贵烟线K162+300至K163+305段道路改造工
程
施
工
组
织
设
计
2014年9月
目录
第一章编制依据及说明 ................................................................................................................................. - 1 1.1编制范围 .............................................................................................................................................. -1 1.2编制依据 .............................................................................................................................................. -1 1.3编制原则 .............................................................................................................................................. -1第二章工程概况 ............................................................................................................................................. - 3 2.1工程简介 ................................................................................................................................................. -3 2.2自然条件 ................................................................................................................................................. -3 2.3路面结构设计 ......................................................................................................................................... -4 2.4技术标准 ................................................................................................................................................. -5 2.5主要工程量 ............................................................................................................................................. -5第三章主要组织设计 ..................................................................................................................................... - 7 3.1总体施工安排 ......................................................................................................................................... -7 3.2施工进度计划 ......................................................................................................................................... -7 3.3水电的配置 ............................................................................................................................................. -7 3.4施工人员组织 ......................................................................................................................................... -7第四章主要施工方案 ................................................................................................................................... - 12 4.1污水工程 ............................................................................................................................................... -12 4.2雨水工程 ............................................................................................................................................... -14 4.3电力、给水工程 ................................................................................................................................... -16
4.5道路照明工程 ....................................................................................................................................... -19 4.6绿化工程 ............................................................................................................................................... -19第五章道路路基工程 ................................................................................................................................... - 21
5.1准备工作 ............................................................................................................................................... -21 5.2路基放样 ............................................................................................................................................... -21 5.3路基处理 ............................................................................................................................................... -21 5.4附属结构施工 ....................................................................................................................................... -25 5.5排水工程 ............................................................................................................................................... -26第六章沥青混凝土面层 ............................................................................................................................... - 27
6.1路基质量检查 ....................................................................................................................................... -27 6.2水泥稳定碎石基层施工 ....................................................................................................................... -27 6.3级配碎石底基层施工 ........................................................................................................................... -27 6.4乳化沥青下封层施工 ........................................................................................................................... -27 6.5沥青混凝土面层施工 ........................................................................................................................... -28第七章冬季、雨季的施工安排 ................................................................................................................... - 32第八章确保工程质量措施 ........................................................................................................................... - 34 8.1.质量目标............................................................................................................................................. -34 8.2质量保证体系 ....................................................................................................................................... -34 8.3质量检查组织机构 ............................................................................................................................... -34 8.4质量监控体系 ....................................................................................................................................... -34 8.5质量保证措施 ....................................................................................................................................... -35第九章工期保证措施 ................................................................................................................................... - 37
9.2劳动管理保证措施 ............................................................................................................................... -37第十章安全生产保证措施 ........................................................................................................................... - 39 10.1建立安全管理体系 ............................................................................................................................. -39 10.2主要项目施工安全技术措施.............................................................................................................. -40第十一章文明施工管理措施 ....................................................................................................................... - 42 11.1文明施工.............................................................................................................................................. -42 11.2环保措施.............................................................................................................................................. -42 11.3消防、防盗措施.................................................................................................................................. -43
附表一施工总体计划表........................................................................................................................... -44附表二施工平面布置 (4)
第一章编制依据及说明
1.1 编制范围
本方案编制范围为贵州省六枝特区贵烟线K162+300至K163+305段道路改造工程设计图纸范围内:起点SP.K0+000=贵烟线K162+300处,终点EP.K1+090.806=贵烟线K163+305处,接六枝迎宾大道K0+000处。编制内容包括路基、路面、雨污水、电力工程以及交通设施、绿化工程。1.2 编制依据
⒈《沥青路面施工及验收规范》及《道路工程质量检验评定标准》;
⒉贵烟线K162+300至K163+305段道路改造工程招相关文件;
⒊贵州通远公路勘察设计咨询有限公司的设计施工图;
⒋中华人民共和国建设部颁发的《建设工程工程量清单计价规范》及现行有关的技术文件及相关规定;
⒌贵州省六盘水市建设行政主管部门的有关规定。
⒍我单位现场调查的相关资料;
⒎我单位现有的施工技术力量、机械设备和建设经验。
⒏本着“质量第一、安全第一、信誉第一”的原则。
1.3 编制原则
⒈严格遵守规定的技术文件及相关规定、计划工期条款要求,严格执行现行的施工技术规范检验评定标准。
⒉有效集中施工力量,按期完工、按期交付,使建设单位尽快发挥经济效益。
⒊结合本工程具体情况,积极采用先进的施工技术和施工工艺,达到
提高劳动效率,提高工程质量,加快施工进度,降低工程成本,提高经济效益的目的。
⒋科学合理安排施工计划,制订好冬季、雨季、高温季度、农忙季节施工技术措施,组织连续、均衡而紧凑的施工。做到布局合理,重点突击,全面展开,平行流水,立体交叉,加快施工进度。
⒌推行全面质量管理,执行ISO9002质量管理标准和程序。认真贯彻“质量第一”和“安全生产”的方针,按照相关要求,制定具体的保证质量和安全措施,确保工程顺利进行,严格现场管理,实行文明施工,创建安全标准工地。
⒍结合现场实际情况,因地制宜,精心规划布置施工现场,减少和节约临时用地,少占农田,不破坏植被,尽量利用原有和就近民房,减少临时工程,尽量利用当地资源,合理安排运输存贮作业,减少物资运输周转工作量。
第二章工程概况
2.1 工程简介
贵烟线K162+300至K163+305段道路改造工程项目位于贵州省六枝特区交通东路,是六枝的重要出口,具有明显的交通区位优势。随着六枝不断的发展和开发,该路段将成为该区集交通和物流为一体的重要线路。拟修建的贵烟线K162+300至K163+305段道路改造工程是城市次干道,道路为一幅路型式路面结构类型为沥青混凝土路面,道路宽度为21m。道路具体分幅情况为:21m=3m(人行道)+0.25m(右侧路缘带)+2×3.5m(行车道)+2×0.25m中心黄色双实线+2×3.5m(行车道)+0.25m(左侧路缘带)+ 3m (人行道)。
路基标准横断面图图1-1
行车道与人行道相互交界处及人行道外缘设置路缘石,人行道按间距5m种植树木,树坑大小为1m×1m正方形,道路两侧均设置雨、污、给水管线及照明管线、燃气管线预留。
2.2 自然条件
2.2.1 地形、地貌
本项目地处黔西高原向黔中丘原过度地带,地势北高南低,地形起伏不大,山脉走向受构造影响,山岭呈南北走向。地貌类型为溶蚀低中山峰丛、缓坡。沟槽地形地貌。
2.2.2 气候、水文
区内属北亚热带冬春半干燥,夏季湿润型气候,冬长而暖,夏短而凉。年平均气温14。5℃,最冷1月平均气温4.9℃,最热7月平均气温22℃,极端最高气温34.1℃,极端最低气温-5.5℃。年平均降水量1482.2mm,
集中于下半年。全年以东南风为主,年平均风速2.2ms。年平均相对湿度为82﹪。伏旱、倒春寒、绵雨、凝冻、冰雹等灾害性天气时有发生。
2.2.3 工程地质条件
⒈地层岩性
本项目展布地层为中生界三叠系和第四系沉积物。第四系残坡积层(Qel+dl):残坡积粘土偶夹碎石,呈不整合覆盖于各时代地层上。多分布于山间沟谷等地势低洼地带及缓坡处,结构松散。大部分地段厚度小于2m,局部地段厚约2~6m。关岭组第二段(T2g2):灰色薄至中厚层夹薄层灰岩、白云岩,泥质灰岩和泥灰岩,有蠕虫状构造。
⒉地质构造
区内属威宁北西向构造变形区,六枝向斜较紧密,北西走向,轴部地层为三迭法郎组。六枝以北受东西向构造的阻挡而发生方向偏转。本项目处于六枝向斜东翼,为关岭组地层。
2.3 路面结构设计
⒈机动车道路面结构:
4cm 厚AC-16中粒式沥青混凝土
粘层沥青
6cm 厚ATB-25热拌沥青碎石
BJG80×8玻璃纤维格栅
乳化沥青下封层
2×20cm厚水泥稳定碎石基层
18cm厚级配碎石底基层
结构层总厚度为68cm。
⒉人行道结构:
60cm×60cm×3cm芝麻白烧毛面花岗岩板
2cm M5水泥砂浆
10cm C15素混凝土
14cm碎石垫层
结构层总厚度为 29cm。
2.4 技术标准
⒈道路等级:城市次干道;
⒉设计速度:60Km;
⒋路面结构类型:沥青混凝土路面;机动车道:BZZ-100,非机动车道:BZZ-60
⒌路面计算荷载:双轮组单轴载100KN(标准轴载BZZ-100)。
主要技术指标表表2-1
2.5 主要工程量
主要工程概况一览表表2-2
第三章主要组织设计
3.1 总体施工安排
⑴路基工程:本项目为老路改造工程,在路基施工中应控制好与老路的搭接处理,管道的开挖和管线的埋设应及时施工,并做好排水处理;
⑵路面工程:开工前提前一个月备料,并确保备料数量达到总数量的70﹪以上;
⑶安全设施及附属工程:路面工程结束后进行安全设施及附属工程的施工。
3.2 施工进度计划
该项目工期为5个月,工期紧,且为老路改造项目,受交通影响大,
所以施工工作要连续、均衡、有计划、分步骤地进行,以达到保质保量按期完成任务的目标。
施工总体计划表见附表一。
3.3 水电的配置
⑴供水
施工生产用水全部利用附近村庄的自来水,水管从指定地点接入,并做好储水池贮水。铺设抽水管道以提供筑路工程用水。
⑵供电
根据实际施工需要安装变压器,以满足施工用电要求,并配备1台发电机组,以备停电使用。
3.4 施工人员组织
3.4.1 人员组织
在施工过程中,加强现场管理与协调指挥将是施工顺利完成的关键,为此,专门成立现场指挥保障体系。总指挥负责处理全面施工工作,副总指挥具体负责工作的全面落实,下设多个职能部门:生产管理部、工程技术部、安全质量部、测量监控部、物资机械部等,各部门在总指挥领导下协同工作,共同确保施工的顺利进行。
组织机构图图3-1
3.4.2 劳动力组织
劳动力计划安排表表3-1
施工队任务划分表表3-2
3.4.3 机械设备
主要施工设备,测量仪器配置及进场计划情况如下:
机械设备进场计划安排表表3-3
3.4.4 安全施设
安全设施主要工程数量表表3-4
第四章主要施工方案
4.1 污水工程
污水工程主要包括了污水管道、污水检查井的施工。污水管道沿道路两侧布置,每30m左右设置污水检查井,且每隔150~200m设置DN315污水预留管,以i=1﹪坡度流向污水干道,管材采用高密度聚氯乙烯双壁波纹管,橡胶圈接口。
管道用砂石基础,检查井用砖砌筑,井盖用超重型防盗复合材料。
4.1.1 污水管道施工
⒈开挖沟槽
沟槽开挖要严格控制基底高程,不得扰动基底原状土层。基底设计标高以上0.2-0.3m的原状土,在铺管前人工清理至设计标高。如遇局部超挖或发生扰动,不得回填泥土,可换填最大粒径10-15mm的天然级配砂石料或最大粒径小于40mm的碎石,并整平夯实。槽底如有坚硬物体必须清除,用砂石回填处理。
⒉基础
管道基础铺设的厚度不得小于设计规定,铺设管道时在接口部位的凹槽随铺随挖。凹槽长度L按管径大小采用,宜为0.4-0.6m,凹槽深度h宜为0.05-0.1m,凹槽宽度B宜为管外径的1.1倍。在接口完成后,凹槽随
即用砂回填密实。
⒊管道安装及连接
⑴管道安装采用人工安装。槽深不大时由人工抬管入槽,槽深大于3m 或管径大于公称直径DN300mm时,用非金属绳索溜管入槽,依次平稳地放在砂砾基础管位上。严禁用金属绳索勾住两端管口或将管材自槽边翻滚抛入槽中。混合槽或支撑槽,采用从槽的一端集中下管,在槽底将管材运送到位。
⑵调整管材长短时用手锯切割,保证断面垂直平整无损坏。
⒋管道与检查井连接
⑴管件或管材与砖砌的检查井接连,采用中介层作法。
⑵检查井底板基底砂石垫层,应与管道基础垫层平缓顺接。管道位于软土地基或低洼、地下水位高的地段时,检查井与管道的连接,宜先采用长0.5~0.8m的短管。
⒌管道密封性检验
⑴管道安装完毕且经检验合格后,进行管道的密闭性检验。采用闭水检验方法。
⑵管道密闭性检验在管底与基础腋角部位用砂回填密实后进行。必要时,可在被检验管段按规程回填到管顶以上一倍管径高度的条件下进行。
⑶闭水检验时,应向管道内充水并保持上游管顶以上2m水头的压力。外面检查,不得有漏水现象。管道24h的渗水量应不大于按下式计算的允许渗水量:
Q = 0.0046Di
式中Q:每公里管道24h的允许渗水量(m3)
Di:管道内径(mm)
4.1.2 污水检查井的施工
⒈砌筑
砌井前应先检查基础尺寸及高程,是否符合规定。
用水冲净基础后,先铺一层砂浆,再压砖砌筑,必须做到满铺满挤,砖与砖间灰缝保持1cm,拌和均匀,严禁水冲浆。支管和预埋管应按设计高程、位置、坡度随砌井即安好,管口与井内壁取齐,预埋管应在还土前用干砖堵抹面,不得漏水。
⒉抹面
抹面完成后,井顶应覆盖草袋,防止干裂。砌井抹面达到要求的强度后方可还土,严禁先还土后抹面。
检查井的做要法符合国标06MS01-3。
4.1.3 回填
⒈管道安装验收合格后应立即回填,应先回填到管顶以上一倍管径高度。
⒉沟槽回填采用人工从两侧同时对称回填回填,严禁用机械推土回填。
⒊管顶上0.5m 以下部分的沟槽回填材料,可采用中粗砂回填,管顶50cm以上采用6%灰土回填,与道路路基处理重叠部分按路基处理要求进行回填。回填土必须符合国标06MS201-2总说明5.6.2及5.6.3相关要求。
⒋回填土含水量应适中,不应含有树枝,大块碎石,冻土等,回填时沟槽须无积水,压实度为轻型击实度标准。。
4.1.4 管道密闭性检验
⒈管道安装完毕且经检验合格后,进行管道的密闭性检验。采用闭水检验方法。
⒉管道密闭性检验在管底与基础腋角部位用砂回填密实后进行。必要时,可在被检验管段按规程回填到管顶以上一倍管径高度(管道接口处外露)的条件下进行。
⒊闭水检验时,应向管道内充水并保持上游管顶以上2m水头的压力。外面检查,不得有漏水现象。管道24h的渗水量应不大于按下式计算的允许渗水量:
Q = 0.0046Di
式中Q→每1km管道长度24h的允许渗水量(m3)
Di→管道内径(mm)
4.2 雨水工程
雨水工程主要包括了雨水、雨水检查井等工程。雨水管沿道路右侧布置,材料用Ⅱ级钢筋混凝土管,每隔30m左右设置检查井和雨水口。检查井用砖砌,雨水管道用混凝土基础,井盖用超重型防盗复合材料。K0+330至K0+600段采用高密度聚氯乙烯双壁波纹管。管道基础采用砂石基础。
雨水管渠流量按公式:i=A×(C+lgP)(t+B)×D进行计算。
4.2.1 施工顺序
放样开挖沟槽砼基础管道安装围管座抹带接口砌筑检查井、回填。
雨水检查井砖砌部分:放样开挖沟槽砼基础砌筑砖墙、粉刷安装盖板→回填。雨水管的做要法符合国标06MS01。
4.2.2 管沟槽开挖
⑴管沟开挖前,必须弄清与施工相关的地下情况,根据图纸及有关资料的提供,可采用人工挖探坑的方法。所施工工程若与已建管道构筑物衔接,必须在挖管沟前对其平面位置和高程进行校对,必要时开挖核实;若施工段的地下情况与施工图及有关资料提供的情况不符合时应及时通知相
关单位予以处理。
⑵遇有地下管线时采用人工开挖,管沟挖深超过2m时应分层开挖,边坡不变。
⑶管沟开挖前,应向机械司机详细交底,交底内容包括挖槽断面、堆土位置、现有地下构筑物情况及施工技术、安全要求等。指定专人与司机配合,配合人员应熟悉机械挖土有关安全操作规程,及时量测槽底高程和宽度,防止超挖。
⑷管沟开挖时,先进行详细的测量定位并标示出开挖边线,复核无误后可指挥挖掘机入管沟开挖范围进行开挖,开挖出的土堆于沟槽两侧,堆土坡脚距槽边2.0m以外堆土高度不超过1.5m,堆土坡度不宜陡于自然休止角。
⑸设计槽底高程以上保留20cm左右的一层要用人工清底。
⑹雨季施工时,为防止管沟底土壤受雨水浸泡,预留人工整平的20cm 土层待下一工序进入前予以挖除。
⑺管沟底成形后,若沟底为淤泥层应先将淤泥清除,换成土或做碎石。
4.2.3 浇筑管道基础
⑴架设管道基础现浇模板,高度略高于平基高度。模板检验合格后及时浇筑砼,用插入式振动器振捣密实,基础终凝后进行养护。平基成型后应留毛面以便与管座结合。
⑵在已硬化的砼表面上继续灌注砼前,应作凿毛处理,除掉水泥薄膜和表面上松动石子或软弱砼层,并加以充分湿润和冲洗干净,并将残留在砼表面的积水清除,铺上和砼内砂浆成分相同的一层砂浆后再灌注。
4.2.4 浇筑管座
⑴管节安装完毕经检验中心线、高程合格后,立即支设模板(清除模
板中的尘渣、异物,核实模板尺寸)。
⑵管座浇筑前先将管座平基冲净。浇注时先从一侧灌注混凝土,当对侧的混凝土与灌注一侧砼高度相同时,两侧再同时浇筑,并保持两侧砼高度一致。
⑶浇筑砼时,留砼抗压强度试块,按每工作班组不少于一组,每组3块,按《砼结
4.2.5 管道安装
⑴沟槽地基、管基质量检验合格后安装管道,安装时宜自下游开始。
⑵管节安装前应将管内外清扫干净,进行外观检查。
⑶采用机械和人工配合下管,管节下入沟槽时,不得与槽壁及槽下的管道相互碰撞,沟内运管不得扰动天然地基。
⑷管节安装时应使管内底高程符合设计规定。逐节调整管节中心及高程,两侧设撑杠,不得发生滚动。
4.2.6 抹带
雨水工程采用水泥砂浆抹带,污水工程采用钢丝网水泥砂浆抹带。
4.2.7 雨水检查井施工
⑴井基础应与管线基础同时进行,符合设计要求、管子排好后方可开始砌井。
⑵砌筑时砖要平顺,砂浆要饱满,特别要注意管头下部及管于周围必须砌筑密实。检查井的流槽应在井壁砌到管顶以下即可砌筑,并用砂浆分层压实抹光。
⑶各部位尺寸均应符合要求,踏步应放平,上下口对正,砂浆密实砖要压紧。砖砌园形检查井,应随时检测直径尺寸。
⑷砌筑检查井的井室内壁应按设计进行抹面,内壁抹面应分层压实,