***110KV变电站

安装工程

施工组织设计纲要批准:

审核:

编制:

年月日

目录

1工程概况及特点 (1)

1.1工程概况 (1)

1.2工程设计特点及主要设备选型 (1)

2公司本部与现场组织机构图及相互关系 (3)

2.1组织机构的设立 (3)

2.2公司本部与现场组织机构图及相互关系图 (3)

2.3各机构主要负责人职责 (4)

2.4工程主要负责人简介 (7)

3施工现场总平面布置图 (7)

3.1施工现场总平面布置原则 (7)

3.2施工总平面布置图:见附图。 (8)

3.3现场平面布置图说明 (8)

4施工方案 (9)

4.1施工准备 (9)

4.2施工工序总体安排 (14)

4.3工程成本的控制措施 (27)

5工期及施工进度计划 (28)

5.1工期规划及要求 (28)

5.2 施工进度计划横道图 (28)

5.3针对关键路线为确保工期所采取的措施 (29)

5.4进度计划风险预测 (30)

5.5主要安装设备及材料供应计划 (32)

6质量目标、质量合格证体系及技术组织措施.... 错误!未定义书签。

6.1质量目标....................................................................................... 错误!未定义书签。

6.2质量管理组织机构及主要职责................................ 错误!未定义书签。

6.3质量管理措施 .......................................................................... 错误!未定义书签。

6.4质量管理及检验标准 ........................................................ 错误!未定义书签。

6.5质量保证技术措施 .............................................................. 错误!未定义书签。7安全目标、安全保证体系及技术组织措施.......... 错误!未定义书签。

7.1安全管理目标 .......................................................................... 错误!未定义书签。

7.2安全管理组织机构及主要职责................................ 错误!未定义书签。

7.3安全管理制度及办法 ........................................................ 错误!未定义书签。

7.4安全组织技术措施 .............................................................. 错误!未定义书签。8环境保护与文明施工 ................................................................ 错误!未定义书签。

8.1文明施工的目标、组织机构和实施方案........ 错误!未定义书签。

8.2加强施工管理、严格保护环境................................ 错误!未定义书签。

8.3文明施工考核、管理办法 ............................................ 错误!未定义书签。

8.4工程卫生技术措施 .............................................................. 错误!未定义书签。9计划、统计报表的编制与传递........................................ 错误!未定义书签。

9.1计划、统计报表的编制与传递................................ 错误!未定义书签。

9.2信息管理....................................................................................... 错误!未定义书签。

1工程概况及特点

1.1工程概况

***110KV变电站为新建变电站一座,围墙内占地面积4.18亩,建筑总平面积2475平方米。安装5万千伏安主变2台,电压等级110/10,110KV GIS共9个间隔,10KV 开关柜26面,电容器4800千乏2组,接地转角变1000千伏安2台,消弧线圈900千乏2台,变电站按无人值班站设计,采用计算机监控系统。其中主变压器:最终3×5三相双绕组自冷有载调压变压器,电压等级为110/10千伏,本期2×5万千伏安。110千伏出线:规模2回,本期2回。10千伏出线:规模36回,本期13回。无功补偿:规模6组4800千乏,本期2组。

1.2工程设计特点及主要设备选型

1.2.1电气一次部分

电气主接线:110千伏采用户内GIS设备,采用扩大内桥接线,共间隔9个分别为出线2回、主变进线间隔3回、母线PT间隔2回、桥间隔2回,110kV避雷器装于GIS设备内,共2组。GIS设备本期一次建成。

10千伏采用单母三分段接线,本期为单母两分段接线,建设2个主变进线间隔(4面柜),13个出线间隔,2个分段间隔(3面柜),2个PT及避雷器间隔,2并联电容器出线间隔,2个消弧线圈出线间隔。

1.2.2电气二次部分

1.2.2.1本站为无人值班变电站,采用计算机监控系统。主变压器和110千伏二次设备集中组屏,10千伏二次设备就地分散布置。

1.2.2.2配置主机兼操作员工作站1套。配置公用测控柜1面。

1.2.2.3全站配置GPS时钟装置1套,实现站控层、间隔层及保护装置的时钟同步,与监控系统统一组屏。

1.2.2.4远动通信设备单配置,设置远动通信柜1面,采用网络传输方式上传地调和。本站按地区电力调度数据网接入点考虑,配置调度数据网络柜1面。

1.2.2.5继电保护室配置:主变保护的配置采用主后一体化双套保护、非电量保护一套,操作箱一套,满足山西电网变压器保护配置及整定原则的要求,每台主变保护设置主变保护柜1面,共两面。110千伏线路保护柜1面,含线路光纤差动保护装置1套。110KV桥保护柜一面,含桥保护装置2套,备自投1套。110千伏配置线路测控柜1面,含线路测控装置2套、操作箱1套。110千伏桥测控柜1面,含桥测控装置2套、PT并列1套。主变测控柜两面,每面含测控装置2套,调压测控、温度变送器等。10千伏配置线路、电容器和接地变测控保护装置17套,电压并列装置1套,电度表17块,均就地安装在开关柜上。10千伏分段配置保护测控及备自投装置1套。配置故障录波柜1面。配置低频低压减载柜1面。主变及110KV配置计量柜1面。全站配置UPS系统1套,容量是3千伏安。配置微机智能控制高频开关电源1套,阀控式铅酸蓄电池1组,蓄电池容量150安时,组屏4面;交流屏1面。视频监控一套,安防系统一套,火灾报警系统一套。

1.2.3主要设备选择

1.2.3.1.主变压器

1台:主变选用SZ10-50000/110三相双绕组自冷有载调压变压器,容量比100/100,电压比为110±8×1.25%/10.5千伏,接线组别YNd11。

1台:主变选用SZ9-50000/110三相双绕组自冷有载调压变压器,容量比100/100,电压比为110±8×1.25%/10.5千伏,接线组别YNd11。1.2.3.2.110千伏设备

110千伏配电装置选用三相共箱、母线共箱GIS设备。母线额定电流2000安;断路器额定电流2000安,开断电流40千安,计4台;隔离开关额定电流2000A;电流互感器变比采用600~1200/5安,进出线全部采用电缆方式。

1.2.3.3.10千伏设备

1.10千伏开关柜选用KYN28A-12型屋内真空开关柜共26面,主变4面、分段3面、出线13面、PT及避雷器2面、电容器出线2面、消弧线圈出线2面,主变进真空断路器,弹簧一体化机构。

2.10千伏母线选择2×TMY-125×10。

3.10千伏主变至10千伏穿墙套管装设绝缘热缩包封,开关柜内母线采用可靠的绝缘材料包封。

1.2.3.4电容补偿设备及站用变、消弧线圈补偿设备

1.电容器选用框架式分散型电容器,装设在室内,本期配置2组容量为4800千乏。

2.站用变选用接地转角变2台,容量1000千伏,其中用于站用变容量100千伏;消弧线圈2台,容量900千乏。

1.4主要工程承包范围及工作内容

1.4.1全部招标项目中的安装、调试、维护、验收、移交、配合整套系统调试和参加联合试运行。

1.4.2自购设备、材料的采购、运输及保管。

1.4.3招标方提供的设备、材料自交接地点至施工现场的运输和保管。参加设备建造。1.4.4站区照明(含电缆)、接地(不含设备接地)计入建筑招标工程量。1.4.5火灾报警系统、视频系统设备、调度数据网设备安装费用不包含在本次范围内。

2公司本部与现场组织机构图及相互关系

2.1组织机构的设立

1.公司在本工程实行项目经理责任制,成立“***110kV变电站工程项目部”。

2.公司任命的项目经理在开工前书面呈报项目法人以及监理工程师,在批准后根据公司法人代表授权的范围、时间和内容,对工程施工项目自开工准备至竣工验收,实施全过程、全面管理。

3.项目部将从公司挑选业务能力强、管理经验丰富的人员来担任个层次管理人员。

4.项目部下设工程部、计划经营部、办公室、质检部、安监部和材料部6个职能部门,负责各自部门归口的管理工作。

2.2公司本部与现场组织机构图及相互关系图

下图为公司本部与***110KV变电站电气安装工程项目组织机构图以及它们之间的相互关系。

施工现场组织机构关系图

错误!

2.3各机构主要负责人职责

2.3.1项目经理

——贯彻执行相关的法律、法规及规章制度。

——参与签订施工合同、安全合同。

——做为本工程的安全、质量及文明施工的第一责任人,负责组建本工程的整合型管理体系(质量、安全职业健康、环境保护),制定各种规章制度并组织实施,使本工程达到优质工程标准,签订和履行《项目管理目标责任书》,进行目标控制,确保目标实现。

——主持组建项目部,编制项目实施计划和方案。

——选择分包商和供应商,报企业主管部门审核确认。

——对生产要素优化配置、科学管理,积极推广新工艺、新材料。

——做好与建设单位、监理单位、设计部门的各项协调工作。

——严格财经制度,加强成本管理,搞好经济核算,正确处理国家、企业、分

包单位、职工之间的利益分配关系。

——强化现场文明施工,及时发现和处理例外性事件。

——工程竣工后及时组织结算、验收和分析总结。

2.3.2项目副经理

——协助项目经理搞好各项工作。

——工作需要时,代理项目经理行使工程管理权。

2.3.3项目总工

——全面负责工程的技术管理工作,对施工质量、安全在技术上全面负责。

——主持制定项目的技术管理工作计划。

——组织有关人员熟悉与审查图纸,编制施工项目管理实施规划并组织实施。

——组织做好测量工作及核定,指导质量检验和试验工作。

——审定技术措施计划并组织实施,进行技术交底工作。

——负责组织开工前期的技术培训和考核,指导施工技术、质量、安全各部门的工作,解决施工中发生的重要技术问题。

——对工程安全、质量和工艺质量,针对工程施工中的质量、安全薄弱环节,组织制定相应的预防措施。

——负责组织工程档案中各项技术资料的签证、收集、整理。

2.3.4各部门主要职责

1.工程部

a.负责施工组织设计、专项方案和技术交底卡的编制,构配件加订货和现场施工技术问题的处理,负责发放施工图纸,设计变更和有关技术文件,负责作为隐蔽工程的验收记录和各项工程技术资料的收集整理工作。

b.负责工程施工中发生的技术问题。

c.负责施工文件资料的管理工作,确保本工程使用文件资料的有效版本。

2.计划经营部

a负责定额核算,计划统计和预决算的编制工作,负责施工现场平面管理、施工调度及内外协调,负责施工测量、放线、负责机械设备管理和安全管理工作。

3.质检部

a.负责工程质量检查、监督、进行分部分项工程的自检评定,开展全面质量管理

和QC小组活动。

b.负责作为经常性的安全生产宣传工作,贯彻“安全第一、预防为主”的方针,组织日常的安全生产检查、监督工作,帮助班组消除隐患,促进安全生产。

c.计量器具的配置和周期检查。

d.严格执行公司《质量三级监、检制度》,负责编制并实施工程质量计划、检验计划,工程施工全过程进行质量监督检查和评价工作;负责对原材料进行分析评价及检验;对隐蔽工程、特殊工艺的质量情况严格监督执行;负责工程质量记录的收集、整理工作。做好质量报表工作,并配合项目法人、质检站、监理工程师及运检单位进行分阶段中间验收,负责竣工资料的整理移交工作。

4.安监部

a.负责本工程的日常安全管理工作,组织开展安全健康与环境保护的宣传教育工作,监督检查本工程施工现场的安全文明施工状况和职工的作业行为,有权制止和处罚违章作业和违章指挥行为。

b.参加开工前的安全技术交底工作,在施工过程中负责执行项目部制定的《安全奖罚条例》,并确保各项管理制度在本工程中得到有效的落实。

c.负责制作安全报表,向项目法人和与管部门报送。

d.负责安全制度和规定的落实执行,现场巡查发现并纠正不安全现象,审核保证安全施工安全措施。

e.负责检查现场所用工器具是否能保证人员、设备安全,检查现场布置是否符合技术方案的规定和要求。

f.对施工现场和安全卫生责任区内的文明施工、环境保护、环境卫生、成品保护措施及生活卫生的管理进行监督检查。

g.负责经常性的内部安全检查,定期和不定期的组织内部安全大检查工作,参加项目法人/项目管理单位组织的安全检查工作,对发现的问题必须在期限内完成整改。

h.负责应急预控措施和针对重大危险因素的应急预案在施工中的实施。

5.材料部

a.负责编制材料供应计划,根据施工进度分析组织材料供应,负责材料的发放和物质保管,进行原材料的检验、化验、抽查、提供有关材料的技术文件。

b.负责组织进场设备、材料的运输、检验,储存及出入库管理工作。

6.办公室

a.负责政治宣传、职工教育、生活后勤、安全保卫、环境卫生、文明卫生及接待

工作。

b.负责项目部人员的安全职业健康工作。

c.负责工程信息的对外发布工作。

2.4工程主要负责人简介

项目经理简历表表

2-2

3施工现场总平面布置图

3.1施工现场总平面布置原则

1.施工总平面布置是根据厂区总平面布置、工艺设计、工程量、厂址、地区交

通条件、材料供应来源、施工力量等因素进行综合考虑的。

2.合理组织交通运输,使施工的各个阶段能做到道路畅通、运输方便,材料堆放

场地安排合理,避免反向运输和二次搬运。

3.按施工只能分区规划,减少施工交叉作业,本变电所内电气布置很紧凑,场内可用的临时设施用地较少,施工布置时应充分利用现有空地,以不占或少占永久设施用地为原则;

4.充分利用地形和区域条件,合理布局,既要有利于生产、易于管理,又要便于生活,并符合国家有关安全、防火、卫生、环境保护等规定,直接为生产服务的设施尽量靠近施工现场,而生活和仓库等设施靠后布置。

5.按合同规定做好安全和环境保护规划,采取必要的措施,保护临时设施周围开

挖后的边坡。

3.2施工总平面布置图:见附图。

3.3现场平面布置图说明

3.3.1场地规划

本工程主要设设备材料仓库、临建设施布置采用隔离布置。临时办公区及生活区集中设置于站外空地,按标准化配置,设置项目部的办公区、生活区、施工生活区等。几个区域有联系地进行设置和管理。

1.施工电源

从项目法人提供地施工电源――站变压器处设总电源配电箱,再由铜芯电缆采用直埋电缆敷设方式(埋设深度不小于0.7米)引至各施工用电区的电源箱内,并在地面设置明显标示。各电源箱的安装必须满足施工要求和施工用电要求。

2.施工水源

本工程施工用水由工程建设单位提供引入水源,采用主供水管道Ф100mm的主管引入,Ф32mm的支管引至各用水点,临时用水用橡胶管进行接续。

3.施工照明

本工程现场采用集中广式照明,局部照明采用移动立竿式金属灯架(禁止使用简易碘钨灯)。

4.消防设施

按工程规定配置灭火器、沙箱及消防桶等消防器材。

5.临时建筑

包括办公区、设备材料库、混凝土搅拌站、钢筋加工场、水泥场、木工棚、沙石堆放场、

6.项目部办公区

项目部工作人员进行施工安排、技术交底、材料供应联系、会议、接待等的工作场所。办公室、会议室配备必要地办公用品。

7.设备材料库

a.设备及材料库各设一座,用于材料及工器具的存放和部分原材料的加工。

b.设备材料(断路器、隔离开关、导线、瓷瓶、电缆、导地线等)可在设备临时存放位置进行放置。设备材料堆场码放整齐成型,安全可靠;大件排放呈现规则形状,

整齐有序。调试用仪器仪表存放在工具库,注意防潮及鼠害。项目部将于项目法人和监理工程师密切配合。控制设备材料的进场时间,避免因设备材料堆放场地过大而影响正常的施工。

c.系统投运前所内所有临建设施均应拆除并将场地清理干净。

8.临时厕所

临时厕所采用管道与临时化粪池相连

9.垃圾场

站内设临时垃圾点2处,定时清理。施工中出现的建筑安装垃圾,临时堆放在建筑垃圾收集站。项目部应与当时环卫部门密切配合及时外运。

4施工方案

4.1施工准备

4.1.1技术资料的准备

1.根据质量、安全、进度、成本管理目标,结合项目管理、工程特点、采用的施工方法及现场调查情况,由公司总工程师组织相关部门,依据公司体系程序文件要求,进行工程策划,由项目经理和项目总工组织技术人员依据策划记录及设计、现场情况等资料,准备本工程的技术资料并及时提交监理工程师进行审批。

施工技术资料的编制计划,见表三

表三施工技术资料的编制计划

2.本工程可使用公司在多次工程施工实践中已成熟的如下作业指导书来指导施工:

1)一次设备安装作业指导书

2)二次设备安装作业指导书

3)变压器安装指导书

4)二次接线作业指导书

5)车辆装卸运输作业指导书

3、配备本工程所要求的现行有效规范、规程及有关技术资料。

4、施工用钢材、防水材料应向监理单位即使报送,并在工程开工前将出厂合格证及复检报告。

4.1.2 施工图纸的管理

1.依照文件资料管理制度,严格作好施工图纸的管理和控制工作,确保使用有效的设计图纸。

2.认真参与甲方组织的施工图纸会审工作,争取尽早纠正图纸问题。

3.在施工中若发现施工图纸有问题,应及时向设计单位或甲方反映,如果要求对

设计提出修改,须按管理制度办理签证手续,不得随意修改。

4.工程设计变更或工程联络单,应及时反馈到施工部门,并由施工部门办理接发手续,依照更改内容由技术人员在相应的图纸和资料上修改,签字并注明日期。

5.及时作好施工图纸的整理、归类工作,以便移交。

4.1.3 文件资料的管理

1、文件资料(包括施工合同,质量体系文件,技术、安全等有效文件)是质量体系运行和保证工程质量、安全的依据,各部门在开工前要对现有的文件资料进行全面的整理工作,确保在施工过程中使用有效的版本。

2、施工技术资料由工程科各专业专工编制,科长审批,主管经理批准。

3、施工技术档案的主要内容有:

1)施工图会审记录

2)主要原材料、构件、设备的出厂资料

3)设计变更、材料设备代用记录

4)施工检查及评级表

5)隐蔽工程与中间检查验收签证

6)竣工图纸

7)重大质量事故和重大设备缺陷情况

8)有关工程建设和为运行单位生产所需的有关协议、文件和

会议记录

9)施工检查及评级记录过程中的原始记录要作到完整、规范、清晰。

4、设备附带的厂方资料不仅对工程施工具有指导性作用,而且在设备试验和后续的维护工作中也有其重要价值。因此,施工单位一定要做好厂方资料的收集、整理、归类、排序工作。

4.1.4 施工力量配置

1、施工力量配置

1)技术力量配置

任用有丰富施工经验的施工管理人员和技术人员。所有人员在项目经理和总工的领导下,既分工明确,又密切合作。

电气安装工程:工程师 2人,助理工程师2人,技术员2人,技师2人。

2)施工人员配置

3)施工力量部署

为确保工期,合理有效地利用人力资源,将施工人员作如下划分:

a.起重队:设备的运输、吊装、就位;

b.安装队:全站电气一次设备安装、调试;

c.二次队:全站电气二次设备安装、接线、电缆敷设;

d.高压班:全站电气一次设备试验;

e.保护班:继电保护及监控系统的调试;

气体化验、导线拉力实验等。

f.综合班:全站仪表校验及绝缘油、SF

6

4.1.5施工工器具和生活设施准备

1.开工前,由施工队负责人结合工程量,列出施工机械配置清单,现有配置若不能满足要求,可向主管经理申请,报总经理申批,由公司配置。保证供给充足合格的资源,以满足工程需要。

2.加强主要施工机械操作人员的培训管理工作,持证上岗。

3.机具使用前,由机具管理人员负责组织全面检查,不合格的机具不准使用。

4.机具在使用过程中,按规定进行维护、保养,并作好记录。

5.操作人员必须严格执行操作规程。

6.公司应为施工队配备煤气灶、电暖气等现代化生活用具,以适应气候影响,保证职工健康生活,安全施工。

4.1.6 施工机械配置

主要施工机械设备表(表一)

4.2施工工序总体安排

为确保工期及质量、安全目标的实现,对各施工工序进行如下总体安排:

1.此次***110KV变电站工程大致分为主变压器装置区、110kVGIS配电装置区、10kV配电装置区及继电保护区等两大区域。

2.根据施工工艺及安全的要求,变电工程一般按从高到低,由里向外的原则进行。调试人员应提前进场,在配合电气安装过程中,尽快熟悉设备,确保调试工程能顺利进行。

3.项目经理应定期召开生产会协调各项工程中各专业的交叉施工,统筹兼顾,密切配合,使施工生产达到事半功倍的效果。

4.施工程序与各资源配置相互协调,以促进均衡施工。

4.2.1重要工序的施工方法

4.2.1.1施工工序项目划分

4.2.1.2重要工序施工方法

1.主变压器安装

1)变压器安装流程

施工准备----主变基层验收交接——附件检查及准备-----绝缘及密封检查-----套管及冷却器安装----抽真空----真空注油----其它附件安装-----二次注油-----热油循环----整体密封试验

2)施工准备

a.由技术员编制施工作业指导书,组织施工人员认真学习并交底。

b.施工前清除施工用场地与安装无关的杂物,合理布置施工电源,合理规划好施工场地。

c.施工用机械及工具的配置

起重机械25吨汽车吊1辆,真空滤油机1台,20t储油管2个,倒链,电动扳手,电焊机,专用取油样瓶,枕木及所用的消耗材料等。

d.劳动力组织

项目部经理及总工,施工班长1名,专业技术员1名,电焊工1名,专业起重工2名,变压器安装人员7名,调试人员两名。

正式施工前要与当地气象部门联系,了解掌握近期的天气情况。确定吊芯检查的准确日期,并通知业主、监理及厂方代表。

对所使用的真空滤油机的各个阀门及电气部分进行彻底的检修和清理。用白布、面团、清理干净储油罐内部杂物。

3)变压器密封检查

检查变压器本身所带的充氮装置上氮气压力表指示的情况,氮气压力应保持在0.01Mpa~0.03Mpa范围内。充油变压器是否渗油,并做好记录。

4)变压器油处理

a.利用滤油机将运至现场的变压器油注入储油罐中,主要是先对新油进行一次粗过滤,滤出油中的杂质。

b.利用真空滤油机进行油净化、干燥处理。

c.滤油前,先取原油样进行耐压试验,并作详细记录;在滤油过程中,间隔24小时从油罐中取油样进行电气强度试验,当三次耐压平均值满足规程要求后,再取油样进行微水介损和色谱的简化分析,合格后封闭油罐。

5)附件检查

a.套管检查:用25t汽吊将高压套管竖立,固定在专用的支架上,外观检查套管瓷件有无损伤,油位是否正常,是否有渗油现象。若无问题进行电气试验。

b.冷却器密封检查:在冷却器内通入0.25MPa(或按制造规定的值)压力的变压器油,持续30分钟,仔细观察有无渗漏现象。若有渗油现象,消除渗漏油后,用合格的变压器油循环冲洗。同时检查潜油泵尾部的观察窗是否完好;风扇转动是否完好;流速继电器的叶片是否完好,动作是否灵活。

c.按照图纸、使用说明书的要求,检查清点所有的螺栓和密封垫的规格和数量,检查其它附件是否齐全完好。

d.胶囊的检查:缓慢向胶囊内充入0.02Mpa压力的干燥空气或高纯氮,检查是否漏气。

e.气体继电器、温度计、测温电阻按规程进行校验,合格后方可安装。

6)套管、冷却器安装

a.套管的安装

首先打开高压套管安装孔和手孔的盖板,用丙酮擦净法兰表面,然后再依次安装绝缘筒、升高座与套管。

在安装绝缘筒时,要注意使缺口方向与引出线方向一致,以保证引线对绝缘筒的距离符合要求。

升高座安装时,放气塞要位于升高座最高处,电流互感器的各铭牌面向油箱外侧。

套管吊装前,先将顶部的接线端子和下部的均压球拆下,擦净污垢,用变压器油冲洗干净后重新拧紧,并在套管内穿入一根ф10mm的尼龙绳做为牵拉引线电缆用。

b.冷却器装置安装

冷却器安装时,先将蝶阀关闭,然后拆除联接法兰临时堵板,并将联结法兰擦洗干净,再装上冷却器。冷却器装上后,松开底部螺丝放尽残油,然后才可打开下部阀

门,给冷却器充油。

7)变压器真空处理

当器身检查完毕,高压套管和冷却器安装好后,连接好专用真空泵与变压器之间抽真空管路,打开冷却器阀门,对变压器进行真空处理,抽真空时,真空度不大于133.3Pa,真空保持时间24h,并且在抽真空的过程中,要监视并记录油箱是否变形。

8)真空注油

连接滤油机、储油罐、变压器之间的油管路,当变压器抽真空处理24h后,关闭真空管线上的阀门,打开油管路上各阀门,启动给油泵、排油泵,投加热器电源,开始向变压器真空注油,当油箱油位淹没铁芯后即可。

9)附件安装

a.储油柜安装

清洗储油柜内部,除去杂物,并用合格的变压器油冲洗,再将胶囊安装在储油柜内,胶囊安装完后,保证胶囊口的密封良好,呼吸畅通。

吊装储油柜就位,联结好其至变压器之间的油管道。

b.气体继电器安装

气体继电器安装时,先装好两侧的联管,但各联结面的螺栓不要拧紧,然后在装继电器,继电器安装要水平,其顶盖上标志的箭头要指向储油柜,连接管的结合处密封要良好。

c.压力释放装置的安装

先将阀盖和升高座内部清理干净,然后再进行安装,安装后方向要正确,使喷油口不要朝向邻近的设备且密封良好。

d.温度计安装

温度计安装前校验合格,信号按点动作正常,导通良好,顶盖上的温度计座内要注变压器油,密封要良好。

10)热油循环

连接好滤油机与变压器之间的油管路,启动滤油机,并将油温控制器调整到60℃,接通加热器电源,开始热油循环,热油循环时间不得少于48h。热油循环过程中,每间隔12小时启动一次潜油泵,使散热器内的变压器油与本体内的油充分混合,使循环后的变压器油的符合规范要求。

11)二次注油

(完整版)110KV变电站及其配电系统设计_毕业设计

河南机电职业学院毕业论文(实习报告) 题目:110KV变电站及其配电系统设计 所属系部:电子工程系 专业班级:输变电工程12-1 学生姓名:刘康 指导教师:梁家裴 2015年6月6日

毕业论文(实习报告)任务书

指导教师签字:教研室主任签字: 年月日 毕业论文(实习报告)评审表

摘要

本文主要进行110KV变电站设计。首先根据任务书上所给系统及线路和所有负荷的参数,通过对所建变电站及出线的考虑和对负荷资料分析,满足安全性、经济性及可靠性的要求确定了110KV、35KV、10KV侧主接线的形式,然后又通过负荷计算及供电范围确定了主变压器台数、容量、及型号,从而得出各元件的参数,进行等值网络化简,然后选择短路点进行短路计算,根据短路电流计算结果及最大持续工作电流,选择并校验电气设备,包括母线、断路器、隔离开关、电压互感器、电流互感器等,并确定配电装置。根据负荷及短路计算为线路、变压器、母线配置继电保护并进行整定计算。本文同时对防雷接地及补偿装置进行了简单的分析,最后进行了电气主接线图及110KV配电装置间隔断面图的绘制 关键词:变电站设计,变压器,电气主接线,设备选择

目录 摘要 ..................................................................................................................... I I 1 变电站的介绍. (1) 1.1 变电站的作用 (1) 1.2 我国变电站及其设计的发展趋势 (2) 1.3 变电站设计的主要原则和分类 (4) 2 电气主接线设计 (4) 2.1 电气主接线设计概述 (5) 2.2 电气主接线的基本形式 (7) 2.3 电气主接线选择 (7) 3 变电站主变压器选择 (10) 3.1 主变压器的选择 (10) 3.2 主变压器选择结果 (11) 4 短路电流计算 (13) 4.1 短路的危害 (13) 4.2 短路电流计算的目的 (13) 4.3 短路电流计算方法 (13) 5 继电保护的配置 (14) 5.1 继电保护的基本知识 (14) 5.2 110kv线路的继电保护配置 (14) 5.3 变压器的继电保护 (14) 5.4 母线保护 (15) 5.5 备自投和自动重合闸的设置 (16)

110kV变电站电气一次部分课程设计

课程设计任务书 设计题目: 110kV变电站电气 一次部分设计 前言 变电站(Substation)改变电压的场所。是把一些设备组装起来,用以切断或接通、改变或者调整电压。在电力系统中,变电站是输电和配电的集结点。主要作用是进行高底压的变换,一些变电站是将发电站发出的电升压,这样一方面便于远距离输电,第二是为了降低输电时电线上的损耗;还有一些变电站是将高压电降压,经过降压后的电才可接入用户。对于不同的情况,升压和降压的幅度是不同的,所以变电站是很多的,比入说远距离输电时,电压为11千伏,甚至更高,近距离时为1000伏吧,这个电压经

变压器后,变为220伏的生活用电,或变为380伏的工业用电。 随着我国电力工业化的持续迅速发展,对变电站的建设将会提出更高的要求。本文通过对110KV变电站一次系统的设计,其中针对主接线形式选择,母线截面的选择,电缆线路的选择,主变压器型号和台数的确定,保护装置及保护设备的选择方法进行了详细的介绍。其中,电气设备的选择包括断路器、隔离开关、互感器的选择和方法与计算,保护装置包括避雷器和避雷针的选择。其中分析短路电流的计算方法和原因,是为了保证供电的可靠性。 目录 第1章原始资料及其分析 (4) 1原始资料 (4) 2原始资料分析 (6) 第2章负荷分析 (6) 第3章变压器的选择 (8) 第4章电气主接线 (11) 第5章短路电流的计算 (14) 1短路电流计算的目的和条件 (14) 2短路电流的计算步骤和计算结果 (15) 第6章配电装置及电气设备的配置与选择 (18) 1 导体和电气设备选择的一般条件 (18) 2 设备的选择 (19) 结束语 (25)

110kV变电站设计开题报告

110kv变电站110kv线路保护及主系统设计 1课题来源 本课题为某110kv中心变电站110kv线路保护记主系统设计课题。该变电站是最末一个梯级电站,装机容量600万千瓦,年发电量301亿千瓦时,用地总面积为8070.1374公顷。向家坝水电站110kV中心变电站为向家坝水电站提供施工供电电源和电站建成以后作为厂用电备用电源的一座变电站。设计容量为3 50MVA,电压等级为110/35/10kV, 110kV进出线有5条,中压35kV侧有10 回出线,低压10kV侧有20 回出线. 2 设计的目的和意义 110kV变电所是电力配送的重要环节,也是电网建设的关键环节。变电所设计质量的好坏,直接关系到电力系统的安全、稳定、灵活和经济运行。它是联系发电厂和用户的中间环节,起着变换和分配电能的作用。电气主接线是发电厂变电所主要环节,电气主接线连接直接影响运行的可靠性、灵活性。它的拟定直接关系着全厂电气设备的选择、配电装置的布置、继电保护、自动装置和控制方式的确定。 随着变电所综合自动化技术的不断发展与进步,变电站综合自动化系统取代或更新传统的变电所二次系统,继而实现“无人值班”变电所已成为电力系统新的发展方向和趋势。 3 国内外的现状和发展趋势 目前,我国小城市和西部地区经济的不断发展对电能资源的要求也越来越高,西部主要是高原地带,在高海拔的条件下,农村现有的变电技术远达不到经济的快速发展,这也在一定程度上影响了西部地区和中小城市变电技术的推广和应用技术的深化。因此,一方面需要创造条件有针对性地提高对小城市以及农村的变电站的建设,加强专业知识的培训来提高变电技术;另一方面,可以通过媒介积极开展技术交流,通过实践去体验、探索。 当今世界各方面因素正冲击着全球电力工业,在国外变电所技术有十分剧烈的竞争,而世界范围内的变电所都采用了新技术; 其次,不同的环境要求给所有的电力供应商增加了额外的责任,使电力自动化设备尤其是高压大功率变电站的市场开发空间大大拓展。另外高压变电所的最终用户对变电站的自动控制、节能、

110kV变电站电气部分设计

毕业设计(论文、作业)毕业设计(论文、作业)题目: 110kV变电站电气部分设计 分校(站、点): 年级、专业: 09秋机械 教育层次:本科 学生姓名: 学号: 指导教师: 完成日期: 2012年5月5日

中文摘要 变电站作为电力系统中的重要组成部分,直接影响整个电力系统的安全与经济运行。本论文中待设计的变电站是一座降压变电站,在系统中起着汇聚和分配电能的作用,担负着向该地区工厂、农村供电的重要任务。该变电站的建成,不仅增强了当地电网的网络结构,而且为当地的工农业生产提供了足够的电能,从而达到使本地区电网安全、可靠、经济地运行的目的。 本论文《110kv变电站一次部分电气设计》,首先通过对原始资料的分析及根据变电站的总负荷选择主变压器,同时根据主接线的经济可靠、运行灵活的要求,选择了两种待选主接线方案进行了技术比较,淘汰较差的方案,确定了变电站电气主接线方案。 其次进行短路电流计算,从三相短路计算中得到当短路发生在各电压等级的母线时,其短路稳态电流和冲击电流的值。再根据计算结果及各电压等级的额定电压和最大持续工作电流进行主要电气设备选择及校验(包括断路器、隔离开关、电流互感器、电压互感器等)。 最后,并绘制了电气主接线图、电气总平面布置图、防雷保护配置图等相关设计图纸。 关键词电气主接线设计;短路电流计算;电气设备选择;设计图纸 Abstract Power system substation as an important part of the entire power system directly affects the safety and economic operation. To be designed in this paper is a step-down substation substation in the system plays the role of aggregation and distribution of electric energy, charged with the factory to the region, the important task of rural electrification. The completion of the substation will not only strengthen the local power grid network structure, but also for the local industrial and agricultural production provides enough power, so that the regional power grid so as to achieve safe, reliable and economic operation purposes. The paper "110kv substation once part of the electrical design," the first original data through the analysis and selection based on total load of the substation main transformer, the main wiring under both economical and reliable, flexible operation requirements, select the main connection of two programs to be selected A technical comparison, out of poor program to determine the main electrical substation connection program. Second, the short-circuit current calculation, obtained from the three-phase short circuit calculation occurs when short-circuit the voltage level of the bus, its steady-state current and the impact of short-circuit current value. According to the results and the voltage level of voltage and maximum continuous operating current of the main electrical equipment selection and validation (including circuit breaker, disconnecting switch, current transformer, voltage transformer, etc.). Finally, the main draw of the electrical wiring diagram, electrical general layout map, lightning protection and other related design layout plan drawings.

110kV变电所毕业设计说明书

目录 第一章原始资料分析 (2) 第二章变电所接入系统设计 (3) 第三章变电所地方供电系统设计 (4) 第四章主变压器的选择 (6) 第五章所用变压器的选择 (14) 第六章主接线的设计 (16) 第七章变电所电器设备的选择 (19) 第八节继电保护的配置 (24) 参考资料 (27)

第一章原始资料分析 一、原始资料 1、待建110KV降压变电所从相距30km的110KV东郊变电站受电。 2、待建110KV降压变电所年负荷增长率为5%,变电站总负荷考虑五年发展规划。 3、地区气温: ?1?年最高气温35℃,年最低气温–15℃。 ?2?年平均气温15℃。 4、待建110KV降压变电所各电压级负荷数据如下表: 二、对原始资料的分析计算 为满足电力系统对无功的需要,需要在用户侧装设电容器,进行无功补偿,使用户的功率因数提高,35kV线路用户功率因数提高到0.9为宜,10kV线路用户功率因数应不低于0.9。 根据原始资料中的最大有功及调整后的功率因数,算出最大无功,可得出以下数据:

第二章变电所接入系统设计 一、确定电压等级 输电线路电压等级的确定应符合国家规定的标准电压等级。选择电压等级时,应根据输送容量和输电距离,以及接入电网的额定电压的情况来确定,输送容量应该考虑变电所总负荷和五年发展规划。因此待建110KV变电所的最高电压等级应为110kV。 二、确定回路数 该110KV变电所建成后,所供用户中存在Ⅰ、Ⅱ类重要负荷,因此110KV变电所应采用双回110KV线路接入系统。 三、确定110KV线路导线的规格、型号 由于该待建110KV变电所距离受电110KV东郊变电站30KM,处于平原河网地区,因此应采用架空线路,导线选择LGJ型。 四、110KV线路导线截面选择 导线截面积选择的一般方法是:先按经济电流密度初选导线标称截面积,然

110kV变电所电气一次设计

第1章原始资料分析 1.变电站的地址和地理位置选择:建设一个变电站要考虑到地理环境、气象条件等因素,包括: ⑴年最高温度、最低温度。 ⑵冬季、夏季的风向以及最大风速。 ⑶该地区的污染情况。 2.确定变电站的建设规模设计⑴电压等级有两个:110kV 10kV。⑵主变压器用两台。⑶进出线情况:110kV有两回进线,10kV有18回出线。 3.设计110kV和10kV侧的电气主接线:通过比较各种接线方式的优缺点、适用范围,确定出最佳的接线方案。 ⑴110kV侧有两回进线,为电源进线,此时宜采用桥形接线,根据桥断路器的安装位置,可分为内桥和外桥接线两种,比较这两种接线的特点,适用范围,确定110kV侧的接线方式为内桥接线。 ⑵10kV侧有18回出线,可供选择的接线方式有: ①单母线分段接线。 ②双母线以及双母线分段。 ③带旁路母线的单母线和双母线接线。 比较这几种接线方式的优缺点,适用范围,确定出10KV侧的接线方式为单母线分段接线。 4.计算短路电流及主要设备选型。 ⑴主变压器的型号、容量、电压等级、冷却方式、结构、容量比和中性点接地方式的选择等。 ①主变的容量: 主变容量的确定应根据电力系统5-10年发展规划进行。当变电所装设两台 第0页共30 页

及以上主变时,每台容量的选择应按照其中任一台停运时,其余容量至少能保证所供一级负荷或为变电所全部负荷的60-80%。 ②接线方式: 我国110kV及以上电压,变压器三相绕组都采用“YN”联接;35kV采用“Y”联接,其中性点多通过消弧线圈接地。因此,普通双绕组一般选用YN,d11接线;三绕组变压器一般接成YN,y,d11或YN,yn,d11等形式。 5.绘制电气主接线图;总平面布置图;110kV和10kV的进出线间隔断面图等有关图纸。 6.简要设计主变压器继电保护的配置、整定计算 选择几个特殊的短路点:如110kV侧、10kV母线上。根据系统的短路容量进行整定计算。 7.防雷接地设计 防雷设计要考虑到年雷暴日,保护范围等因素。接地设计考虑到主要的电气设备能可靠的接地,免受雷电以及短路。 第1页共30 页

110kV变电站设计

110KV变电所电气设计说明 所址选择: 首先考虑变电所所址的标高,历史上有无被洪水浸淹历史;进出线走廊应便于架空线路的引入和引出,尽量少占地并考虑发展余地;其次列出变电所所在地的气象条件:年均最高、最低气温、最大风速、覆冰厚度、地震强度、年平均雷暴日、污秽等级,把这些作为设计的技术条件。 主变压器的选择: 变压器台数和容量的选择直接影响主接线的形式和配电装置的结构。它的确定除依据传递容量基本原始资料外,还应依据电力系统5-10年的发展规划、输送功率大小、馈线回路数、电压等级以及接入系统的紧密程度等因素,进行综合分析和合理选择。 选择主变压器型式时,应考虑以下问题:相数、绕组数与结构、绕组接线组别(在电厂和变电站中一般都选用YN,d11常规接线)、调压方式、冷却方式。 由于本变电所具有三种电压等级110KV、35KV、10KV,各侧的功率均达到变压器额定容量的15%以上,低压侧需装设无功补偿,所以主变压器采用三绕组变压器。为保证供电质量、降低线路的损耗此变压器采用的是有载调压方式,在运行中可改变分接头开关的位置,而且调节范围大。由于本地区的自然地理环境的特点,故冷却方式采用自然风冷却。 为保证供电的可靠性,该变电所装设两台主变压器。当系统处于最大运行方式时两台变压器同时投入使用,最小运行方式或检修时只投入一台变压器且能满足供电要求。 所以选择的变压器为2×SFSZL7-31500/110型变压器。 变电站电气主接线: 变电站主接线的设计要求,根据变电站在电力系统中的地位、负荷性质、出线回路数等条件和具体情况确定。 通常变电站主接线的高压侧,应尽可能采用短路器数目教少的接线,以节省投资,随出线数目的不同,可采用桥形、单母线、双母线及角形接线等。如果变电站电压为超高压等级,又是重要的枢纽变电站,宜采用双母线带旁母接线或采用一台半断路器接线。变电站的低压侧常采用单母分段接线或双母线接线,以便于扩建。6~10KV馈线应选轻型断路器,如SN10型少油断路器或ZN13型真空断路器;若不能满足开断电流及动稳定和热稳定要求时,应采用限流措施。在变电站中最简单的限制短路电流的方法,是使变压器低压侧分列运行;若分列运行仍不能满足要求,则可装设分列电抗器,一般尽可能不装限流效果较小的母线电抗器。 故综合从以下几个方面考虑: 1 断路器检修时,是否影响连续供电; 2 线路能否满足Ⅰ,Ⅱ类负荷对供电的要求; 3大型机组突然停电对电力系统稳定运行的影响与产生的后果等因素。 主接线方案的拟定: 对本变电所原始材料进行分析,结合对电气主接线的可靠性、灵活性及经济性等基本要求,综合考虑。在满足技术、经济政策的前提下,力争使其技术先进,供电可靠,经济合理的主接线方案。此主接线还应具有足够的灵活性,能适应各

110KV变电站电气部分设计

110KV变电站电气部分设计 二〇〇九年八月 目录 设计任务书 (4) 第一部分主要设计技术原则 (5) 第一章主变容量、形式及台数的选择 (6) 第一节主变压器台数的选择 (6) 第二节主变压器容量的选择 (7) 第三节主变压器形式的选择 (8) 第二章电气主接线形式的选择 (10) 第一节主接线方式选择 (12) 第三章短路电流计算 (13) 第一节短路电流计算的目的和条件 (14) 第四章电气设备的选择 (15) 第一节导体和电气设备选择的一般条件 (15) 第二节断路器的选择 (18) 第三节隔离开关的选择 (19) 第四节高压熔断器的选择 (20) 第五节互感器的选择 (20) 第六节母线的选择 (24) 第七节限流电抗器的选择 (24) 第八节站用变压器的台数及容量的选择 (25) 第九节 10kV无功补偿的选择 (26) 第五章 10kV高压开关柜的选择 (26) 第二部分计算说明书 附录一主变压器容量的选择 (27) 附录二短路电流计算 (28) 附录三断路器的选择计算 (30) 附录四隔离开关选择计算 (32) 附录五电流互感器的选择 (34) 附录六电压互感器的选择 (35) 附录七母线的选择计算 (36) 附录八 10kV高压开关柜的选择 (37) (含10kV电气设备的选择) 第三部分相关图纸 一、变电站一次主结线图 (42) 二、10kV高压开关柜配置图 (43) 三、10kV线路控制、保护回路接线图 (44) 四、110kV接入系统路径比较图 (45) 第四部分 一、参考文献 (46)

二、心得体会 (47) 设计任务书 一、设计任务: ***钢厂搬迁昌北新区,一、二期工程总负荷为24.5兆瓦,三期工程总负荷为31兆瓦,四期工程总负荷为20兆瓦;一、二、三、四期工程总负荷为75.5兆瓦,实际用电负荷 34.66兆瓦,拟新建江西洪都钢厂变电所。本厂用电负荷设施均为Ⅰ类负荷。 第一部分主要设计技术原则 本次110kV变电站的设计,经过三年的专业课程学习,在已有专业知识的基础上,了解了当前我国变电站技术的发展现状及技术发展趋向,按照现代电力系统设计要求,确定设计一个110kV综合自动化变电站,采用微机监控技术及微机保护,一次设备选择增强自动化程度,减少设备运行维护工作量,突出无油化,免维护型设备,选用目前较为先进的一、二次设备。 将此变电站做为一个终端用户变电站考虑,二个电压等级,即110kV/10kV。 设计中依据《变电所总布置设计技术规程》、《交流高压断路器参数选用导则》、《交流高压断路器订货技术条件》、《交流电气装置的过电压保护和绝缘配合》、《火力发电厂、变电所二次接线设计技术规程》、《高压配电装置设计技术规程》、《110kV-330kV变电所计算机监控系统设计技术规程》及本专业各教材。 第一章主变容量、形式及台数的选择 主变压器是变电站(所)中的主要电气设备之一,它的主要作用是变换电压以利于功率的传输,电压经升压变压器升压后,可以减少线路损耗,提高了经济效益,达到远距离送电的目的。而降压变压器则将高电压降低为用户所需要的各级使用电压,以满足用户的需要。主变压器的容量、台数直接影响主接线的形式和配电装置的结构。因此,主变的选择除依据基础资料外,还取决于输送功率的大小,与系统的紧密程度,同时兼顾负荷性质等方面,综合分析,合理选择。 第一节主变压器台数的选择 由原始资料可知,我们本次设计的江西洪都钢厂厂用电变电站,主要是接受由220kV双港变110kV的功率和220KV盘龙山变供110kV的功率,通过主变向10kV线路输送。由于厂区主要为I类负荷,停电会对生产造成重大的影响。因此选择主变台数时,要确保供电的可靠性。 为了提高供电的可靠性,防止因一台主变故障或检修时影响整个变电站的供电,变电站中一般装设两台主变压器。互为备用,可以避免因主变故障或检修而造成对用户的停电,若变电站装设三台主变,虽然供电可靠性有所提高,但是投资较大,接线网络较复杂,增大了占地面积和配电设备及继电保护的复杂性,并带来维护和倒闸操作的许多复杂化,并且会造成短路容量过大。考虑到两台主变同时发生故障的几率较小,适合负荷的增长和扩建的需要,而当一台主变压器故障或检修时由另一台主变压器可带动全部负荷的70%,能保证正常供电,故可选择两台主变压器。 第二节主变压器容量的选择 主变压器容量一般按变电站建成后5--10年规划负荷选择,并适当考虑到远期10--20年的负荷发展,对于城郊变电站主变压器容量应与城市规划相结合,该变电站近期和远期负荷都已给定,所以,应接近期和远期总负荷来选择主变容量。根据变电站所带负荷的性质和电网的结构来确定主变压器的容量,对于有重要负荷的变电站应考虑当一台主变压器停用时,其余变压器容量在计及过负荷能力的允许时间内,应保证用户的一级和二级负荷,对一般性变电站当一台主变压器停用时,其余变压器容量应能保证全部负荷的70--80%。该变电站的主变压器是按全部负荷的70%来选择,因此装设两

10kv变电站毕业设计

毕业设计(论文)任务书 一、题目:10kv变电所设计 指导思想和目的: 1、灵活运用本专业所学的基础和专业知识。 2、培养学生的专业技术知识和技能,能运用所学理论知识和技能解决生产第一线的运行、维护、检修及技术管理等实际工作,具有分析解决一般技术和业务问题的能力。 3、对学生进行一次高级人才基本技能的综合训练,培养学生分析和解决本专业技术实际问题的能力,包括技术经济政策的理解能力;查阅和综合分析各种文献资料、掌握使用工程技术规范和手册、图表等技术资料的能力;计算机应用能力;绘图和设计说明书(论文)的撰写等方面的能力。 4、培养学生树立严肃认真的工作作风,实事求是、严谨论证的科学态度,团结勤奋、协同作战的优良作风和应有的职业道德。 二.设计任务或主要技术指标: 1.设计任务 要求根据用电负荷实际情况,并适当考虑发展。按照安全可靠、技术先进、经济合理的要求,确定变电所的位置与形式,确定变电所主变压器的参数、容量与类型。选择变电所主接线方案及高低压设备和进出线,确定二次回路方案,选择整定继电保护装置、确定防雷和接地装置,最后按要求写出设计说明书,绘制设计图纸。 二、设计进度与要求: 第1周:收集10kv降压变电所资料。 第2周:了解掌握10kv降压变电站的基本组成。 第3周:根据设计背景计算变电所负荷。 第4周:短路电流计算。 第5周:电气主接线选择与校验。 第6周:继电保护预防雷保护的设计。 弟7周:制作10kv降压变电站设计报告。 弟8周:答辩 三、主要参考书及参考资料: [1]刘介才编著.《工厂供电》,第4版,机械工业出版社,2005 [2]雷振山编著.《中小型变电所实用设计手册》,第1版,中国水利水电出版社,2000。 [3]雷振山编著.《实用供配电技术手册》,第1版,中国水利水电出版社,2002。 [4]王子午编著.《常用供配电设备选型手册》,第一版,煤炭工业出版社,1998。 [5]徐泽植编著.《10kV及以下供配电设计与安装》,第一版,煤炭工业出版社,2002。 教研室主任(签名):系(部)主任(签名):2012年2月21日

110KV变电所毕业设计毕业设计

“发电厂及电力系统”专业大学毕业设计任务书 设计题目:区域电力网及降压变电所设计 毕业设计任务书 一、区域电网的设计内容 1、根据负荷资料,待设计变电所的地理位置。据已有电厂的供电情况。作出功率平衡。 2、通过技术经济综合比较,确定电网供电电压、电网接线方式及导线截面。 3、进行电网功率分布及电压计算,评定调压要求,选定调压方案。 4、评定电网接线方案。 二、在区域电网设计的基础上,设计110 kV;kV A降压变电所的电气部分。具体要求如下: 1、对B 变电所在系统中的地位作用及所供用户的分析。 2、选择变电所主变压器的台数、容量、型式。 3、分析确定高低压主接线方式及配电装置型式。 4、分析确定所用电接线方式。 5、进行继电保护及互感器的配置。 6、进行选择设备所必须的短路电流计算。 7、选择变电所高低压侧回路的断路器、隔离开关。 8、选择10kV 硬母线。 9、进行防雷及保护接地的规划。 三、设计文件及图纸要求: 1、设计说明书一份; 2、计算书; 3、图纸(2号)。 (1)区域电网接线图; (2)变电所一次接线图;

原 始 资 料 一、区域电网设计的有关原始资料 1、发电厂、变电所及新选定变电所地理位置(见附图一):D 图; 2、原有发电厂、变电所主接线图及设备规范(见附图二); 3、新变电所有关资料; 变电所 编 号 最大负荷 MW 功率因数 COSφ 二次侧 电压kV 调 压 要 求 负荷曲线 性 质 重要负荷 % A 20 0.92 10 顺 A 60 B 23 0.9 10 逆 B 51 C 27 0.9 10 逆 B 60 D 20 0.92 10 常 A 70 4、典型日负荷曲线 典型日负荷曲线(A ) % 100 90 80 70 60 50 40 30 20 10 0 2 4 6 8 10 12 14 16 18 20 22 24

110kv变电站安全距离110kv变电站设计规范.

110kv变电站安全距离110kv变电站设计规范 110kv变电站安全距离 国家《电磁辐射管理办法》规定100千伏以上为电磁强辐射工程,第二十条规定:在集中使用大型电磁辐射设备或高频设备的周围,按环境保护和城市规划要求,在规划限制区内不得修建居民住房、幼儿园等敏感建筑。 不过,据环保部门介绍,我国目前对设备与建筑物之间的距离有一定要求。比如一般10KV —35KV变电站,要求正面距居民住宅12米以上,侧面8米以上;35KV以上变电站的建设,要求正面距居民住宅15米以上,侧面12米以上;箱式变电站距居民住宅5米以上。 北京市规划委(2004规意字0638号)110千伏的地下高压变电站工程项目,明确要求距离不得少于300米。 35~110KV变电站设计规范 第一章总则 第1.0.1条为使变电所的设计认真执行国家的有关技术经济政策,符合安全可靠、技术先进和经济合理的要求,制订本规范。 第1.0.2条本规范适用于电压为35~110kV,单台变压器容量为5000kV A及以上新建变电所的设计。 第1.0.3条变电所的设计应根据工程的5~10年发展规划进行,做到远、近期结合,以近期为主,正确处理近期建设与远期发展的关系,适当考虑扩建的可能。 第1.0.4条变电所的设计,必须从全局出发,统筹兼顾,按照负荷性质、用电容量、工程特点和地区供电条件,结合国情合理地确定设计方案。 第1.0.5条变电所的设计,必须坚持节约用地的原则。 第1.0.6条变电所设计除应执行本规范外,尚应符合现行的国家有关标准和规范的规定。第二章所址选择和所区布置 第2.0.1条变电所所址的选择,应根据下列要求,综合考虑确定: 一、靠近负荷中心; 二、节约用地,不占或少占耕地及经济效益高的土地; 三、与城乡或工矿企业规划相协调,便于架空和电缆线路的引入和引出; 四、交通运输方便; 五、周围环境宜无明显污秽,如空气污秽时,所址宜设在受污源影响最小处; 六、具有适宜的地质、地形和地貌条件(例如避开断层、滑坡、塌陷区、溶洞地带、山区风口和有危岩或易发生滚石的场所),所址宜避免选在有重要文物或开采后对变电所有影响的矿藏地点,否则应征得有关部门的同意; 七、所址标高宜在50年一遇高水位之上,否则,所区应有可靠的防洪措施或与地区(工业企业)的防洪标准相一致,但仍应高于内涝水位; 八、应考虑职工生活上的方便及水源条件; 九、应考虑变电所与周围环境、邻近设施的相互影响。 第2.0.2条变电所的总平面布置应紧凑合理。 第2.0.3条变电所宜设置不低于2.2m高的实体围墙。城网变电所、工业企业变电所围墙的高度及形式,应与周围环境相协调。 第2.0.4条变电所内为满足消防要求的主要道路宽度,应为3.5m。主要设备运输道路的宽度可根据运输要求确定,并应具备回车条件。 第2.0.5条变电所的场地设计坡度,应根据设备布置、土质条件、排水方式和道路纵坡确定,

10KV变电所毕业设计(论文)

10KV变电所毕业设计 1 变电所总体设计及供配电系统分析 1.1 变电所设计原则 进行变电所设计时须遵照变电所设计规范所规定的原则。 根据《35—10kV变电所设计规范》要求: 第1.0.3条变电所的设计应根据工程的5—10年发展规划进行,做到远近结合、以近为主,正确处理近期建设与远景发展的关系,适当考虑扩建的可能性。 第1.0.4条变电所的设计必须从全局出发、统筹兼顾,按照负荷性质、用电容量、工程特点和地区供电条件,结合国情合理地确定设计方案。 第1.0.5条变电所的设计,必须节约用地的原则。 1.2 变电所设计目的与任务 毕业设计是本专业教学计划中的重要环节。此次毕业设计的目的是通过变电所设计实践,综合运用所学知识,贯彻执行我国电力工业有关方针政策,理论联系实践,锻炼独立分析和解决电力工程设计问题的能力,为未来的实际工作奠定必要的基础。 1.3 PG新校区供电需求分析 PG新校区10KV变电所为位于PG新校的变电所,由系统S1、系统S2向PG 新校区供电,来供给该校教学、实验、施工及生活用电,PG新校区变电所的建立可保障新校区的正常用电,提高供电质量和供电可靠性。PG新校区变电所变电压等级为10/0.4KV,是以向终端用户供电为主的变电所,全所停电后将对该校中断供电。 1.4 变电所总体分析 1.4.1 建站必要性与建站规模 1 建站必要性 PG新校区10KV变电所为终端变电所,在系统中主要起变配电作用,全所停电将造成全校停电,它供给该校教学、实验、施工及生活用电。故为满足该校用电要求决定建设本变电站。 2 建站规模

PG新校区10KV变电所电压等级为10/0.4KV 线路回路数: 近期6回,远期2回; 近期最大负荷4627KW。 1.4.2 所址概况与所址条件 1 所址概况 PG新校区10KV变电所位于该校图书馆周围,西部电源和东部电源进线先通过10kV变电所高压侧开关站进行电能分配,然后馈出六回线分配给两个独立变电所和四个箱式变电站,独立变电所和箱式变电站经过变压后供给其所带负荷用电。 2 所址条件 依据《10kV及以下变电所设计规范》GB50053-94 第2.0.1条,变电站所址的选择,应根据下列要求经技术、经济比较确定: 一、接近负荷中心; 二、进出线方便; 三、接近电源侧; 四、设备运输方便; 五、不应设在有剧烈振动或高温的场所; 六、不宜设在多尘或有腐蚀性气体的场所,当无法远离时,不应设在污染源盛行风向的下风侧; 七、不应设在厕所、浴室或其他经常积水场所的正下方,且不宜与上述场所相贴邻; 八、不应设在有爆炸危险环境的正上方或正下方,且不宜设在有火灾危险环境的正上方或正下方,当与有爆炸或火灾危险环境的建筑物毗连时,应符合现行国家标准《爆炸和火灾危险环境电力装置设计规范》的规定; 九、不应设在地势低洼和可能积水的场所。 PG新校区10KV变电所建在该校内部,为节约用地、接近负荷中心、进出线方便,故采用建立两个独立变电所和四个箱式变电站的方针。 1.5 负荷分析 1.5.1 负荷的分类与重要性 1一级负荷: 对供电要求最高,要求不断电或可极短时间断电。必须有两个独立电源供电,且当任何一个电源断开后,能保证对全部一级负荷不间断供电; 2 二级负荷: 对供电要求较高,要求基本不断电或可短时间断电。一般要有

110KV降压变电所设计_毕业设计论文

《发电厂电气部分》结业论文 110KV降压变电所设计 课程名称:发电厂电气部分 任课教师:姜新通 所在学院:信息技术学院 专业:电气工程及其自动化 中国·大庆 2012 年 5 月 毕业设计(论文)原创性声明和使用授权说明

原创性声明 本人郑重承诺:所呈交的毕业设计(论文),是我个人在指导教师的指导下进行的研究工作及取得的成果。尽我所知,除文中特别加以标注和致谢的地方外,不包含其他人或组织已经发表或公布过的研究成果,也不包含我为获得及其它教育机构的学位或学历而使用过的材料。对本研究提供过帮助和做出过贡献的个人或集体,均已在文中作了明确的说明并表示了谢意。 作者签名:日期: 指导教师签名:日期: 使用授权说明 本人完全了解大学关于收集、保存、使用毕业设计(论文)的规定,即:按照学校要求提交毕业设计(论文)的印刷本和电子版本;学校有权保存毕业设计(论文)的印刷本和电子版,并提供目录检索与阅览服务;学校可以采用影印、缩印、数字化或其它复制手段保存论文;在不以赢利为目的前提下,学校可以公布论文的部分或全部内容。 作者签名:日期:

学位论文原创性声明 本人郑重声明:所呈交的论文是本人在导师的指导下独立进行研究所取得的研究成果。除了文中特别加以标注引用的内容外,本论文不包含任何其他个人或集体已经发表或撰写的成果作品。对本文的研究做出重要贡献的个人和集体,均已在文中以明确方式标明。本人完全意识到本声明的法律后果由本人承担。 作者签名:日期:年月日 学位论文版权使用授权书 本学位论文作者完全了解学校有关保留、使用学位论文的规定,同意学校保留并向国家有关部门或机构送交论文的复印件和电子版,允许论文被查阅和借阅。本人授权大学可以将本学位论文的全部或部分内容编入有关数据库进行检索,可以采用影印、缩印或扫描等复制手段保存和汇编本学位论文。 涉密论文按学校规定处理。 作者签名:日期:年月日 导师签名:日期:年月日

BY市110kv降压变电所设计--牛

BY市110kv降压变电所设计--牛

课程设计 电气工程及其自动化_专业班级 题目BY市110kV降压变电所设计 姓名 学号 指导教师 二О年月日

一.变电站概括 1.1变电站总体分析 BY市变电站位于市边缘,供给城市和近郊工业、农业及生活用电,是新建地区变电所。变电站做为电力系统中起着重要的连接作用,是联系发电厂与负荷的重要环节。本课程设计主要是关于本变电站的一次设计,为了是变电站的一次设计能够很好的接入电力系统,使电力系统安全可靠的运行,下面对本变电站做初步分析的原始数据进行分析。 1.变电站类型:110KV地方降压变电站 2.电压等级:110/10KV 3.线路回数:110KV:2回,备用2回;10KV:13回,备用2回; 4.地理条件:平均海拔100m,地势平坦,交通方便,有充足水源,属轻地震区。年最高气温+42℃,年最低气温-18℃,年平均温度+16℃,最热月平均最高温度+32℃。最大风速35m/s,主导风向西北,覆冰厚度。5.负荷情况:主要是一、二级负荷,市内负荷主要为市区生活用电、棉纺厂、印染厂等工业用电;郊区负荷主要为郊区变电站及其他工业用电。 6.系统情况:根据任务书中电力系统简图可以看到,本变电站位于两个电源中间,有两个发电厂提供电

能,进而经过该变电站降压后用于工业、农业等负荷用电,需要一定的可靠性。 1.2 负荷分析及主变压器的选择 负荷计算的目的: 计算负荷是供电设计计算的基本依据,计算负荷确定得是否正确合理,直接影响到电器和导线电缆的选择是否经济合理。如计算负荷确定过大,将使电器和导线选得过大,造成投资和有色金属的消耗浪费,如计算负荷确定过小又将使电器和导线电缆处子过早老化甚至烧毁,造成重大损失,由此可见正确确定计算负荷重要性。 负荷分析 10KV 侧: 近期负荷:P 近=(2+2+1+1+2+3+2+1.5+1.5+1.5)MW=17.5MW 远期负荷: P 远=(3+3+1.5+1.5+3+4.5+3.5+2+2+2+2+2)=30MW ∑=n i Pi 1=17.5MW+30MW=47.5MW 综合最大计算负荷计算公式: S js =Kt*1 cos n i i i P φ =∑*(1+α%) (注:Kt:同时系数,取85%; %:线损,取5%) S js 近=Kt*max 1cos n i i i P ? =∑近 *(1+α%)

110kV变电站电气一次部分课程设计

110k V变电站电气一次部分课程设计 -CAL-FENGHAI-(2020YEAR-YICAI)_JINGBIAN

课程设计任务书 设计题目: 110kV变电站电气 一次部分设计 前言 变电站(Substation)改变电压的场所。是把一些设备组装起来,用以切断或接通、改变或者调整电压。在电力系统中,变电站是输电和配电的集结点。主要作用是进行高底压的变换,一些变电站是将发电站发出的电升压,这样一方面便于远距离输电,第二是为了降低输电时电线上的损耗;还有一些变电站是将高压电降压,经过降压后的电才可接入用户。对于不同的情况,升压和降压的幅度是不同的,所以变电站是很多的,比入说远

距离输电时,电压为11千伏,甚至更高,近距离时为1000伏吧,这个电压经变压器后,变为220伏的生活用电,或变为380伏的工业用电。 随着我国电力工业化的持续迅速发展,对变电站的建设将会提出更高的要求。本文通过对110KV变电站一次系统的设计,其中针对主接线形式选择,母线截面的选择,电缆线路的选择,主变压器型号和台数的确定,保护装置及保护设备的选择方法进行了详细的介绍。其中,电气设备的选择包括断路器、隔离开关、互感器的选择和方法与计算,保护装置包括避雷器和避雷针的选择。其中分析短路电流的计算方法和原因,是为了保证供电的可靠性。 目录 第1章原始资料及其分析 (4) 1原始资料 (4) 2原始资料分析 (6) 第2章负荷分析 (6) 第3章变压器的选择 (8) 第4章电气主接线 (11) 第5章短路电流的计算 (14) 1短路电流计算的目的和条件 (14) 2短路电流的计算步骤和计算结果 (15) 第6章配电装置及电气设备的配置与选择 (18) 1 导体和电气设备选择的一般条件 (18) 2 设备的选择 (19)

变电所设计毕业论文

前言 在这次设计的选题上我是根据自己现在所实习的岗位来确定的,题目是《110KV降压变电站的部分设计》,而且我认为这次选题也是很好的结合了我在学校所学的工厂供电这门课程,让实践和理论知识相结合。 学习了工厂供电,为了更好的掌握这门功课,切实保证工厂生产的正常工作需要,我们进行了这次设计.要完成这次设计就必须了解工厂供电的基本知识.包括供电系统的一般原则,内容和程序.须要进行负荷计算,无功补偿以及继电保护。 首先介绍工厂供电设计的基本知识,包括供电设计的内容和程序,供电设计依据的主要技术基础,供电设计常用的电气图形符号和文字符号.接着依次讲述负荷计算和无功补偿,变配电所主接线方案的设计,短路计算及一次设备选择,继电保护及二次回路的选择,变配电所的布置与结构设计,供配电线路的设计计算,防雷保护和接地装置的设计。本次设计最重要的设计原则和方法,我们认为,就是在设计中一定要遵循国家的最新标准和设计规范.因此设计中着力介绍与工厂供电设计有关的最新标准和设计规范的规定和要求.限于我们的水平,加之时间非常的紧促,因此设计书中可能有错漏和不妥之处,是很难避免的,请老师批评指正。 毕业设计(论文)任务书 题目110kV降压变电站电气一次部分设计 一、毕业设计(论文)内容 本所位于某市区。向市区工业、生活等用户供电,属新建变电所。 电压等级: 110kV:近期2回,远景发展2回; 10kV:近期12回,远景发展2回。 电力系统接线简图、负荷资料及所址条件见附件。 二、毕业设计(论文)应达到的主要指标 1、变电所总体分析; 2、负荷分析计算与主变压器选择; 3、电气主接线设计; 4、短路电流计算及电气设备选择; 5、配电装置及电气总平面布置设计。 三、设计(论文)成品要求 1.毕业设计说明书(论文)1份; 2.图纸:1套(电气主接线)。

110kV降压变电所电气部分的初步设计(doc 6页)

110kV降压变电所电气部分的初步设计(doc 6页)

2008级电气工程基础课程设计指导书 110kV降压变电所电气部分初步设计 一、设计目的 (1) 复习和巩固《电气工程基础》课程所学知识; (2) 培养分析问题和解决问题的能力; (3) 学习和掌握变电所电气部分设计的基本原理和设计方法。 二、设计内容及设计要求 1 设计内容 本次设计的是一个降压变电站,有三个电压等级(110kV/35kV/10kV)。本设计只做电气部分的初步设计,不作施工设计和土建设计。 (1) 主接线设计 分析原始资料,根据任务书的要求拟出各级电压母线的接线方式(可靠性、经济性和灵活性), (2) 主变压器选择 根据负荷选择主变压器的容量、型式、电压等级等,通过技术经济比较选择主接线最优方案; (3) 短路电流计算 根据所确定的主接线方案,选择适当的计算短路点计算短路电流,并列表表示出短路电流的计算结果; (4) 主要电气设备的选择:断路器、隔离开关、电流互感器、电压互感器、高 压熔断器、消弧线圈、避雷器等 (5) 编制设计成果 1)编制设计说明书 2)编制设计计算书 3)绘制变电所电气主接线图纸1张(A2图纸) 2 设计要求 设计按照国家标准要求和有关设计技术规程进行,要求对用户供电可靠、保证电能质量、接线简单清晰、操作方便、运行灵活、投资少、运行费用低,.并 且具有可扩建的方便性。要求如下: (1) 通过经济技术比较,确定电气主接线。 (2) 短路电流计算

(1) 变电站供电范围:110 kV 线路:最长100 km,最短50 km;35 kV 线路:最长70 km,最短20 km;10 kV 低压馈线:最长30km,最短10km (2) 未尽事宜按照设计常规假设。 四、要求 1.在资料一、二中任选一种情况作设计。 2.画图软件自选,手画也可。 4.主要参考资料 [1] 熊信银, 张步涵.电气工程基础.华中科技大学出版社,2005 [2] 何仰赞温增银,电力系统分析,华中科技大学出版社,2001 [3] 西北电力设计院东北电力设计院,电力工程设计手册,上海人民出版社,1972 [4] 电力工业部西北电力设计院,电力工程电气设备手册,中国电力出版社,1998 [5] 电力工业部西北电力设计院,电力工程电气设计手册,中国电力出版社,1998 [6] 陈跃.电力工程专业毕业设计指南.电力系统分册.中国水利水电出版 [7] 吴靓,谢珍贵.发电厂及变电所电气设备. 第一版.北京.中国水利水电出版社.2004 [8] 志溪.电气工程设计. 第一版.北京. 机械工业出版社.2002 [9] 张华.电类专业毕业设计指导.机械工业出版社 [10] 陈慈萱. 电气工程基础. 第一版.北京.中国电力出版社.2003