 51-MJ01-B increase all instrument tag numbers of 500, for 51-MJ01-C increase all instrument tag numbers of 1000 and for 51-MJ01-D increase all instrument tag Description 100 Mesh basket strainer on 10” manhole of Lube Oil Tank Rated Hose and Clamp Pressure Gauge PG-5158 numbers of 1500. Qty 1 1 1 Comments Require isolation valve for cleaning. To connect TP-120 to basket strainer. Ensure calibration is current.
Step 1: Lube oil short circulation bypassing Lube Oil Cooler
Procedure?
1. Remove the TCV-5184, installing a proper three ways piping spool. 2. Remove the restriction orifice RO-5240. 3. Turn in close position the spectacle blind on TP-121 and relocate the spectacle blinds on three ways spool so as to close the supply line from the cooler. 4. Install 100 Mesh basket strainer on Lube Oil Tank. 5. Install by-pass hose from TP-120 to the 100 Mesh basket strainer, with isolation valve before it in order to control the oil flow and to allow basket strainer cleaning. 6. Isolate the PT-5183 and LT-5175. 7. Start the Aux. Lube Oil Pump PL-2 for the first time just run for 1 minute and monitor pump discharge pressure with PG-5158. Start flushing the circuit and verify the cleanliness of the 100 Mesh basket strainer. 8. Energize the Lube Oil Tank Heaters 23QT-1/2/3/4 and monitor the oil temperature with TG-5181. 9. Continue the flushing until acceptance criteria for particulate at basket strainer is satisfied and then proceed to Step 2.
Material?Requirements?
?
Step 2: Lube oil short circulation including Lube Oil Cooler
Procedure?
1. Relocate the spectacle blinds on three way spool so as to isolate the lube oil cooler bypass line and turn in closed position the spectacle blind on TP-121. 2. Install 100 Mesh strainer on TP-121 at inlet of Lube Oil Cooler. 3. Install 100 Mesh strainer on TP-120 at inlet of the temporary hose. 4. Start the Aux. Lube Oil Pump PL-2 and monitor pump discharge pressure with PG-5158. 5. Energize the Lube Oil Tank Heaters 23QT-1/2/3/4 and monitor the oil temperature with TG-5181. 6. Continue flushing cycle until acceptance criteria for particulate at TP-120, TP-121 and basket strainer is satisfied and then proceed to Step 3.

C
EA D EAD
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 11 / 13 A 0 1 2 IFC
Material?Requirements?
Step 2 3 Description 100 Mesh Screen 6” 100 Mesh Screen 6” Qty 1 1 Comments At TP-120. At TP-121.
Step 3: Lube oil long circulation on main circuit
Procedure?
1. Remove 100 Mesh at TP-120 and make up joint with final gasket 2. Confirm that cartridge filter is installed at FL-1A and FL-1B and put in service only one. 3. Turn in closed position the spectacle blinds on TP-121 (removing the 1000 Mesh screen) and relocate the spectacle blinds on three ways spool so as to close the supply line from the cooler (same configuration of Step 1). 4. Isolate the PDT-5157. 5. Disconnect the impulse line on PCV-5164. 6. Remove RO-5165. 7. Disconnect and plug tubing to IGV System located upstream of TG-5167. 8. Install blind gasket on accessory gear box supply line. 9. Disconnect the supply line for turbine bearing 1 and install a 100 Mesh screen on the bypass line to the Lube Oil Tank. 10. Disconnect the supply line for turbine bearing 2 and install a 100 Mesh screen on the bypass line to the Drain Box-3. 11. Disconnect the supply line for the load gear bearings and install a 100 Mesh screen on the bypass line to the connection point BL-162. 12. Disconnect the supply lines for the generator bearings and install two 100 Mesh screens on the bypass lines to the related return line. 13. Install 12” blind gasket on load gear return line. 14. Locked close the 1 ?” valve on common suction line of Jacking Oil Pumps PJ-1A/1B and PJ-2A/2B. 15. Remove suction and return line on mist oil separator for air blown and mechanical brush for cleanliness and inspection. 16. Inspect the oil mist separator filter. 17. Fill the Drain Box. 18. Start Mineral Oil Vapour Extractor Fan 88-QV-1. 19. Start the Aux. Lube Oil Pump PL-2 and monitor pump discharge pressure with PG-5158. 20. Energize the Lube Oil Tank Heaters 23QT-1/2/3/4 and monitor the oil temperature with TG-5181. 21. Start oil flushing cycle until acceptance criteria for particulate is satisfied and then proceed to Step 4.
Material?Requirements
Step 2 7 8 Description Cartridge Filter ?” Plug for Tubing 2” blind gasket Qty 2 1 1 Comments At FL-1A and FL-1B. To isolate tubing to IGV. To isolate accessory gear.

C
EA D EAD
9 9 9 10 10 10 11 11 11 12 12 12 13
Snamprogetti
CLIENT
SONATRACH
PLANT LOCATION
JOB 318800
UNIT 00
GNL-3Z
PROJECT TITLE
ARZEW - ALGERIE
DOC n.: LEAD-GNL3Z-CP-052
Rev. Page 12 / 13 A 0 1 2 IFC
2” 150 lb flange for hose bypass 2” 100 Mesh Screen 2” Rated Hose and Clamps 1” 150 lb flange for hose bypass 1”100 Mesh Screen 1” Rated Hose and Clamps 4” 150 lb flange for hose bypass 4” 100 Mesh Screen 4” Rated Hose and Clamps ?” 150 lb flange for hose bypass ?” 100 Mesh Screen ?” Rated Hose and Clamps 12” blind gasket
1 1 1 1 1 1 1 1 1 2 2 2 1
To bypass turbine bearing 1. On bypass turbine bearing 1. To connect turbine bearing 1 supply line to Lube Oil Tank. To bypass turbine bearing 2. On bypass turbine bearing 2. To connect turbine bearing 2 supply line to Drain Box-3. To bypass load gear bearing. On bypass load gear bearing. To connect load gear bearing supply line to BL-162 To bypass generator bearings. On bypass generator bearings. To connect generator bearing supply lines to the return lines. To isolate load gear return line.

Step 4: Hydraulic oil circuit
Procedure
1. After lube oil flushing completion, connect the Hydraulic Oil Auxiliary Pump PH2-1 with protection panel (rotation test to be done in advance). 2. Verify Hydraulic Oil Filter cartridge at FH2-1 and FH2-2. 3. Line up one Hydraulic Oil Filter Cartridge, FH2-1 or FH2-2. 4. Install blind gasket on IGV Control System supply line. 5. Disconnect the supply line for DLN skid installing a bypass line to the Drain Box-2. 6. Start Hydraulic Oil Auxiliary Pump PH2-1 and run for 5 min. 7. Stop the Hydraulic Oil Auxiliary Pump PH2-1. 8. Reconnect supply line for DLN skid. 9. Install tubing bypasses around ZCV-5010, XV-5009 and XEV-5024. 10. Install tubing bypasses around ZCV-5013, XV-5012 and XEV-5025. 11. Install tubing bypasses around ZCV-5020, XV-5021 and XEV-5026. 12. Install tubing bypasses around ZCV-5021, XV-5022 and XEV-5027. 13. Start Hydraulic Oil Auxiliary Pump PH2-1 and run for 5 min. 14. Stop the Hydraulic Oil Auxiliary Pump PH2-1.
Material?Requirements?
Step 4 5 5 9, 10, 11, Description ?” blind gasket 1” 150 lb flange for hose bypass 1” Rated Hose and Clamps ?” Tubing Fitting OD ?” M/F Qty 1 1 1 3m 24 Comments To isolate IGV Control System. To bypass DNL skid. To connect supply line for DLN to Drain Box-2. To bypass ZCV-5010, XV-5009, XEV5024 ZCV-5013, XV-5012, XEV-5025

C
EA D EAD
12
Snamprog getti
CLIE ENT
SON NATRACH
PLAN LOCATION NT
JOB 318800
UNIT T 00
GNL-3Z G
PROJ JECT TITLE
ARZEW - ALGERIE
DOC n.: GNL3Z-CP-052 2 LEAD-G
Rev. Page 13 / 13 3 A 0 1 2 IFC
Union fitting OD ? F/F ?”
12
ZCV-5 5020, XV-502 XEV-502 ZCV21, 26 5021, XV-5022, XE EV-5027.


8.At ttechmen nts:
8.1.T TYPICAL IN NLINE FLUS SHING SCR REEN ISOL LATION CO ONFIGURA ATION
8.2. A Attchment 2: Typical Inline Flus shing Screen

C
EA D EAD
Snamprog getti
CLIE ENT
SON NATRACH
PLAN LOCATION NT
JOB 318800
UNIT T 00
GNL-3Z G
PROJ JECT TITLE
ARZEW - ALGERIE
DOC n.: GNL3Z-CP-052 2 LEAD-G
Rev. Page 14 / 13 3 A 0 1 2 IFC



二级造价师《基础知识》模拟试题

二造真题下载 一、单项选择题(共60题,每题1分。每题的备选项中,只有1个符合题意) 1.工程造价咨询业的首要功能()。 A.服务功能 B.引导功能 C.联系功能 D.审核功能 2.大中型建设工程项目立项批准后,在工程开工前,按照有关规定申请领取施工许可证的单位是()。 A.建设单位 B.设计单位 C.施工单位 D.监理单位 3.依据《建筑法》的规定,大型基础设施工程已按照国务院有关规定批准开工,但因故未能按期开工,其开工时间超过()个月,该工程应当重新办理开工报告的批准手续。 A.1 B.2 C.4 D.6 4.对于可撤销的合同,当事人必须从知道或者应当知道撤销事由之日起()年内行使撤销权。 A.1 B.2 C.3 D.4 5.一方当事人的违约行为导致工程受到5万元的损失时,对方及时地采取了减损措施支出的费用为1万元,但仍未能终止损害,工程实际损害费用为7万元。依据《合同法》的违约责任规定,违约方应承担的赔偿额为()万元。 A.5 B.6 C.7 D.8 6.依据《合同法》的规定,执行政府定价或政府指导价的合同,合同当事人一方逾期交付标的物时,遇价格上涨,应()。 A.按新价格执行 B.按原价格执行 C.按原价和新价的平均价执行 D.按市场价执行 7.在一个建设工程项目中,具有独立的设计文件,竣工后可以独立发挥生产能力或效益的一组配套齐全的工程项目是指() A.单项工程 B.单位工程 C.分部工程 D.分项工程 8.基础设施工程、房屋建筑的地基基础工程和主体结构工程的最低保修期限为()。 A.2年 B.5年 C.50年 D.设计文件规定的该工程的合理使用年限 9.下列关于评标委员会的说法,正确的是()。 A.成员人数为3人以上的单数 B.由招标人代表和有关技术、经济等方面的专家组成 C.评标委员会成员的名单应在开标时公开 D.其中招标人以外的专家不得少于成员总数的2/5 10.发包人应在收到承包人进度款支付申请后的()天内根据计量结果和合同约定对申请内容予以核实,确认后向承包人出具进度款支付证书。 A.7 B.14 C.28 D.30 11.建设工程合同签订以后,发包人往往会支付给承包人一定比例的预付款,一般为合同金额的()。

有色金属行业标准

有色金属行业标准 高镍锍化学分析方法 第6部分铅、锌和砷含量的测定电感耦合等离子体原子发射光谱法 编制说明 标准编制组 2018年11月3日

一、工作简况 1.1方法概况 1.1.1 项目的必要性 高镍锍是镍冶炼过程中产生的很重要的中间产品,其中所含的铅、锌、砷含量的高低直接影响镍产品生产质量和生产工艺中除杂工序的负荷,是原料投入生产工序前的重点关注对象。现行有色行业标准《高镍锍化学分析方法》YS/T 252.1~.5包括5个部分,分别是镍重量法、铁磺基水杨酸光度法、钴火焰原子吸收光谱法、铜硫代硫酸钠滴定法及硫燃烧中和滴定法,没有铅锌砷的分析方法,为了有效指导生产和为贸易提供高镍锍中有害元素的检测方法,制定一个行业认可、方法准确可靠的高镍锍中铅、锌、砷含量的分析标准显得尤为重要和迫切。 1.1.2 适用范围 本标准适用于高镍锍中铅、锌、砷含量的测定。测定范围:铅0.02%~0.5%,锌 0.01%~0.5%,砷0.02%~1%。 1.1.3 可行性 金川集团股份有限公司是中国的镍钴生产基地、铂族金属提炼中心和国内第三大铜生产企业,其中承担集团公司最终产品及各类外购原料检测的检测中心,取得了17025国家认可实验室、甘肃省强制检定计量器具专项计量授权等资质,拥有ICP-MS、ICP-AES、直读光谱仪、X-荧光光谱仪、原子吸收光谱仪、原子荧光光谱仪等诸多国内外先进的检测仪器,项目成员多次参与国家标准、ISO标准、有色行业标准的起草、验证等工作,具有丰富的方法研究经验。 高镍锍作为生产电解镍的主要原料,在镍金属原料贸易中占有较大的市场份额,交易量逐年增大,仅金川公司每年的采购量近3万吨。其中所含的铅、锌、砷含量的高低直接影响镍产品生产质量和生产工艺中除杂工序的负荷,是原料投入生产工序前的重点关注对象。电感耦合等离子发射光谱分析已成为全国各实验室进行微量及常量检测项目分析的主流手段,该设备具有检测效率高,抗干扰能力强,检出限低等优势,建立电感耦合等离子发射光谱法测定高镍锍中杂质元素的方法,为高镍锍生产、贸易提供数据结算的依据,填补了有色行业标准没有铅、锌、砷分析标准的空白。因此,有必要建立电

计算机二级基础知识整理

计算机基础知识部分 1.1计算机概述 考点1计算机发展简史 1946年2月日,世界上第一台电子计算机Eniac在美国宾夕法尼亚大学诞生,它的出现具有划时代的伟大意义。 从第一台计算机的诞生到现在,计算机技术经历了大型机、微型机及网络阶段。对于传统的大型机,根据计算机所采用电子元件的不同而划分为电子管、晶体管、集成电路和大规模、超大规模集成电路等四代, 我国在微型计算机方面,研制开发了长城、方正、同方、紫光、联想等系列微型计算机我国在巨型机技术领域中研制开发了“银河”、“曙光”、“神威”等系列巨型机。 考点2计算机的特点 现代计算机算一般具有以下几个重要特点。 (1)处理速度快(2)存储容量大。(3)计算精度高。(4)工作全自动。 (5)适用范围广,通用性强。 考点3计算机的应用 计算机具有存储容量大,处理速度快,逻辑推理和判断能力强等许多特点,因此已被广泛应用于各种科学领域,并迅速渗透到人类社会的各个方面,同时也进人了家庭。计算机主要有以下几个方面的应用。 (1)科学计算(数值计算)。(2)过程控制。(3)计算机辅助设计(CAD)和计算机辅助制造(CAM)。(4)信息处理。(5)现代教育(计算机辅助教学(CAI)、计算机模拟、多媒体教室、网上教学和电子大学)。(6)家庭生活。 考点4计算机的分类: 巨型机,小巨型机,大型主机,小型机,工作站,个人计算机。 1.3 计算机中字符的编码考点7 西文字符的编码 计算机中常用的字符编码有EBCDIC码和ASCII码。IBM系列大型机采用EBCDIC码,微型机采用ASCII码是美国标准信息交换码,被国际化组织指定为国际标准。它有7位码和8位码两种版.国际的7位ASCII码是用7位二进制数表示一个字符的编码,其编码范围从0000000B一1111111B,共有7=128个不同的编码值,相应可以表示128个不同的编码。7位ASCII码表:p41 考点8汉字的编码 1.汉字信息的交换码 汉字信息交换码简称交换码,也叫国标码。规定了7 445个字符编码,其中有682个非汉字图形符和6763个汉字的代码。有一级常用字3755个,二级常用字3 008个。两个字节存储一个国标码。国标码的编码范围是2121H一7E7EH。区位码和国标码之间的转换方法是将一个汉字的十进制区号和十进制位号分别转换成十六进制数,然后再分别加上20H,就成为此汉字的国标码: 汉字国标码=区号(十六进制数)+20H位号(十六进制数)+ 20H 而得到汉字的国标码之后,我们就可以使用以下公式计算汉字的机内码:

计算机二级公共基础知识题汇总5套真题

第一套2008年9月 一、选择题 (1)一个栈的初始状态为空。现将元素1、2、3、4、5、A、B、C、D、E依次入栈,然后依次出栈,则元素出栈的顺序是________。 A)12345ABCDE B)EDCBA54321 C)ABCDE12345 D)54321EDCBA B【解析】栈的特点是先进后出,所以全部入栈后再全部出栈所得的序列顺序必然及入栈序列的顺序相反。 (2)下列叙述中正确的是________。 A)循环队列有队头和队尾两个指针,因此,循环队列是非线性结构 B)在循环队列中,只需要队头指针就能反映队列中元素的动态变化情况 C)在循环队列中,只需要队尾指针就能反映队列中元素的动态变化情况 D)循环队列中元素的个数是由队头指针和队尾指针共同决定的 D【解析】循环队列是线性表的一种,所以选项A)错误。循环队列的入队和出队需要队尾指针和队头共同指针完成,所以选项B)和C)错误。 (3)在长度为n的有序线性表中进行二分查找,最坏情况下需要比较的次数是________。 A)O(n) B)O(n2) C)O(log2n) D)O(nlog2n) C【解析】二分查找法也称为折半查找法。它的基本思想是:将n个元素分成个数大致相同的两半,取a[n/2]及欲查找的x作比较,如果x=a[n/2],则找到x,算法终止;如果xa[n/2],则只要在数组a的右半部继续搜索x。每次余下n/(2i)个元素待比较,当最后剩下一个时,即n/(2i)=1。故,n=2i; 所以i=log2n。 (4)下列叙述中正确的是________。 A)顺序存储结构的存储一定是连续的,链式存储结构的存储空间不一定是连续的 B)顺序存储结构只针对线性结构,链式存储结构只针对非线性结构 C)顺序存储结构能存储有序表,链式存储结构不能存储有序表 D)链式存储结构比顺序存储结构节省存储空间 A【解析】顺序存储方式是把逻辑上相邻的结点存储在物理上相邻的存储单元里,结点之间的关系由存储单元的邻接关系来体现。其优点是占用最少的存储空间。所以选项D)错误。顺序存储结构可以存储如二叉树这样的非线性结构,所以选项B)错误。链式存储结构也可以存储线性表,所以选项C)错误。 (5)数据流图中带有箭头的线段表示的是________。 A)控制流B)事件驱动 C)模块调用D)数据流 D【解析】在数据流图中,矩形表示数据的外部实体,圆角的矩形表示变换数据的处理逻辑,双横线表示数据的存储,箭头表示数据流。 (6)在软件开发中,需求分析阶段可以使用的工具是________。 A)N-S图B)DFD图 C)PAD图D)程序流程图 B【解析】数据流图简称DFD图,采用图形方式来表达系统的逻辑功能、数据在系统内部的逻辑

组件间缝隙填堵密封胶的施工工艺

大棚组件间缝隙填堵密封胶施工方案 一、注胶条件 1、相邻的两排或一排组件按要求安装整齐并且安装牢固; 2、组件间的密封条已按要求填堵可靠; 3、注胶时环境清洁无尘土、无火种、通风良好; 4、注胶前应对所用硅酮结构密封胶与组件边框型材进行粘接性测试,与所用密封条进行相容性试验,以确保所会使用结构胶符合施工要求,未做粘结性试验和相容性试验的严禁使用; 5、有对硅酮结构胶气味过敏的人禁止做注胶工作; 6、禁止使用过期变硬或离析的密封胶。 二、注胶工艺 1、工艺流程 组件边框清洁填入密封条注密封胶整形清除余胶静置养护固化符合要求。 2、注胶环境 1注胶人员严禁吸烟、严禁使用火种, 2通风良好,并采用必要的安全防护措施; 3禁止在烈日当头的中午或组件边框表面温度低于4℃或高于40℃时施工。 4施工条件:温度在5度到30度之间,相对湿度35%--75%,无油污无灰尘,禁止在大风、雨雪天施工。 3、施工步骤

1注胶前要核对所使用的硅酮结构胶品牌符合设计要求、质量资料相对应、胶在在有效期,完全正确方可使用,并做好材料验收核实记录。 2注胶的组件边框使用干净、柔软不易脱绒的棉布和合适的溶剂进行清洁; 3把干净的密封条填入组件间缝隙,要求密封条均匀低于组件边框5mm,并清洁干净; 4清洁干净后立即开始由上而下一次性均匀注入足量的硅酮结构专用胶; 5用专用的胶刀对注入的硅酮结构胶进行刮平整形,清理余胶(必须在注胶后10-20分钟内完成); 6对需要补胶的地方要及时补胶、刮平后清除余胶(必须在注胶后10-20分钟内完成); 7静置养护3天达到粘接强度,7-14天,达到固化要求。 4、余胶清洁 1注完胶的组件清洁污渍要用相适应的溶剂清洁; 2在距离密封胶缝1cm的范围内不可使用溶剂,以免胶缝粘接效果。实际效果图

硅酮密封胶的基本知识

硅酮密封胶的基本知识 newmaker 室温硫化硅橡胶(RTV)是六十 年代问世的一种新型的有机硅弹性体,这种橡胶的最显著特点是在室温下无须加热、如压即可就地固化,使用极其方便。因此,一问世就迅成为整个有机硅产品的一个重要组成部分。现在室温硫化硅橡胶已广泛用作粘合剂、密封剂、防护涂料、灌封和制模材料,在各行各业中都有它的用途。室温硫化硅橡胶由于分子量较低,因此素有液体硅橡胶之称,其物理形态通常为可流动的流体或粘稠的膏状物,其粘度在100~1000000厘沲之间。 根据使用的要求,可把硫化前的胶料配成自动流平的灌注料或不流淌但可涂刮的腻子。室温硫化硅橡胶所用的填料与高温硫化硅橡胶类似,采用白炭黑补强,使硫化胶具有10~60公斤/厘米2扯断强度。填加不同的添加剂可使胶料具有不同的比重、硬度、强度、流动性和触变性,以及使硫化胶具有阻燃、导电、导热、耐烧蚀等各种特殊性能。室温硫化硅橡胶按其包装方式可分为单组分和双组分室温硫化硅橡胶,按硫化机理又可分为缩合型和加成型。因此,室温硫化硅橡胶按成分、硫化机理和使用工艺不同可分为三大类型,即单组分室温硫化硅橡胶、双组分缩合型室温硫化硅橡胶和双组分加成型室温硫化硅橡胶。 单组分和双组分缩合型室温硫化硅橡胶的生胶都是α,ω-二羟基聚硅氧烷;加成型室温硫化硅橡胶则是含烯基和氢侧基(或端基)的聚硅氧烷,因为在熟化时,往往在稍高于室温的情况下(50~150℃)能取得好的熟化效果,所以,又称低温硫化硅橡胶(LTV)。这三种系列的室温硫化硅橡胶各有其优缺点:单组分室温硫化硅橡胶的优点是使用方便,但深部固化速度较困难;双组分室温硫化硅橡胶的优点是固化时不放热,收缩率很小,不膨胀,无内应力,固化可在内部和表面同时进行,可以深部硫化;加成型室温硫化硅橡胶的硫化时间主要决定于温度,因此,利用温度的调节可以控制其硫化速度。 单组分室温硫化硅橡胶的硫化反应是靠空气中的水分来引发的。常用的交链剂是甲基三乙酰氧基硅烷,它的Si-O-C键很易被水解,乙酰氧基与水中的氢基结合成醋酸,而将水中的羟基移至原来的乙酰氧基的位置上,成为三羟基甲基硅烷。三羟基甲基硅烷极不稳定,易与端基为羟基的线型有机硅缩合而成为交链结构。平时,将含有硅醇端基的有机硅生胶与填料、催化剂、交链剂等各种配合剂装入密封的软管中,使用时由容器挤出,借助于空气中的水分而硫化成弹性体,同时放出低分子物。交链剂除甲基三乙酰氧基硅烷外,还可以是含烷氧基、肟基、胺基、酰胺基、酮基的硅烷。当与烷氧基交链后放出醇,称为脱醇型单组分室温硫化硅橡胶,当与肟基交链后生成肟,称为脱肟型室温硫化硅橡胶、因此,随着交链剂的不同,单组分室温硫化硅橡胶可为脱酸型、脱肟型、脱醇型、脱胺型、脱酰胺型和脱酮型等许多品种,但脱酸型是目前最广泛使用的一种。单组分室温硫化硅橡胶的硫化时间取决于硫化体系、温度、湿度和硅橡胶层的厚度,提高环境的温度和湿度,都能使硫化过程加快。在典型的环境条件下,一般15~30分钟后,硅橡胶的表面可以没有粘性,厚度0.3厘米的胶层在一天之内可以固化。固化的深度和强度在三个星期左右会逐渐得到增强。

计算机二级考试历年公共基础知识真题

2010年9月全国计算机等级考试公共基础知识试题及答案 一、选择题(每小题2分)下列各题A)、B)、C)、D)四个选项中,只有一个选项是正确的。请将正确选项填涂在答题卡相应位置上,答在试卷上不得分。 (1)下列叙述中正确的是 A)线性表的链式存储结构与顺序存储结构所需要的存储空间是相同的 B)线性表的链式存储结构所需要的存储空间一般要多于顺序存储结构 C)线性表的链式存储结构所需要的存储空间一般要少于顺序存储结构 D)上述三种说法都不对 (2)下列叙述中正确的是 A)在栈中,栈中元素随栈底指针与栈顶指针的变化而动态变化 B)在栈中,栈顶指针不变,栈中元素随栈底指针的变化而动态变化 C)在栈中,栈底指针不变,栈中元素随栈顶指针的变化而动态变化 D)上述三种说法都不对 (3)软件测试的目的是 A)评估软件可靠性B)发现并改正程序中的错误 C)改正程序中的错误D)发现程序中的错误 (4)下面描述中,不属于软件危机表现的是 A)软件过程不规范B)软件开发生产率低 C)软件质量难以控制D)软件成本不断提高 (5)软件生命周期是指 A)软件产品从提出、实现、使用维护到停止使用退役的过程 B)软件从需求分析、设计、实现到测试完成的过程 C)软件的开发过程 D)软件的运行维护过程 (6)面向对象方法中,继承是指 A)一组对象所具有的相似性质B)一个对象具有另一个对象的性质 C)各对象之间的共同性质D)类之间共享属性和操作的机制 (7)层次型、网状型和关系型数据库划分原则是 A)记录长度B)文件的大小 C)联系的复杂程度D)数据之间的联系方式 (8)一个工作人员可以使用多台计算机,而一台计算机可被多个人使用,则实体工作人员、与实体计算机之间的联系是 A)一对一B)一对多C)多对多D)多对一 (9)数据库设计中反映用户对数据要求的模式是 A)内模式B)概念模式C)外模式D)设计模式 (10)有三个关系R、S和T如下:

硅酮密封胶生产工艺相关

加成型室温硫化硅橡胶(双组份为主) 当前市场的硅胶牌子有很多,从高端到低端有: 高端:GE东芝,瓦克(张家港),道康宁(美国),野牛(荷兰),罗纳星(法国),千里马,白云(中国),之江(杭州),高士。(12元以上) 中档:新展,安泰,硅宝,森戈,快事达,宏英,欧利雅、永安(以上均为国产)。 低端品牌:金鹰翔,豪威,美城,基亿,恒德,宏华,宏固,精硅等等,小厂家特别多。目前市场做的较好的有道康宁,建华,之江,硅宝、欧利雅、新展等牌子。 生产方法 107室温硫化硅橡胶和碳酸钙、白炭黑、助剂等混合均匀,抽真空制成玻璃胶。 化学方程式:107RTV+SiO2+CaCO3=玻璃胶 常见种类 1. 单双组份分类:单组份和双组份 2. 酸碱性分类:酸性和中性胶 3. 颜色分类:黑色、瓷白、透明、银灰、灰、古铜六种 4. 耐候胶性、防霉性分类:耐候硅酮密封胶适用于各种幕墙耐候密封,特别推荐用于玻璃幕墙、铝塑板幕墙、石材干挂的耐候密封。耐候密封胶适合金属、玻璃、铝材、瓷砖、有机玻璃、镀膜玻璃间的接缝密封;耐候硅酮密封胶混凝土、水泥、砖石、岩石、大理石、钢材、木材、阳极处理铝材及涂漆铝材表面的接缝密封。大多数情况下都无需使用底漆。 防霉硅酮密封胶是未来的趋势,有防霉效果的硅酮胶比一般的胶使用时间更长,更牢固,不易脱落,特别适用于一些潮湿、容易长霉菌的环境,如卫浴、厨房等。 缩合型室温硫化硅酮密封胶的组成:基础聚合物、交联剂、催化剂、填料及添加剂等配制而

成,前3种为必须成分,但作为实用产品,后两种往往也不可缺少。 1、基础聚合物:α ,ω -二羟基聚二甲基硅氧烷,即HO(MeRSiO)nH(式中,R 为Me、 CF3CH2CH2、Ph 等;n=100~2000)是制备缩合型单组分室温硫化硅酮密封胶最重要的基础聚合物。其中,HO[Me(CF3CH2CH2)SiO]n H 用于制备耐油耐溶剂产品;HO(Me2SiO) (MePhSiO)m H用于制备耐寒及抗辐照产品。 n (2)交联剂 交联剂指能将基础聚合物联结成网状结构并具有三个以上水解性官能团的硅烷或聚硅氧烷,是单组分室温硫化硅酮密封胶的核心组分,是决定产品交联机理的基础。目前使用的典型交联剂品种有MeSi(OAc)3、MeSi(ON=CMeEt)3、MeSi(OMe)3等。 不同结构交联剂与水反应的能量及活性不同,不过,交联剂水解能与硫化胶表面消粘时间有关,活性越高、消粘时间越短。相同催化剂用量条件下,交联剂的水解反应活性的顺序为:丙酮型>酰胺型>醋酸型>酮肟型>醇型 (3)催化剂 催化剂是一类能提高基础聚合物与交联剂在室温下的反应速度的有机化合物。主要使用锡化合物及钛化合物。其中,锡化合物类催化剂主要是有机羧酸锡及有机锡鳌合物,如辛酸亚锡、二月桂酸二丁基锡、二辛酸二丁基锡、二乙酸二丁基锡、二甲氧基二丁基锡、二丁基氧化锡、Bu2Sn(OMeC=CHCOMe)2等,常用的钛化合物类催化剂主要是钛酸酯及钛的鳌合物,如四异丙氧基钛酸酯、四正丁基钛酸酯、四(三甲基硅烷氧基)钛、二异丙氧基-双(乙酰丙酮基)钛等。 (4)填料 单组份室温硫化硅酮密封胶所用的填料可分为补强性填料和非补强性填料(增量填 料)两大类。补强性填料包括气相法白炭黑、沉淀法白炭黑和表面处理白炭黑等。半补 强填料包括硅藻土、沉淀法碳酸钙和高岭土(SiO2-Al2O3)。增量填料包括硅微粉、云母粉、二氧化钛和硅酸锆等。 (5)添加剂 单组份室温硫化硅酮密封胶的添加剂通常包括增塑剂(又称稀释剂)、链增长剂、硫化促进剂、颜料、触变性、增粘剂、稳定剂(羟基清除剂),耐热剂及防霉剂等。 加成型室温硫化硅橡胶主要由含乙烯基的有机聚硅氧烷作为基础聚合物,低聚合度含氢硅油作为交联剂,铂化合物作为催化剂,炔醇作为反应抑制剂,白炭黑、石英粉、硅树脂

有色金属行业基础知识(更新)

有色金属行业基础知识 1.概述 1.1 有色金属的分类 有色金属是指铁、铬、锰三种金属以外所有的金属,包括:铜、铝、铅、锌、镍等常用金属;钨、钼、锡、锑等稀有金属;金、银等贵金属;铈、镧等稀土金属,以及硅、硒等半金属,共计64种元素。 国际上的研究机构大多数都将有色金属分为基本金属(Basemetals)、贵金属(Preciousmetals)、小金属(Minormetals)、稀土金属(rare earth metal)和半金属(semimetal)。基本金属包括铜、铝、铅、锌、锡、镍六种金属;贵金属包括金、银、铂、钯、钌、铑、锇、铱;小金属主要包括钨、钼、锑、钛、镁等;稀土金属包括包括镧系元素及性质相近的钪和钇,共17种元素。 1.2 有色金属的生产过程 有色金属的生产,包括地质勘探、采矿、选矿、冶炼和加工等过程。 地质勘探:“地质勘探”即是通过各种手段、方法对地质进行勘查、探测,需找、发现有工业意义的有色金属矿床,并查明矿产的质和量,以及开采利用的技术条件,提供矿山建设设计所需要的矿产储量和地质资料。 采矿:采矿是自地壳内或地表选择性地采集和搬运矿石的过程。绝大部分矿床用普通机械化方法开采。机械化开采又分为露天开采(包括

矿石和砂矿)和地下开采两大类。露天开采将矿体上覆的岩层剥离,然后自上而下顺次开采矿体。露天矿敞露地表,可以使用大型采矿机械,作业较安全,矿石损失少,贫化率低,生产能力大,采矿成本低,大型贫铁矿床和建筑材料矿床多用此法。当矿体赋存深度大,矿体厚度小,剥离工作量很大,其经济效益低于地下开采或需要保护地表和景观时,则用地下开采方法。赋存条件复杂,工业储量较小的有色和稀有金属矿床多用此法。 采矿的主要生产过程包括:①采准:在已经开拓完毕的矿床里,按开采方法的要求掘进采准巷道,将阶段划分成矿块作为独立的回采单元。②回采:将矿石崩落破碎,装入运输容器。地下回采包括落矿、出矿作业;露天回采包括穿孔、爆破和采装作业。③运输:将装入运输容器的矿石运交选矿厂或矿仓。 选矿:用物理或化学方法将矿物原料中的有用矿物和无用矿物(通常称脉石)或有害矿物分开,或将多种有用矿物分离开的工艺过程,又称“矿物加工”。 选矿的主要生产过程包括:①破碎:将矿山采出的矿块碎裂至粒度为 5~25mm的过程。②磨碎:以研磨和冲击为主。将破碎产品磨至粒度为10~300μm大小。③筛分和分级:按筛面筛孔的大小将物料分为不同的粒度级别称筛分,常用于处理粒度较粗的物料。按颗粒在介质(通常为水)中沉降速度的不同,将物料分为不同的等降级别,称分级,用于粒度较小的物料。筛分和分级是在粉碎过程中分出合适粒度的物料,或把物料分成不同粒度级别分别入选。④选别作业:矿物原料经粉碎作

计算机二级公共基础知识(全)

1.1 算法 考点1 算法的基本概念 计算机解题的过程实际上是在实施某种算法,这种算法称为计算机算法。 算法(algorithm)是一组严谨地定义运算顺序的规则,并且每一个规则都是有效的,同时是明确的;此顺序将在有限的次数后终止。算法是对特定问题求解步骤的一种描述,它是指令的有限序列,其中每一条指令表示一个或多个操作。 1算法的基本特征 (1)可行性(effectiveness):针对实际问题而设计的算法,执行后能够得到满意的结果。 (2)确定性(definiteness):算法中的每一个步骤都必须有明确的定义,不允许有模棱两可的解释和多义性。 (3)有穷性(finiteness):算法必需在有限时间内做完,即算法必需能在执行有限个步骤之后终止。 (4)拥有足够的情报:要使算法有效必需为算法提供足够的情报当算法拥有足够的情报时,此算法才最有效的;而当提供的情报不够时,算法可能无效。 2算法的基本要素 (1)算法中对数据的运算和操作:每个算法实际上是按解题要求从环境能进行的所有操作中选择合适的操作所组成的一组指令序列。 计算机可以执行的基本操作是以指令的形式描述的。一个计算机系统能执行的所有指令的集合,称为该计算机系统的指令系统。计算机程序就是按解题要求从计算机指令系统中选择合适的指令所组成的指令序列在一般的计算机系统中,基本的运算和操作有以下4类: ①算术运算:主要包括加、减、乘、除等运算; ②逻辑运算:主要包括“与”、“或”、“非”等运算; ③关系运算:主要包括“大于”、“小于”、“等于”、“不等于”等运算; ④数据传输:主要包括赋值、输入、输出等操作。 (2)算法的控制结构:一个算法的功能不仅仅取决于所选用的操作,而且还与各操作之间的执行顺序有关。算法中各操作之间的执行顺序称为算法的控制结构。 算法的控制结构给出了算法的基本框架,它不仅决定了算法中各操作的执行顺序,而且也直接反映了算法的设计是否符合结构化原则。描述算法的工具通常有传统流程图、N-S结构化流程图、算法描述语言等。一个算法一般都可以用顺序、选择、循环3种基本控制结构组合而成。 (3)算法设计的基本方法 计算机算法不同于人工处理的方法,下面是工程上常用的几种算法设计,在实际应用时,各种方法之间往往存在着一定的联系。 (1)列举法 列举法是计算机算法中的一个基础算法。列举法的基本思想是,根据提出的问题,列举所有可能的情况,并用问题中给定的条件检验哪些是需要的,哪些是不需要的。 列举法的特点是算法比较简单。但当列举的可能情况较多时,执行列举算法的工作量将会很大。因此,在用列举法设计算法时,使方案优化,尽量减少运算工作量,是应该重点注意的。 (2)归纳法 归纳法的基本思想是,通过列举少量的特殊情况,经过分析,最后找出一般的关系。从本质上讲,归纳就是通过观察一些简单而特殊的情况,最后总结出一般性的结论。

2019年二级造价工程师考试《基础知识》考前模拟试题

【例题·单选】关于我国项目前期各阶段投资估算的精度要求,下列说法中正确的是( )。 A.项目建议书阶段,允许误差大于±30% B.投资设想阶段,要求误差控制在±30%以内 C.预可行性研究阶段,要求误差控制在±20%以内 D.可行性研究阶段,要求误差控制在±15%以内 【答案】C 【解析】A选项,项目建议书阶段,要求误差控制在±30%以内。D选项,可行性研究阶段,要求误差控制在±10%以内。选项C,预可行性阶段即为初步可行性研究阶段。 【例题·单选】详细的可行性研究阶段投资估算的要求为误差控制在±( )%以内。 【答案】B 【解析】投资决策是一个由浅入深、不断深化的过程,不同阶段决策的深度不同,投资估算的精度也不同。如在投资机会和项目建议书阶段,投资估算的误差率在±30%左右;而在详细可行性研究阶段,误差率在±10%以内。 【例题·单选】决策阶段影响工程造价的主要因素包括( )。A.项目建设规模B技术方案 C.设备方案 D.外部协作条件 E.环境保护措施 【答案】ABCE

【解析】工程决策阶段影响造价的主要因素有:项目建设规模、建设地区及地点(厂址)、技术方案、设备方案、工程方案和环境保护措施等。 【例题·单选】确定项目建设规模时,应该考虑的首要因素是( )。A.市场因素B.生产技术因素 C 管理技术因素D.环境因素 【答案】A 【解析】市场因素是确定建设规模需考虑的首要因素。 【例题·单选】总平面设计中,影响工程造价的主要因素包括( )。A.现场条件B.占地面积 C.工艺设计 D.功能分区 E.柱网布置 【答案】BD 【解析】总平面设计中影响工程造价的主要因素包括:(1)占地面积(2)功能分区(3)运输方式。 【例题·单选】关于建筑设计对工业项目造价的影响,下列说法正确的有( )。A.建筑周长系数越高,单位面积造价越低 B.单跨厂房柱间距不变,跨度越大,单位面积造价越低 C.多跨厂房跨度不变,中跨数目越多,单位面积造价越高 D.大中型工业厂房一般选用砌体结构来降低工程造价 【答案】B

硅酮密封胶生产工艺相关.docx

v1.0可编辑可修改加成型室温硫化硅橡胶(双组份为主) 组份名称相应种类 基础聚合物含乙烯基的有机聚二甲基硅氧烷,如双端乙烯基聚二甲基硅氧烷 交联剂低粘度的线型甲基含氢硅油 第八族过渡金属(如铂、钯、铑、镍等)及其化合物或配合物 催化剂 填料补强 :气相法白炭黑、沉淀法白炭黑和表面处理白炭黑等; 非补强:硅藻土、沉淀法碳酸钙和高岭土(SiO2-Al 2O3) 抑制剂延迟硅氢化反应的抑制剂,如炔醇类抑制剂 当前市场的硅胶牌子有很多,从高端到低端有: 高端: GE东芝,瓦克(张家港),道康宁(美国),野牛(荷兰),罗纳星(法国),千里马,白云(中国),之江(杭州),高士。(12 元以上) 中档:新展,安泰,硅宝,森戈,快事达,宏英,欧利雅、永安(以上均为国产)。 低端品牌:金鹰翔,豪威,美城,基亿,恒德,宏华,宏固,精硅等等,小厂家特别多。 目前市场做的较好的有道康宁,建华,之江,硅宝、欧利雅、新展等牌子。 生产方法 107室温硫化硅橡胶和碳酸钙、白炭黑、助剂等混合均匀,抽真空制成玻璃胶。 化学方程式: 107RTV+SiO2+CaCO3=玻璃胶 常见种类 1.单双组份分类:单组份和双组份 2.酸碱性分类:酸性和中性胶 3.颜色分类:黑色、瓷白、透明、银灰、灰、古铜六种 4.耐候胶性、防霉性分类:耐候硅酮密封胶适用于各种幕墙耐候密封,特别推荐用于玻璃幕 墙、铝塑板幕墙、石材干挂的耐候密封。耐候密封胶适合金属、玻璃、铝材、瓷砖、有机

玻璃、镀膜玻璃间的接缝密封;耐候硅酮密封胶混凝土、水泥、砖石、岩石、大理石、钢材、木材、阳极处理铝材及涂漆铝材表面的接缝密封。大多数情况下都无需使用底漆。 防霉硅酮密封胶是未来的趋势,有防霉效果的硅酮胶比一般的胶使用时间更长,更牢固,不易脱落,特别适用于一些潮湿、容易长霉菌的环境,如卫浴、厨房等。 缩合型室温硫化硅酮密封胶的组成:基础聚合物、交联剂、催化剂、填料及添加剂等配制而成,前 3 种为必须成分,但作为实用产品,后两种往往也不可缺少。 1、基础聚合物:α ,ω- 二羟基聚二甲基硅氧烷,即HO(MeRSiO)nH(式中,R为Me、CF3 CH2CH 2、Ph 等; n=100~ 2000)是制备缩合型单组分室温硫化硅酮密封胶最重要的基础聚 合物。其中, HO[Me(CF3CH2CH2)SiO] n H 用于制备耐油耐溶剂产品;HO( Me2SiO)n(MePhSiO) m H 用于制备耐寒及抗辐照产品。 (2)交联剂 交联剂指能将基础聚合物联结成网状结构并具有三个以上水解性官能团的硅烷或聚硅 氧烷,是单组分室温硫化硅酮密封胶的核心组分,是决定产品交联机理的基础。目前使用的 典型交联剂品种有 MeSi(OAc) 3、 MeSi(ON=CMeEt)3、 MeSi(OMe)3等。 不同结构交联剂与水反应的能量及活性不同,不过,交联剂水解能与硫化胶表面消粘时 间有关,活性越高、消粘时间越短。相同催化剂用量条件下,交联剂的水解反应活性的顺序 为:丙酮型>酰胺型>醋酸型>酮肟型>醇型 (3)催化剂 催化剂是一类能提高基础聚合物与交联剂在室温下的反应速度的有机化合物。主要使用锡化合物及钛化合物。其中,锡化合物类催化剂主要是有机羧酸锡及有机锡鳌合物,如辛酸亚锡、二月桂酸二丁基锡、二辛酸二丁基锡、二乙酸二丁基锡、二甲氧基二丁基锡、二丁 基氧化锡、 Bu2Sn(OMeC=CHCOMe)2等,常用的钛化合物类催化剂主要是钛酸酯及钛的鳌合物, 如四异丙氧基钛酸酯、四正丁基钛酸酯、四(三甲基硅烷氧基)钛、二异丙氧基- 双(乙酰丙酮基)钛等。 (4)填料 单组份室温硫化硅酮密封胶所用的填料可分为补强性填料和非补强性填料(增量填

初三化学金属及其性质资料

------------------------------------------------------------精品文档-------------------------------------------------------- 第五讲金属及其性质【知无巨细】常见的金属知识点一: 纯金属(90多种) 1、金属材料(几千种)合金 (1)常温下一般为固态(汞为液态),有金属光泽。 (2)大多数呈银白色(铜为紫红色,金为黄色)、金属的物理性质:2(3)有良好的导热性、导电性、延展性,密度较大,熔点较高 二、金属之最 (1)铝:地壳中含量最多的金属元素 (2)钙:人体中含量最多的金属元素 (3)铁:目前世界年产量最多的金属(铁>铝>铜) (4)银:导电、导热性最好的金属(银>铜>金>铝) (5)铬:硬度最高的金属 (6)钨:熔点最高的金属 (7)汞:熔点最低的金属 (8)锇:密度最大的金属 (9)锂:密度最小的金属 现在世界上产量最大的金属依次为铁、铝和铜 三、金属分类: 黑色金属:通常指铁、锰、铬及它们的合金。 重金属:如铜、锌、铅等 有色金属 轻金属:如钠、镁、铝等; 有色金属:通常是指除黑色金属以外的其他金属。 四、合金 1、定义:一种或几种金属(或金属与非金属)一起熔合而成的具有金属特性的物质。 ★:一般说来,合金的熔点比各成分低,硬度比各成分大,抗腐蚀性能更好 注:钛和钛合金:被认为是21世纪的重要金属材料,钛合金与人体有很好的“相容性”,因此可用来制造人造骨等。 (1)熔点高、密度小

优点(2)可塑性好、易于加工、机械性能好 (3)抗腐蚀性能好 拓展:常见的合金 页)8页(共1第 (1)钢铁 钢铁是铁与C、Si、Mn、P、S以及少量的其他元素所组成的合金。其中除Fe外,C的含量对钢铁的机械性能起着主要作用,故统称为铁碳合金。它是工程技术中最重要、用量最大的金属材料。 (2)铝合金 铝是分布较广的元素,在地壳中含量仅次于氧和硅,是金属中含量最高的。纯铝密度较低,为2.7 g/cm3,有良好的导热、导电性(仅次于Au、Ag、Cu),延展性好、塑性高,可进行各种机械加工。铝的化学性质活泼,在空气中迅速氧化形成一层致密、牢固的氧化膜,因而具有良好的耐蚀性。但纯铝的强度低,只有通过合金化才能得到可作结构材料使用的各种铝合金。 例1:铝、铜、铁、金四种金属都具有的相似性质是() A.都是银白色的固体B.都有导电性 C.都能和稀硫酸反应D.通常状况下都能与氧气反应 解析:A、铜、铁、金等物质不是银白色物质.故选项错误; B、铝、铜、铁、金四种金属都能导电.故选项正确; C、铜、金不能和稀硫酸反应.故选项错误; D、通常情况下铜、金的化学性质不活泼,不能和氧气反应.故选项错误. 故选B. 例2:铁及其合金在生产、生活中应用广泛。下列关于铁及其合金的说法中正确的是() A.铁是地壳中含量最丰富的金属元素 B.铁的抗腐蚀性好,可用于制造医疗器械 C.铁丝能在氧气中剧烈燃烧、火星四射,生成氧化铁 D.铁生锈是铁与空气中的氧气、二氧化碳、水发生缓慢氧化的过程 解析:A、地壳中含量最丰富的金属元素是铝,铁排第二位,故A错; B、铁比较容易氧化,医疗器材课用不锈钢来制造,故B错; C、铁丝在氧气中能燃烧,产物是黑色四氧化三铁,不是氧化铁,故C错; D、铁生锈是铁与水、氧气在空气中缓慢氧化的结果,故D正确. .D故选 <举一反三> 1. 2010年上海世博会中国馆—“东方之冠”给人强烈的视觉冲击,它的主体结构为四根巨型钢筋混凝上制成的陔心筒。其中钢属于() A.金属材料B.合成材料C.天然材料D.复合材料 2. 据《都市晨报》报道,2009年3月11日,沪宁铁路丹阳段施工工地由于残留的铝粉爆炸造成严重伤亡事故。下列关于铝粉的说法错误的是() A.铝粉和铝块的组成元素和化学性质都不同

2019年二级造价工程师考试《基础知识》模拟试题(十四)

【·单选】根据《建设工程工程量清单计价规范》(GB50500-2013),关于工程量清单计价的有关要求,下列说法中正确的是( )。 A.事业单位自有资金投资的建设工程发承包,可以不采用工程量清单计价 B.使用国有资金投资的建设工程发承包,必须采用工程量清单计价 C.国有资金投资总额占40%以上的项目,必须采用工程量清单计价 D.招标工程量清单的准确性和完整性由清单编制人负责 『正确答案』B 『答案解析』本题考查的是工程量清单编制。事业单位自有资金投资的建设工程发承包,必须采用工程量清单计价;国有资金投资总额占50%以上的项目,必须采用工程量清单计价;招标工程量清单的准确性和完整性由招标人负责。参见教材P213。 【·单选】《建设工程工程量清单计价规范》规定,分部分项工程量清单项目编码的第三级为表示( )的顺序码。 A.分项工程 B.扩大分项工程 C.分部工程 D.专业工程

『正确答案』C 『答案解析』本题考查的是工程量清单编制。第三级为分部工程顺序码,01表示砖砌体。参见教材P215。 【·单选】在工程量清单中,最能体现分部分项工程项目自身价值的本质的是( )。 A.项目特征 B.项目编码 C.项目名称 D.项目计量单位 『正确答案』A 『答案解析』本题考查的是工程量清单编制。项目特征是构成分部分项工程项目、措施项目自身价值的本质特征。参见教材P216。 【·单选】关于工程量清单编制中的项目特征描述,下列说法中正确的是( )。 A.措施项目无需描述项目特征 B.应按计算规范附录中规定的项目特征,结合技术规范、标准图集加以描述 C.对完成清单项目可能发生的具体工作和操作程序仍需加以描述

关于硅酮玻璃胶的基本知识

关于硅酮玻璃胶的基本知识 一、分类: 二、简述: 单组份硅酮玻璃胶是一种类似软膏,一旦接触空气中的水分就会固化成一种坚韧的橡胶类固体的材料。硅酮玻璃胶的粘接力强,拉伸强度大,同时又具有耐候性、抗振性,和防潮、抗臭气和适应冷热变化大的特点。加之其较广泛的适用性,能实现大多数建材产品之间的粘合,因此应用价值非常大。硅酮玻璃胶由其不会因自身的重量而流动,所以可以用于过顶或侧壁的接缝而不发生下陷,塌落或流走。它主要用于干洁的金属、玻璃,大多数不含油脂的木材、硅酮树脂、加硫硅橡胶、陶瓷、天然及合成纤维,以及许多油漆塑料表面的粘接。质量好的硅酮玻璃胶在摄氏零度以下使用不会发生挤压不出、物理特性改变等现象。充分固化的硅酮玻璃胶在温度到204℃(400oF)的情况下使用仍能保持持续有效,但温度高达218℃(428oF)时,有效时间会缩短。硅酮玻璃胶有多种颜色,常用颜色有黑色、瓷白、透明、银灰、灰、古铜六种。其它颜色可根据客户要求订做。三、用途(一)、酸性玻璃胶1、适宜作密封、堵塞防漏及防风雨用途,室内室外两者皆宜(室内效果更佳),防渗防漏效果显著。2、粘接汽车的各种内部装饰,包括:金属、织物和有机织物及塑料。3、接合加热和制冷设备上的垫片。4、在金属表面加装无螺孔的筋条、铭牌以及漆加塑料材料。5、对烘箱门上的窗口、气体用具上的烟道、管道接头、通道门进行封口。6、为齿轮箱、压缩机、泵提供即时成形的防漏垫。7、对船仓以及窗口密封。8、拖车、卡车驾驶室玻璃窗的密封。9、粘合和密封设备部件。10、形成防磨涂层。11、镶嵌和填充薄金属片迭层、道管网络和设备机壳。(二)、中性耐候胶1、适用于各种幕墙耐候密封,特别推荐用于玻璃幕墙、铝塑板幕墙、石材干挂的耐候密封;2、金属、玻璃、铝材、瓷砖、有机玻璃、镀膜玻璃间的接缝密封;3、混凝土、水泥、砖石、岩石、大理石、钢材、木材、阳极处理铝材及涂漆铝材表面的接缝密封。大多数情况下都无需使用底漆。(三)、硅酮结构胶1、首要用于玻璃幕墙的金属和玻璃间结构或非结构性粘合装配。2、它能将玻璃直接和金属构件表面连接构成单一装配组件,满足全隐或半隐框的幕墙设计要求。3、中空玻璃的结构性粘接密封。四、限制条件各种硅酮玻璃胶使用时均会受到以下限制:1、长期浸水的地方不宜施工;2、不与会渗出油脂、增塑剂或溶剂的材料相溶;3、结霜或潮湿的表面不能粘合;4、完全密闭处无法固化(硅胶需*空气中的水分固化);5、基材表面不干净或不牢固。(一)、酸性玻璃胶更有以下限制条件:酸性硅酮玻璃胶会腐蚀或不能粘合铜、黄铜(及其它含铜合金)、镁、锌、电镀金属(及其它含锌合金),同时建议砖石料制成物品及碳化铁体基质上不要使用酸性玻璃胶,在甲基异丁烯酸盐(PLEXIGLAS)、聚碳酸、聚丙烯、聚乙烯和TEFLON(特氟隆、聚四氟乙烯)制成的材料上使用本品将无法获得很好的粘接效果及好的相溶性。移动大于接缝宽度25%的连接也不适合用酸性玻璃胶,在结构用玻璃上也最好不用普通酸性玻璃胶(酸性结构胶除外),另外在有磨蚀以及会产生实质弊端的地方不应使用酸性玻璃胶。硅酮酸性胶的基材表面温度超过40℃不宜施工。(二)、中性耐候胶还有以下限制条件:中性耐候胶不适用于结构性玻璃装配;基材表面温度超过50℃不宜施工。(三)、硅酮结构胶还有以下限制条件:硅酮结构胶的基材表面温度超过40℃不宜施工。五、使用方法1、使用:单组份硅酮玻璃胶即时可以使用,用打胶枪很容易将它从胶瓶内打出,并可用抹刀或木片修整其表面。 2、粘住时间:硅酮胶的固化过程是由表面向内发展的,不同特性的硅胶表干时间和固化时间都不尽相同(固化时间的详细说明请参阅第四篇的《技术参数》内容),所以若要对表面进行修补必须在玻璃胶表干前进行(酸性胶、中性透明胶一般应在5-10分钟内,中性杂色胶一般应在30分钟内)。如果采用分色纸来覆盖某一地方,涂胶后,一定要在外皮形成前取走。 3、固化时间:玻璃胶的固化时间是随着粘接厚度增加而增加的,例如12mm厚度的

计算机二级公共基础知识(全)

1.1 算法 考点1 算法的基本概念计算机解题的过程实际上是在实施某种算法,这种算法称为计算机算法。 算法(algorithm)是一组严谨地定义运算顺序的规则,并且每一个规则都是有效的,同时是明确的;此顺序将在有限的次数后终止。算法是对特定问题求解步骤的一种描述,它是指令的有限序列,其中每一条指令表示一个或多个操作。 1 算法的基本特征 (1) 可行性(effectiveness):针对实际问题而设计的算法,执行后能够得到满意的结果。 (2) 确定性(definiteness):算法中的每一个步骤都必须有明确的定义,不允许有模棱两可的解释和多义性。 ⑶有穷性(finiteness):算法必需在有限时间内做完,即算法必需能在执行有限个步骤之后终止。 (4)拥有足够的情报:要使算法有效必需为算法提供足够的情报当算法拥有足够的情报时,此算法才最有效的;而当提供的情报不够时,算法可能无效。 2 算法的基本要素 (1) 算法中对数据的运算和操作:每个算法实际上是按解题要求从环境能进行的所 有操作中选择合适的操作所组成的一组指令序列。计算机可以执行的基本操作是以指令的形式描述的。一个计算机系统能执行的所有指令的集合,称为该计算机系统的指令系统。计算机程序就是按解题要求从计算机指令系统中选择合适的指令所组成的指令序列在一般的计算机系统中,基本的运算和操作有以下 4 类: ①算术运算:主要包括加、减、乘、除等运算; ②逻辑运算:主要包括“与” 、“或”、“非”等运算; ③关系运算:主要包括“大于” 、“小于”、“等于”、“不等于”等运算; ④数据传输:主要包括赋值、输入、输出等操作。 (2) 算法的控制结构:一个算法的功能不仅仅取决于所选用的操作,而且还与各操 作之间的执行顺序有关。算法中各操作之间的执行顺序称为算法的控制结构。算法的控制结构给出了算法的基本框架,它不仅决定了算法中各操作的执行顺序,而且 也直接反映了算法的设计是否符合结构化原则。描述算法的工具通常有传统流程图、N-S 结构化流程图、算法描述语言等。一个算法一般都可以用顺序、选择、循环3 种基本控制结构组合而成。 (3) 算法设计的基本方法 计算机算法不同于人工处理的方法,下面是工程上常用的几种算法设计,在实际应用时,各种方法之间往往存在着一定的联系。 (1) 列举法 列举法是计算机算法中的一个基础算法。列举法的基本思想是,根据提出的问题,列举所有可能的情况,并用问题中给定的条件检验哪些是需要的,哪些是不需要的。 列举法的特点是算法比较简单。但当列举的可能情况较多时,执行列举算法的工作量将会很大。因此,在用列举法设计算法时,使方案优化,尽量减少运算工作量,是应该重点注意的。 (2) 归纳法 归纳法的基本思想是,通过列举少量的特殊情况,经过分析,最后找出一般的关系。从 本质上讲,归纳就是通过观察一些简单而特殊的情况,最后总结出一般性的结论。 (3) 递推递推是指从已知的初始条件出发,逐次推出所要求的各中间结果和最后结果。其中初始条件或是问题本身已经给定,或是通过对问题的分析与化简而确定。递推本质上也属于归纳法,工程上许多递推关系式实际上是通过对实际问题的分析与归纳而得到的,因此,递推 关系式往往是归纳的结果。对于数值型的递推算法必须要注意数值计算的稳定性问题。

相关主题
文本预览
相关文档 最新文档