Total01-Jan-1528-Feb-17564 2 X 35 MW
2 X 35 MW COGENERATION POWER PLANT M/S PT. WILMAR ...01-Jan-1528-Feb-17564
A1020Basic Design Complete30-Apr-150 A1030Detail Design Complete30-Oct-150 A1040Boiler Erection & Installation start01-Jun-150 A1048Boiler 1 Hydraulic Test Complete02-Mar-160 A1049Boiler 2 Hydraulic Test Complete31-May-160 A1054Water Treatment Plant Commissioning complete31-May-160 A10566kV Power have provided(Purchaser's scope)16-Mar-160 A1059Boiler 1 Ignition07-Jul-160 A1060Boiler 2 Ignition07-Dec-160 A1065STG Erection & Installation start01-Jan-160 A10701# STG Synchronisation19-Sep-160 A10711# STG Full Load Operation30-Sep-160 A10722# STG Synchronisation15-Feb-170 A10802# STG Full Load Operation28-Feb-170 Engineeri
Engineering01-Jan-1530-Oct-15217 A1000Civil foundation load data - Boiler & Aux Columns30-Jan-150 A1005Civil foundation load data - ESP & Other30-Apr-150 A1010Civil foundation load data -STG & Aux30-Apr-150 E1000Basic Design01-Jan-15*28-Apr-1584 E1010Basic Design Review Meeting29-Apr-15*30-Apr-152 E1020Detail Design01-May-15*28-Oct-15129 E1030Detail Design Review Meeting29-Oct-15*30-Oct-152 Procurem
Procurement01-Jan-1530-Jun-16391 P1000MRQ:Long-Preriod equipment; return imformation fr...01-Jan-15*27-Feb-1542 P1010TBA/CBA/SBA:Long-Preriod equipment02-Feb-15*02-Apr-1544 P1020PO Issue(MRP):Long-Preriod equipment02-Mar-15*29-Apr-1543 P1030MRQ:Aux equipment; return imformation from supplier01-Apr-15*15-May-1533 P1040TBA/CBA/SBA:Aux equipment30-Apr-15*12-Jun-1532 P1050PO Issue(MRP):Aux equipment18-May-15*01-Jul-1533 P1055Anchor Bolt Deliver to site for Boiler 1&225-Mar-15*30-Apr-1527 P10581st Part of Steel Structure for Boiler 1 Deliver to site27-Apr-15*29-May-1525 P1060Deliver to Site:Long-Preriod equipment01-Oct-15*30-Jun-16196 P1070Deliver to Site:Aux equipment01-Jan-16*30-Jun-16130 Constract
Constraction02-Feb-1528-Feb-17542 C0960Design & constraction Civil Foundation Boiler & Aux ...02-Feb-15*30-Jun-15107 C0970Design & constraction Civil Foundation ESP & Other...01-May-15*30-Sep-15109 C0980Design & constraction 1# STG Pedestal,TG Building...01-May-15*31-Dec-15175 C0990Design & constraction 2# STG Pedestal,TG Building...01-May-15*29-Jan-16196 C1000Civil Foundation Boiler & Aux Columns complete01-Jun-15*01-Jun-151 C1005Civil Foundation ESP & Other Auxiliaries complete01-Oct-15*01-Oct-151Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
28-Feb-17, Total
28-Feb-17, 2 X 35 MW Basic Design Complete
Detail Design Complete
Boiler Erection & Installation start
Boiler 1 Hydraulic Test Complete
Boiler 2 Hydraulic Test Complete
Water Treatment Plant Commissioning complete
6kV Power have provided(Purchaser's scope)
Boiler 1 Ignition
Boiler 2 Ignition
STG Erection & Installation start
1# STG Synchronisation
1# STG Full Load Operation
2# STG Synchronisatio
2# STG Full Load Op
30-Oct-15, Engineering
Civil foundation load data - Boiler & Aux Columns
Civil foundation load data - ESP & Other
Civil foundation load data -STG & Aux
Basic Design
Basic Design Review Meeting
Detail Design
Detail Design Review Meeting
30-Jun-16, Procurement
MRQ:Long-Preriod equipment; return imformation from supplier
TBA/CBA/SBA:Long-Preriod equipment
PO Issue(MRP):Long-Preriod equipment
MRQ:Aux equipment; return imformation from supplier
TBA/CBA/SBA:Aux equipment
PO Issue(MRP):Aux equipment
Anchor Bolt Deliver to site for Boiler 1&2
1st Part of Steel Structure for Boiler 1 Deliver to site
Deliver to Site:Long-Preriod equipment
Deliver to Site:Aux equipment
28-Feb-17, Constract Design & constraction Civil Foundation Boiler & Aux Columns(Purchaser's scope)
Design & constraction Civil Foundation ESP & Other Auxiliaries(Purchaser's scope)
Design & constraction 1# STG Pedestal,TG Building & EOT Crane(Purchaser's scope)
Design & constraction 2# STG Pedestal,TG Building & EOT Crane(Purchaser's scope)
Civil Foundation Boiler & Aux Columns complete
Civil Foundation ESP & Other Auxiliaries complete
实际尚需关键尚需工作
里程碑
汇总
Page 1 of 2 2 X 35 MW COGENERATION POWER PLANT
M/S PT. WILMAR NABATI INDONESIA
C1010Erection of Boiler 101-Jul-15*29-Jan-16153 C1020Erection of Boiler 201-Sep-15*29-Apr-16174 C1024Coal Handling System 1 Installation01-Dec-15*15-Mar-1676 C1025Coal Handling System 1 commissioning16-Mar-16*31-Mar-1612 C1026Coal Handling System 2 Installation01-Mar-16*15-Jun-1677 C1027Coal Handling System 2 commissioning16-Jun-16*30-Jun-1611 C1030Hydraulic Test for Boiler 101-Feb-16*02-Mar-1623 C1040Hydraulic Test for Boiler 202-May-16*31-May-1622 C1044Ash Handling System 1 Installation01-Jan-16*15-Apr-1676 C1045Ash Handling System 1 Commissioning18-Apr-16*29-Apr-1610 C1046Ash Handling System 2 Installation01-Apr-16*15-Jul-1676 C1047Ash Handling System 2 Commissioning18-Jul-16*29-Jul-1610 C1050Commissioning & Testing for Boiler 102-May-16*30-Jun-1644 C1060Commissioning & Testing for Boiler 201-Sep-16*30-Nov-1665 C1062Water Treatment Plant Installation01-Jan-16*29-Apr-1686 C1063Sea Water availability(purchaser's Scope)29-Apr-16*29-Apr-161 C1064Water Treatment Plant Commissioning02-May-16*31-May-1622 C1070Boiler 1 Ignition and Steam Blow01-Jul-16*15-Jul-1611 C1080Boiler 2 Ignition and Steam Blow01-Dec-16*15-Dec-1611 C1087Coal availability(purchaser's Scope)01-Jul-16*01-Jul-161 C1088Fuel Oil availability(purchaser's Scope)01-Jul-16*01-Jul-161 C1090Boiler 1 Full Load18-Jul-16*08-Aug-1616 C1100Boiler 2 Full Load16-Dec-16*09-Jan-1717 C1110Civil of 1# STG Pedestal complete31-Dec-15*31-Dec-151 C11201# TG Building & EOT Crane Ready for use31-Dec-15*31-Dec-151 C1130Civil of 2# STG Pedestal complete29-Jan-16*29-Jan-161 C11402# TG Building & EOT Crane Ready for use29-Jan-16*29-Jan-161 C1150Erection of 1# STG01-Jan-16*30-Jun-16130 C1160Erection of 2# STG31-May-16*30-Nov-16132 C1170Commissioning & Testing for 1# STG01-Jul-16*30-Aug-1643 C1180Commissioning & Testing for 2# STG01-Dec-16*31-Jan-1744 C11901# STG Synchronisation01-Sep-16*19-Sep-1613 C12002# STG Synchronisation01-Feb-17*15-Feb-1711 C12101# STG Full Load Operation19-Sep-16*30-Sep-1610 C12202# STG Full Load Operation16-Feb-17*28-Feb-179Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Erection of Boiler 1
Erection of Boiler 2
Coal Handling System 1 Installation
Coal Handling System 1 commissioning
Coal Handling System 2 Installation
Coal Handling System 2 commissioning
Hydraulic Test for Boiler 1
Hydraulic Test for Boiler 2
Ash Handling System 1 Installation
Ash Handling System 1 Commissioning
Ash Handling System 2 Installation
Ash Handling System 2 Commissioning
Commissioning & Testing for Boiler 1
Commissioning & Testing for Boiler 2
Water Treatment Plant Installation
Sea Water availability(purchaser's Scope)
Water Treatment Plant Commissioning
Boiler 1 Ignition and Steam Blow
Boiler 2 Ignition and Steam Blow
Coal availability(purchaser's Scope)
Fuel Oil availability(purchaser's Scope)
Boiler 1 Full Load
Boiler 2 Full Load
Civil of 1# STG Pedestal complete
1# TG Building & EOT Crane Ready for use
Civil of 2# STG Pedestal complete
2# TG Building & EOT Crane Ready for use
Erection of 1# STG
Erection of 2# STG
Commissioning & Testing for 1# STG
Commissioning & Testing
1# STG Synchronisation
2# STG Synchronisatio
1# STG Full Load Operation
2# STG Full Load Op
实际尚需关键尚需工作
里程碑
汇总
Page 2 of 2 2 X 35 MW COGENERATION POWER PLANT
M/S PT. WILMAR NABATI INDONESIA